The provided file is a Sources Sought Information Form for Project P-481 Energy Resilience Phases 3 & 4 at the Mountain Warfare Training Center in Bridgeport, California, issued by the Department of the Navy Naval Facilities Engineering Command. The solicitation is a pre-solicitation opportunity seeking contractors to develop a comprehensive energy resilience solution for a military training center located in a challenging mountain environment prone to power disruptions.
The project requires installing a 1 MW generator, 500 kW of solar photovoltaics, electrical infrastructure upgrades, and an advanced microgrid control system to enhance energy reliability and redundancy. Additional options include expanding solar PV capacity up to 2 MW, providing a central monitoring building, and installing a 500 kW Battery Energy Storage System (BESS). The project emphasizes cybersecurity, with requirements for certification and accreditation of facility-related control systems, and aims to enable the base to operate critical services independently during extended grid outages. The solicitation appears to be targeting small businesses, with checkboxes for various SBA certification types, and includes forms for contractors to detail their construction experience and capabilities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P481_SOURCES SOUGHT NOTICE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(Rev. 11/21)
SOURCES SOUGHT – CONTRACTOR INFORMATION FORM
FOR
PROJECT P-481 ENERGY RESILIENCE PHASES 3 & 4, VARIOUS LOCATIONS AT MOUNTAIN
WARFARE TRAINING CENTER, BRIDGEPORT, CALIFORNIA
Use this form to provide contractor’s general information. Please limit response to one page. The box at the bottom of this form may be used to clarify any requested information.
1. Contractor Information:
Unique Entity
ID:
CAGE Code:
Firm Name:
Address:
Name of POC for firm:
Phone Number of POC: Email of POC:
2. Type of Business: (check all that apply)
SBA certified 8(a) firm SBA certified HUBZone Small Business
Service-Disabled Veteran-Owned Small Business Small Business
SBA certified Women-Owned Small Business Other than Small Business
3. Bonding Capacity:
Surety Name:
Maximum bonding capacity per project: $ Aggregate maximum bonding capacity: $
4. This space may be used to provide any additional information to clarify the above items only:
Form may be expanded. Please DO NOT change content of the form.
SOURCES SOUGHT – CONSTRUCTION EXPERIENCE PROJECT DATA FORM
for
MILCON PROJECT P-480 ENERGY RESILIENCE PHASE 1 & 2 AND MILCON PROJECT P-481
ENERGY RESILIENCE PHASES 3 & 4, VARIOUS LOCATIONS AT MOUNTAIN WARFARE
TRAINING CENTER, BRIDGEPORT, CALIFORNIA
Use this form (one per project) to provide supporting information that demonstrates project experience relevant to the subject announcement. Submit up to five (5) projects. Please limit response to two (2) pages per project.
1. Contractor Name:
2. Project No. (check one): - 1 - 2 - 3 - 4 - 5
3. Contract Number: Delivery/Task Order No.:
Project Number:
Title:
Location:
4. Award Date (mm/dd/yy): 5. Final Contract Price: $ Completion Date (mm/dd/yy): (includes all options and mods)
Project is % complete (as of submission due date) This is the total project subcontract price.
6. Type of work: New Construction Repair Renovation
7. Customer/Owner Name:
Point of Contact Name/Title:
(person with project knowledge)
POC Phone Number: POC Email Address:
8. Were you the Prime contractor for this project? Yes No Were you a subcontractor for this project? Yes No
If subcontractor, who was the Prime contractor?
9. Type of Contract (check all that apply):
Design-Build Design-Bid-Build Other (explain):
If Design-Build, provide the following information: Design accomplished in-house Lead design firm name: Years working together:
Address:
10. Provide a detailed description of the project:
11. Percentage of work you self-performed on this project: %.
Provide a detailed description of the work your firm self-performed on this project:
Form may be expanded. Please DO NOT change content of the form.
PROJECT P-481 ENERGY RESILIENCE PHASES 3 & 4, VARIOUS LOCATIONS AT MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, CALIFORNIA