Period of Performance 25Z6AH2.pdf
PDF 223 KB Posted
- Solicitation number
- 25Z6AH2
About this file
This is a memorandum from the Federal Bureau of Prisons (FBP) Facilities Management establishing the period of performance for contract 25Z6AH2, an emergency repair project for fire detection and suppression systems at FDC SeaTac (Federal Detention Center SeaTac). The memorandum is dated February 13, 2026, and is addressed to the Contracting Officer E. Kramer at FDC SeaTac from Facility Manager B. J Halbeisen.
The total performance period allocated is 90 calendar days (12 weeks) from contract award to final acceptance. The anticipated timeline breaks down as follows: Security Clearance (7 days), Lead Time/Mobilization (28 days), Scope of Work—Repair Fire Detection and Suppression Systems per Statement of Work (28 days), Inspections (7 days), De-Mobilization (7 days), and Contingency (7 days). The facility manager notes that this timeframe is necessary to allow adequate time for obtaining security clearances, ordering and delivering materials, removing old equipment, completing work, conducting system testing, and demobilizing from the work site. No response dates, pricing information, or other procurement terms are included in this document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW - 25Z6AH2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Justice Federal Bureau of Prisons
Facilities Management
Washington, DC 20534
February 13, 2026
MEMORANDUM FOR E. KRAMER, CONTRACTING OFFICER,
FDC SEATAC
FROM: B. J Halbeisen, Facility Manager, FDC SeaTac
SUBJECT: Period of Performance, 25Z6AH2, Emergency Repair Fire Detection and Suppression Systems
It is anticipated that from the completion of the current contract to testing and acceptance of the project, a performance period of 90 calendar days will be required. The timeframe allotted will allow adequate time for security clearances to be obtained, materials to be ordered and delivered on site, the removal of the old equipment, the work to be completed, system testing to be completed, and demobilization from the work site and the extent or amount of the damage would be difficult to estimate accurately or prove.
The following is an anticipated time frame for this project:
Security Clearance 7 Calendar Days 1 Week Lead Time/Mobilization 28 Calendar Days 4 Weeks Scope of Work Repair Fire Detection and Suppression Systems Per SOW
28 Calendar Days 4 Weeks
Inspections 7 Calendar Days 1 Week De-Mobilization 7 Calendar Days 1 Week Contingency 7 Calendar Days 1 Week
Total Performance Period: 90 calendar days / 7 days = 12 Weeks
A total of 12 weeks has been allotted from time of award to final acceptance for all work identified in the Statement of Work.