South Cobb Water Reclamation Facility Plan Summary
This document is a comprehensive facilities plan prepared by Ardurra Group, Inc. for the Cobb County Water System (CCWS) to evaluate and plan the expansion of the South Cobb Water Reclamation Facility (SCWRF) located in Austell, Georgia. The facility, which currently operates under NPDES Permit No. GA0026158 with a permitted capacity of 40 million gallons per day (MGD) Maximum Month Flow (MMF), serves southwestern Cobb County and portions of Douglas and Paulding Counties. The primary objective is to expand the facility from 40 MGD MMF to 50 MGD MMF while addressing infrastructure rehabilitation needs, ensuring operational reliability, and achieving increasingly stringent regulatory compliance requirements. The plan evaluates existing facility conditions, identifies rehabilitation and reliability needs, assesses future treatment requirements through 2050, and develops comprehensive strategies for expansion. Major planning triggers for implementation are identified at 29.2 MGD Average Daily Flow (ADF) and 36.5 MGD MMF, with the facility projected to reach current capacity around 2031 based on historical flow trends of growth from 23.8 MGD in 2017 to 28.6 MGD in 2024.
The plan was significantly influenced by the November 2025 Georgia Environmental Protection Division (EPD) Wasteload Allocation (WLA) No. WLA000309, which established substantially more stringent planning-level effluent targets for future 50-MGD operation: CBOD5 of 2.9 mg/L (current permit: 13.0 mg/L), TSS of 5.0 mg/L (current: 10.0 mg/L), Ammonia-N of 0.5 mg/L (current: 1.8 mg/L), and Total Phosphorus of 0.30 mg/L (current: 0.52 mg/L). The plan identified three primary drivers: capacity expansion due to population and flow growth, infrastructure rehabilitation needs for aging treatment processes and equipment, and regulatory compliance with WLA requirements and anticipated future Total Nitrogen limitations for downstream West Point Lake protection. The facility plan developed multiple treatment alternatives, with Alternatives A11.3 (4-Stage Bardenpho Process with Deep Bed Denitrifying Filters, estimated $373 million CAPEX) and A14.2 (5-Stage Bardenpho Process with Tertiary Membranes, estimated $307 million CAPEX) advancing as primary alternatives for detailed refinement. Future permitting requirements identified include completion of an Antidegradation Analysis, Environmental Information Document (EID), Design Development Report (DDR), and Watershed Protection Plan updates. The plan recommends phased implementation tied to flow triggers and operational needs rather than a single comprehensive construction project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pre_Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The South Cobb WRF Facility Plan is provided for informational purposes only. Cobb County assumes no liability or responsibility for any errors, omissions, or inaccuracies within this document. By accessing this document, prospective Proposers acknowledge that they bear the sole burden of conducting all independent investigations and data verifications they deem necessary to assume full responsibility prior to submitting a proposal.
10 | P a g e
THIS PAGE INTENTIONALLY LEFT BLANK
1 | P a g e
TABLE OF CONTENTS
Executive Summary
Section 1 – Introduction and Background
1.1 Project Purpose
1.2 Facility Background
1.3 Project Drivers
1.4 Planning Horizon
1.5 Population and Flow Planning Basis
1.6 Regulatory Background
1.7 Facility Planning Process
1.8 Purpose of the Final Facilities Plan and Deliverables
Section 2 – Existing Facilities Evaluation
2.1 Existing Facility Overview
2.2 Existing Facility Performance Summary
2.3 Existing Facility Assessment Summary
2.4 Existing Capacity and Reliability Constraints
2.5 Existing Facility Improvement Needs
Section 3 – Regulatory Planning Basis
3.1 Existing NPDES Permit Requirements
3.2 WLA Requirements
3.3 Potential Future Nutrient Requirements
3.4 Antidegradation Analysis Requirements
3.5 Environmental Information Document Requirements
3.6 Watershed Protection Plan Requirements
Appendix A – Existing Regulatory Framework
Appendix A.1 Current NPDES Permit No. GA0026158 Appendix A.2 Wasteload Allocation No. WLA000309
Section 4 – Process Modeling and Alternatives Evaluation Basis
4.1 Planning Assumptions
4.2 Hydraulic Evaluation Summary
2 | P a g e
4.3 Process Modeling Summary
4.4 Alternatives Evaluation Methodology
4.5 Alternatives Advanced for Refinement
Section 5 – Alternatives Evaluation and Refinement
5.1 Alternative Development Overview
5.2 Initial Alternatives Screening Summary
5.3 Alternative Advancement Framework
5.4 Primary Alternatives Evaluation
Appendix B – Alternatives Evaluation Supporting Documentation
Section 6 – Implementation and Capital Planning Framework
6.1 Evaluation Findings
6.2 Recommended Planning Strategy
6.3 Implementation Strategy Framework
6.4 Recommended Next Steps
6.5 Capital Planning Framework
Section 7 – Conclusions and Recommendations
7.1 Key Findings
7.2 Recommendations
7.3 Future Planning Considerations
7.4 Closing Statement
3 | P a g e
LIST OF FIGURES
Section 1
Figure 1.2-1 CCWS Wastewater Service Areas and South Cobb WRF Service Boundary Figure 1.5-1 South Cobb WRF Long-Term Flow Projection Summary
Section 2
Figure 2.1-1 Existing South Cobb WRF Process Flow Schematic Figure 2.1-2 Existing South Cobb WRF Hydraulic Profile
Section 5
Figure 5.4-1 Alternative A11.3 Conceptual Site Layout Figure 5.4-2 Alternative A14.2 Conceptual Site Layout
4 | P a g e
LIST OF TABLES
Section 1
Table 1.3-1 Major Drivers Influencing the South Cobb WRF Facilities Plan Table 1.5-1 South Cobb WRF Planning Trigger Flow Summary Table 1.6-1 Existing Permit Requirements, WLA Requirements, and Future Planning Targets Table 1.8-1 Alternative Advancement Framework
Section 2
Table 2.2-1 Existing Facility Performance Summary Table 2.3-1 Summary of Existing Facility Assessment Findings Table 2.5-1 Existing Facility Improvement Needs Summary
Section 3
Table 3.1-1 Existing NPDES Permit Effluent Limitations Table 3.2-1 Georgia EPD WLA Planning-Level Effluent Targets for 50-MGD Expansion Table 3.2-2 Existing Permit vs. WLA Planning Targets Table 3.3-1 Nutrient Planning Basis for Alternatives Evaluation
Section 4
Table 4.1-1 Planning Basis Summary(proposed) Table 4.3-1 Summary of Modeled Effluent Performance Targets Placeholder
Section 5
Table 5.1-1 Alternative Evaluation Criteria Summary Table 5.1-2 Alternative Advancement Framework Summary Table 5.2-1 Screening-Level Alternative Categories Table 5.4-1 Primary Alternative Comparison Matrix
Section 6
Table 6.5-1 Capital Planning Framework Summary
ACRONYMS AND ABBREVIATIONS
Acronym Definition
AADF Annual Average Daily Flow ADF Average Daily Flow AFP6 Air Force Plant 6 (Lockheed Martin Facility) ARC Atlanta Regional Commission Ardurra Ardurra Group, Inc.
BFP Belt Filter Press BHP Brake Horsepower BNR Biological Nutrient Removal BOD Biochemical Oxygen Demand CBOD₅ Carbonaceous Five-Day Biochemical Oxygen Demand CCD Cobb County Department CCWS Cobb County Water System CFD Computational Fluid Dynamics CIP Capital Improvement Program CNOP Comprehensive Nutrient Optimization Plan CPR Condition and Performance Report DAFT Dissolved Air Flotation Thickener DDR Design Development Report DO Dissolved Oxygen EID Environmental Information Document EPD Georgia Environmental Protection Division FM Fairbanks Morse FOG Fats, Oils, and Grease FRED Federal Reserve Economic Data GAWP Georgia Association of Water Professionals GBT Gravity Belt Thickener GIS Geographic Information System HLR Hydraulic Loading Rate HVAC Heating, Ventilation and Air Conditioning I&C Instrumentation and Controls I&I Inflow and Infiltration ILS Influent Lift Station IR Internal Recycle LS Lift Station MBR Membrane Bioreactor MGD Million Gallons per Day ML Mixed Liquor MLSS Mixed Liquor Suspended Solids MLVSS Mixed Liquor Volatile Suspended Solids MMADF Maximum Monthly Average Daily Flow MMF Maximum Month Flow
MNGWPD Metropolitan North Georgia Water Planning District MOPO Maintenance of Plant Operations MS4 Municipal Separate Storm Sewer System NRCY Nitrate Recycle NPDES National Pollutant Discharge Elimination System O&M Operations and Maintenance ORP Oxidation Reduction Potential PDB Progressive Design-Build PDF Peak Daily Flow PE Professional Engineer PER Preliminary Engineering Report PLC Programmable Logic Controller PWWF Peak Wet Weather Flow RAS Return Activated Sludge RDT Rotary Drum Thickener RFP Request for Proposal SCADA Supervisory Control and Data Acquisition SCWRF South Cobb Water Reclamation Facility SIC Standard Industrial Classification SLR Solids Loading Rate SOR Surface Overflow Rate SST Stainless Steel SW Stormwater TKN Total Kjeldahl Nitrogen TM Technical Memorandum TN Total Nitrogen TP Total Phosphorus TRC Total Residual Chlorine TSS Total Suspended Solids UV Ultraviolet Disinfection VFD Variable Frequency Drive VSS Volatile Suspended Solids WAS Waste Activated Sludge WET Whole Effluent Toxicity WLA Wasteload Allocation WPCP Water Pollution Control Plant WPP Watershed Protection Plan WRF Water Reclamation Facility
Key Flow Definitions Term Definition AADF Annual Average Daily Flow ADF Average Daily Flow MMF Maximum Month Flow PDF Peak Daily Flow PWWF Peak Wet Weather Flow Design Capacity Permitted treatment capacity of the facility
Key Regulatory Definitions Term Definition NPDES Permit National Pollutant Discharge Elimination System
Permit WLA Wasteload Allocation issued by Georgia EPD CNOP Comprehensive Nutrient Optimization Plan EID Environmental Information Document DDR Design Development Report WPP Watershed Protection Plan Antidegradation Analysis Regulatory evaluation supporting increased discharge authorization
EXECUTIVE SUMMARY
ES.1 Introduction
The Cobb County Water System (CCWS) retained Ardurra Group, Inc. to prepare a long-range Facilities Plan for the South Cobb Water Reclamation Facility (SCWRF) located in Austell, Georgia. The primary purpose of the planning effort was to evaluate the existing SCWRF, identify rehabilitation and reliability needs, assess future treatment requirements, and develop a comprehensive strategy for expanding the facility from its current permitted capacity of 40 million gallons per day (MGD) Maximum Month Flow (MMF) to 50 MGD MMF.
The SC WRF is one of four major wastewater treatment facilities operated by CCWS and serves the southwestern portion of Cobb County, including portions of Austell, Mableton, Powder Springs, Marietta, Smyrna, Douglas County, and Paulding County. Treated effluent is discharged to the Chattahoochee River under National Pollutant Discharge Elimination System (NPDES) Permit No. GA0026158.
Originally conceived as a conventional capacity expansion study, the Facility Plan evolved into a broader evaluation of infrastructure rehabilitation, nutrient removal capability, operational reliability, regulatory compliance, implementation strategy, and long-term capital planning following issuance of a new Georgia Environmental Protection Division (EPD) Wasteload Allocation (WLA) in November 2025.
ES.2 Planning Drivers Three primary drivers established the need for this Facility Plan:
Capacity Expansion
Population and flow projections indicate wastewater flows within the South Cobb service area will continue to increase throughout the planning period. Historical wastewater flows increased from approximately 23.8 MGD in 2017 to approximately
28.6 MGD in 2024. Based on historical trends, the SCWRF is projected to reach its current permitted 40 MGD MMF capacity around 2031. Inclusion of projected intergovernmental contributions from Douglas County, Paulding County, and Lockheed Martin/AFP6 may accelerate this need to approximately 2029.
Infrastructure Rehabilitation Facility assessments identified numerous treatment processes, equipment systems, electrical systems, and support facilitiesare approaching or exceeding their expected useful life. Rehabilitation needs were identified throughout the headworks, grit removal facilities, primary clarifiers, secondary clarifiers, solids handling facilities, reuse water system, instrumentation system, and electrical infrastructure. The chemical system of the plant was found to be in adequate condition.
Regulatory Compliance The November 2025 Georgia EPD WLA established substantially more stringent planning-level effluent objectives for future operation at 50 MGD MMF. These requirements significantly expanded the planning effort beyond a conventional hydraulic capacity study and required evaluation of advanced nutrient removal technologies capable of achieving future regulatory objectives.
ES.3 Major Technical Findings Existing Facility Performance
The SCWRF has consistently met current permit requirements and has historically demonstrated reliable treatment performance. However, evaluations completed as part of this planning effort identified multiple operational and reliability concerns requiring attention.
Urgent Facility Issues Technical Memorandum (TM)No. 3 identified four urgent facility concerns:
1. Stormwater management concerns associated with elevated fecal indicator monitoring results.
2. Excessive rag loading throughout the treatment process.
3. Maintenance-intensive solids handling systems.
4. Reuse water system reliability concerns.
These concerns were found to be interconnected and represent significant contributors to current maintenance demands and long-term reliability challenges.
Equipment and Infrastructure Assessment TM No. 4 concluded several major treatment systems have reached or exceeded their anticipated useful life and require rehabilitation or replacement. Key concerns include:
Ineffective aerated grit removal facilities.
Aging primary clarifier equipment.
Secondary clarification limitations.
Maintenance-intensive RAS (Return Activated Sludge) and WAS (Waste Activated Sludge) pumping systems.
Solids thickening inefficiencies.
Reuse water system deterioration.
Obsolete instrumentation and control equipment.
ES.4 Regulatory Planning Basis SCWRF currently operates under NPDES Permit No. GA0026158 with effluent limitations that include:
CBOD₅ = 13.0 mg/L TSS = 10.0 mg/L Ammonia-N = 1.8 mg/L Total Phosphorus = 0.52 mg/L Maximum Month Flow = 40 MGD
Georgia EPD subsequently issued WLA No. WLA000309 to support future expansion to 50 MGD MMF and established the following planning-level objectives:
CBOD₅ = 2.9 mg/L TSS = 5.0 mg/L Ammonia-N = 0.5 mg/L Total Phosphorus = 0.30 mg/L Flow = 50 MGD MMF
The WLA further identified the potential for future Total Nitrogen limitations associated with protection of downstream West Point Lake. For planning purposes, this Facility Plan evaluated alternatives against future targets of approximately:
Total Nitrogen (TN) = 4.0 mg/L Total Phosphorus (TP) = 0.13 mg/L
ES.5 Alternatives Evaluation Multiple treatment alternatives were developed and evaluated through hydraulic analysis, BioWin process modeling, constructability assessments, implementation sequencing reviews, site utilization evaluations, planning-level cost estimating, and lifecycle cost comparisons.
The Facilities Plan evaluated multiple nutrient removal approaches, including advanced biological nutrient removal processes, tertiary membrane treatment systems, and deep bed denitrifying filtration systems. These evaluations were completed for planning purposes and should not be interpreted as owner selection of a final treatment technology.
While deep bed denitrifying filtration was evaluated during preparation of the Facilities Plan, CCWS does not currently identify this technology as preferred but should expect the evaluation of alternative approaches to be capable of achieving equivalent or superior treatment performance, reliability, maintainability, and lifecycle value.
Alternatives included:
MLE 2-Stage Bardenpho BNR 3-StageBardenpho BNR 4-Stage Bardenpho BNR 5-Stage Bardenpho BNR Deep Bed Denitrifying Filter Alternatives Membrane-Based Alternatives
Following screening and refinement, an Alternative Advancement Framework was established.
Primary Alternatives Alternative A11.3
4-Stage Bardenpho Process with Deep Bed Denitrifying Filters
Key characteristics include:
Conventional treatment configuration.
New BNR basins.
Primary replacement and additional secondary clarification.
Deep bed denitrifying filtration.
Strong long-term nutrient compliance capability.
Estimated total CAPEX project cost of approximately $373 million.
Alternative A14.2
5-Stage Bardenpho Process with Tertiary Membranes
Key characteristics include:
Membrane-based solids separation.
Efficient site utilization.
Reduced facility footprint.
Strong constructability profile.
Excellent future nutrient compliance flexibility.
Estimated total CAPEX project cost of approximately $307 million.
Both alternatives demonstrated the ability to satisfy current WLA requirements and future nutrient planning objectives.
Planning-Level Cost Estimate Disclaimer The capital cost estimates presented throughout this Facilities Plan are intended solely for planning, screening, and comparative evaluation purposes. These estimates were developed to allow CCWS to evaluate relative differences between treatment alternatives and implementation strategies and should not be interpreted as construction bids, Guaranteed Maximum Prices (GMPs), or final project budgets.
Consistent with the planning-level nature of this evaluation, the reported Total Project Costs do not include a separate contingency allowance. Excluding contingency allows for direct comparison of the base costs associated with the alternatives evaluated during the Facilities Planning process.
Prior to budgeting, capital programming, procurement, or project implementation, Ardurra recommends application of an overall project contingency appropriate for the level of project definition available at the time of estimate preparation. For planning purposes, a contingency allowance of approximately 30 percent should be considered to account for market uncertainty, inflation, labor and material cost escalation, procurement conditions, project delivery considerations, regulatory requirements, design development, and other factors that may influence future project costs.
Accordingly, the planning-level Total Project Costs presented within this Facilities Plan should be viewed as comparative baseline estimates, and future project budgeting should incorporate an appropriate contingency allowance and escalation analysis based on the
5 | P a g e selected project delivery approach and level of design completion.
ES.6 Implementation Framework The Facility Planning effort concluded future development should occur as a phased program rather than as a single comprehensive construction project. Trigger-based implementation provides the ability to align capital investments with actual growth, operational needs, and regulatory requirements.
Key planning triggers include:
29.2 MGD Average Daily Flow (ADF)
36.5 MGD Maximum Month Flow (MMF)
Recommended implementation phases include:
Headworks and grit removal improvements.
Clarification reliability improvements.
Expansion to 50 MGD MMF.
Future nutrient compliance improvements.
Long-term facility optimization.
ES.7 Recommendations Based on the findings of this Facility Plan, CCWS should:
1. Continue planning and permitting efforts supporting expansion of SCWRF to 50
MGD MMF.
2. Complete currently active reliability projects, including:
Influent Lift Station (ILS) Recovery and Roller Gates Restoration (T5004) ILS HVAC Systems Replacement (T3026) Headworks Improvements (T3017) Secondary Clarifier Rehabilitations (T3028) Effluent Filter Rehabilitation (T3023) Biosolids Thickening Improvements (T3027)
3. Initiate required permitting activities, including:
Antidegradation Analysis Environmental Information Document (EID) Design Development Report (DDR) Watershed Protection Plan (WPP) review and updates
4. Utilize this Facility Plan as the basis for future Progressive Design-Build (PDB) procurement activities.
5. Continue refinement of the treatment approaches represented by Alternatives A11.3 and A14.2 during preliminary engineering and procurement.
6. Continue monitoring flow trends, intergovernmental contributions, regulatory developments, and future nutrient management initiatives.
ES.8 Conclusion The South Cobb Water Reclamation Facility has served as a critical component of the
6 | P a g e
(CCWS) for more than sixty years. This Facility Plan demonstrates expansion to 50 MGD MMF is both necessary and achievable. Multiple technically viable treatment pathways exist; however, future success will depend upon balancing capacity expansion, infrastructure rehabilitation, regulatory compliance, operational reliability, and implementation flexibility. Through proactive permitting, phased capital investment, and continued advancement of the preferred treatment alternatives, CCWS is well-positioned to maintain reliable wastewater treatment service and meet anticipated stringent regulatory compliance through at least the year 2050.
SECTION 1
INTRODUCTION AND BACKGROUND
1.1 Project Purpose
The CCWS retained Ardurra Group, Inc. to evaluate the existing SCWRF and develop a long-range Facility Plan supporting expansion of the facility from its current permitted 40 MGD MMF capacity to 50 MGD MMF while maintaining regulatory compliance, operational reliability, and future treatment flexibility.
The Facility Plan is intended to provide CCWS with a technically defensible and financially responsible roadmap for facility rehabilitation, treatment process improvements, capacity expansion, nutrient removal planning, and phased capital improvements through at least the year 2050.
The final deliverable is intended to serve as a planning framework supporting future permitting efforts, project prioritization, capital budgeting, procurement strategy development, preliminary engineering, and subsequent design activities.
1.2 Facility Background
The SCWRF is one of four major wastewater treatment facilities owned and operated by CCWS. The facility is located at 490 Lee Industrial Boulevard in Austell, Georgia and serves the southwestern quadrant of Cobb County, including portions of the Cities of Austell, Mableton, Powder Springs, Marietta, and Smyrna, as well as portions of Douglas and Paulding Counties. Treated effluent is discharged to the Chattahoochee River under NPDES Permit No. GA0026158. The SCWRF service area and its relationship to other CCWS wastewater service basins are shown in Figure 1.2-1 which was pulled from previous CCWS studies and is denoted as Figure 2.1 in the following Figure 1.2-1.
P a g e
Fi gu re
.2
-1
C C
W S
W as te w at er
S er vi ce
A re as a nd S
C W
RF
S er vi ce B ou nd ar y
As shown in Figure 1.2-1, the SCWRF serves one of the largest wastewater basins within the CCWS system and receives flows from both in-county and intergovernmental service areas, making it a critical regional treatment facility for the southwestern portion of Cobb County.
The SCWRF currently operates with a permitted 40 MGD MMF capacity and was originally constructed in 1963. The facility has undergone numerous expansions and rehabilitation projects, including major upgrades completed in 1976, 1994, 1998, 2004, 2012, and 2015, and today functions as one of the largest wastewater treatment facilities within Cobb County. Recent capital investments include rehabilitation of the ILS roller gates and HVAC systems replacement, headworks improvements, secondary clarifiers, effluent filtration facilities, , replacement of the dissolved air flotation thickening system with rotary drum thickening facilities, and other reliability and process improvement projects.
At the time this Facility Plan was initiated, SCWRF operated as a conventional activated sludge facility consisting of influent screening, aerated grit removal, primary clarification, conventional activated sludge treatment, secondary clarification, tertiary filtration, chlorination/dechlorination, effluent discharge to the Chattahoochee River, and biosolids thickening and dewatering facilities.
The facility was designed to treat:
Average Daily Flow (ADF): 33 MGD Maximum Month Flow (MMF): 40 MGD Peak Wet Weather Flow (PWWF): 86 MGD
1.3 Project Drivers
1.3.1 Capacity Expansion Driver
The original driver for this project was the projected need to expand SCWRF from 40 MGD MMF to 50 MGD MMF in response to anticipated growth within the South Cobb service area. Historical flow evaluations performed as part of TM No. 2 demonstrated future wastewater flows are expected to continue increasing over the planning period and additional treatment capacity will be required before existing permitted limits are exceeded.
TM No. 2 identified a planning triggers of approximately:
29.2 MGD ADF
36.5 MGD MMF
as the point at which planning, permitting, design, and procurement activities should promptly begin to provide sufficient time for implementation of facility improvements.
1.3.2 Infrastructure Rehabilitation Driver
A second major driver was the condition and age of key SCWRF infrastructure. A significant portion of the facility's process equipment and treatment infrastructure have reached the end of their useful life and require systematic rehabilitation or replacement as part of this long-term expansion program. Previous assessments, workshops, and condition evaluations identified numerous process, equipment, electrical, instrumentation, structural, and operational improvements requiring consideration within the planning horizon. This exhaustive effort has been captured in the Condition and Performance Reports (CPRs).
1.3.3 Regulatory Driver
A third and ultimately defining primary driver emerged during development of the Facility Plan when Georgia EPD issued a WLA for the proposed 50-MGD expansion. The WLA established significantly more stringent planning-level limits than those currently imposed under the existing NPDES permit and indicated future Total Nitrogen (TN) limitations may be required to address downstream impacts on West Point Lake, ,located in west-central Georgia along the Chattahoochee River.
Capacity Driver Infrastructure Driver Regulatory Driver
Population Growth
Aging Facilities Existing NPDES Permit
Intergovernmental Flows
Equipment Condition November 2025 WLA
Industrial Growth Process Reliability Future TN/TP Limits
50 MGD Expansion Need
Rehabilitation Needs Nutrient Compliance Planning
Table 1.3-1 Primary Drivers Influencing the SCWRF Facility Plan
The combination of projected flow growth, aging infrastructure, and increasingly stringent regulatory requirements created the basis for this Facility Plan effort. While the original planning effort focused primarily on expansion of treatment capacity from 40 MGD MMF to 50 MGD MMF, issuance of the November 2025 WLA expanded the planning effort to include evaluation of treatment technologies capable of meeting both current and future nutrient removal objectives.
Table 1.3-1 summarizes the primary drivers that collectively established the need for the SCWRF Facility Plan.
1.4 Planning Horizon
The original Request for Proposal (RFP) asked for the development of a Facility Plan extending through the year 2040. During the planning process, CCWS requested additional emphasis on long-term flexibility, regulatory adaptability, and implementation sequencing. Consequently, the planning horizon utilized throughout this Facility Plan extends beyond the immediate 2040 timeframe and considers the implications of future growth, nutrient regulations, and facility development through approximately 2050.
The planning horizon includes:
Near-Term Planning (2026-2035) Mid-Term Expansion and Compliance (2035-2045) Long-Term Facility Development (2045-2050+)
1.5 Population and Flow Planning Basis
As documented in TM No. 2, multiple forecasting approaches were evaluated to establish a planning basis for future treatment capacity needs at the SCWRF. Historical wastewater flow data, population growth trends, Metropolitan North Georgia Water Planning District (MNGWPD) planning information, intergovernmental flow commitments, and U.S. Census data were evaluated as part of the forecasting effort. Both linear and exponential forecasting methodologies were analyzed to establish a reasonable range of future wastewater flow projections for the SCWRF service area.
The SCWRF currently operates with a permitted MMF capacity of 40 MGD. Historical flow evaluations showed average daily flow (ADF) increased from approximately 23.8 MGD in 2017 to
28.6 MGD in 2024, reflecting continued growth throughout the South Cobb service area.
Evaluation of historical operating data further demonstrated flow growth has progressed at a faster rate than population growth due to a combination of service area development, intergovernmental flow contributions, system dynamics, and other factors influencing wastewater demand.
TM No. 2 concluded that the historical linear flow projection methodology provides the most reliable planning basis for future facility improvements. Using this approach, the SCWRF is projected to reach its current permitted 40 MGD MMF capacity at approximately the year 2031.
When future projected contributions from Douglas County, Paulding County, and Lockheed/AFP6 are considered, the projected capacity limitation could occur as early as 2029 based on anticipated intergovernmental contributions.
Although the precise timing of future flow increases may vary as growth patterns evolve, the forecasting effort identified several planning trigger points that should be monitored by CCWS.
These trigger values are intended to serve as early warning indicators allowing sufficient time for permitting, design, procurement, and construction before existing treatment capacity limitations are encountered. The trigger values do not represent facility failure thresholds, but rather planning milestones intended to preserve implementation flexibility and protect long-term regulatory compliance.
Planning Metric Flow
Current Average Daily Flow (2024)
28.6 MGD
Average Daily Flow Planning Trigger
29.2 MGD
Current Maximum Month Flow (2024)
35.0 MGD
Maximum Month Flow Planning Trigger
36.5 MGD
Existing Permitted Capacity
40.0 MGD MMF
Planned Expansion Capacity
50.0 MGD MMF
Table 1.5-1 SCWRF Planning Trigger Flow Summary
Note: Planning Trigger values identify the point at which facility planning, permitting, design, and implementation activities should be actively progressing. These values are intended to provide approximately five years of implementation flexibility before existing permitted capacity is reached.
Table 1.5-1 demonstrates that the SCWRF has already approached the planning trigger range identified within TM No. 2. Consequently, the population and flow projection effort recommended expansion planning should begin immediately and major facility improvements supporting expansion to 50 MGD MMF should not be delayed beyond the current planning cycle.
In addition to flow projections, TM No. 2 identified several key factors that should continue to be monitored by CCWS throughout implementation of the Facility Plan. These include annual influent flow trends, South Cobb Tunnel Lift Station loading patterns, actual intergovernmental contributions from Douglas and Paulding Counties, industrial loading changes associated with Lockheed/AFP6, future zoning and land use amendments, and ongoing inflow and infiltration (I&I) reduction efforts. Continued monitoring of these factors will help refine future projections and support more accurate timing of subsequent capital improvements.
Figure 1.5-1 SCWRF Long-Term Flow Projection Summary
Figure 1.5-1 illustrates the relationship between historical flow trends, planning trigger criteria established in TM No. 2, current permitted capacity of the facility, and the planned 50 MGD expansion target. The upward trend in the projection summary reinforces the conclusion that immediate expansion planning is justified to maintain adequate schedule flexibility and avoid future treatment capacity constraints.
Accordingly, the population and flow projection effort established the foundation for the remainder of this Facility Plan and confirmed the need for both facility rehabilitation and expansion planning. These findings subsequently became one of the primary drivers influencing alternative development, technology evaluation, implementation sequencing, and the selection of Alternatives A11.3 and A14.2 for detailed refinement during the final phase of the Facility Plan effort.
1.6 Regulatory Background
The SCWRF currently operates under NPDES Permit No. GA0026158 issued by the Georgia EPD.
The permit authorizes discharge of up to 40 MGD MMF to the Chattahoochee River and establishes effluent limitations, monitoring requirements, sludge management requirements, Watershed Protection Plan requirements, Whole Effluent Toxicity testing requirements, and CNOP obligations.
The current permit includes monthly average effluent limitations of:
CBOD₅ = 13.0 mg/L TSS = 10.0 mg/L Ammonia-N = 1.8 mg/L Total Phosphorus = 0.52 mg/L along with nutrient monitoring requirements for Total Nitrogen and associated nitrogen species, implementation of a CNOP, and permit reopener language that allows future nutrient limits to be incorporated as EPD continues implementation of nutrient management strategies throughout Georgia.
As discussed previously, expansion of SCWRF from 40 MGD MMF to 50 MGD MMF was identified as a planning necessity through the Population and Flow Projections effort. To support future planning activities, CCWS submitted a WLA request to the Georgia NPDES seeking planning-level guidance for a future 50-MGD discharge.
The resulting WLA was issued on November 10, 2025, and became the predominant milestone affecting development of this Facility Plan. Rather than simply authorizing additional flow capacity, the WLA established substantially more stringent planning-level treatment objectives than those contained in the existing NPDES permit and introduced additional long-term nutrient removal considerations that required re-evaluation of all previously screened treatment alternatives.
The WLA established planning-level targets for future expansion to 50 MGD MMF that included:
CBOD₅ = 2.9 mg/L TSS = 5.0 mg/L Ammonia-N = 0.5 mg/L Total Phosphorus = 0.30 mg/L
Additionally, EPD specifically noted that future Total Nitrogen limitations may ultimately be required to address nutrient impacts associated with downstream West Point Lake. The WLA further identified the need for completion of an Antidegradation Analysis, Environmental Information Document (EID), and Design Development Report (DDR) prior to future permit issuance for the expanded facility.
As a result of these regulatory developments, alternative evaluation efforts originally focused on
7 | P a g e capacity expansion and rehabilitation were expanded to include advanced nutrient removal capabilities, future Total Nitrogen compliance flexibility, tertiary treatment technologies, filtration strategies, denitrification approaches, and future treatment process optimization requirements.
Parameter Existing Permit WLA Planning Target Future Planning Basis
CBOD₅ 13.0 mg/L 2.9 mg/L 2.9 mg/L
TSS 10.0 mg/L 5.0 mg/L 5.0 mg/L
Ammonia-N 1.8 mg/L 0.5 mg/L 0.5 mg/L
Total Phosphorus 0.52 mg/L 0.30 mg/L 0.13 mg/L
Total Nitrogen Monitor Only Monitor Only 4.0 mg/L
Table 1.6-1 Existing Permit Requirements, WLA Requirements, and Future Planning Targets
Future Planning Basis values reflect planning assumptions used during evaluation of alternatives and long-term regulatory compliance flexibility and do not represent currently enforceable permit limits.
The progression shown in Table 1.6-1 demonstrates the regulatory challenge facing the SCWRF expansion effort. While the existing facility has consistently performed well under current permit requirements, the WLA introduced significantly lower planning-level effluent targets and highlighted the potential for future Total Nitrogen limitations. As a result, future treatment technologies had to be evaluated not only on their ability to achieve the required increase in hydraulic capacity, but also on their capability to maintain compliance under increasingly stringent nutrient removal requirements. These considerations became a central decision factor during the alternatives evaluation process and directly influenced advancement of Alternatives A11.3 and A14.2 into the final refinement phase of the Facility Plan.
In addition, NPDES permits are generally renewed on five-year cycles. The current permit is scheduled to expire in 2027, and future permit reissuances occurring throughout the planning horizon may incorporate additional nutrient management requirements as Georgia Environmental Protection Division (EPD) initiatives continue to evolve. For planning purposes, CCWS anticipates that future permit reissuances, including the permit cycle anticipated around 2032, could potentially include more stringent nutrient removal requirements than those currently contained within the existing permit. Consequently, future treatment alternatives were evaluated not only for current WLA compliance, but also for their ability to adapt to evolving regulatory requirements over the life of the facility.
1.7 Facility Planning Process
Development of the Facility Plan was completed through multiple technical memoranda, condition assessment reports, hydraulic evaluations, BioWin® wastewater process modeling efforts, alternative screening workshops, and collaborative review sessions involving CCWS, Jacobs, owner advisor, and Ardurra.
Initial planning efforts evaluated numerous biological treatment and nutrient removal alternatives including conventional activated sludge expansion, multiple Biological Nutrient Removal (BNR) configurations, tertiary membrane treatment systems, deep-bed denitrifying filtration systems, and combinations thereof. These alternatives were analyzed using hydraulic modeling, process
8 | P a g e simulation, capital cost estimating, present value evaluations, constructability assessments, site utilization studies, sequencing evaluations, and implementation planning analyses.
Following completion of the alternatives evaluation process and subsequent review by CCWS and Jacobs, a formal Alternative Advancement Framework was established. This process identified Alternatives A11.3 and A14.2 as the primary candidates for continued refinement during the final phase of Facility Plan development.
1.8 Purpose of the Final Facility Plan and Deliverables
The purpose of the Final Facility Plan is to:
Document the evaluation of existing SCWRF facilities.
Establish planning criteria based upon current permit requirements and future WLA planning objectives.
Evaluate future regulatory compliance requirements and treatment needs.
Compare alternatives capable of supporting expansion to 50 MGD MMF.
Define recommended treatment process improvements and facility rehabilitation projects.
Establish phased implementation strategies tied to projected flow triggers and regulatory needs.
Support future permitting, environmental review, and project delivery efforts.
Provide a long-term planning framework through at least 2050.
The Facility Plan is intended to function as a living planning document and should be periodically updated as regulatory requirements, treatment technologies, growth projections, and operational conditions continue to evolve. Future updates should incorporate actual operating experience, revised population and flow projections, facility performance data, regulatory developments, and lessons learned from implementation of future capital projects.
1.8.1 Facility Planning Process
Development of the Facility Plan was completed through a progressive series of technical evaluations, workshops, condition assessments, hydraulic evaluations, process modeling efforts, alternatives analyses, and collaborative review sessions involving CCWS, Jacobs, and Ardurra.
The planning process evolved significantly following issuance of the November 2025 WLA, which expanded the scope of the evaluation from a conventional capacity expansion study into a long-range regulatory compliance and treatment technology planning effort.
Major project deliverables included:
TM No. 1 – Sampling Plan Recommendations TM No. 2 – Population and Flow Projections TM No. 3 – Initial Findings and Urgent Issues TM No. 4 – Evaluation of Facilities and Equipment Condition Performance Reports (CPRs) Workshop #1 Workshop #2 Alternative Screening Evaluation Revised TM No. 5 – Process Model and Hydraulics Revised TM No. 6 – Development of Preliminary Scenarios Alternative Refinement Phase
9 | P a g e
Final Facility Plan Development
1.8.2 Alternative Advancement Framework
Following completion of Workshop #2 and subsequent review of alternative evaluation results by CCWS, Jacobs, and Ardurra, an Alternative Advancement Framework was established to guide the Technical Refinement Phase of the Facility Plan. The purpose of the framework was to focus detailed evaluation efforts on the alternatives that offered the most favorable combination of treatment performance, future regulatory compliance flexibility, site utilization, constructability, implementation sequencing, and lifecycle cost considerations.
Alternatives were categorized as Primary Alternatives, Secondary Alternatives, and Alternatives Not Advanced Further.
Category Alternatives
Primary Alternatives A11.3, A14.2
Secondary Alternatives A12, A13, A14.1, A15
Not Advanced Further A9, A10.1, A10.2, A11.1, A11.2
Table 1.8-1 Alternative Advancement Framework
The Alternative Advancement Framework did not constitute final selection of a preferred alternative. Rather, it identified the alternatives considered most appropriate for continued development and refinement during completion of the Facility Plan. Among those alternatives, A11.3 represents a conventional treatment approach centered on a consolidated 4-Stage Bardenpho process with deep bed denitrifying filtration, while A14.2 represents a compact footprint alternative utilizing a 5-Stage Bardenpho process with tertiary membrane treatment.
Detailed evaluation of these alternatives is presented in Sections 5 and 6 of this Facility Plan.
SECTION 2
EXISTING FACILITIES EVALUATION
2.1 Existing Facility Overview
The SCWRF is one of four major wastewater treatment facilities owned and operated by the CCWS. Located at 490 Lee Industrial Boulevard in Austell, Georgia, the facility serves the southwestern portion of Cobb County, including portions of the Cities of Austell, Mableton, Powder Springs, Marietta, and Smyrna, as well as limited service areas within Douglas and Paulding Counties. Treated effluent from the facility is discharged to the Chattahoochee River under NPDES Permit No. GA0026158.
The SCWRF currently operates as a conventional activated sludge facility with primary clarification, secondary clarification, tertiary filtration, chemical phosphorus removal, disinfection, and biosolids handling processes. The facility has a permitted MMF capacity of 40 MGD and is designed to treat an ADF of approximately 33 MGD and a Peak Wet Weather Flow (PWWF) of approximately 86 MGD.
Since its original construction in 1963, the SCWRF has undergone multiple expansions, modifications, rehabilitation projects, and process upgrades. Major improvements completed over the life of the facility have included expansion of liquid treatment capacity, implementation of biological nutrient removal processes, installation of tertiary filtration, biosolids handling modifications, construction of the South Cobb Tunnel and Influent Lift Station, and various other reliability improvement projects. More recent capital investments have included rehabilitation of the effluent filtration facility, improvements to the plant headworks, and other process reliability upgrades. Additional facility improvements underway include replacement of the dissolved air flotation thickening process with rotary drum thickening facilities and rehabilitation of the five existing secondary clarifiers.
P a re
.1
-1
Ex is tin g
So ut h C ob b
W at er R ec la m at io n
Fa ci lit y
Pr oc es s
Fl ow
S ch em at ic
P a re
.1
-2
Ex is tin g
So ut h C ob b
W at er R ec la m at io n
Fa ci lit y
H yd ra ul ic P ro fil
The existing facility layout and treatment configuration reflect more than sixty years of incremental growth and development. As a result, treatment processes, hydraulic conveyance systems, support facilities, and equipment installed during different construction eras must now function together to meet increasingly stringent regulatory requirements while supporting future expansion of the facility to 50 MGD MMF. Evaluation of these existing facilities and their ability to support future treatment objectives is a key component of this Facility Plan.
Figure 2.1-1 above presents the existing SCWRF process flow schematically illustrating the movement of liquid and solids through the treatment process through the existing South Cobb Water Reclamation Facility. The SCWRF currently operates as a conventional activated sludge treatment facility consisting of influent screening, grit removal, primary clarification, biological treatment, secondary clarification, tertiary filtration, disinfection, biosolids thickening, and dewatering processes. The process flow diagram reflects the treatment configuration evaluated during development of this Facility Plan.
Figure 2.1-2 presents the existing hydraulic profile utilized during development of this Facility Plan and illustrates key hydraulic control elevations throughout the treatment process.
Detailed evaluations of existing facility performance, condition assessments, equipment reliability, hydraulic limitations, and rehabilitation needs were previously documented within TM No. 3 – Initial Findings and Urgent Issues Report and TM No. 4 – Evaluation of Facilities and Equipment. The following sections summarize the key findings from those evaluations that are most relevant to future expansion planning, regulatory compliance, and development of the recommended capital improvement program.
2.2 Existing Facility Performance Summary
2.2.1 Historical Facility Performance
The South Cobb Water Reclamation Facility has historically provided reliable wastewater treatment and has consistently met the requirements of NPDES Permit No. GA0026158 under existing operating conditions. Operational data reviewed during development of this Facility Plan indicate that the facility has maintained compliance with established permit limitations for carbonaceous biochemical oxygen demand (CBOD₅), total suspended solids (TSS), ammonia-nitrogen, total phosphorus, and other regulated parameters while treating flows approaching the facility's current design capacity.
The facility currently operates as a conventional activated sludge treatment plant with chemical phosphorus removal, tertiary filtration, disinfection, and biosolids management processes. Historical operating data demonstrate that the SCWRF has benefited from proactive operations and maintenance practices and continued capital investment, allowing the facility to maintain regulatory compliance despite the age of many treatment processes and support systems.
While overall treatment performance remains satisfactory, the evaluations completed as part of this Facility Plan identified multiple process areas where aging infrastructure, operational limitations, and maintenance-intensive equipment are placing increasing demands on operations staff and limiting the facility's ability to accommodate future regulatory requirements and projected flow increases.
2.2.2 Flow and Loading Trends
The Population and Flow Projections evaluation documented continued increases in wastewater flows within the South Cobb service area. ADF increased from approximately
23.8 MGD in 2017 to approximately 28.6 MGD in 2024. Population and flow forecasting completed as part of TM No. 2 concluded that the SCWRF is projected to approach its current permitted 40 MGD MMF capacity around 2031 based on historical trends, with projected intergovernmental contributions potentially accelerating this timeline to approximately 2029.
TM No. 2 further established planning trigger criteria of approximately:
29.2 MGD ADF
36.5 MGD MMF
to initiate implementation of facility improvements needed to support future expansion and permit compliance objectives.
These findings confirmed that expansion planning should proceed immediately to maintain adequate schedule flexibility for planning, permitting, procurement, design, and construction activities.
2.2.3 Existing Process Limitations
Although current permit compliance has generally been maintained, previous evaluations completed by CCWS and its consultants identified several process limitations that affect long-term facility reliability and future expansion capability.
These limitations include:
Ineffective grit removal performance.
Aging primary clarification equipment.
Secondary clarification capacity constraints.
Maintenance-intensive solids pumping systems.
Biosolids thickening inefficiencies.
Reuse water system reliability concerns.
Aging instrumentation, controls, and electrical infrastructure.
In addition, TM No. 3 identified four urgent facility issues requiring attention:
1. Stormwater-related concerns associated with elevated fecal sampling results.
2. Excessive rag loading throughout treatment processes.
3. High maintenance requirements for solids management pumping systems.
4. Reliability concerns associated with the plant reuse water system.
These issues were found to be interconnected and have influenced both the rehabilitation recommendations and expansion alternatives developed throughout this Facility Plan.
Category Summary Finding
Permit Compliance Facility historically meets current permit requirements
Current Permitted Capacity
40 MGD MMF
Current Operating Flow (2024)
Approximately 28.6 MGD ADF
Primary Expansion Driver
Future flow growth and need for 50 MGD capacity
Major Operational Challenge
Aging infrastructure and increasing maintenance demands
Major Regulatory Challenge
Compliance with WLA requirements and future nutrient limits
Urgent Facility Concerns
Stormwater, rag loading, solids management pumps, reuse water reliability
Primary Planning Objective
Expansion to 50 MGD MMF while maintaining future regulatory compliance
Table 2.2-1 Existing Facility Performance Summary
The operational evaluations, condition assessments, and process reviews completed under TM No. 3 and TM No. 4 established that the SCWRF is capable of continuing to meet current permit requirements; however, significant rehabilitation needs, process limitations, and future regulatory requirements must be addressed to support long-term operation and expansion to 50 MGD MMF. The following section summarizes the key findings from those evaluations that directly influence future capital improvement planning and alternative development.
2.3 Existing Facility Assessment Summary
2.3.1 Overview
Detailed facility assessments were previously completed and documented in TM No. 3 – SCWRF Initial Findings and Urgent Issues Report and TM No. 4 – SCWRF Evaluation of Facilities and Equipment. These evaluations included site inspections, staff interviews, historical document reviews, equipment assessments, operational observations, and preliminary condition evaluations of major treatment processes and support systems throughout the facility.
The purpose of these evaluations was to identify facility conditions that could impact long-term reliability, operational efficiency, maintenance requirements, treatment performance, future expansion capabilities, and regulatory compliance. The findings from TM No. 3 and TM No. 4 formed a critical basis for development of the rehabilitation recommendations, capital improvement planning efforts, process evaluations, and alternatives screening completed during the Facility Planning process.
2.3.2 Summary of TM No. 3 Findings
TM No. 3 identified four facility issues that were considered urgent due to their ongoing impact on operations, maintenance, system reliability, and future plant performance.
These issues were also determined to be highly interconnected, requiring consideration as part of a comprehensive facility improvement strategy.
The four urgent concerns identified were:
1. Stormwater Management Concerns associated with elevated fecal indicator concentrations observed within stormwater runoff potentially originating from offsite sources connected to the SCWRF drainage system.
2. Excessive Rag Loading throughout the treatment process resulting from limitations of the existing screening systems and operational impacts associated with flows received from the South Cobb Tunnel Influent Lift Station. Rag accumulation was documented in multiple downstream treatment processes and support systems.
3. Maintenance Intensive Solids…
This is the start of the file's text. The full file is on GovTribe.