SOW_Contract-DCMR_Ramp_Improvement_-.pdf

PDF 373 KB Posted

Attached to
Statement of Work for DCMR Ramp Improvement Project
Solicitation number
SS7815
Issued by

About this file

This is a Statement of Work (SOW) for a ramp improvement project at the Deputy Chief of Mission Residence (DCMR) of the American Embassy in Bangui, Central African Republic (BMIS Number SS-7815). The project involves repair and extension of concrete driveway surfaces, creation of a sloped transition from the roadway shoulder to the driveway ramp, and incorporation of stormwater channels to mitigate erosion.

The contractor must remove deteriorated concrete and soil from approximately 60 square meters and replace it with a 15-centimeter thick wire-reinforced concrete slab (9 cubic meters of concrete), and pour an additional 15-square-meter sloped reinforced concrete ramp (7 cubic meters of concrete) along the roadway. Concrete specifications require minimum 35 MPa strength, 320 kg/m³ cement content, 19mm maximum coarse aggregate, and 50-100mm slump. Welded wire reinforcing (6x6 W4 or heavier) shall be centered in the driveway slab, with reinforcing bars (#6 or heavier) in the ramp/gutter channel. Control joints must be spaced at 3-meter intervals, with surfaces achieving FF 12 flatness and FL 12 levelness tolerances and a course broom finish.

Qualified contractors must possess minimum five years of construction experience specifically in concrete placement and provide three references from similar projects within the past five years. A mandatory pre-proposal site visit is scheduled for June 23, 2026, at 09:00 AM. Bids must be submitted electronically to Banguiprocurement@state.gov no later than June 26, 2026, before 13:30 (Post COB). The anticipated contract award and Notice to Proceed is June 30, 2026, with construction commencing July 27, 2025, and completion within 60 days of construction start. The contractor must submit a fixed price lump sum proposal with monthly progress payment requests retaining 10% until final completion. The contractor is responsible for all labor, materials, equipment, debris removal, transportation, and services. The USG will provide electric power and pressurized water at no cost. Contractors must comply with EM 385-1-1 Safety and Health Requirements Manual, obtain Regional Security Office clearance for all personnel and vehicles, and provide proof of local employee insurance. A one-year contractor installation guarantee is required, and all documents become Embassy property upon project completion.

View the file

Other files

File Type Posted
DRAWING_DCMR_Entrance_Ramp_2025.06.07.pdf PDF
03.Activity Hazard Analysis-Blank Work Sheet.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SENSITIVE BUT UNCLASSIFIED

Statement of Work

DCMR Ramp Improvement

BMIS Number SS-7815

American Embassy Bangui

Avenue David Dacko, B.P. 924

Bangui, Central African Republic

16 June 2026

STATEMENT OF WORK

United States Department of State Overseas Buildings Operations Embassy Bangui, Central African Republic

UNCLASSIFIED 2

Invitation to bid

The U.S. Embassy in Bangui invites qualified contractors to submit bids for ramp improvement project at the Deputy Chief of Mission Residence (DCMR).

The project includes repair and extension of the concrete surface area of the driveway ramp, creation of a lower slope transition from the roadway shoulder to the driveway ramp, and seal of the roadway shoulder berm to mitigate erosion as outlined in the

Statement of Work (SOW).

Key Details:

• Location: DCMR

• Site Visit: June 23, 2026, at 09am

• Minimum Requirements: Five years of construction experience and three references.

Solicitation Availability

The solicitation package is available through the following channels:

• The solicitation package is available through the following channels:

• SAM.gov: The solicitation is posted on the System for Award Management (at https://sam.gov/ Interested vendors are encouraged to register on SAM.gov to receive updates and amendments.

• Embassy Website: The solicitation package is also available for download on the

U.S. Embassy Bangui official website https://cf.usembassy.gov/ .

• Embassy Gate (Hard Copy): Physical copies of the solicitation package are available for collection at the U.S. Embassy Bangui main gate, Monday through https://sam.gov/ https://cf.usembassy.gov/

Embassy Bangui, Central African Republic

UNCLASSIFIED 3

Friday, from 7:30 a.m. to 5:00 p.m. local time. Vendors should bring a valid form of identification to collect their copy.

• Interested offerors are encouraged to obtain the solicitation package as early as possible to allow sufficient time for preparation and submission of a complete offer by the closing date.

• Embassy Gate (Hard Copy): Physical copies of the solicitation package are available for collection at the U.S. Embassy Bangui main gate, Monday through

Friday, from 7:30 a.m. to 5:00 p.m. local time. Vendors should bring a valid form of identification to collect their copy.

Interested offerors are encouraged to obtain the solicitation package as early as possible to allow sufficient time for preparation and submission of a complete offer by the closing date.

The solicitation package is available at the gate of the Embassy from 7.30am to

5pm.

Interested parties must submit bids electronically to Banguiprocurement@state.gov no later than June 26, 2026, before Post COB (13:30). Late submissions will not be accepted. For inquiries, contact Banguiprocurement@state.gov.

mailto:Banguiprocurement@state.gov mailto:Banguiprocurement@state.gov

Embassy Bangui, Central African Republic

UNCLASSIFIED 4

STATEMENT OF WORK

CONTENTS

1. INTRODUCTION

2. OBJECTIVES

3. REQUIREMENTS

4. GOVERNMENT FURNISHED PROPERTY (GFP), GOVERNMENT

FURNISHED MATERIAL (GFM), GOVERNMENT FURNISHED EQUIPMENT

(GFE), and CONTRACTOR FURNISHED MATERIAL (CFM)

5. CONTRACT ADMINISTRATION

6. RESPONSIBILITIES OF THE CONTRACTOR

7. CONSTRUCTION REQUIREMENTS

8. STANDARDS AND SPECIFICATIONS

9. DELIVERABLES SCHEDULE

10. SAFETY REQUIREMENTS

11. SECURITY REQUIREMENTS

12. PAYMENTS

13. REFERENCES

14. ATTACHMENTS

Embassy Bangui, Central African Republic

UNCLASSIFIED 5

1. INTRODUCTION

1.1 The driveway entrance ramp to the USG property on Route de La Moyenne

Corniche requires improvement because a recent roadway improvement project has raised the height of the shoulder approximately .44m (18”) above the previous shoulder height. This condition creates two problems: 1. A steep incline onto the driveway level, and 2. Potential erosion of the roadway shoulder berm that is comprised of compacted soil. Based upon the configuration of the site the stormwater runoff will lead to undermining and washout of the roadway unless mitigated with top seal and stormwater management. The surface of the new road is bitumen surface treatment (BST) and the road base soil is a low-grade processed gravel with a homogenous mixture throughout the depth of the roadbed.

The objectives are to repair and expand the concrete surface area of the driveway ramp, create a lower slope transition from the roadway shoulder to the driveway ramp, and seal the roadway shoulder berm to mitigate erosion.

The area is approximately 70m2 and will require approximately 16m3 of concrete. This will likely require two separate concrete pours, the base driveway and the ramp/stormwater construct.

1.2 Bids should include all labor, materials, equipment, debris/trash removal, transportation and services for accomplishment of work outlined and shall be in accordance with U.S. standard construction specifications or equivalent.

GFE (Government Furnished Equipment) and/or GFM (Government

Furnished Materials) may be provided if in the best interest of the USG.

1.3 Bidders need to possess a minimum of five (5) years’ experience in the construction trade, specifically in concrete placement. All bidders must provide three (3) references (with contact information) of companies the bidder has performed similar jobs within the past five (5) years. If bidders plan to subcontract any work, the subcontractor must furnish the information required above.

1.4 A Contracting Officer’s Representative (COR) will be designated by the

Facility Manager (FM) and Contracting Officer’s Technical Representatives

Embassy Bangui, Central African Republic

UNCLASSIFIED 6

(COTR) may be designated as necessary. A Post Occupational Safety and

Health Officer Assistant (POSHOA) will be designated to ensure site safety compliance. The Contractor is expected to collaborate with assigned designees in good faith to ensure that cost, quality, schedule, and safety targets are achieved. USG designees are responsible to be readily available for Contractor engagement and to ensure that the Contractor receives necessary information as early as possible during the construction process.

1.5 Material acceptance shall be requested through the COR who will assist and direct the Contractor to obtain approved materials.

1.6 All questions concerning coordination of material and installation activities shall be directed to the COR. (COR contact information will be provided via separate correspondence.) The COR has no authority to add or authorize any modification to this SOW or associated contract(s), all changes must be approved in writing by the Contracting Officer (CO).

1.7 The Facility Manager may also designate Contracting Officer Technical

Representatives (COTR) for respective disciplines. The COTR(s) will be responsible for technical aspects of the project such as appropriate use of tools and equipment, and approval of construction practices and techniques. The

COTR has no authority to add or authorize any modification to this SOW or associated contract(s), all changes must be approved in writing by the

Contracting Officer (CO).

1.8 Work shall be completed as expeditiously as possible to meet the schedule targets. The Contractor shall submit to the COR a phased work plan with the construction schedule for review and approval prior to commencement of work at the DCMR site.

2. OBJECTIVES

2.1 Remove the deteriorated concrete/soil driveway surface and replace with 15cm thick wire reinforced concrete slab driveway. Approximately 60m2 (645ft2) area, and 9m3 (10yd3) concrete.

Embassy Bangui, Central African Republic

UNCLASSIFIED 7

2.2 Pour a sloped reinforced concrete ramp along the roadway transitioning onto the driveway according to the attached road profile drawings. Approximately

15m2 (161ft2) area, and 7m3 (19yd3) concrete.

2.3 Incorporate stormwater channels into the concrete ramp construct according to the attached road profile drawings.

3. REQUIREMENTS

3.1 The Contractor shall deliver a completed project IAW the attached drawings, diagrams, and the specifications contained in this SOW.

3.2 Concrete strength shall be minimum (35 MPa), minimum cement content (320 kg/m3), maximum size of coarse aggregate (19 mm), slump (50 to 100 mm).

3.3 Welded wire reinforcing (6x6 W4 or heavier) shall be installed generally centered in the driveway slab cross-section.

3.4 Reinforcing bars(#6 or heavier) shall be installed within the ramp/gutter channel construct in accordance with the attached drawing.

3.5 Control joints (cut lines) should be provided at intervals of about 3m transversely along the length of the driveway. The joint is a sawcut or trowel cut about one quarter the depth of the slab that provides a weak plane in the slab where stress cracks will form.

3.6 The concrete driveway surface shall have a flatness of FF 12 (approximately

1/2” gap per 10’).

3.7 The concrete driveway surface shall have a levelness of FL of 12

(approximately 1/2” gap per 10’).

3.8 The driveway and ramp surfaces shall have a course broom finish cut parallel to the entry gate.

3.9 Any disturbed soil or added soil shall be compacted using a mechanical compactor and water soaked to promote compaction.

3.10 The Contractor shall provide construction personnel with adequate materials, tools, equipment, clothing, personal protective equipment (PPE), shaded rest area, fresh drinking water, and supervision as needed to perform the construction services necessary to meet the requirements of this SOW. It is

Embassy Bangui, Central African Republic

UNCLASSIFIED 8

expected that the Contractor shall coordinate closely with COR and APOSHO to develop work related risk management strategies.

3.11 The contractor is responsible for supplying all required material and equipment to meet the specifications in this SOW and the attached design drawings.

Unless otherwise directed by the CO to use GFP, which will be prorated at prevailing pricing.

3.12 The Contractor shall perform continuous operations throughout the construction process and maintain gainful activities during employee presence on the site.

3.13 The Contractor shall prepare and submit the following documents for review:

concrete batch tickets.

3.14 The Contractor shall submit the following documents for approval: quality assurance plan, safety plan, and work schedules. These documents shall provide the necessary contacts, communication, and coordination between the

Embassy and the Contractor for the delivery of a completed project.

3.15 The work shall be executed in a diligent manner in accordance with a negotiated firm fixed price and period of performance (POP). The POP for all phases of the project (60 days after construction start) shall be determined prior to

Contract Award, with consideration for verified inclement weather days or disruptions beyond the Contractor’s control.

3.16 The Contractor shall meet the design specifications contained in this SOW and attachments, and/or manufacturers’ specifications for all materials, to include:

• Concrete (batch plant produced)

• CMU (Concrete Masonry Units)

• Reinforcing steel and mesh

• Exterior pavers and/or tile

4. GOVERNMENT FURNISHED PROPERTY (GFP), GOVERNMENT

FURNISHED MATERIAL (GFM), GOVERNMENT FURNISHED

EQUIPMENT (GFE), and CONTRACTOR FURNISHED MATERIAL

(CFM)

4.1 Pursuant to Contract Clause FAR 52-245-2, Government Furnished Property

(Short Form).

Embassy Bangui, Central African Republic

UNCLASSIFIED 9

4.2 The USG will provide electric power and pressurized water to the site at no cost to the contractor.

4.3 The Government will not furnish material or tools for this project, including personal or tradesman tools unless in the best interest of the USG and authorized by the CO; the associated costs will be prorated for contractual consideration.

4.4 The Contractor shall furnish non-expendable tools as well as expendable tools, e.g., saw blades, drill bits, rags, cleaning materials, etc.

4.5 Contractor shall provide adequate quantities of materials to provide a complete project as specified.

4.6 Material Procurement –All local material procurements shall be executed in cognizance with the COR. The Contractor shall refer to the security requirements in section 10 for further guidance as required.

5. CONTRACT ADMINISTRATION

5.1 The Contractor shall not conduct any work that is beyond this SOW and accompanying specifications unless directed in writing by the CO. Any work done by the Contractor beyond this SOW and accompanying specifications without direction from the CO will be at the Contractor’s own risk and at no cost to the Embassy.

5.2 The Contacting Officer shall provide a Notice to Proceed (NTP) to the

Contractor. No work shall be initiated until the NTP is issued by the CO.

5.3 The Contracting Officer may designate more than one individual to serve as the

Contracting Officer’s Representative (COR). The Contractor will be furnished evidence of COR appointments, including explicit authority delegated to each

COR and their responsibilities.

5.4 The Embassy’s review, approval, or acceptance of, or payment for the services required under this contract shall be construed to operate as a waiver of any rights under this contract or any cause of action against the Contractor arising out of the performance of this contract.

5.5 The Embassy has the right to inspect and test all services specified by the contract, to the extent practicable at all times and places during the term of the

Embassy Bangui, Central African Republic

UNCLASSIFIED 10

contract. The COR and the COTR may perform Quality Assurance Inspections

(QAI) and tests during construction to confirm the work is installed according to the SOW.

5.6 The Contracting Officer has the authority to issue a temporary stop order during the execution of any phase of this SOW. This authority may be executed when the Embassy requires time for official functions or is in possession of specific credible information indicating that the lives of Embassy personnel are immediately threatened, and that the execution of the project will increase the

Embassy’s vulnerability. The Contractor shall promptly notify the CO that work has been stopped.

5.7 If any of the Contractor’s services do not conform to the contract requirements, the COR may require the Contractor to perform the services again in conformity with the contract requirements. The Embassy may by contract or otherwise, perform the services and charge the Contractor any cost incurred by the Embassy that is directly related to the performance of such service or terminate the contract for default.

5.8 The Embassy has the right to terminate this contract of convenience at any time in whole, or from time to time, if the Contracting Officer determines it is in the interest of the Embassy.

6. RESPONSIBILITIES OF THE CONTRACTOR

6.1 The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this Contract. The Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.

6.2 The Contractor shall identify a Project Site Manager who shall be responsible for the overall management of the project and shall represent the Contractor on the site during construction. The Project Site Manager shall be approved by the COR.

6.3 The Project Site Manager shall attend all project meetings, prepare Status

Reports for the project and submit them to the COR. Status reports shall contain

Embassy Bangui, Central African Republic

UNCLASSIFIED 11

meeting minutes, construction progress reports, arising concerns and proposed solutions, proposed changed orders, and other pertinent information.

6.4 All documents produced for this project will become the property of the

Embassy at the completion of the project.

6.5 The Contractor shall verify that all materials, equipment, and systems incorporated into the project provide operational dependability and durability.

The Contractor assures that the completed construction shall be easily maintained or replaced with readily available materials and services.

6.6 Any cost associated with services subcontracted by the Contractor shall be borne by and be the complete responsibility of the Contractor under the fixed price of this contract.

6.7 The Contractor is responsible and accountable for their employees, subcontractor personnel and personal safety and shall comply with all OSHA regulations and where applicable, local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters. The Contactor shall promptly report all accidents to the COR resulting in lost time, disabling, or fatal injuries.

6.8 The Contractor shall be and remain liable to the Embassy in accordance with applicable law for all damages to the Embassy caused by the Contractor’s negligent performance of any of the services furnished under this contract. The rights and remedies for the Embassy provided for by this contract are in addition to any other rights and remedies provided by law. Notice to the COR shall be within one calendar day.

6.9 The Contractor shall examine all the documents and visit the site to fully inform themselves of all the conditions and limitations applied to the work and submit a firm fixed price cost proposal for all the work. No subsequent cost allowance will be made to the Contractor for failure to recognize the existing conditions.

The Contractor will be afforded ample time to assess and inspect the existing structures and conditions.

6.10 The Contractor shall prepare and submit a Quality Control Schedule (QCS) and

Project Safety Plan (PSP) to address the project. The QCS and PSP should be projected to document the entire project from beginning to end, although can

Embassy Bangui, Central African Republic

UNCLASSIFIED 12

be amended during the project through collaboration with the COR and

APOSHO.

6.11 Submit a copy of a Contractor’s Installation Guarantee covering the work, labor, and equipment for a period of one (1) year at no cost to the Embassy signed by the Contractor.

6.12 The Contractor will be fully responsible for providing physical protection against wet concrete splatter, failing scaffolding, and falling objects for visitors and employees, their clothing and personal effects, and their vehicles for the duration of this contract and any subsequent contract extensions. The

Contractor will be responsible for the complete cleaning and removal of concrete splatter, residue or stains from buildings and sidewalks.

7. CONSTRUCTION REQUIREMENTS

7.1 Documentation – No construction shall begin until the Contract Administration

Documents are received and accepted by the COR, see Section 11.2.

7.2 Material – The Contractor shall provide materials and equipment (except

GFM), and personnel to administer, manage, and supervise the project. All materials and equipment incorporated into the project shall be new unless noted otherwise. The Contactor shall transport and safeguard all materials and equipment required for construction.

7.3 Workmanship – All workmanship shall be of good quality and performed in a skillful manner as verified by the COTRs and CORs.

7.4 Storage – Equipment and materials shall be carefully handled, properly stored, and adequately protected to prevent damage before and during installation, IAW manufacturers’ recommendations. Damaged or defective items will be replaced. The Contractor is responsible for the security of all materials and equipment to prevent loss or pilferage. The Contractor will be provided with a storage and staging area as determined by the COR. The Contractor shall be responsible for restoring the area to its original condition at the completion of the work. The Contractor shall be responsible for repair of any damage incurred to buildings or pavement as a result of storage activities. The Contractor is

Embassy Bangui, Central African Republic

UNCLASSIFIED 13

responsible for obtaining any additional off–compound storage areas as required.

7.5 Receipt of Materials – Shipment of equipment, materials, and supplies shall be addressed to the Contractor, unless authorized by previous written agreement.

The Contractor must be available to accept shipments unless authorized by previous written agreement. The Embassy will not accept shipments without express written agreement with the Contractor.

7.6 Housekeeping – The Contractor shall at all times keep the work area free from accumulation of waste materials. Upon completing construction, the Contractor shall remove all temporary facilities and leave the project site in a clean and orderly condition acceptable to the COR.

7.7 Hours of Operation – The Contractor shall perform the work at the site during the Embassy’s normal workday hours of 07:30h – 17:30h unless agreed upon with the COR in advance.

7.8 Utility Services – The Contractor shall coordinate temporary utilities including water and power lines with the COR. The Contractor shall bear the costs of connecting, converting, and transferring the utilities for the duration of the project. The Contractor shall be responsible for making connections including providing back flow preventer devices on connections to domestic water lines, providing transformers, and post project restorations.

7.9 Work Stoppages – In the event of a lengthy work stoppage the Contactor shall:

lower and remove all scaffolding, temporary work platforms, and/or harnesses;

secure all construction related building access points; store all tools and equipment; Disconnect unnecessary services and perform general housekeeping to leave site in a neat and orderly condition. Contractors shall notify the COR of the temporary barricade locations and remove the temporary barricades as soon as deemed safe.

7.10 Storm Protection - Should warnings of wind of gale force or stronger be issued, the Contactor shall take every practical precaution to minimize danger to person, the work and adjacent property. Precautions shall include, but not be limited to, closing all openings, removing all loose materials, tools and

Embassy Bangui, Central African Republic

UNCLASSIFIED 14

equipment from exposed locations, and securing material that may become airborne.

7.11 Cleanup – The Contractor shall keep the work area, including storage areas, free from accumulations of waste materials on a daily basis and comply with all national and local regulations pertaining to the storage, transport, and disposal of wastes. The Contractor shall not use Embassy waste disposal facilities including garbage cans, trash piles, or dumpsters.

7.12 Landscape Restoration – The surfaces of all unpaved areas disturbed by construction activities shall be stored to grade level. Landscape shrubs killed or damaged by construction activities shall be replaced with same species and size.

8. STANDARDS AND SPECIFICATIONS

8.1 The Contactor’s work shall be in accordance with current U.S. codes and standards. The COR will review and comment on the Contractor’s submittals using this SOW for Construction Services and the following codes and standards:

a. American Society for Testing & Materials

b. 2003 International Building Code

c. 2003 International Plumbing Code

d. 2002 National Electrical Code (NFPA)

e. ADA compliant

f. EM 385-1-1 Safety and Health Requirements Manual

9. DELIVERABLES SCHEDULE

9.1 The Contractor shall commence work to the agreed schedule, execute the work diligently, and achieve final completion and acceptance including final cleanup of the premises within the period specified.

9.2 Milestones:

a. Contractor Pre-Proposal Site Visit DATE: June 23, 2026, at

09am

b. Award of Contract & Notice to Proceed DATE: June 30, 2026

Embassy Bangui, Central African Republic

UNCLASSIFIED 15

c. Pre-Construction Submittals Within DATE days of

Notice to Proceed

d. Embassy Submittal Review DATE:

e. Construction Start DATE: Monday July 27, 2025

f. Construction Finish DATE 60 days after construction start

9.3 Project Completion: Contractor’s one year workmanship guarantee.

10. SAFETY REQUIREMENTS

10.1 All construction activities must use appropriate safety equipment IAW the EM

385-1-1, Safety and Health Requirements Manual. The Embassy APOSHO and/or the FM, the Post Occupational Safety and Health Officer (POSHO) will continually monitor the site for proper use of appropriate safety equipment required by EM 385-1-1.

10.2 The purpose of this section is to ensure the health and safety of personnel and avoid damage to property during the execution of this project. The Contractor will accept all legal requirements or regulations currently enforced that concern safety for staff and workers, as well as for the public who directly or indirectly may be affected by the work.

10.3 The COR will ensure that safety protocols are implemented before and during the project and will confer with the POSHO to ensure all the safety standards and practices are followed and enforced. In the event of a discrepancy between the EM 385-1-1 Safety and Health Requirements Manual and the local laws on industrial safety as established by the Central African Republic Labor

Authority, the Contractor will follow the more restrictive standard. In addition, the Contractor shall meet the following requirements:

10.3.1 The Contractor must demonstrate understanding of his/her responsibilities related to the safety requirements by addressing hazards in preplanning processes and meetings.

Embassy Bangui, Central African Republic

UNCLASSIFIED 16

10.3.2 Prior to starting a project, the Contractor is required to review the work site and identify hazards that may occur while performing the job.

10.3.3 The Contractor is expected to provide a “competent person” to implement a Site Health and Safety Plan and oversee its compliance. A competent person is an individual who, by way of training and/or experience, is knowledgeable of applicable standards, can identify workplace hazards relating to the specific operation, is designated by the employer, and has authority to take appropriate actions.

10.3.4 The Contractor should provide the Activity Hazard Analysis (Job Safety

Analysis) related with the Load Handling Equipment procedure before commencing the project.

10.3.5 The Contractor is required to provide the proof of payment of local insurances of all the employees that will be involved in the project. Likewise, the Contractor is required to provide monthly payment documents of local insurance for the length of work.

10.3.6 The Contractor will conduct a safety briefing before starting daily work.

10.3.7 Contractor personnel who have signs of drunkenness or who are under the influence of stimulants or hallucinogens will be denied entry to the work area.

10.3.8 The Contractor shall ensure individuals working at the site are trained and aware of potential hazards. The Contractor shall ensure that these individuals are provided with proper safety equipment to prevent accidental injury in accordance with the requirements of the contract.

10.3.9 The Contractor must accept the safety standards set by the U.S.

Embassy.

10.3.10 All workers will remove all chains, rings, watches and/or bracelets during the execution of work.

10.3.11 Smoking is prohibited at the work site and will use only the designated area for smoking.

10.3.12 The Contractor will report mishaps (injuries, accidents, incidents, damage, errors) to the COR who will pass the proper data to the POSHO.

Embassy Bangui, Central African Republic

UNCLASSIFIED 17

10.3.13 The Contractor must place provisional barricades and warning signs to maintain a safe and accessible path-of-travel for all pedestrians, including those with disabilities, to avoid accidents to third parties. Barricades alert others about hazards created by construction activities and should be used to control vehicular traffic around the work site as well.

10.3.14 Contractor personnel must use personal protective equipment (PPE) required and in accordance with the type of work performed.

10.3.15 The Contractor is required to inspect and maintain spare PPE in case of damage, deterioration, or loss of the equipment.

10.3.16 The PPE used must meet the technical specifications required by local regulation and international standards.

10.3.17 Sharp cutting tools must be carried in Tools Carrying Cases; under no circumstances are they to be carried in uniform pockets.

10.3.18 In those tasks where PPE certification is required, the Contractor must provide the current certification.

10.3.19 The Contractor must provide records of PPE received for all the employees involved in the task.

10.4 The following DOSAR 652.236-70 Additional Safety Measures is applicable.

Reference: https://www.acquisition.gov/dosar/652.236-70-additional-safety-measures

11. SECURITY REQUIREMENTS

11.1 The Project Site Manager shall be responsible for the overall management and execution of the onsite construction activities and shall represent the Contractor on the site during construction. The Site Manager shall be responsible for ensuring the Contractor’s employees, team, and subcontractors follows the

Construction Security Plan (CSP). The Site Manager shall have a copy of the

CSP and a copy of the certification/confirmation cable in his/her possession during the project.

11.2 All Contractors that require access to the site shall be cleared in advance by the

Post Regional Security Office (RSO). No local Contractors will be granted

Embassy Bangui, Central African Republic

UNCLASSIFIED 18

access unless the Post RSO receives a written request 24 hours in advance of the scheduled access. Contractors must provide the RSO 24 hours in advance in writing the names of personnel required to enter the site, and the personnel must provide valid identification upon entering the site. The Contractor shall submit vehicles’ make, model and registration number to the RSO within 10 days of the Notice to Proceed, and 24 hours in advance of additional vehicles that may require access to the site. Vehicles with steady leaks or deemed unsafe will not be permitted to enter the site.

11.3 The work to be performed under this contract requires that the Contractor, its employees, and sub-contractors submit corporate, financial and personnel information for review by the Embassy. Information submitted by the

Contractor will not be disclosed beyond the Embassy.

11.4 Material or equipment shall not block access or egress from Chancery at any time. If egress must be blocked for a specific task the Project Site Manager must coordinate the event with the COR and RSO.

11.5 All material items such as anchors that attach to the Office Building walls must be approved by RSO before use.

12. PAYMENTS

12.1 The Contractor shall provide a fixed price lump sum proposal to the

Contracting Officer. The Contractor may submit requests for progress payments at monthly intervals to cover the value of labor and materials completed to date. In making progress payments there shall be retained 10% of the amount due until final completion.

12.2 The Contractor shall submit one copy of all payment invoices, with the appropriate backup documents to the COR. The COR will determine if the invoice is complete and proper as submitted. The COR also will determine if billed services have been satisfactorily performed and if expenses skilled are correct. If it is determined that the invoice is incorrect, the COR will within seven (7) days, request the Contractor to submit a revised invoice. Under no circumstance shall the Contractor provide cash, goods, favors, or services to any U.S. Government employee. This behavior constitutes fraud and

Embassy Bangui, Central African Republic

UNCLASSIFIED 19

may result in penalties and disbarment form future U.S. Government contracts. Any incidents should be reported directly to the CO.

12.3 The Contractor shall specifically identify his last invoice “Final Invoice.” The

Final Invoice shall include the remaining payment claimed to be due under the basic contract and all modifications issued, if any.

Embassy Bangui, Central African Republic

UNCLASSIFIED 20

13. REFERENCES

13.1 Contract Administration Documentation and Submittals

DOCUMENT SOURCE SCHED

Project Schedule Contractor Pre-Award

Insurance Binder Contractor Pre-Award

Notice to Proceed Embassy - CO Post-Award

Construction Security Plan RSO / COR Pre-

Construction

List of Personnel for access Contractor Pre-

Construction

List of Vehicles for access Contractor Pre-

Construction

Sub-contractors’ administrative information

Contractor Pre-

Construction

Safety Plan Contractor - APOSHO

Pre-

Construction

Activity Hazard Analysis Contractor - APOSHO Pre-

Construction

Mishap Reports Contractor - APOSHO Each occurrence

Stop Work Notice Contractor - CO Each occurrence

Test and Inspection Reports Contractor Each occurrence

Progress Report Contractor Sched TBD

Request for Payment Invoice Contractor As needed

Equipment Operation, Care, and Maintenance literature

Contractor Project Close-

Out

13.2 Acronyms

A/E Architecture and Engineering

Embassy Bangui, Central African Republic

UNCLASSIFIED 21

ADA American Disabilities Act

APOSHO Assistant Post Occupational Safety and Health Officer – U.S.

personnel

BOM Bill of Materials

C/E Construction and Engineering

CFM Contractor Furnished Equipment

CMR Chief of Mission’s Residence

CO Contracting Officer

COR Contracting Officer’s Representative

COTR Contracting Officer’s Technical Representative

CSP Construction Security Plan

FM Facility Manager

GFM Government Furnished Equipment

NTP Notice to Proceed

OBO Overseas Buildings Operations

POSHOA Post Occupational Safety and Health Officer Assistant – Local Staff

QAI Quality Assurance Inspection

RSO Regional Security Officer

SOW Statement of Work

TBD To be Determined

USG United States Government

14. ATTACHMENTS

a. Attachment A: Design Drawing

b. Attachment B: Activity Hazard Analysis Template

c. Attachment C: Work Plan Template

END OF STATEMENT OF WORK

Embassy Bangui, Central African Republic

UNCLASSIFIED 22

File details come from the government source that posted it. Updated .