This is a Statement of Work for the Federal Aviation Administration's procurement of ASR-8 Weather Path Kit conversion kits to support modifications to Air Traffic Control Beacon Interrogator systems at Airport Surveillance Radar facilities.
The FAA requires the contractor to fabricate and deliver conversion kits that add an additional signal path to existing rotary joints to accommodate Weather Signal transmission, enabling compatibility with the Radar System Replacement Program architecture. The scope includes two contract line items: CLIN 001 for one first article verification unit and CLIN 002 as an option to purchase up to thirty-nine production units upon first article approval. The first article unit must be delivered no later than ninety days after receipt of order and must contain all parts listed in Attachment 1 – Parts List. The FAA will conduct visual inspection within thirty days to accept or reject the first article. Once approved, the contractor becomes an approved source for production units, with delivery of all thirty-nine production units required no later than 180 days after notification of first article approval. The contractor must furnish all labor, facilities, equipment, and materials required for kit fabrication. Preservation, packaging, and packing must comply with Provision 61. The Contracting Officer's Representative is Brandon Brumley from the Radar Technical and Program Support Branch.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ASR-8 Weather Kit - Parts List.xlsx | XLSX spreadsheet | |
| 6973GH-26-Q-00130.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Procurement of ASR-8 Weather Path Kit
1. BACKGROUND
The Federal Aviation Administration (FAA) has identified a requirement to procure conversion kits to support modifications to the Air Traffic Control Beacon Interrogator (ATCBI-5) configuration at Airport Surveillance Radar Model 8 (ASR-8) facilities as part of the Brand-New Air Traffic Control System (BNATCS) implementation under the Radar System Replacement (RSR) Program.
The rotary joints currently installed at ASR-8/ATCBI-5 sites do not provide the number of signal paths required to support integration with the RSR architecture. To achieve compatibility, the existing rotary joints must be converted to the configuration utilized at ASR-8 sites equipped with the Mode Select Beacon System (Mode-S). This conversion requires the installation of a kit developed by AJW-1433, which adds an additional signal path to accommodate Weather Signal transmission through the rotary joint.
2. CONTRACTING OFFICER’S REPRESENTATIVE (COR):
The COR formally designated this responsibility by the Contracting Officer to provide direction and Government oversight to the contractor on matters related to this contract. The COR is:
Brandon Brumley AJW-L910, Radar Technical and Program Support Branch
3. SCOPE OF WORK
The contractor must furnish all labor, facilities, equipment, and materials to fabricate a kit as outlined in each section that follows.
A. CLIN 001 – One (1) First Article Unit B. CLIN 002 – Option to purchase up to thirty-nine (39) Production Units after first article approval
4. REQUIREMENTS
4.1 Design, Construction, and Testing
The contractor shall procure and package the parts listed in Attachment 1 – Parts List into a Kit.
4.2 First Article Unit Delivery
Contractor must deliver one verification unit. Delivery shall occur no later than (NLT) ninety (90) days at receipt of order
(ARO).
4.3 Verification Unit Analysis
Upon receipt of first article unit, FAA shall perform visual inspection to determine conformance to Attachment 1 – Parts List. FAA will have 30 days to accept or reject first articles.
4.4 Production Units
Once approval is provided for the first article unit, the contractor shall be considered an approved source of production units. The number of units for production is thirty-nine (39). Delivery of production units shall occur NLT 180 days after notification of First Article Approval.
5. PREPARATION FOR DELIVERY
5.1 Preservation, Packaging, and Packing
Preservation, packaging, and packing shall be IAW Provision 61.