SOW - 25Z6AH2.pdf
PDF 821 KB Posted
- Solicitation number
- 25Z6AH2
About this file
This is a Statement of Work (SOW) for emergency repair of fire detection and suppression systems at the Federal Bureau of Prisons' Federal Detention Center (FDC) SeaTac in SeaTac, Washington. The document was approved by FMB-CERS on February 10, 2026.
The contractor must provide all materials, equipment, and labor to identify and repair fire detection and suppression devices, parts, and components at the facility. Work scope includes replacement of 128 itemized sprinkler heads across various institutional locations (kitchen, cell blocks, medical areas, education facilities, and administrative offices) and mechanical/fire alarm system repairs including missing escutcheons, failing air maintenance devices, air pressure relief components, leaking air line valves, failing gauges, deluge system failures, smoke detector failures, elevator recall function issues, fire control panel system troubles, and waterflow switch failures. The contractor must perform comprehensive system-wide testing per NFPA 13, 20, 25, and 72 standards and deliver final documentation including Fire Alarm System Record of Completion/Test Reports, Fire Pump Performance Test Reports, and Sprinkler System Inspection, Testing, and Maintenance Reports. All work must comply with International Building Code, National Electrical Code, NFPA standards, OSHA requirements, and American Correctional Association Standards. The contractor is responsible for obtaining permitting, site assessment, constraint identification, and providing mitigation plans for any identified constraints.
Work hours are 6:00 AM–2:00 PM, Monday through Friday, excluding weekends and federal holidays. Contractor personnel must pass Federal Bureau of Prisons security clearance requirements, including NCIC background checks, and comply with strict facility rules including no contraband, tobacco prohibition except in designated outdoor areas, and restrictions on wearing green or khaki clothing. The contractor must submit all required documentation including shop drawings and product data within 15 days of Notice to Proceed, provide three copies of Material Safety Data Sheets, maintain daily tool inventories, and ensure proper worksite housekeeping and debris disposal in compliance with federal, state, and local regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Period of Performance 25Z6AH2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEDERAL BUREAU OF PRISONS
FDC SeaTac Project # 25Z6AH2 Emergency Repair Fire Detection and Suppression
STATEMENT OF WORK
I. SPECIFICATIONS:
A. INTRODUCTION
1. The Federal Bureau of Prisons (FBOP), Federal Detention SeaTac, intends to make a single award to a responsible entity to provide all necessary materials, equipment, and incidental labor to identify and perform all the necessary repairs of Fire Detection and Suppression devices, parts and components at FDC SeaTac 2425 S. 200th Street, SeaTac, WA. It is the Contractor’s responsibility to obtain permitting, should it be required.
2.
availability for review and approval. The government reserves the right to determine if the product is equal
3. The contractor and subcontractors must be reputable and possess a valid, current contracting license. If competency in performing the work. Such proof must be
4. All work and materials must comply with applicable local, state, and federal codes, including the latest editions of the International Building Code, National Plumbing Code, National Electrical Code, NFPA, Life Safety Code, OSHA, American Correctional Association Standards, and other relevant regulations. In addition, all work shall be performed in accordance with industry best practices, ensuring high-quality craftsmanship, durability, and safety.
B. SCOPE OF WORK
B.1 Constraints and Site Assessment 1.
commencement of work to verify the itemized work, identify any physical, environmental, or operational
2.
of discovery.
3.
B.2 System Testing and Project Closeout
1.
comprehensive system-wide testing to ensure full operational readiness and compliance with the 2023/2026 editions of NFPA 13, 20, 25, and 72.
2.
a.
b.
c.
d.
B.3 Itemized Work
1. Contractor is not responsible for the repair of pre-repair options and associated costs. F and coverage warranties.
2. This scope includes the replacement of all broken sprinkler heads (All institutional pendants, 1 upright, all Sprinkler) discovered during the initial site walkthrough. Any repairs
B.3.1 Sprinkler Head & Device Replace Log and their Locations:
Item # Location / Area Quantity Replace Type / Note
1 Kitchen (by Ice Maker) 1 Sprinkler Head
2 Kitchen Freight Elevator (Front) 1 Sprinkler Head
3 -down Door) 2 Sprinkler Heads (Outside)
4 -down Door 1 Sprinkler Head
5 1 Sprinkler Head
6 Kitchen Entrance 2 Sprinkler Heads
7 Outside CC7H03 1 Sprinkler Head
8 Mop Closet by CC7H03 1 Sprinkler Head
9 Powerhouse Fire Sprinkler Shut-off 1 Sprinkler Head
10 1 Sprinkler Head
11 ZA Kitchen 3 Sprinkler Heads
12 1 Sprinkler Head
13 Kitchen Stairwell 1 Sprinkler Head
14 2 Sprinkler Heads
15 Hallway by Facilities 6 Sprinkler Heads
16 Elevator Lobby 2 Sprinkler Heads
17 12 Sprinkler Heads
18 Medical Training 5 Sprinkler Heads
19 Stairwell / Stairwell 5 2 Sprinkler Heads
20 SIA Shop 1 Sprinkler Head
21 Outside SIA Shop 2 Sprinkler Heads
22 Loading Doors (Outside) 3 Sprinkler Heads
23 Freight Elevator 2 Sprinkler Heads
24 1 Sprinkler Head
25 Outside Bathroom 1 Sprinkler Head
26 1 Sprinkler Head
27 Discharge (by Fridge) 1 Sprinkler Head
28 Supervisor Mechanical 1 Sprinkler Head
29 Specialist Office (Between) 1 Sprinkler Head
30 Maintenance Shop 1 Sprinkler Head
31 Elevator Lobby (Outside) 1 Sprinkler Head
32 1 Sprinkler Head
33 Cell 2 (Past Lobby) 1 Sprinkler Head
34 Outside AA- 1 Sprinkler Head
35 Outside AA5F01 9 Sprinkler Heads
36 1 Sprinkler Head
37 2 Sprinkler Heads
38 1 Sprinkler Head
39 Outside AA3D01 2 Sprinkler Heads
40 Laundry Entrance 1 Sprinkler Head
41 Outside AB5K01 2 Sprinkler Heads
42 Dental (Outside) 2 Sprinkler Heads
43 1 Sprinkler Head
44 - 1 Sprinkler Head
45 1 Sprinkler Head
46 Outside AB2H02 (3H02) 1 Sprinkler Head
47 Staff Bathroom 1 Sprinkler Head
48 Education (Outside Class) 2 Sprinkler Heads
49 Education Class 4 1 Sprinkler Head
50 Outside B4K01 2 Sprinkler Heads
51 1 Sprinkler Head
52 Office by Stair 4 1 Sprinkler Head
53 2 Sprinkler Heads
54 Affairs Office 1 Sprinkler Head
55 1 Sprinkler Head
56 1 Sprinkler Head
57 2 Sprinkler Heads
58 1 Sprinkler Head
59 Contract Specialist Office 1 Sprinkler Head
60 Elevator Lobby (Outside) 1 Sprinkler Head
61 DA (Outside) 1 Sprinkler Head
62 1 Sprinkler Head
63 Medical Services (Outside) 1 Sprinkler Head
64 DC 6 (Outside) 1 Sprinkler Head
65 1 Sprinkler Head
66 Outside EC (Psychology) 1 Sprinkler Head
67 Service Storage (Mop Closet) 2 Sprinkler Heads
68 2 Sprinkler Heads
69 1 Sprinkler Head
70 ZB Entrance 3 Sprinkler Heads
71 Entrance BB4L01 2 Sprinkler Heads
72 1 Sprinkler Head
73 BA123 1 Sprinkler Head
74 Women's Lockers (Outside) 1 Sprinkler Head
75 2 Sprinkler Heads
76 1 Sprinkler Head
77 1 Sprinkler Head
78 Kitchen Mop Closet 1 Sprinkler Head
79 Bakery 3 Sprinkler Heads
80 Staff Dining Area 1 Sprinkler Head
81 1 Sprinkler Head
82 2 Sprinkler Heads
83 1 Sprinkler Head
84 BA5F01 (Supervisor Mechanical) 1 Sprinkler Head
85 Elevator Lobby 1 Sprinkler Head
86 Education Class 1 1 Sprinkler Head
87 2 Sprinkler Heads
88 ESL Coordinator Office 1 Sprinkler Head
89 Education Classroom 2 2 Sprinkler Heads
90 1 Sprinkler Head
91 2 Sprinkler Heads
92 Visitation Storage (Front Desk) 1 Sprinkler Head
93 2 Sprinkler Heads
94 1 Sprinkler Head
95 1 Sprinkler Head
96 1 Sprinkler Head
97 Warden's Office Kitchen 1 Sprinkler Head
98 2 Sprinkler Heads
99 Staff Dining Area 1 Sprinkler Head
100 Outside CC7H03 1 Sprinkler Head
101 1 Sprinkler Head
102 1 Sprinkler Head
103 1 Sprinkler Head
104 Outside CCM701 1 Sprinkler Head
105 Outside Screen 1 Sprinkler Head
106 1 Sprinkler Head
107 1 Sprinkler Head
108 Mop Closet 1 Sprinkler Head
109 Elevator Lobby 1 Sprinkler Head
110 1 Sprinkler Head
111 Dental Chair 4 1 Sprinkler Head
112 Education Entrance 1 Sprinkler Head
113 ZA Kitchen 1 Sprinkler Head
114 Outside Cell 56 1 Sprinkler (Institutional Head)
115 1 Sprinkler (Institutional Head)
116 Outside Cells 43, 39, 58 3 Sprinkler (Institutional Head)
117 Outside Cells 31, 63 2 Sprinkler (Institutional Head)
118 2nd Floor Showers 3 Sprinkler (Institutional Head)
119 Outside Cells 39, 40, 63 3 Sprinkler (Institutional Head)
120 Psychology 1 Sprinkler (Institutional Head)
121 1 Sprinkler (Institutional Head)
122 Outside Cell 17 1 Sprinkler (Institutional Head)
123 Cells Entrance 1 Sprinkler (Institutional Head)
124 Outside Cells 25, 26, 28, 29, 30, 22, 20 7 Sprinkler (Institutional Head)
125 Outside Cells 26, 25 2 Sprinkler (Institutional Head)
126 Outside Showers 1 Sprinkler (Institutional Head)
127 Outside Cells 30, 29, 18, 13, 11, 8, 7 7 Sprinkler (Institutional Head)
128 2 Incorrect Install
B.3.2 Mechanical & Fire Alarm System Addendum
Item
Location/System Quantity
1 Various 10 Missing Escutcheons:
sprinkler heads.
2 DA, EB, EC, FA, ZA, 6 Failing Air Maintenance Devices (AMD): AMDs require replacement in all listed locations.
3 ZB Stair 4 1 Failing Air Pressure Relief "Popper":
4 Downstream of AMD 1 Leaking Air Line Valve:
5 2 Failing Gauges:
6 Deluge System 1 Deluge System Failure: System is non-operational (converted to conversion to shotgun riser to eliminate failure points and liability risks.
7 Freight Elevator
1 Smoke Detector Failure: Troubleshoot, replace if required and test nonfunctional smoke detector located in room.
8 Freight Elevator
1 Recall Function Failure: Troubleshoot Heat Detector Activation , replacing all defective parts if required. Test Freight proper operation upon Heat Detector Activation
9 Main Elevator Shafts 4 Recall Function Failure: Troubleshoot Heat Detector Activation Main upon Heat Detector Activation.
10 Freight Elevator 1 Missing Recall Function: and test Smoke Detector
- Door in corridor to initiate Freight
Verify all detectors required to operation as per
A17.1 compliance).
11 Main Fire Control
Panel in Control
6 System Troubles: Troubleshoot, repair/replace defective parts in on Main Fire Panel
Strobe Quad C. (2) Elevator Speakers Ca Strobe Quad 23110600
Annunciator Supervision. (6) 0006 Common Trouble Act Smoke Det 1 In addition troubleshoot and repair intermittent occur.
12 DB Dry System 1 13 DC Dry System 1 14 A Level Pre-action
Panel 1 set Failing Batteries:
batteries.
C. UTILITIES AND OTHER FACILITIES
1.
-related equipment and activities. Any additional requirements must be coordinated with
2. Non- -potable water sources for purposes such as cleaning or construction tasks. These sources will be clearly marked and communicated.
Contractors must adhere to site rules and guidelines for the safe use of electricity and non-potable water the standard access provided.
3. -site restroom facilities, which will be clearly marked and communicated to all personnel. If such facilities are unavailable, the contractor will restrooms. These portable restrooms must be placed in a ensuring regular maintenance of these facilities to uphold cleanliness and sanitation standards.
4.
or arrangements beyond the allocated area.
5.
Items must be removed, and the area restored afte .
D. HOUSEKEEPING AND MATERIAL DISPOSAL
1. The contractor is responsible for cleaning up after equipment delivery, including collecting and disposing of all packaging, debris, and waste to ensure the area is left clean and safe.
2. The contractor must maintain a clean worksite, free of waste and debris at all times. This includes daily
3.
long- Debris must be disposed of at agreed intervals in compliance with federal, state, and local regulations.
E. PROJECT SUBMITTALS:
1. The contractor must submit all required documentation, including but not limited to shop drawings, product
Notice to Proceed for review and approval.
2. The contractor must provide three (3) copies of Material Safety Data Sheets (MSDS) for all materials and the material is not approved by the Safety Manager, the contractor is responsible for sourcing and procuring an approved alternative product.
II. CONTRACTOR SECURITY/WORKING REGULATIONS
A. WORK HOURS:
1. Normal working hours for contractors and subcontractors are 6:00 AM–2:00 PM, Monday through Friday, authorized for tasks causing institutional downtime.
2.
subcontractors must familiarize themselves with prison facility working conditions, which may result in uced hours due to institutional emergencies or
3. Contractors must allocate time for security procedures such as check-in screenings, delays caused by inmate movements, lockdowns, or emergencies. In the event of an emergency, contractors will be directed to secure all tools, equipment, and materials. If necessary, they will be escorted out, with work resuming only after the emergency is resolved per FBOP's determination.
B. DELIVERY:
1.
2. 1 contractor must provide their own resources for loading and unloading materials or equipment.
3. The contractor is prohibited from using the institution's entry or driveway for loading, unloading, or storage.
Driveways must remain unblocked during and after work hours.
4. The contractor is responsible for maintaining proper housekeeping in the assigned laydown yard, ensuring materials are covered to protect against the elements. If the laydown yard is temporarily used as a disposal ged accordingly.
C. TOOLS AND EQUIPMENT:
1.
-upon storage
2.
contractor and the other by the institution. If needed, a contractor-supplied heavy-duty chain may be used to facilitate security. All items within the container must be stored safely and kept in an orderly condition.
3.
of all tools brought into and removed from the institution.
4. All contractor-approved for use within the institution. Ladders must be stored in a designated area and secured to a
-duty chain and lock to prevent unauthorized removal.
D. SECURITY CLERANCE, BADGING AND ESCORTING:
1. Contractor personnel may be required to meet certain security requirements prior to entering the secured side of the institution. Contractor personnel shall go thru a security vetting process to acquire the necessary security clearance as required. The assigned program manager at FDC SeaTac is responsible the prison facility.
2. As soon as the award has been accepted and signed both by the Contractor and the FBOP’s Contracting FDC SeaTac security clearance form (NCIC). Security clearance documents shall only be accepted from the prime Contractor. It is the prime Contractor’s responsibility to review security clearance submissions to ensure they are accurate and complete and submitted on a timely manner.
3. In the event a Contractor or Subcontractor employee cannot pass the security clearance process, it shall be the Contractor’s responsibility to provide a replacement. By law the FBOP cannot, and shall not, release any information to the Contractor concerning the nature of why Contractors or Subcontractor personnel was not able to pass the FBOP’s security clearance process.
4. The Contractor shall provide a daily list of names of all approved personnel who shall be working on site
5. The daily operation of this facility follows strict security checks and may require additional time to process into and out of the institution. Entry into the secure area of the facility and shall require passage of security screening to include a metal de
6. FBOP shall ensure a minimum of one representative (escort) is present daily to allow access to all areas requested by the Contractor as needed.
E. SAFETY:
1. Contractors and personnel must wear industry-standard personal protective equipment (PPE) at all times
2. All ladders must be securely stored in a predetermined area using a chain and lock to prevent removal. If promptly.
3. Sprinkler For systems requiring Lock-out/Tag-out, both contractor and FDC SeaTac locks must secure the isolation point to prevent electrical shock. All Lock-out/Tag-out procedures must comply with the institution's Lock-out program.
F. ADDITIONAL CONSIDERATIONS:
1. Vendors, their employees, and agents are strictly prohibited from introducing or possessing any form of authorized for retention or possession by federal, state, or local law, or by the facility's rules, regulations, and post orders, including but not limited to electronic devices, weapons, drugs, alcohol, and currency.
2. All vendor personnel shall adhere to the Federal Bureau of Prisons' comprehensive ban on smoking and tobacco products. The possession or use of any tobacco product (including but not limited to cigarettes, cigars, pipes, and e- -designated outdoor smoking area (which must be outside the secure perimeter and out of view of inmates).
3. During the startup warranty, Vendor representative must wear professional attire appropriate for the work being performed, prioritizing safety and a secure institutional environment. The following clothing items are strictly prohibited on institution groun clothing that is green or khaki in color (these colors are worn by inmates) shorts inappropriate language/graphics.
4.
leave the premises.
File details come from the government source that posted it. Updated .