SOW and Specifications.pdf
PDF 3 MB Posted
- Solicitation number
- 36C25026B0034
About this file
This is a Statement of Work and comprehensive specification package for roof replacement at the Chillicothe VA Medical Center. The project involves complete removal of the existing 10-year-old EPDM roofing system on the B31 SPS Addition and installation of a new fully-adhered EPDM roofing system with tapered polyisocyanurate insulation. The scope encompasses demolition of existing membrane, insulation, and flashings down to the structural concrete deck; inspection and repair of the deck; installation of new tapered insulation with proper drainage slopes; application of 60-mil reinforced EPDM membrane; installation of new metal flashing and roof accessories; temporary removal and reinstallation of the existing lightning protection system; and site cleanup and restoration. The work must be completed within a 75-calendar-day performance period and includes all required submittals.
The project specifications mandate strict compliance with OSHA regulations (29 CFR 1910 and 1926), EM 385-1-1 safety standards, NFPA codes, and the National Roofing Contractors Association manual. Contractor responsibilities include providing a certified Competent Person with construction safety experience; developing and submitting a detailed Accident Prevention Plan; conducting Activity Hazard Analyses for each work phase; maintaining daily safety inspections; implementing HEPA filtration dust control measures; providing TB screening documentation for all workers; maintaining infection control protocols in the occupied medical facility; and submitting monthly health and safety performance reports. The contract includes a five-year extended warranty on all roofing work beyond standard FAR warranty requirements. Key submittals required prior to work commencement include shop drawings, product data, construction schedules, safety plans, and manufacturer certifications. Carlisle Sure-Seal 60-mil EPDM or equivalent is specified for the membrane, with polyisocyanurate tapered insulation meeting R-33 overall thermal performance. All work must maintain the medical center's 24/7 operational status with coordinated scheduling to minimize service interruptions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 538-26-202 Site-Visit Sign-in Sheet.pdf | ||
| 36C25026B0034_0001.docx | DOCX document | |
| 538-26-202 RFI Tracker as of 20260413.docx | DOCX document | |
| 36C25026B0034_1.docx | DOCX document | |
| Wage Rates - OH20260053.pdf | ||
| Drawings.pdf | ||
| PDAT - Contractor.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
538-26-202 Replaced Failed Roof, B31 SPS Addition
1.0 Project overview
1.1. Purpose: The existing EPDM roof on the B31 SPS Addition is failing. Please see the attached report from RDA Architects dated September 22nd, 2025. From the report, it appears the adhesion between the bottom layer of insulation and the existing concrete deck has failed. Core samples indicate less than manufacturers recommendations for adhesive. Other potential factors are identified as well such as possible inadequate “weighting” of the insulation during curing and checking the air seal at all roof penetrations. See attached report.
The Contractor will provide all supervision, labor, materials, tools, and equipment necessary for the complete removal of the existing EPDM roofing system and the installation of a new EPDM roofing system in accordance with the plans and specifications. All work will be performed in a professional manner, adhering to industry standards, manufacturer specifications, and all applicable local, state, and federal building codes.
1.2. Project location: B31 SPS Addition, Chillicothe VA Medical Center, 17273 State Route 104, Chillicothe Ohio 45601.
1.3. Project start and completion: Period of Performance will be 75 calendar days. This time includes all required submittals.
2.0 Scope of work
2.1. Contractor responsibilities:
• General Requirements: The Chillicothe VA Medical Center campus is smoke free.
No smoking is permitted on the campus. Abusive language will not be tolerated and could result in removal from the Medical Center. See specification section 01 00 00 (General Requirements).
• Submittals: Contractor shall provide all submittals to Planning and Design department. Submittals required include the project schedule, product submittals and construction safety plan. Please see contract documents for requirements.
• Site protection: Implement measures to protect the building, surrounding property, landscaping, and all other structures from damage during the project.
Install 6’ high temporary fencing to enclose lay-down yard. Contractor to maintain this work area by keeping it clear from weeds and trash.
• Construction Safety: All work shall comply with the requirements in Specification Section 01 35 26 (Safety Requirements), OSHA 1910 and OSHA 1926.
• Demolition and removal:
o Remove and legally dispose of the existing EPDM membrane, flashings, counter-flashings, insulation, drain covers, coping and any other associated roofing materials down to the structural deck.
o Clean all debris from the roof surface.
• Deck inspection and repair:
o Inspect the exposed structural roof deck for any signs of deterioration, water saturation, or damage.
o Replace any damaged or compromised decking material to ensure a structurally sound surface for the new roof installation. Any necessary deck replacement will be completed at a pre-approved cost. Seal around all roof penetrations to eliminate any air leakage as identified in the attached roof assessment report.
• New roof system installation:
o Provide and install new tapered polyisocyanurate insulation to ensure proper positive drainage across 100% of the roof surface. Slope ¼” per foot from high points to internal roof drains. Mechanically fasten the first layer to the existing concrete deck. Use fully adhered methods after that.
o Provide and install a new [60-mil] reinforced EPDM membrane system, fully adhered to the new insulation.
o Install all associated accessories, including new drip edges, termination bars, fasteners, and sealants, in strict accordance with the manufacturer's installation instructions.
o Furnish and install new EPDM manufacturer-approved pipe boots, collars, and pitch pockets for all roof penetrations.
• Roof accessories:
o Install new metal flashing, counter-flashing and wall coping as required.
o Install retrofit drain assemblies on all existing roof drains.
o Ensure all flashings and accessories are installed to be watertight.
• Site cleanup:
o Clean up and remove all construction debris from the job site on a daily basis.
o Ensure the site is returned to its original condition upon project completion.
3.0 Materials
• Primary membrane:
Carlisle Sure-Seal 60-mil Reinforced EPDM or equivalent. See specification section 07 53 23 for product characteristics.
• Insulation: [Polyisocyanurate (ISO) tapered insulation]
See specification section 07 22 00 for product characteristics.
• Flashings and sealants: [flashings]
See specification section 07 60 00 for product characteristics.
• Lightning Protection: Contractor to temporarily remove and re-install the lightning protection. Please see attached approved submittal from the project that installed it originally.
4.0 Deliverables
Upon project completion, the Contractor will provide the following:
• A fully installed and watertight EPDM roofing system (fully adhered).
• Manufacturer's labor and material warranty.
• A fully cleaned work site, free of debris and restored.
• Confirmation of manufacturer’s warranty.
• Re-certify the Lightning Protection per specification section 26 41 00.
5.0 Warranties
• Roofing work subject to the terms of the Article “Warranty of Construction”, FAR clause 52.246-21, except extend the warranty period to five years.
September 22, 2025
Brian Merriman, PE Healthcare Engineer, Planning and Design Chillicothe VA Medical Center 17273 State Route 104 Chillicothe, OH 45601
ROOF CONDITION ASSESSMENT REPORT
CHILLICOTHE VA
BUILDING 31 – SPD ADDITION
INTRODUCTION
RDA Group Architects [RDA] visited the SPD Addition Roof at Building 31 on the Chillicothe VA Campus on September 19, 2025 to review the existing conditions related to the roof system building enclosure components.
RDA was engaged by the VA to provide an assessment of the existing conditions, specifically related to the roof system deficiencies where the roof system has become loose and detached from the structure. RDA will provide a short and long term forecast for the anticipated repair and/or replacement work that will be required due to the conditions. This report is the result of the field investigation.
BACKGROUND
The SPD Addition was constructed approximately 10 years ago. It is a 1-story addition with medical uses within the space. The addition is located at the north side of the existing building.
The building is a protected steel structure with metal framed walls. The roof deck is a metal deck with concrete topping over [designed for a future second floor]. The roof system is original to the building.
ROOF SYSTEM DESCRIPTION
The addition generally contains [2] roof areas as outlined on the below roof sketch. There is a total of approximately 12,500 SF of roof among all [2] areas. Refer to the roof key plan below for identification of the roof areas.
RDA cored the existing roof system as part of the investigative work. The roof composition is generally as follows [listed from top to bottom]:
• 60 mil EPDM roof membrane [fully adhered]
• Tapered polyisocyanurate insulation [set in low rise foam adhesive]
• Concrete roof deck [flat – no slope]
RDA was able to review the original building drawings and roofing submittals as part of our investigation. Generally, it appears that the building was constructed as designed. The roof system installed is Carlisle, and currently under warranty per information received from RDA.
The roof is accessed from the penthouse at the adjacent portion of the building.
The roof areas ‘A’ and ‘B’ are bound by parapet walls at all sides.
The parapet walls are 18” to 24” in height, framed with metal stud framing, and capped with a metal coping. The roof system extends up and over the top of the parapet wall and is terminated at the exterior face of the parapet under the coping.
Primary roof drainage is via internal roof drains. The roof slopes via tapered insulation in two directions with tapered insulation saddles between the roof drains / along drain lines. Secondary [overflow] roof drainage is via scupper openings in the parapet walls. RDA did not verify adequacy of the drainage systems as part of this condition assessment. It is assumed that the drainage is properly sized for the respective roof area.
RDA inquired with the building facilities representative, Trent Vartorella, who indicated that there have been no leak issues with the roof. It should be noted that considering the construction of the building, it is possible for there to be water intrusion issues that may go undetected inside of the building.
OBSERVATIONS / ROOF CONDITIONS
1. The primary purpose for the roof condition assessment is to review the obvious displacement of the insulation
/ roof system which are creating displacement of the insulation / raised areas within the roof system.
2. The EPDM membrane itself is generally in good condition considering the issues experienced. It was noted that there are what appear to be air pockets between insulation boards as well as additional mole runs within the field of the roof.
3. RDA cut [4] cores into the existing roof system as part of the investigation. RDA patched the same at the conclusion of the site visit.
3.1. Core #1: The location selected is in an area of displaced roof system. The EPDM membrane was not well adhered to the top layer of insulation / facer [this could be from someone stepping on the roof system with the insulation being able to move, detaching it from the insulation]. There are [3] layers of insulation at this core location, which total approximately 6” in thickness. The insulation was wet / damp to the touch, particularly with the middle layer of insulation. The [3] layers of insulation were still adhered to each other via the low rise foam adhesive. The bottom layer of insulation was detached from the concrete deck with a void of approximately 5”.
3.2. Core #2: The location selected is at an area of intact roof system. The EPDM membrane was adhered to the top layer of insulation / facer. There are [3] layers of insulation at this core location, which total approximately 6” in thickness. The insulation was dry. The [3] layers of insulation were still adhered to each other via the low rise foam adhesive. The bottom layer of insulation was adhered to the concrete deck. No void present below the insulation.
3.3. Core #3: The location selected is in an area of displaced roof system. The EPDM membrane was adhered to the top layer of insulation / facer. There are [2] layers of insulation at this core location, which total approximately 3” in thickness. The insulation was relatively dry, but showed signs of being wet / damp, particularly between the layers of insulation. The [2] layers of insulation were still adhered to each other via the low rise foam adhesive. The bottom layer of insulation was detached from the concrete deck with a void. There was noted positive air flow from within the cavity under the roof insulation.
3.4. Core #4: The location selected is in an area of displaced roof system. The EPDM membrane was adhered to the top layer of insulation / facer. There are [2] layers of insulation at this core location, which total approximately 3” in thickness. The insulation was wet / damp to the touch, particularly at the bottom layer adjacent to the concrete deck. The [2] layers of insulation were still adhered to each other via the low rise foam adhesive. The bottom layer of insulation was detached from the concrete deck with a void. There was noted positive air flow from within the cavity under the roof insulation.
4. The bond failure between the concrete deck and the insulation is resulting in the insulation being raised off the deck. This is impacting the ability of the roof to drain properly.
5. It was noted that the areas of failure appear to be located adjacent to the primary roof drains, emanating from the drain out either side of the drain in the direction of the primary tapered insulation slope. This condition is evident at each roof drain to varying extents.
6. The roof contains a lightning protection system with lightning rod aerials located on the parapet walls and grounding leads into the building through the roof system.
PHOTOGRAPHS
01 – Overview of roof ‘A’ 02 – Overview of roof ‘B’
03 – Typical failure area 04 – Typical failure area
05 – Typical failure area 06 – Core #1
07 – Core #1 08 – Core #1
09 – Core #2 10 – Core #2
11 – Core #3 12 – Core #4
RECOMMENDATIONS / SUMMARY
Generally, a fully adhered EPDM roof system should last in excess of 20 years. The roof is currently approximately 10 years old and is at the point of failure within the roof system itself, not necessarily the actual EPDM membrane. These failures are impacting and shortening the service life. The current roof conditions leave the roof at risk of failure during an extreme wind event as the insulation is no longer attached to the concrete roof deck in multiple areas. Additionally, the roof system warranty that is currently in place with Carlisle is a leak warranty. Since there have not been leaks into the building, the warranty has not come into play.
RDA believes that the failures could be a result of the quality of the original bond between the concrete deck and the first layer of insulation. RDA cannot confirm the temperature / weather conditions [50 degrees and rising] at the time of original installation; the conditions of the concrete deck [temperature, relative humidity, etc.]; if the insulation was properly weighted in place during the cure time of the adhesive [which varies based upon the temperature / humidity, etc.]. RDA only observed [1] bead of adhesive at the roof deck at Core #1, and it appeared less than the 1/2" to 3/4” wide spacing recommended by the manufacturer. It appears that there is positive pressure within the building which may be the root cause for the failures. Two of the cores taken had positive air flow from within the cavity. There are not but a couple of penetrations on the roof with the exception of the roof drains. The failures generally emanate from the proximity of the roof drains outward into the roof system. It is likely that the original bond between the concrete and the first layer of insulation was compromised by weather, proper adhesive application rates and spacing, lack of proper weighting of the insulation during curing thereby weakening that bond from the start.
RDA recommends replacement of the roof system in its entirety. The bond of the adhesive is deficient between the concrete deck and the bottom layer of insulation in multiple locations [at areas of failure]. The only way to effectively address this issue is to remove all layers of the insulation to the deck and start with new. RDA recommends, prior to the roof replacement, evaluating the air seal at the roof drain openings in the roof deck. If the building is under positive pressure [as was noted on-site] and this positive pressure is able to get up and around the roof drains, it could continue to put pressure into the roof insulation, and thereby create the failures exhibited. The approach for the new roof system would be the same with tapered insulation adhered in place and a fully adhered EPDM roof system.
For the short term, additional ballast / weight could be installed over the EPDM membrane to assist in preventing a blow off in an extreme weather / wind event. Considering the building is designed for a future second floor, the additional weight should not pose an issue.
Please contact me if you have any questions regarding this conditions assessment report.
Sincerely, Jonathan Schaaf
PRINCIPAL | SR. PROJECT ARCHITECT
RA | LEED AP | RRO
538-26-202 REPLACE FAILED ROOFING B31 SPS TABLE OF CONTENTS
VAMC CHILLICOTHE, OHIO
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 10 Table of Contents 00 01 15 List of Drawing Sheets
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 01 33 23 Shop Drawings, Product Data, and Samples 11-08 01 35 26 Safety Requirements 01 42 19 Reference Standards 09-11 01 74 19 Construction Waste Management 05-12
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 06-10
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 07 22 00 Roof and Deck Insulation 10-10 07 53 23 Ethylene-Propylene-Diene-Monomer Roofing 10-11 07 60 00 Flashing and Sheet Metal 10-10 07 72 00 Roof Accessories 10-11 07 84 00 Firestopping 10-11 07 92 00 Joint Sealants 12-11
DIVISION 22 – PLUMBING
22 14 00 Facility Storm Drainage – Roof Drains (Reference for Existing)
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 26 41 00 Facility Lightning Protection (Reference for Existing)
538-26-202 REPLACE FAILED ROOFING B31 SPS GENERAL REQUIREMENTS
VAMC CHILLICOTHE, OHIO 01-01-21
01 00 00 - 1
SECTION 01 00 00 GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.01 SAFETY REQUIREMENTS
1.02 GENERAL INTENTION
1.03 STATEMENT OF BID ITEM(S)
1.04 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.05 CONSTRUCTION SECURITY REQUIREMENTS
1.06 OPERATIONS AND STORAGE AREAS
1.07 ALTERATIONS
1.08 DISPOSAL AND RETENTION
1.09 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES,
AND IMPROVEMENTS (FAR 52.236-9)
1.10 RESTORATION
1.11 NOT APPLICABLE
1.12 NOT APPLICABLE
1.13 NOT APPLICABLE
1.14 AS-BUILT DRAWINGS
1.15 NOT APPLICABLE
1.16 USE OF ROADWAYS
1.17 NOT APPLICABLE
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.19 TEMPORARY USE OF EXISTING ELEVATORS
1.20 NOT APPLICABLE
1.21 TEMPORARY TOILETS
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
1.23 NOT APPLICABLE
1.24 TESTS
1.25 INSTRUCTIONS
1.26 NOT APPLICABLE
1.27 RELOCATED ITEMS
1.28 NOT APPLICABLE
1.29 NOT APPLICABLE
1.30 NOT APPLICABLE
01 00 00 - 2
1.31 NOT APPLICABLE
1.32 NOT APPLICABLE
1.33 HISTORIC PRESERVATION
1.34 NOT APPLICABLE
01 00 00 - 3
PART 1 - GENERAL
1.01 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.02 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the installation of walls, data cabling, electrical devices, architectural finishes, etc. in multiple buildings for 538-26-202 Replace Failed Roofing B31 SPS at VAMC Chillicothe, Ohio as required by drawings and specifications.
B. Visits to the site by Bidders will be as outlined in the solicitation.
C. Not Applicable
D. Not Applicable
E. All employees of the general contractor and subcontractors shall adhere to the Chillicothe VAMC contractor identification process and obtain VA issued badges. All employees of general contractor and subcontractors shall comply with VA security management program, be identified by project and employer, and restricted from unauthorized access.
F. REQUEST FOR INFORMATION
In the event an explanation or interpretation of the drawings or specifications is necessary, submit the request using an approved RFI (Request for Information) Form with the following information (at a minimum):
1. Project title, location and number.
2. Construction contract number
3. Current date
4. RFI Number
5. Specification number that the RFI refers to (if applicable)
6. Drawing sheet number that the RFI refers to (if applicable)
7. RFI question
8. Space for RFI response
9. Line for responder's name and date
Such requests shall be submitted to the Contracting Officer soon enough to allow a reply so as to affect the project as little as possible.
1.03 STATEMENT OF BID ITEM(S)
See Block 10, Standard Form (SF) 1442, and any continuation thereto, for a detailed list of Bid Items.
1.04 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
Drawings and contract documents may be obtained from the website where the solicitation is posted.
Additional copies will be at Contractor's expense.
1.05 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
01 00 00 - 4
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
Refer to section 01 00 02, BADGING, INFORMATION SECURITY, PRIVACY, HISTORIC PRESERVATION, AND PARKING PERMIT REQUIREMENTS for badging requirements.
2. Not Applicable
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
Patients and staff are not to be photographed at any time.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Not Applicable Guards:
D. Key Control:
1. Any keys necessary to gain entry to work areas or other spaces associated with performing work will be issued to the Contractor's representative in accordance with the exhibit Standard Operating Procedure (SOP) 41 Contractor Key Control. In accordance with Facilities Management Service, Engineering Section Standard Operating Procedure 41, there is a $500 per key charge for unreturned keys at project completion. The method of collection of fines is at the Government’s discretion. Fines for unreturned keys may be withheld during project financial closeout or collected via bill of collection to the contractor and/or by other means necessary.
2. The General Contractor shall provide duplicate keys and lock combinations to the Contracting Officers Representative (COR) for the purpose of security inspections of every area of the project and parked machines and to take any emergency action.
E. Not Applicable
F. Motor Vehicle Restrictions
Reference Chillicothe VAMC Policy Memorandum No. 07-29, Parking and Motor Vehicle Operations, and Designated Parking for Contractors and Contractor Employees exhibit. Refer to section 01 00
02, BADGING, INFORMATION SECURITY, PRIVACY, HISTORIC PRESERVATION, AND
PARKING PERMIT REQUIREMENTS for parking permit requirements.
1.06 OPERATIONS AND STORAGE AREAS
The following paragraphs are in addition to (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
01 00 00 - 5
No fuel storage tanks are acceptable for contractor staging areas.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, roads, or lawn areas.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by the COR.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to COR Contractor. , as follows:
H. All building areas adjacent to this project will be occupied during performance of work.
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period. This may include evening or weekend work.
01 00 00 - 6
I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, six feet minimum height, around the construction area and/or dumpster as indicated on the drawings or required by the COR. Provide gates as required for access with necessary hardware, including hasps, padlocks, heavy duty gate wheels, etc. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade.
Details of fence construction and finish thereof shall be submitted to COR for approval. Remove the fence when directed by COR.
J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements with the COR for pre inspection of site with Chillicothe VAMC Fire Department who is required to respond to an alarm from Contractor's employee or watchman.
K. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR.
Such approval will be confirmed in writing as soon as practical.
6. Not Applicable.
7. Access to Data Rooms requires escorts at all times. Access requests must be requested in writing a minimum of 7 days in advance of the proposed dates of work. Requests shall state reason, date, exact time of, and approximate duration of such work activity.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and
01 00 00 - 7 sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Parking will be limited adjacent to B31 SPS Addition. Contractor’s employees will have to use the stadium parking lot.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the Resident Engineer COR.
3. Impacts to roads, walks and entrances to grounds, to parking and to occupied areas of buildings shall require contractor provided signage indicating danger work zone as well as signage for detour routes at points of safe turn off prior to reaching dead ends requiring turn around, or if detour isn’t required and there is a change in the traffic or pedestrian flow signage shall be provided indicating the proper flow. The contractor shall be responsible for adequately marking the construction zone for safety reasons to stop entry to the construction zone, this might include but is not limited to signage, cones, barrels, lights, stanchions, colored tape, partitions, jersey barriers etc. Impacts to roads requires contractor provided traffic control in compliance with the Ohio Department of Transportation Guidelines for Traffic Control in Work Zones. Submit in accordance with Specification Section 01 33 23 work plans including signage, safety measures, and traffic control plans to the COR for approval for all detour and change in pedestrian or vehicular traffic affecting roads, walks, and entrances.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF
ROADWAYS.
O. Not Applicable
P. Hours of Work:
1. The work of this contract is to be executed between 7:30 a.m. and 4:00 p.m., Monday through Friday, except as required by the specifications and/or otherwise authorized by the COR. No work will be performed on Government recognized holidays, or weekends except as required by the specifications and/or otherwise authorized by the COR.
2. Submit in writing to the COR requests for proposed hours of work changes.
3. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapse in operations occur. See section 1.06G Phasing for additional requirements. Work hours interrupting service or utilities shall be scheduled at times convenient to the Medical Center and least impactful to the government. Due to the operations being 24 hours a day 7 days a week acceptable scheduled service interruption times may vary and be any time of day depending on the location and impact of the interruption.
4. Hours of work may vary depending on the area of work being performed. Work in occupied spaces shall be scheduled at times convenient to the occupant and the Medical Center.
5. Hot work shall stop prior to the specified end of work day at a minimum equal to the time required for final inspection.
01 00 00 - 8
1.07 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, to the Contracting Officer.
1. Existing condition of items required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in the opinion of the COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and
VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
4. Dampen debris to keep down dust.
5. Provide temporary construction partitions as described in Specification Section 01 35 26 paragraph Temporary Construction Partitions.
6. Block off ducts and diffusers to prevent circulation of dust into occupied areas during construction. Coordinate with COR.
7. See Specification Section 01 35 26 paragraph Infection Control for additional required measures.
1.08 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
01 00 00 - 9
1. Reserved items which are to remain property of the Government are identified by attached tags as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re installation and reuse.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be relocated, reused, or demolished will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
4. Not Applicable
1.09 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (FAR 52.236-9)
The following paragraph is in addition to FAR 52.236-9 Clause PROTECTION OF EXISTING
VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Not Applicable
D. Not Applicable
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
01 00 00 - 10
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 NOT APPLICABLE
1.12 NOT APPLICABLE
1.13 NOT APPLICABLE
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain One full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 NOT APPLICABLE
1.16 USE OF ROADWAYS
For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.17 NOT APPLICABLE
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new permanently installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2020 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be
01 00 00 - 11 thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use;
maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired to new condition with the original manufacturer’s parts and certified by a manufacturer’s technical representative or replaced by the contractor at the contractor’s expense.
1.19 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators. The COR will ascertain that elevators are in proper condition.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
1.20 NOT APPLICABLE
1.21 TEMPORARY TOILETS
Contractor shall provide (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge. Failure to stop leakage or other waste will be cause for revocation (at COR's discretion).
B. Not Applicable.
C. Not Applicable.
01 00 00 - 12
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Temporary heating plans must be approved by the Chillicothe VAMC Fire Department; refer to Specification Section 01 35 26 Safety Requirements. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating or steam distribution system.
2. Steam is available at no cost to Contractor. Contractor shall ensure steam is delivered to condensate return system.
3. Maintain connections, pipe, fittings and fixtures and conserve steam-use so none is wasted.
Failure to stop leakage or other waste will be cause for revocation (at COR's discretion), of use of steam from the Medical Center's system
4. Contractor is responsible for providing all necessary equipment, including pressure reduction, temperature control, condensate collection, and safety related equipment.
5. The Government will not extend or modify the system for the use of the contractor.
6. Contractor is responsible for coordinating alternate methods of heating when outages are required for work on steam system.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
Obtain electricity by connecting to the Medical Center electrical distribution system.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. For connection to hose bibs a vacuum breaker shall be used. In freezing conditions when the water source is not in use the vacuum breaker shall be removed. Water is available at no cost to the Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted.
Failure to stop leakage or other wastes will be cause for revocation (at COR’s discretion) of use of water from Medical Center's system.
1.23 NOT APPLICABLE
1.24 TESTS
A. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre tested.
B. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
C. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed.