SOW - 91st Paint booth.docx

DOCX document 5 MB Posted

Attached to
Paint Barn
Solicitation number
F3CTMG5120AW01
Issued by

About this file

This Statement of Work (SOW) details the requirements for removing and installing a new paint booth for the 91st Missile Maintenance Squadron at Minot Air Force Base in North Dakota. The project involves procuring and installing a paint booth with specific technical specifications, including interior dimensions of 14'1" wide x 9' high x 24' long, dual-skinned doors with windows, a 30" tube-axial exhaust fan with 20,000 CFM capacity, a natural gas-fired heater unit with spray and cure capabilities, and a three-stage filtered intake and exhaust system.

The project must be completed within 120 days of contract award, with work performed Monday through Thursday from 0700-1600 hours. Contractors must obtain base access through an Entry Authority Letter and pass a background check, entering through the South Gate. The paint booth will support corrosion control operations for ICBM missile system support equipment. The government points of contact are Michael LaBonte, Greg Wiggins, and William Bray, all from the Corrosion Control Section, and the solicitation is issued by the Department of the Air Force Global Strike Command under solicitation number F3CTMG5120AW01.

View the file

Other files

File Type Posted
Paint Barn Q and A.docx DOCX document
Paint Barn Q and A.docx DOCX document
Combo-Paint Barn-Final.pdf PDF
MFR Site Visits - Paint Barn.pdf PDF
Combo-Paint Barn-Final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK FOR

REMOVAL AND INSTALLATION OF PAINT BOOTH FOR 91 MMXS/MXSFC

537 Bomber Blvd, Bldg 537, Minot AFB, ND 58705

1.0 Background

This Statement of Work (SOW) describes the installation requirements for a new paint booth to be installed for 91 MMXS/MXSFC section located at 537 Bomber Blvd, Bldg 537, Minot AFB, ND 58705

2.0 Scope

This contract effort is to provide and install a new paint booth in the 91 MMXS/MXSFC section of bldg. 537. Heated outside air shall enter through the top of the booth using a booth-mounted heater unit. Air shall be filtered through a filtered plenum in the booth ceiling. Air shall exit booth through the existing filtered exhaust in the ceiling. All booth panels shall be at a minimum of 18-gauge galvanized steel with 2” flanges. All panels shall be nut/bolt assembled. All assembly hardware shall be provided by installer.

Prior to the removal of existing booth, the contractor shall be responsible for the disconnection of the existing gas lines, fire suppression system and all electrical hookups.

Upon turnover the new booth must be in full working order and all gas lines, fire suppression systems and all electrical hookups shall be reconnected and functioning.

Booth Dimensions

I.D. 14’ 1” wide x 9’ high x 24’ long O.D 15’ 8.25’ wide x 10’5” high x 24’6.25” long Variations in final dimensions are authorized to accommodate engineering considerations with prior coordination and approval from requesting unit to ensure it will fit the desired location and accommodate the vehicles at Minot AFB.

Booth doors

Main door dimensions are 10’ long (2 bi-fold doors are 4’ 11.5” wide) barn door or bi-fold doors are acceptable. Doors shall be dual skinned with one window on each door. Man access door shall be located on left hand side of booth side wall. Door dimension 3’ x 7’ tall. Each personnel door shall have a window and be dual skinned.

Exhaust System

Exhaust fan 30” Tube-axial fan. The motor shall be 460Volt 3 Phase type with a minimum capacity of 20,000 CFM. The Duct Velocity must be at least 2,000 fpm (Feet Per Minute). For area up to 4 ft squared the required acfm (Actual Cubic Feet per Minute) is 200. For an area above 4ft squared the required acfm is 150. There must be 12 inches of clearance on each side of the worker and above the worker (Length and Width excluding the workers immediate workspace). Horizontal airflow is perfectly fine however, depending on positioning we may need to address how the worker is spraying to reduce exposure.

Intake and exhaust air shall be filtered (3-stage) using appropriate industry standard filter material.

Booth Heater

Heater unit shall be indoors, atop booth with downward discharge unit with spray and cure cycle capabilities. Heater shall be natural- gas fired unit with adequate BTU to assure proper booth working temps throughout the range of regularly occurring ambient temps.

Spray System

Must have adjustable magna-helic gauges for reading/adjusting static pressure

3.0 Objectives

The new paint booth will be installed to continue to perform painting operations to support corrosion control of all ICBM missile system support equipment

4.0 Task Requirement

4.1 Tasks

Measurement of this application area can be provided by the government POC’s found in section 11.

It is the vendor’s responsibility to ensure the product dimensions are complied with if required prior to manufacture of the paint booth to assure area is in compliance with requirements. Local codes and product restrictions are to be verified by the End User prior to order from vendor. Substitutions and/or deviation from these specifications and/or drawings submitted must be itemized and in writing with detailed product drawings indicating each deviation from this specification along with each bid.

4.2 Requirements

Required to meet OSHA requirements, reference https://www.osha.gov/

5.0 Government Furnished Property – Equipment

5.1 While on site to support the paint booth installation requirements, the contractor may use power, water, and restroom facilities while operating within the work areas of bldg. 537.

5.2 Laydown/Storage Area – Please coordinate with the Site POC for storage area or laydown area as needed.

6.0 Security Requirements – Base/Site Access

All commercial vehicles are required to enter Minot AFB through the South Gate, just off US-83. This includes construction, food, supply, FedEx, and UPS deliveries, as well as contractors entering with company trucks. Hours of operation for the main gate are 0600-1800. In order to obtain a pass, contractors will have to submit information required for an Entry Authority Letter (EAL) to include, but may not be limited to: Full name, SSN, Date of Birth, and driver’s license number and state of issue. As of now, the REAL ID Act affects state-issued identification card or driver’s license holders from Missouri, Minnesota, Maine, and Montana. Individuals from these State are no longer able to access Minot AFB unescorted with only a state-issued identification card or driver’s license. A background check of each contract employee will be conducted utilizing the National Crime Information Center (NCIC) system. Badges will only be issued to those contractors who pass this background check.

7.0 Place of Performance

Mailing Address:

91 MMXS/MXSFC

537 Bomber Blvd, Bldg 537 Ste 215 Minot AFB, ND 58705

8.0 Period of Performance

The project must be completed within 120 days from contract award including the completion of the installation & removal of the existing system.

9.0 Hours of Work

Work on this project shall be accomplished during the following times, except legal holidays and AFGSC down days. Once the period of work is determined, POC can provide a list of the aforementioned days.

Monday 0700-1600 Tuesday 0700-1600 Wednesday 0700-1600 Thursday 0700-1600

Any work desired to be accomplished during other than the posted hours will require prior approval of the Contracting Officer & Site POC. The Contractor must submit a written request to the Contracting Officer no later than the preceding Wednesday of the current work week.

Contractor work requiring shutting down facility power will need to be coordinated with facility POCs in advance of requested power outage. Although not anticipated with this project, in cases where power outage requests may affect critical functions affecting the facility’s primary mission systems, power outage requests are required 1 day in advance due to critical operations within the building areas.

It should be noted that the Contractor’s performance may be interrupted from time to time because of high priority mission schedules or no-notice events. For each calendar day and/or portion of a calendar day that the Contractor is removed/denied access from the job site, the contractor schedule will be adjusted by one calendar day.

Base Closure:

The Government may stop or delay work at Minot AFB due to weather, exercises, or mission necessities. This requirement is not considered mission essential. The Contractor is not expected to continue work during weather emergencies. The Contractor must listen to local radio, television, or other alerting systems to learn the condition of the base. When applicable the Government will let the Contractor know of the delay.

US-83 between the town of Minot and Minot AFB is prone to road closures during inclement weather.

Work scheduled but not carried out because of base closure due to weather, exercises, or mission necessities must begin as soon as possible after the base reopens, unless otherwise directed by the Government.

If weather, exercises, or mission necessities delay Contractor work, the Contractor must let the Government know of the consequence of the delay as soon as possible.

10.0 Federal Holidays

No work is authorized on Federal Holidays. The following Federal Holidays are normally observed by Government personnel:

New Year’s Day, Martin Luther King’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day, and any other day designated by Federal Statute, Executive Order, and/or Presidential Proclamation.

11.0 Site Project Managers (POC)

Mr. Michael LaBonte Job Title: Supervisor, Corrosion Control Section Phone: (701) 723-4906 E-mail: michael.labonte.2@us.af.mil

Mr. Greg Wiggins Job Title: Maintenance Mechanic Phone: (701) 723-4906 Email: gregory.wiggins.2@us.af.mil

Mr. William Bray Job Title: Maintenance Mechanic Work Leader Telephone: (701) 723-4906 E-mail: william.bray.4@us.af.mil

12.0 Clean Up

The Contractor is required to clean up daily, remove all debris from installation project from the base and to maintain a safe working area at all times. The contractor will remove and dispose of the old shelving

13.0 Training

The Contractor is required to provide initial training on proper use of paint booth operation upon completion of installation.

14.0 Attached Map Images – Project Location

91 MMXS/MXSFC

image4.jpeg image5.jpeg image6.jpeg image1.png image2.jpeg image3.jpeg

File details come from the government source that posted it. Updated .