SOW 210801.pdf

PDF 307 KB Posted

Attached to
Camp Davis North Runway Erosion Repairs Federal contract opportunity
Solicitation number
N4008521R2501
Issued by
Department of the Navy Naval Facilities Engineering Command

View the file

Other files for this federal contract opportunity

Other files attached to Camp Davis North Runway Erosion Repairs, newest first.
File Type Posted
210801 Amendment 0001.pdf PDF
UPDATED SOW 210801.pdf PDF
RFP 210801.pdf PDF
RFP 210801.pdf PDF
MAP 210801.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Contractor shall furnish all labor, supervision, management, tools, materials, equipment, transportation, incidental engineering, and other items necessary to repair the erosion on the northeast side of Camp Davis North Runway.

1. Remove and dispose of properly any Foreign Object Debris (FOD) on the surface and surrounding eroded area (immediate work area) of the Camp Davis North Runway.

2. Remove 3” – 6” of Aggregate Base Course (ABC) rock in several areas as noted in photosand maps.

Dispose of ABC rock properly and at the contractor’s expense (off Base). No ABC rock shall be used or seen at this repair effort.

3. De-water all holes within the project area as outlined in the red polygon and noted on page 2of the Site

Plan.

4. Fill in eroded areas using earth fill for the bottom layer and topsoil for top layer. The contractor shall make the decision on the depths of each layer depending on the ground and situation at the time the work is actually being done.

5. Contour or enhance existing drainage swales for positive drainage to larger drainage swales to the east.

Drainage to remain unchanged from existing except where necessary.

6. Install sod:

a .Inside the entire area outlined in red, approximately 44,500 Square Feet as depicted on page 2 of the

Site Plan.

b. Sod to be installed is approximately 44,500 square feet.

c. Stake sod in place according to industry standard.

d. After installation, water sod once daily for 15 days.

e. Newly emplaced sod to be same elevation as the surface of the existing runway.

7. See attached Area Map and Site Plan for location specifics and photographs of the Camp Davis North

Runway erosion repair.

Special Instructions:

1. The contractor shall call “Blackburn”, 451-3064, when the contractor arrives on site at the beginning of the work day and when the contractor leaves the site at the end of the work day.

2. Ruts or tire tracks created by the contractor during operations shall be filled in with topsoil capable of establishing plant growth and seed the disturbed are with a coastal mix of grass seed.

3. The contractor shall coordinate the work schedule and access to the work areas with the Point of

Contact (POC) at Range Maintenance. The POC is Kimberly

5058258

SAP

Ingram and can be reached at 451-1234. Work areas shall be cleaned up and debris disposed of properly on a daily basis. No equipment or material shall be stored on the work site without specific permission from Range Maintenance.

4. The contractor may use GFE or other Range Maintenance equipment and tools for this project with prior notice to the government and the submission of an equipment list. Range Maintenance equipment and tools to be returned at the end of the project with reasonable wear and tear.

Unserviceable equipment and tools to be replaced with new like item.