This is a Pre-Solicitation Notice issued by Cobb County Water System for progressive design-build services related to the expansion of the South Cobb Water Reclamation Facility. The County seeks a Design-Builder to provide professional, construction, and commissioning services to expand the facility from its current permitted capacity of 40 Million Gallons per Day (MGD) Maximum Month Flow to 50 MGD MMF. The RFP is scheduled for release on Friday, January 8, 2027, with a response submission deadline of Thursday, February 25, 2027. Proposers must submit both technical qualifications and cost proposals, which will be evaluated concurrently using a single-step, best-value selection process. The project will follow a two-phase progressive design-build delivery method, with Phase One encompassing site investigations, preliminary engineering, design development, and preconstruction services, culminating in a proposed price, schedule, and Guaranteed Maximum Price (GMP) based on 60% design completion. Phase Two services, contingent upon Owner approval, will include final design completion, construction, and commissioning. All responses must be submitted electronically via the County's eProcurement Portal.
The estimated project budget is between $300 million to $400 million, with the final GMP dependent on final process design and value engineering during Phase One services. Proposers and their key firms must be licensed in the State of Georgia, with the Design-Builder possessing a valid Georgia Utility Contractor License and/or Georgia Commercial General Contractor License, and the Engineer of Record must be licensed as a Professional Engineer in Georgia. Proposers must demonstrate capacity to obtain 100% Performance and Payment bonds for the project. The County is considering two primary treatment alternatives—Alternative A11.3 (4-Stage Bardenpho Process with Deep Bed Conventional Filters) and Alternative A14.2 (5-Stage Bardenpho Process with flat plate membranes)—while remaining receptive to innovative solutions that meet or exceed project goals. A significant constraint involves obtaining subsurface approvals and easements from both Fulton County and the Federal Aviation Administration to route utilities under restricted Fulton County Airport property. No inquiries will be accepted until the official RFP is issued in January 2027, at which time a formal Q&A process will be established via the OpenGov portal.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| South Cobb WRF Facility Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Solicitation Notice Page 1
PRE-SOLICITATION NOTICE
REQUEST FOR PROPOSALS FOR PROGRESSIVE DESIGN-BUILD SERVICES
SOUTH COBB WATER RECLAMATION FACILITY EXPANSION
PROGRAM NO. T3030
PURPOSE OF NOTICE
NO ACTION IS REQUIRED BY PROPOSERS AT THIS TIME. This Notice provides preliminary information to prospective Proposers (also referred to herein as Design-Builders) regarding an upcoming Request for Proposals (RFP). This is NOT a formal solicitation. No awards will be made from this notice, and the timeline provided, budget, and scope are subject to change.
INTRODUCTION/BACKGROUND
Cobb County Water System (“Owner” or “County”) intends to select a Design-Builder to provide professional, construction, and commissioning services for the expansion of South Cobb Water
Reclamation Facility from its current permitted capacity of 40 Million Gallons per Day (MGD)
Maximum Month Flow (MMF) to 50 MGD MMF. The project will use the Progressive Design-Build delivery method. The upcoming RFP will require Proposers to submit both technical qualifications proposal and cost proposal, which will be reviewed and evaluated concurrently using a single-step, best-value selection process.
ESTIMATED TIMELINE
The estimated timeline for the RFP solicitation is as follows:
RFP Release Date: Friday, January 8, 2027
Response Submission Deadline: Thursday, February 25, 2027
ESTIMATED BUDGET
The estimated budget for this project is between $300M to $400M.
Proposers are advised that the final Guaranteed Maximum Price (GMP) will depend on the final process design and value engineering accomplished during the Phase One services.
PROCUREMENT METHODOLOGY
It is anticipated that a contract for the described services will be entered into with the firm that, in the opinion of County, offers the most favorable combination of qualifications and pricing. The
Evaluation Committee considers the cost information merely as one of the selection criteria and not the final determinant. The County may request additional information and/or may conduct interviews of responding firms.
Procurement will be in accordance with the Competitive Proposals section of the Policy for the
Procurement of Professional Services as adopted on July 22, 1997 and most recently revised on
November 20, 2025 by the Board of Commissioners.
All responses to the upcoming RFP must be submitted electronically via the County’s eProcurement
Pre-Solicitation Notice Page 2
Portal at: https://procurement.opengov.com/portal/cobbcoga
PROGRESSIVE DESIGN-BUILD CONCEPT & CONTRACT
The progressive design-build method of delivering infrastructure projects combines the Owner’s direct control over project concept and detailed design with the Design-Builder’s innovation and creates a single point of accountability. The goal is to create a collaborative Project Team with the
Owner, Owner’s Advisor, and Design-Builder to work seamlessly to successfully design and construct the proposed Project.
The Project consists of two phases. Phase One services generally consists of site investigations, preliminary engineering, design development, and preconstruction services as well as preparation of a proposed price and schedule in close collaboration with the Owner. The proposed price and schedule would be based on preparing a design to sixty percent (60%) level of completion, a GMP, the project schedule, and supporting documentation such as detailed open-book costing for the GMP. At the discretion of the Owner, the Owner can convert the GMP to a lump sum price for the Phase Two
Services. The Phase Two Services, if approved by the Owner, generally encompass completing the project’s final design, construction, and commissioning.
The County anticipates utilizing a modified version of the Design-Build Institute of America (DBIA)
Contract Document No. 545, Progressive Design-Build Agreement for Water and Wastewater
Projects, and DBIA Contract Document No. 535, Standard Form of General Conditions of Contract
Between Owner and Design-Builder.
TEAMING, LICENSING & BONDING EXPECTATIONS
Proposers and their key firms must be licensed in the State of Georgia for the type of work to be performed.
The Design-Builder shall possess a valid Georgia Utility Contractor License and/or a Georgia
Commercial General Contractor License. The designated Engineer of Record must be licensed as a
Professional Engineer in the State of Georgia.
Proposers must have the capacity to obtain 100% Performance and Payment bonds for the estimated
$300M - $400M project budget.
PLANNING DOCUMENTS
The County retained Ardurra Group, Inc. to prepare a long-range Facilities Plan for the South Cobb
WRF. The primary purpose of the planning effort was to evaluate the existing facility, identify rehabilitation and reliability needs, assess future treatment requirements, and develop a comprehensive strategy for expanding the facility. Portions of the Facility Plan have been removed for clarity. A copy of the redacted plan can be found in ATTACHMENT A.
Disclaimer: The redacted South Cobb WRF Facility Plan is provided for informational purposes only. The redacted Facility Plan contains preliminary data. This includes, but is not limited to, flow projections, cost estimates and construction sequencing narratives. Cobb
County assumes no liability or responsibility for any errors, omissions, or inaccuracies within this document. By accessing this document, prospective Proposers acknowledge that they bear https://procurement.opengov.com/portal/cobbcoga
Pre-Solicitation Notice Page 3 the sole burden of conducting all independent investigations and data verifications they deem necessary to assume full responsibility prior to submitting a proposal.
PROJECT SCOPE CLARIFICATIONS & CONSTRAINTS
Please note the following scope clarifications and constraints:
Scope Clarifications: The Facility Plan evaluated 11 alternatives. A decision was not made during the conclusion of the Facility Plan on which of these alternatives to implement; however, the County is considering two Primary Alternatives (Alternative A11.3 – consisting of a 4-Stage Bardenpho
Process with Deep Bed Denitrifying Filters and Alternative A14.2, consisting of 5-Stage Bardenpho
Process with Tertiary Membranes) but with strict modifications. If Alternative A11.3 is selected in
Phase 1, the Owner requires Deep Bed Conventional Filters and not Deep Bed Denitrification Filters.
If Alternative A14.2 is selected in Phase 1, the Owner requires a flat plate membrane design and not hollow-fiber membrane design. The Owner remains receptive to other innovative solutions that the
Design-Builder may propose that meet or exceed project goals. During Phase One, the Design-
Builder will lead an Alternative Evaluation Phase to finalize the selected technology pathway to carry into 30% design.
Easements: Immediately north of the South Cobb WRF, Fulton County, Georgia owns three parcels of land housing an approach lighting system for the Fulton County Airport. The Design-Builder will be prohibited from accessing these Fulton County parcels due to Federal Aviation Administration
(FAA) flight zone restrictions. Just north of these three parcels, Cobb County owns two parcels of adjoining land that are available to the Design-Builder for temporary staging and/or permanent construction. Connecting the available Cobb County parcels to the South Cobb WRF will require routing utilities under the restricted Fulton County land. The Design-Builder will be responsible for obtaining all necessary subsurface approvals and easements from both Fulton County and FAA.
PROJECT INFORMATION & INQUIRIES
A formal Q&A process will be established via the OpenGov portal once the official RFP is released in January 2027. NO INQUIRIES ACCEPTED UNTIL RFP IS ISSUED.