SOO-B41 PURCHASE AC SPLIT SYSTEM.pdf

PDF 115 KB Posted

Attached to
20TON Split A/C Unit
Solicitation number
FA301620TONSplitACUnitRAN
Issued by

About this file

This is a Statement of Objectives for the replacement of an air conditioning system at JBSA Randolph Air Force Base, Building 41. The requirement is for equipment purchase only, with no installation or labor services included by the contractor.

The scope requires procurement of a complete 20-ton split air conditioning system to replace an existing unsupportable system currently using R-22 refrigerant. The new system must consist of an outdoor condensing unit with dual scroll compressors (tandem or two-stage configuration) and an indoor air handler capable of delivering a minimum 8,000 CFM airflow with a multi-row DX cooling coil and belt-driven fan system. The system must operate on 208/230V, 3-Phase, 60Hz power and include an integrated or compatible electric heat kit with approximately 20 kW capacity. All equipment must be new and unused, meet or exceed US DOE 2023 minimum efficiency standards per AHRI Standard 340/360, and use a modern low Global Warming Potential refrigerant such as R-454B in compliance with EPA regulations. The outdoor unit must feature forkable base rails and be designed for replacement with minimal structural modifications to the existing mounting pad. Contractor submittals must include complete technical data sheets and performance data for government review and approval prior to procurement, along with manufacturer's operating and maintenance manuals. The contractor shall provide the manufacturer's standard commercial warranty with a minimum one-year warranty on all parts and deliver all equipment to 1615th Street East, Building 2, Randolph AFB, Texas 78150-2100.

View the file

Other files

File Type Posted
Solicitation Amendment - FA301626Q00460001.pdf PDF
IMG_0227.jpeg JPEG file
Heating Element for AHU B41.jpg JPG image
Name Plate AHU B41.jpg JPG image
IMG_0226.jpeg JPEG file
IMG_0225.jpeg JPEG file
Pic4.jpg JPG image
Statement of Need.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF OBJECTIVE

FOR

JBSA RANDOLPH AIR FORCE BASE

B41 AIR CONDITIONING SYSTEM REPLACEMENT EQUIPMENT PURCHASE

ONLY

1.0 Needs Statement

Lakland Air Force Base requires the replacement of an existing, unsupportable 20-ton split air conditioning (A/C) system. The current system utilizes R-22 refrigerant, which is being phased out of production and is no longer available in new equipment. The objective of this project is to replace the aging system with a modern, energy-efficient, and fully compliant 20-ton split A/C system. The new system must provide reliable cooling and heating, meet current Department of Energy (DOE) efficiency standards, and adhere to all relevant environmental and safety regulations.

2.0 Existing System

The current system is a 20-ton commercial split A/C system. The system's outdoor condensing unit and indoor air handler have reached the end of their service life. The contractor shall be responsible for just purchasing and delivering the equipment only.

3.0 Requirements

3.1 General Requirements

The contractor shall provide a complete, turn-key solution including all necessary equipment, materials, and labor to replace the existing A/C system. The proposed system must meet the following general criteria:

• Equipment: The system shall consist of a new outdoor condensing unit and a matching indoor air handler.

• Capacity: The system shall have a nominal cooling capacity of 20 tons (approximately 240,000 BTU/h).

• Compliance: All equipment must be new and unused. The system shall meet or exceed the US DOE 2023 minimum efficiency standards and be rated in accordance with AHRI Standard 340/360.

• Refrigerant: The system must use a modern, low Global Warming Potential (GWP) refrigerant, such as R-454B, in compliance with current EPA regulations.

• Electrical: The system must operate on a 208/230V, 3-Phase, 60Hz power supply.

3.2 System-Specific Requirements

• Outdoor Condensing Unit:

• Shall feature dual scroll compressors (tandem or two-stage) for improved efficiency and reliability.

• Must be designed for replacement with minimal structural modifications to the existing mounting pad.

• Shall be constructed with forkable base rails to facilitate handling and installation.

• Indoor Air Handler:

• Must be capable of delivering a minimum airflow of 8,000 CFM.

• Shall include a multi-row DX cooling coil and a belt-driven fan system designed to meet the required static pressure.

• Heating Capability:

• The system must include an integrated or compatible electric heat kit with a capacity of approximately 20 kW.

4.0 Implementation Services

• Submittals: Prior to procurement, the contractor shall submit complete technical data sheets, and performance data for all proposed equipment for government review and approval.

• Documentation: The contractor shall provide the manufacturer’s operating and maintenance manuals for the new system.

5.0 Logistics Requirements

• Warranty: The contractor shall provide the manufacturer's standard commercial warranty, which shall include a minimum of a one (1) year warranty on all parts.

• Contractor will deliver all equipment to the following address.

1615th St East

BLDG. 2

Randolph AFB, Texas 78150-2100

US