SOO.pdf

PDF 6 MB Posted

Attached to
Shaw OS2 High Speed Fiber Optic Cable
Solicitation number
FA480326Q0112
Issued by

About this file

This Statement of Objectives (SOO) defines requirements for a contractor to Engineer, Furnish, Install, and Test (EFI&T) 48-strand single-mode fiber optic cable (FOC) infrastructure at Shaw Air Force Base, South Carolina. The project involves installing approximately 11,400 linear feet of new FOC distributed across four primary cable routes connecting Buildings B01109, B00216, B00710, B01129, and B01601. The contractor must provide new Fiber Optic Distribution Panels (FODPs) with LC-type connectors, install geotextile fabric inner-duct (MaxCell) infrastructure, and perform comprehensive testing in accordance with TIA 526-7-A standards, including bi-directional optical attenuation testing at 1310 nm and 1550 nm wavelengths.

Key project requirements include: obtaining AF Form 103 digging permits 14 calendar days in advance, processing Site Visit Request Letters within 5 calendar days of award, coordinating confined space operations with base safety per AFMAN 91-203, and maintaining weekly status reports throughout performance. The contractor must chair weekly Integrated Process Team (IPT) meetings, provide as-built drawings in Visio and PDF formats, deliver geospatial shape files with ±3 feet GPS accuracy within 30 days of completion, and provide a one-year workmanship warranty. Installation must comply with TIA standards (606-D, 607-E, 758-B), RUS Bulletin 1735F-401 for fiber splicing using core alignment fusion splice methods, and current BICSI standards. The contractor is responsible for environmental compliance including NPDES approvals, site restoration with sod in common areas, disposal of horizontal directional boring residue off-base, and maintaining cable maintenance loops of minimum 50 feet at specified manhole locations. All equipment and materials must be new, not refurbished, with performance occurring at Shaw AFB SC during normal duty hours unless otherwise coordinated with contracting officer approval at least 10 calendar days in advance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

38TH CYBERSPACE ENGINEERING INSTALLATION GROUP (ACC)

TINKER AIR FORCE BASE OKLAHOMA

STATEMENT OF OBJECTIVES (SOO)

OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade

(VLSB-2024-00001-00001)

Shaw AFB SC

21-Feb 2026

Prepared By

38 ES/ENIU

4064 Hilltop Road

Tinker AFB OK 73145-2713

2/13/2026

SOO-OS2 High FOC Infrastructure Upgrade. Shaw AFB SC

1.0 SCOPE.

This SOO defines the requirement for the Contractor to Engineer, Furnish, Install and Test (EFI&T) 48 Strand (ST), Single Mode (SM) FOC as shown below at Shaw AFB SC.

Bldg (B)01109 to B00216.

B01109 to B00710.

B01109 to B01129.

B01109 to B01601.

2 . 0 REQUIREMENTS.

2 . 1 GENERAL REQUIREMENTS.

2.1.1 Safety Requirements.

The contractor shall remain in compliance with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.

2.1.2 Site Coordination.

The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.

2 .1. 2 .1 Confined Space.

The Contractors and Sub-contractors entering spaces on Shaw AFB SC are responsible for the safety of their personnel and for their own permit space program as outlined in AFMAN 91-203. All confined space operations must be coordinated with the Base

Safety Office prior to starting work. The primary Contractor is responsible for all

Sub-contractor confined space operations.

2.1.2.2Accident/Incident Reporting and Investigation.

The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel. Notification shall be provided to the 20CS/SCX Project Manager and the Base Safety Office unless otherwise stated in the SOO. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base

POC. If the Government elects to conduct an investigation of the incident, the

Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.

2.1.2.3 Work Area(s).

At day's end, the Contractor shall remove all debris and surplus materials from the workplace. Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the workday. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard. The contractor shall co-ordinate with the 20CS/SCX to ensure that any locking manhole covers are put back in place at the end of each workday.

2 .1. 2. 4 Traffic control.

In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall notify the 20CS/SCX PM LT 10 calendar days in advance to inform base Security Forces and Emergency Services personnel of the planned disruptions.

2/13/2026 Page 2 of 28

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade. Shaw AFB SC

2 .1. 2. 5 Airfield Driving.

Any person operating a motor vehicle inside the airfield fence on Shaw AFB SC shall coordinate with airfield management to obtain the required training/certifications IAW local procedures.

2.1.3 Security Requirements.

The Contractor shall process and provide a Site Visit Request Letter to 20CS/SCX within 5 calendar days after contract award. This letter shall identify the names (as shown on the driver's license), driver's license numbers and state of issue, and birth date of the personnel who will be performing work under this SOO. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.

2 . 1 . 3. 1 Security Clearances .

Stated work and associated products shall be performed at the UNCLASSIFIED level.

However, some of this work may take place in secure areas where Contractor employees must be escorted at all times. The Contractor must coordinate access to secure areas at least five (5) calendar days ahead of time. It is the Government's responsibility to provide escorts.

2 .1. 3. 2 Country Clearances. "Reserved".

2.1.3.30perational Security (OPSEC).

Network infrastructure drawings (MHDS, MH/HH locations, fiber paths, etc.) are on 7 CS/SCXP Critical Information List and must be protected. The Contractor shall take appropriate measures to protect detailed information pertaining to the EFI&T effort, to include appropriate marking of documents as "Controlled Unclassified Information (CUI)," and ensuring limited distribution of documents and schematics/drawings to only those individuals with a valid need to know. IAW AFI 10-701, OPSEC Considerations, the contractor shall follow the OPSEC guidance/plan (AFil0-701) to ensure the protection of CUI data either furnished by the government or produced by the contractor.

2.1.4 Environmental Compliance.

The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations, and Air Force policies, instructions, and plans.

The federal Government is not exempt from compliance with environmental regulations.

The Contractors are responsible to know and follow all applicable Federal, State, Local and Air Force regulations for environmental protection, including waste disposal, sewer discharge, air emissions, and storm water requirements. The contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Shaw AFB SC. The Prime Contractor shall ensure that their subcontractors (if any) comply with these specifications.

2.1.5 Permits (If applicable).

The Contractor shall be responsible to coordinate, complete and process all permits required to complete the installation prior to any trenching, horizontal directional boring or modifications to a facility, maintenance hole (MH) or hand-hole (HH). For example:

2/13/2026 Page 3 of 28

• Digging permit, AF Form 103 shall be submitted through BCE 14 calendar days in advance of digging activities. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 remains current.

• Confine space entry permit, AF Form 1024 shall be coordinated through base safety office. The Contractor shall be prepared to provide proof of their

Confined Space Training Program along with the AF Form 1024 to base safety.

• Base Civil Engineering Work Clearance Request, AF Form 332 shall be submitted through BCE 14 calendar days in advance of planned work.

• The Contractor shall trench, excavate, and mark and barricade open trenches IAW OSHA Standards.

All utility markings, flags, etc. shall be maintained by the contractor after the responsible work center/shop identifies/locates them and ensure that the AF Form 103 remains current. The contractor shall take precautions to protect existing infrastructure. If a utility is severed or damaged due to neglect or if attributed to the fault of the contractor, then the contractor shall repair and return the utility back to the same condition it was in prior to the damage.

2.1. 6 Integrated Process Team (IPT).

The Contractor shall chair a weekly IPT meeting that includes Contractor representatives, the Government Contracting Officer (CO), the CSI-B, the System

Engineer(s), the Government Project Manager, and other base personnel as required.

The Contractor shall provide an agenda NLT 1 working day prior to the scheduled meetings. The Contractor shall provide worldwide "Meet Me" teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute to the attendees NLT 1 working day after each meeting.

2.1. 7 Quality Assurance.

The Contractor shall provide Quality Assurance Support for the entire life of the project. The Contractor's quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The

Contractor shall be responsible for identifying system and outside plant deficiencies and/ or discrepancies throughout the life of the project. A weekly report ( soft copy) shall be submitted indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them.

2.1.8 Contractor Personnel.

2 .1. 8 .1 Project Management.

The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project

Manager's or alternate's range of authority to act for the Contractor relating to daily contract operation.

2 .1. 8. 2 Site Point of Contact (POC).

The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site POC for individual projects in their Site Visit Request Letter. The

Site POC or alternate(s) shall be on site during duty hours for the duration of the project, up to and until final acceptance by the Government PM and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters.

2/13/2026 Page 4 of 28

2 .1. 8. 3 Personnel Requirements.

The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English and shall be on site to coordinate permits, clearances, and receive shipments/material related to the task order.

2.1.8.4Minimwn Contractor Qualifications.

All work shall be performed by an experienced Telecommunications Contractor. The

Contractor shall have a minimum of 3 years of experience in Telecommunications

Systems installations.

2 .1. 8. 5 System for Award Management (SAM) .

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for

Installation via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address https://www.sam.gov.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs from October 1 through September

30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the SAM help desk.

2 .1. 9 Warranty

The Contractor shall provide a one-year warranty or manufacturer's standard commercial warranty, whichever is longer. The warranty shall be, at a minimum, IAW the standard or equivalent. This warranty shall include a one-year workmanship warranty. The warranty period shall start from the date of system and/or project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.

2 .1.10 Manuals and Practices.

The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new equipment.

2.2 SPECIFIC REQUIREMENTS.

The Contractor shall EFI&T the followings:

Approximately 4200 feet of 48 St OS2 SM FOC from B01109 to B00216.

Approximately 1600 feet of 48 St OS2 SM FOC from B01109 to B0710.

Approximately 1600 feet of 48 St OS2 SM FOC from B01109 to B01129.

Approximately 4000 feet of 48 St OS2 SM FOC from B01109 to B01601.

The contractor shall install new Fiber Optic Distribution Panel (FODP) and all other associated equipment/materials required to install, terminate and test the new FOC.

The Contractor shall provide all tools, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOO. The Contractor shall comply with the current TIA telecommunication installation and testing commercial standard and base installation standards. All equipment, supplies, and materials provided shall be new and not refurbished.

2/13/2026 Page 5 of 28

2 . 2 . 1 Backboards. "Reserved"

2.2.2 Equipment Cabinets. "Reserved".

2.2.2.1 Grounding and Bonding

All new and existing racks/cabinets housing equipment for this project, as well as all ladder rack/and cable tray shall be bonded and grounded to the Equipotential Ground Plane IAW TIA-607-E. All Equipment racks and cabinet rails shall be Telecommunications style rails that are unpainted and have drilled and tapped mounting holes IAW DISN Implementation Standards, Ch. 2.7.20 to 2.7.26. Equipment cabinets shall be capable of containing any standard equipment shelves for communications equipment per the current revision of EIA/ECA-310. The Contractor shall test any new or extended ground at the cabinet/rack and at the new grounding/bonding points. The government reserves the right to test and validate newly installed grounds to ensure they meet compliance.

2.2.2.2 Bushings

All penetrations into the rack/cabinet must be reamed, filed and have installed bushing or grommet material. No exposed metal edges shall come in contact with telecommunication cabling.

2.2.3 Outside Plant Requirements.

2.2.3.lExisting Maintenance Holes.

The Contractor shall be responsible for pumping out maintenance holes/handholes.

Water from maintenance holes/handholes shall be pumped into the storm drain system unless it is not available; then it may be pumped out onto the surrounding ground, as long as there is no impact to roads, driveways, or vehicle traffic. Mud and debris shall be disposed of IAW base requirements. If Contractor comes across a manhole with contaminated water, the Contractor shall coordinate with the environmental office in Base CE.

2. 2. 3. 2 Measurements.

Any distances provided in this SOO are approximations and should NOT be used for ordering materials or determining duct lengths.

2 . 2 . 3. 3 Underground Utilities Markings.

The Contractor shall coordinate with base agencies to ensure markings are placed over existing base infrastructure prior to digging or horizontal directional boring and shall take precautions to protect existing infrastructure. The Contractor is responsible for repair of any damage caused during installation when the infrastructure is clearly marked. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 (Dig Permit).

2.2.3.4Closures for Cable Splicing in Maintenance Holes.

2.2.3.4.1 Fiber Optic Splices. "Reserved"

2 . 2 . 3. 5 Splice Connectors .

All splicing shall be performed in accordance with RUS Bulletin 1735F-401, Standards for Splicing Fiber Cable.

The Core Alignment fusion splice method shall be used for all splicing and terminations of fiber optic cable.

2/13/2026 Page 6 of 28

2 . 2 . 3. 6 Labeling.

The Contractor shall label all equipment and cables they install, and cables identified for re-use in accordance with TIA-606-C and as directed by the 20CS/SCX.

2.2.3.6.1 Cable Tags.

All tags shall be permanently labeled, easily visible and corrosion resistant.

Install cable tags in all maintenance holes/hand-holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a maintenance-hole, put a tag on the cable, approximately 2 feet from each duct entrance. Information on the cable tag shall identify cable by size, type, cable number and count. Tagging and labeling of new cables shall be IAW the following:

• Fiber Optic Tags:

A36L8.3F

FO B241-B100, 1-12 +

FO B241-Bl01, 13-24 +

FO B241-B102, 25-36

Line One: A = Armored Sheath (otherwise leave blank) 36

Tube Buffer or (T) Tight Tube Buffer. 8.3 = Single Mode.

leave blank) .

Fiber Count. L = Loose

F = Filled core (otherwise

Lines Two, three and four: 241-100

Count.

From-To Building numbers. 1-12 Cable/strand

2.2.3.6.2 Fiber Optic Distribution Panel (FODP) Marking.

Each FODP shall be stenciled/marked with black ink or paint or adhesive backed decals in letters and numbers. The cover of all new fiber optic distributions (FODPs) shall be labeled to conform to the system used by local maintenance personnel to identify FODPs that terminate fiber. If the manufacturer has not identified the sequence in which ports on FODPs (pigtail modules) are counted, the Contractor shall provide designation labels/strips to identify the sequence in which they are counted.

Each splice tray shall be marked to identify the fiber count contained in the splice tray. The marking shall identify the FODP by number (building number), cable number, and count.

FODP-B3

FO B3-B1038, 1-12

FO B3-B1400, 13-24

2.2.3.6.3 New Ducts. 'Reserved".

2. 2. 3. 7 Cable Terminations.

2.2.3.7.1 Fiber Optic Terminations.

Newly installed fiber optic cables shall be terminated on new fiber optic distribution panels using fusion spliced pigtails with LC (per UFC 3-580) connectors or LC fusion splice direct connectors. Distribution panels shall be designed for rack mounting in 19-in (48 cm) racks or wall mounted as required. Panels shall be sized according to cable and method of termination.

2/13/2026 Page 7 of 28

2.2.3.7.2 Grounding and Bonding.

In the Equipment room/Mechanical room in which the cable is to be terminated, there is either a telecommunications main grounding busbar (TMGB) or a telecommunications grounding busbar (TGB) . If a grounding busbar doesn't exist in the equipment room/mechanical room, then the Contractor shall provide it and bond it to the electrical service equipment (power) ground. The grounding conductor shall be tagged with a nonmetallic tag as close as practicable to the point of termination in a readable position. The information on the tag shall contain the following information "If this connector or wire is loose or must be removed, please call Base

Communications Office" or some similar wording. Although it is not anticipated that any splicing will be required in a Maintenance hole, should there be some practical reason that a splice be made, the cable shield (armor) shall be bonded and continuous throughout the cable length. In addition, the splice case shall be bonded to the

Maintenance hole bonding ribbon, if it exists. Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc. necessary to properly bond/ground the cable in MHs/HHs shall be provided by the contractor. Reference TIA

607.

2. 2. 3. 8 FOC Maintenance Loop.

The Contractor shall install a minimum of a 50-foot fiber optic cable maintenance loop at the first MH from the building, at each splice point MH location and at every third manhole. The maintenance loop shall be properly labeled and securely supported by two cable hooks. Cable hooks are to be positioned so the highest one supports the underside of the top of the coil, and the bottom hook supports the underside of the bottom of the coil. The maintenance loop shall have a cable tag.

The same information shall appear on the Contractor's completed as-built-drawings.

2. 2. 3. 9 New Maintenance Holes/Hand-holes. "Reserved' .

2.2.3.9.1 Cable Racks and Cable Rack Supports.

Cable racks shall be installed in maintenance holes and hand holes as required -this includes new and existing MHs/HHs. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case. Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips. All cables shall be supported using racking clips, cable racks, and cable hooks.

2.2.3.10 Underground Conduit System." Reserved".

2.2.3.10.1 Composition.

2.2.3.10.2 Installation.

2. 2. 3 .10. 3 Any open ducts/ innerducts shall be sealed to prevent moisture from entering the maintenance holes.

2.2.3.10.4 Bends and Sealing.

2.2.3.10.5 Utility Separation.

2.2.3.10.6 Spacers and Tracer Wire.

2.2.3.10.7 Warning Tape.

2.2.3.10.8 Entrance Conduits into Existing Maintenance Holes.

2.2.3.10.9 Pull Boxes/NEMA 4 Enclosures. "Reserved".

2.2.3.10.10 Excavation/Building Penetrations.

All wall penetrations, including inside buildings, shall be restored to meet the required base fire ratings.

2/13/2026 Page 8 of 28

2.2.3.10.11 Conduit Protection. 'Reserved".

2.2.3.10.12 Pull Tape. "Reserved".

2.2.4 New Outside Plant Installation.

This section describes the underground maintenance hole/conduit system, flexible geotextile multiple cell fabric inner-duct and fiber optic cable installation requirements. The Contractor shall design and install Customer-Owned "Outside Plant Telecommunications Infrastructure" in according with TIA-758-B. Each cable installation shall be coordinated with the 20CS/SCX so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor's discretion.

See attached Project Sketches reference and estimated distances of existing and proposed infrastructure and cables routes. This is only a proposed solution. The Contractor is free to make any recommendations pertaining to the accomplishment of this requirement in their proposal.

The Contractor shall install underground outside plant infrastructure as described below.

2.2.4.1 Infrastructure Installation.

The contractor shall install the following new infrastructure. All new locations and distances are approximate. (See Project Sketches for additional information).

2. 2. 4 .1.1 New Manholes/Hand-holes. "Reserved".

2.2.4.1.2 New Duct bank Infrastructure. 'Reserved'

2/13/2026 Page 9 of 28

2.2.4.1.3 New Geotextile Fabric Inner-duct (AKA MaxCell).

The contractor shall provide and install new 3", 3-cell (total of 3) Geotextile

Fabric Innerduct inside existing 4-inch conduit as shown at the following table.

Each new 3-cell shall have a separate thread color. Distances are approximate and shown in feet.

From To Distance

MH-lA MH-2A 310

MH-2A MH-2 30

2. 2. 4. 2 New Fiber Optic Cable Installation

The Contractor shall provide and install single mode (SM), loose buffer tube, water blocked, outside plant (OSP) cable suitable for underground applications. The intent is to install the cable in one continuous length, to the extent that it is practical.

The cable shall meet RUS 7 CFR 1755.900 criteria; shall comply with industry standards with regard to manufacturers' cable marking, jacket, rip cords, water blocking, fiber color coding, jacketing materials, etc. In addition, the fibers shall comply with industry standards with regard to mode field diameter, core cladding concentricity, attenuation, and dispersion characteristics at 1310 nm and 1550nm.

All fiber optic cables shall be installed in new or existing geotextile innerduct/ innerduct. Distances are approximate and shown in feet.

Notes:

• Innerduct (Either corrugated/smooth wall).

• Geotextile Fabric Innerduct (AKA MaxCell).

Install the Following 48-St SM Fiber Optic Cables (FOC).

1. Approximately 4000 feet from B01109 to B00216. See the table below and Sketch-

1 & 2 for suggested cable route and additional information.

See the proposed route below (ITB01109 To EB00216)

From To Dist. Path

B01109 MH-31 170 Use existing Vacant MaxCell

MH-31 MH-30 165 Use existing Vacant MaxCell

MH-30 MH-48 335 Use existing Vacant Innerduct

MH-48 MH-49 555 Use existing Vacant Innerduct

MH-49 MH-50 425 Use existing Vacant Innerduct

MH-50 MH-9 155 Use existing Vacant Innerduct

MH-9 MH-10 385 Use existing Vacant Innerduct

MH-10 MH-11 360 Use existing Vacant Innerduct/MaxCell

MH-11 MH-12 410 Use existing Vacant Innerduct/MaxCell

MH-12 MH-13 310 Use existing Vacant Innerduct/MaxCell

MH-13 MH-14 290 Use existing Vacant Innerduct/MaxCell

MH-14 B00216 85 Use existing Vacant MaxCell

2/13/2026 Page 10 of 28

2. Approximately 1600 feet from B01109 to B00710. See the table below and Sketch- 3 for suggested cable route and additional information.

See the proposed route below (ITB01109 To EB00710)

From To Dist. Path

B01109 MH-lA 230 Use existing Vacant MaxCell

MH-lA MH-2A 310 Use new MaxCell

MH-2A MH-2 30 Use new MaxCell

MH-2 MH-3 285 Use existing Vacant MaxCell

MH-3 MH-4 185 Use existing Vacant Innerduct/MaxCell

MH-4 MH-5 420 Use existing Vacant MaxCell

MH-5 B00710 75 Use existing Vacant MaxCell

3. Approximately 1600 feet from B01109 to B01129. See the table below and Sketch- 4 for suggested cable route and additional information.

See the proposed route below (ITB01109 To EB01129)

From To Dist. Path

B01109 MH-lA 235 Use existing Vacant MaxCell

MH-lA MH-2A 310 Use new MaxCell

MH-2A MH-32 30 Use existing Vacant MaxCell

MH-32 MH-33 430 Use existing Vacant MaxCell

MH-33 MH-33B 270 Use existing Vacant MaxCell

MH-33B B01129 310 Use existing Vacant Innerduct/MaxCell

4. Approximately 4000 feet from B01109 to B01601. See the table below and Sketch- 5, 6 & 7 for suggested cable route and additional information.

See the proposed route below (ITB01109 To EB01601).

From To Dist. (Feet) Path

B01109 MH-31 170 Use existing Vacant MaxCell

MH-31 MH-45 265 Use existing Vacant MaxCell

MH-45 MH-46 470 Use existing Vacant MaxCell

MH-46 MH-47 460 Use existing Vacant MaxCell

MH-47 MH-61 775 Use existing Vacant MaxCell

MH-61 MH-60 415 Use existing Vacant MaxCell

MH-60 MH-59 555 Use existing Vacant MaxCell

MH-59 MH-40 545 Use existing Vacant MaxCell

MH-40 HH-105 85 Use existing Vacant MaxCell

HH-105 B01601 165 Use existing Vacant MaxCell

38 E 2/13/2026 Page 11 of 28

2.2.4.3In Building FODP, cable installation and termination.

B01109: The contractor shall provide and install a new Equipment Rack (7' X 19") by removing an existing Equipment Cabinet in the frame room. The new FOC will come through the vault, then through the existing floor penetration to the new Rack. All the new FODPs (4, 48 ports, provided by the contractor) will be installed in the new Rack. The new FOC will be terminated in the new FODPs. LC type connector will be used to terminate the new FOC. FOC cassettes may be used to terminate the new cable.

The installer shall follow the existing cable path/route from the entry location to the Frame Rm. The installer shall verify the final design (cable path and new equipment placement location) with 20CS/SCX. See attached sketch-10 for more information.

The contractor shall test the new FOC and provide the test result to 20CS/SCXP.

B00216: The contractor shall install 48-Port FODP at the Communication/Mechanical Room (#106, 1st floor) in an existing Network (NW) rack (#2). See Sketch-8 for more information. LC type connector will be used to terminate the new FOC. FOC cassettes may be used to terminate the new cable.

The new FOC will come through MH-14 by using existing vacant MaxCell.

The installer shall verify the final design (cable path and new equipment placement location) with 20CS/SCX.

The contractor shall test the new FOC and provide the test result to 20CS/SCXP.

B00710: The contractor shall install 48-Port FODP at the TR Room (#118) at an existing Network (NW) rack. See Sketch-9 for more information.

The contractor shall terminate the new 48-St SM FOC at the new FODP. LC type connector will be used to terminate the new FOC. FOC cassettes may be used to terminate the new cable.

The new FOC will come through MH-5 by using existing vacant MaxCell.

The installer shall verify the final design (cable path and new equipment placement location) with 20CS/SCX.

The contractor shall test the new FOC and provide the test result to 20CS/SCXP.

B01129: The contractor shall install 48-Port FODP at the Frame Room at an existing Network (NW) rack. The new FOC will come through the vault to the existing Rack (frame room). The new FOC will be terminated in the new FODP. LC type connector will be used to terminate the new FOC. FOC cassettes may be used to terminate the new cable.

The installer shall follow the existing cable path/route from the entry location to the Frame Rm. The installer shall verify the final design (cable path and new equipment placement location) with 20CS/SCX.

The contractor shall test the new FOC and provide the test result to 20CS/SCXP.

B01601: The contractor shall install 48-Port FODP at the Communication/Mechanical Room at an existing Network (NW) rack. The new FOC will be terminated in the new FODP. LC type connector will be used to terminate the new FOC. FOC cassettes may be used to terminate the new cable.

The new FOC will come through HH-105 by using existing vacant MaxCell.

The installer shall verify the final design (cable path and new equipment placement location) with 20CS/SCX.

The contractor shall test the new FOC and provide the test result to 20CS/SCXP.

2/13/2026 Page 12 of 28

2.2.5 Project Residue.

All residue from this project shall be disposed of off base and in accordance with

Federal, State, local and base environmental laws and regulations. All residue produced by horizontal directional boring operations (i.e., slurry) shall be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor's expense, IAW federal and state environmental laws and regulations. Under no circumstances will the contractor stage or store boring residue in slurry ponds or other containment areas on Shaw AFB SC.

2.2.6 Site Restoration.

The Contractor shall restore all disturbed grounds to the "as found" condition or better after installation. The Contractor shall comply with all base ground's restoration requirements. Common use areas shall be restored with sod.

2.2.7 Service Outages.

The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).

2.2.8 National Pollution Discharge Elimination System (NPDES).

If required by Base Civil Engineer (BCE), the Contractor shall obtain approvals for

NPDES at State and/or Federal level [in some locations this may be called the Storm

Water Pollution Prevention Plan (SWPPP)]. The storm water/environmental plan is the sole responsibility of the Contractor. Base Civil Engineering/CEV will review and advise to ensure minimum standards and storm water controls/BMPs are in place to ensure compliance; this is a compulsory item in the SOO and contract. The Contractor shall implement storm water controls/BMPs to ensure sediment, as a result of storm water runoff, does not enter storm drainage channels and/or inlets.

The Contractor shall conduct an initial meeting within 10 days of the Contractor site survey with the base environmental office to identify NPDES preparations and/or the storm water/environmental plan.

The Contractor shall review the NPDES requirements applicable to the base; develop a plan to comply with the NPDES; obtain approval of the NPDES plan from all appropriate government agencies; and comply with any other applicable state requirements for construction

2.2.9 Identification/Marking.

The Contractor shall clearly mark all

(CFP/CFE) with their company's name.

very visible, sign (minimum 8.5" x 11") or un-manned rental vehicles while on company name and both the Contractor numbers.

Contractor-Furnished Property and Equipment

The Contractor shall place an easily read, on large containers, construction equipment, the Government installation indicating the and Site POC' s names and local telephone

2/13/2026 Page 13 of 28

2. 2 .10 Installation Schedules.

The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system. All submissions shall be delivered electronically in MS Office-compatible format NLT 10 business days after contract award and as significant schedule changes occur to be determined by the IPT.

2. 2 .11 Weekly Status Reports.

The Contractor shall prepare a Weekly Status Report and distribute to the Government Contracting Officer (CO), the System Engineer(s), the Government Project Manager, and other base personnel as required. The purpose of the report is to inform IPT members of the project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.

2 . 2 . 12 Drawings.

2.2.12.1 As-Built Drawings.

The 20CS/SCX shall supply existing system drawings, and the Contractor shall provide updated drawings in Visio for building and rack elevation; Visio and .pdf for OSP.

These drawings shall depict the entire pathway and details of the installation, including but not limited to labeling, cables, innerducts and maintenance holes/handholes, conduits, maintenance loops, distances, bores, trenches, building entrances. Detailed butterfly drawings will also be required. If the existing cable diagram or butterfly drawings are not available, the contractor shall create the missing cable diagram/ butterfly drawings to include all the components used in this project. The Contractor shall record/deliver geospatial data of new outside plant distribution system.

2.2.12.2 Butterfly Drawings.

The Contractor shall record and submit butterfly, cable path and building penetration drawing information for all new installations including butterfly drawings for all maintenance holes and pull boxes that contain new or reused FOC. Drawings shall record the path and arrangement of new and reused fiber optic cables, splices, and the arrangement of duct banks, ducts, inner-duct and shall show maintenance hole orientation with respect to geodetic north. Drawings shall be submitted in an easily read electronic format such as pdf. Scanned data sheets or legible sketches are acceptable.

2.2.12.3 Geospatial Deliverables.

The Contractor shall collect and record geospatial data and provide as-built documentation (shape files) of all new installed maintenance hole/duct system components and new cable components (including metadata) compatible with the Cyberspace Infrastructure Planning System (CIPS) Visualization Component (CVC) drawing system. Data points shall be recorded at the center of each manhole/hand-hole lid and at intervals not to exceed 25 feet along cable routes. Sufficient data points shall be recorded to capture any change in direction along the route. All GPS coordinates shall have +/- 3 feet accuracy for all readings. The government will review the shape files and transcribe the information to the CVC system. Provide geospatial data via CD as Environmental Systems Research Institute (ESRI) Shape files. Shape files shall be delivered within 30 days of project completion.

38 2/13/2026 Page 14 of 28

2.2.13 Test and Acceptance/Installation Test Plan.

The Contractor shall provide a test plan as to how the system shall be pre-tested, in-progress-tested and post-tested. Draft Cut-over Test Plan shall be submitted NLT

10 calendar days after contract award. Government comments will be provided after review of the draft. A final plan will be submitted 30 calendar days before the actual cut-over date. The Contractor shall test the system to demonstrate to the

Government quality assurance representative that the system is fully operational and meets or exceeds the specified requirements and that the system is fully ready to be placed into service. These tests shall be accomplished prior to the system being placed into service.

2.2.13.1 Testing.

The Contractor shall conduct on-site testing IAW OEM's installation manuals, practices and the appropriate vendor's test procedures. The Contractor shall furnish all test equipment and personnel required to conduct all required testing. During any testing phase, the Government reserves the right to perform any of the contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing. The Contractor shall participate with the Government in testing the complete communications system. When any system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance and payment will be withheld until such time as the cause of the failure is corrected to the

Government's satisfaction. After appropriate corrective action has been taken, all tests including those previously completed, related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance.

2.2.13.1.1 Fiber Optic Tests.

All strands of all fiber optic cables shall be tested in accordance with TIA 526-7-

A, Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant, or equivalent. As a minimum, the following tests shall be performed. Both Optical

Time Domain Reflectometer (OTDR) and Optical Power Meter tests will be used for all end-to-end circuits. Between FODPs, bi-directional testing at 1310 nm and 1550 nm is required. For incomplete circuits that end in Maintenance Holes, only one-way

OTDR testing is required.

2.2.13.1.1.1 Optical Attenuation.

End to end attenuation tests shall be conducted on all fiber optic cable strands.

Tests shall be accomplished to ensure the installed cable is within the specified parameters.

2.2.13.1.1.2 Distance.

Test to determine the installed cable length between optical patch panels. All strands of all fiber optic cables shall be tested.

2.3 Acceptance/Installation Test Report.

The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan NLT 10 business days after

Government Witness Testing is complete.

2.4 Final Acceptance.

The Contractor shall schedule a final project walk-through with the Base POC. This should be scheduled 5 calendar days prior to acceptance.

2/13/2026 Page 15 of 28

2.5 Deliverable Summary.

All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this Task Order. All deliverables shall be produced using recommended software tools/versions as accepted by the Government.

3. 0 GENERAL INFORMATION.

3.1 Period of Performance.

The period of performance for the project shall be determined based on the proposed schedule and actual contract award date.

3.2 Place of Performance.

The place of performance is Shaw AFB SC.

3.3 Hours of Operation.

The Contractor shall routinely work during normal duty hours of the site. However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the 20CS/SCX and approved by the Contracting Officer at least 10 calendar days in advance.

3.4 Holidays/Down Days.

The Contractor shall not perform under this contract on federal holidays or site unique down-days unless expressly authorized by the CO and coordinated with the base

POC.

3.5 Base Support.

The Contractor shall identify any base support requirements (for example, laydown and storage areas) necessary to complete this project in their proposal. The contractor shall return all government furnished lay-down and storage areas to their original condition upon completion of the project.

2/13/2026 Page 16 of 28

4 . 0 APPENDICES.

4 . 1 Appendix A: APPLICABLE STANDARDS.

The following list is not all-exclusive. The Contractor shall comply with applicable commercial code and standards.

DAFMAN 91-203 - Air Force Consolidated Occupational Safety Instruction

OSHA CFR 29 Part 1910-268 - Telecommunications

NEMA TC 2- Electrical Polyvinyl Chloride (PVC) Tubing and Conduit

TIA-606-D Administration Standard for Telecommunications Infrastructure

TIA-568.1-E Commercial Building Telecommunications (568C.l, 568C.2, 568C.3) Cabling

Standard

TIA-607-E Commercial Building Grounding (Earthing) and Bonding Requirements for

Telecommunications

TIA-526-7-A Measurement of Optical Power Loss of Installed Single-mode Fiber Cable

Plant

TIA-569-E - Commercial Building Standard for Telecommunications Pathways and Spaces

TIA-570-E -Residential Telecommunications Infrastructure Standard

TIA-758B Customer-owned Outside Plant Telecommunication Infrastructure Standard

BICSI TDM Manual Building Industries Consulting Services International

Telecommunications Distribution Methods (TDM) Manual

BICSI OPDRM - Outside Plan Design Reference Manual

RUS Bulletin 345-65 (PE-33) - Specification for Shield Bonding Connectors

RUS Bulletin 1735F-401, Standards for Splicing Copper and Fiber Cable

RUS Bulletin 1751F-643 - Underground Plant Design

RUS Bulletin 1751F-644 Underground Plant Construction Telecommunications

Engineering Shield Continuity and Construction Manual (TE&CM) 451.2

RUS Bulletin 1751F-801 - Electrical Protection Fundamentals

RUS Bulletin 1753F-151 (515b) - Specifications and Drawings for Underground Cable

Installation

RUS Bulletin 1753F-201 (PC-4) - RUS Standard for Acceptance Tests and Measurements of Telecommunications Plant

RUS Bulletin 1753F-207 (PE-87) - REA Specification for Terminating Cables

NFPA 70 - National Electric Code

Unified Facilities Criteria 3-260-01

Unified Facilities Criteria 3-580

FGDC-STD-007. 3-1998 - Geospatial Positioning Accuracy Standards Part 3: National

Standard for Spatial Data Accuracy.

2/13/2026 Page 17 of 28

5.0 Project Sketches.

Notes:

0 �isting MH/HH.

c==:::J 2. Existing Conduit/Innerducts/Geotextile Innerducts to install the new FOC.

(Drawing NOT to ScaJ.e, Distances are approximate)

Sketch-1 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.

Shaw AFB SC

Sketch-2 of 2

0 �isting MH/HH.

�2. Existing Conduit/Innerducts/Geotextile Innerducts to install the new FOC.

(Drawing NOT to Sea.le, Distances are approximate)

Sketch-2 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.

0 �isting MH/HH.

�2. Existing Conduit/Innerducts/Geotextile Innerducts to install the new FOC.

(Drawing NOX to Scale, Distances are approximate)

Sketch-3 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.

0 �isting MH/HH.

� 2. Existing Conduit/Innerducts/Geotextile Innerducts to install the new FOC.

(Drawing NOX to Sca1e

Distances are approximate)

Sketch-4 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.

(Sketch 1 of 3)

0 �isting MH/HH.

� 2. Existing Conduit/Innerducts/Geotextile Innerducts to install the new FOC.

(Drawing NOX to Sca1e

Distances are approximate)

Sketch-5 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.

(Sketch 2 of 3)

0 1. Existing MH/HH.

c:::=:>2. Existing Conduit/Innerducts/Geotextile

Innerducts to install the new FOC.

(Drawing NOX to Sea.le, Distances are approxiJnate)

Sketch-6 (Cable Route)

2/13/2026 Page 23 of 28

(Sketch 3 of 3)

0 �isting MH/HH.

c::::::::) 2. Existing Conduit/Innerducts/Geotextile Innerducts to install the new FOC.

(Drawing NOT to Sca1e

Distances are approximate)

Sketch-7 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.

Existing condu it to M H-14 (available vacant MaxCell to install new FOC)

N o te:

Existing Rack (#2) with space available to install new FODP

The installer shall coordinate/verify with 20CS/SCX for the final location before installing the new FODP.

B00216 (Rm-106). Comm/Mech Room

Sketch-8 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.

Existing conduit to M H-5 (available

N o te:

Existing Rack with space available to install new FODP

The installer shall coordinate/verify with 20CS/SCX for the final location before installing the n ew FODP.

B00710 (TR-118)

Sketch-9 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.

The installer is required to move this cabinet to the right and install a new 7 'X19" Rack to install the new FODPs

From Cable Vault To MH-lA (Existing vacant MaxCell)

N o te:

From Cable Vault To MH-31A (Existing vacant MaxCell)

The installer shall coordinate/verify with 20CS/SCX for the final location of any new installation.

B01109 (Frame Room)

Sketch-10 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.

Existing conduit to HH-105 (available

N o te:

Existing Rack with space available to install new FODP

The installer shall coordinate/verify with 20CS/SCX for the final location before installing the n ew FODP.

B01601 (Mech/Conm Room)

Sketch-11 (Cable Route)

2/13/2026

SOO-OS2 High Speed Fiber Optic Cable (FOC) Infrastructure Upgrade.