210801 Amendment 0001.pdf

PDF 122 KB Posted

Attached to
Camp Davis North Runway Erosion Repairs Federal contract opportunity
Solicitation number
N4008521R2501
Issued by
Department of the Navy Naval Facilities Engineering Command

View the file

Other files for this federal contract opportunity

Other files attached to Camp Davis North Runway Erosion Repairs, newest first.
File Type Posted
UPDATED SOW 210801.pdf PDF
RFP 210801.pdf PDF
RFP 210801.pdf PDF
SOW 210801.pdf PDF
MAP 210801.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFIC T ON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLIC TION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 3

AMENDMENT NO. 0001 9/2/21 21-0801

N40085

NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1005 Michael Road Camp Lejeune, NC 28547-2521

See Item 6

✘ N40085-21-R-2501

8/23/21

21-0801, Camp Davis North Runway Erosion Repairs Amendment 0001, Answer Requests for Information Remove "SOW 210801" and Replace with "UPDATED SOW 210801" The time and date for receipt of proposals remains 1400, 8 September 2021.

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.

See Continuation Page(s)

N40085-21-R-2501 Amendment 0001

CONTINUATION SHEET

1. QUESTION: Please advise what the designated working hours are for this project.

ANSWER: 0600-1900 Monday - Sunday

2. QUESTION: Please confirm that there will be a designated laydown area onsite for any equipment/materials.

ANSWER: Yes an area will be identified on site

3. QUESTION: Please advise whether the runway will be shut down when work is in progress?

ANSWER: Yes the runway will be scheduled for the duration of the project.

4. QUESTION: Please advise whether the Contractor can use the fill dirt from the Camp Lejeune Landfill.

ANSWER: Yes the contractor can use the government fill dirt there are 2 sites authorized

1) OP-5 at the intersection of Sneads Ferry Rd/Marines Rd

2) TLZ Condor located on the south side of Verona Loop Rd east of HWY 17

5. QUESTION: Please advise if Centipede sod is acceptable for use on this project.

ANSWER: Yes Centipede is acceptable

6. QUESTION: Is there an accessible water source near the runway site that may be used for filling the water trucks to water the sod?

ANSWER: There are two ditches that water can be pumped from at Camp Davis depending on the water levels. The closest Government water source (fire hydrant) is located on CC Rd by the SR-6 Range approximately 10 miles to the north from the entrance of Camp Davis South

7. QUESTION: Will there be Airfield Traffic Control Devices, such as Lighted Barricades or Closure Crosses required?

ANSWER: No

8. QUESTION: Will the portion of the runway adjacent to the project area be active at any time during this project, prior to ground stabilization?

N40085-21-R-2501 Amendment 0001

ANSWER: The project area will be closed to training and use of the run way will be restricted to the southern half.

9. QUESTION: Please confirm that the Bond requirement has changed from $35K to $40K per the RFP.

ANSWER: Yes

10. QUESTION: If the Government is furnishing all borrow material (fill dirt and topsoil) for this project, will the Government be loading that material into trucks furnished by the Contractor, or will it be the Contractor’s responsibility to furnish labor and equipment to load trucks at the Base Landfill?

ANSWER: No the contractor is responsible to provide their own equipment and labor to load and haul the dirt

11. Please note that Special Instruction Paragraph 4. Was removed from the original “SOW 210801” attachment. Corrected SOW is now attached in SAM.gov titled “UPDATED SOW 210801”

12. All other terms and conditions remain unchanged.