SOW Construction 657-21-702JC.pdf

PDF 80 KB Posted

Attached to
Y1DZ--657-21-702JC EHRM Training and Admin Space Construction - St Louis VAMC - John Cochran
Solicitation number
36C77622B0056
Issued by

About this file

This scope of work document outlines a construction project at the VA St. Louis Health Care System. The project involves renovating and constructing new training and administrative spaces totaling 2,077 square feet on the first floor of Building 2. Renovation work includes demolishing portions of existing spaces, upgrading two training rooms with audiovisual equipment, and renovating offices and a data closet. New construction comprises three new classrooms of approximately 480 square feet each, a new storage space, an electrical space, and reconfiguring two restrooms into a single unisex restroom. Exterior work involves building a permanent canopy over existing accessible ramps and a temporary canopy connecting to an existing awning. The related federal contract opportunity is a sealed bid construction solicitation issued by the VA Technology Acquisition Center Austin under solicitation number 36C77622B0056 for the EHRM Training and Administrative Support Space project at the John J Cochran Division of the Saint Louis VAMC.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA St. Louis Health Care System

Scope of Work: 657-21-702JC EHRM Training and Admin Space Support – John Cochran

9 May 2022

Scope of Work:

The construction area consists of first floor training and admin space in Building 2. The project will include demolishing and renovation of 2,077 square feet of existing space in the western portion of Building, provide renovation to existing training rooms, hallway, 1 breakroom, 1 data closet, 2 offices, and improve exterior access. New construction includes:

• Reconfiguring existing two restrooms into a single unisex restroom in the northwest corner, three new classrooms approximately 480 square feet each, one new storage space approximately 68 square feet, and an electrical space approximately 33 square feet; existing south stair and a portion of the stage will be demolished and a new stair will be provided.

• Renovation of existing space includes integrated audio/visual equipment, flush-mounted floor ports for data and power in the existing training classrooms in the norther portion of Building 2. Provide light renovation of existing offices. Provide reconfiguration and renovation of existing data closet to meet new EHRM standards.

• A new permanent canopy will be constructed to cover the existing accessible ramps at the northwest corner of Building 2, a temporary canopy will be constructed to tie into the existing awning west of Building 2.