Solicitation W912WJ26QA164.pdf

PDF 4 MB Posted

Attached to
Fuel Tank Removal and Replacement, Colebrook River Lake, Colebrook, CT
Solicitation number
W912WJ26QA164
Issued by

About this file

Summary

This is a Request for Quotation (RFQ) issued by the U.S. Army Corps of Engineers (USACE) New England District for fuel tank removal and replacement services at Colebrook River Lake in Colebrook, Connecticut. The solicitation (W912WJ26QA164) is a firm fixed-price construction contract with a performance period of 120 calendar days from award. Quotations must be submitted by 5:00 PM on September 27, 2026, via email to Contract Specialist Alicia N. LaCrosse. The work involves removing one existing 600-gallon fuel tank with approximately 300 gallons of fuel remaining and replacing it with two new 275-gallon insulated, double-walled fuel tanks, along with associated components including a new 10-gallon day tank, fuel transfer pump, grounding systems, vent pipes, fill whistles, crossover/manifold kits, fuel level gauges, and tie-down kits. New fuel supply and return lines (1/2" Type L copper) must be installed from the tanks to the furnace and generator.

The contractor must complete all pre-construction submittals within 21 days of contract award, including an Accident Prevention Plan, Activity Hazard Analysis, Site Safety and Health Officer designation, and Environmental Protection Plan. Work is restricted to Monday through Friday, 7:00 AM to 3:00 PM, with no weekend or holiday work permitted without approval. Safety requirements are extensive and include compliance with EM 385-1-1 standards, OSHA regulations, daily safety meetings, and participation of a Level 3 Site Safety and Health Officer. The contractor is responsible for providing all labor, materials, equipment, and transportation. Site visits are strongly recommended and can be arranged with Park Ranger Tyler Chaivanik at Tyler.A.Chaivanik@usace.army.mil or (978) 551-3818. Evaluation criteria include technical capability, price, and past performance. The estimated project cost is less than $25,000, and no bid guarantee is required, though payment protections apply based on final contract value.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION

(THIS IS NOT AN ORDER)

THIS RFQ IS IS NOT A SMALL BUSINESS SET-ASIDE

15. DATE OF QUOTATION

16. SIGNER

a. NAME (Type or print)

c. TITLE (Type or print)

b. TELEPHONE

AREA CODE

NUMBER

STANDARD FORM 18 (REV. 6-95)

Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition not usable

8. TO:

b. COMPANYa. NAME

c. STREET ADDRESS

d. CITY e. STATE f. ZIP CODE

9. DESTINATION

a. NAME OF CONSIGNEE

b. STREET ADDRESS

c. CITY

d. STATE e. ZIP CODE

7. DELIVERY

FOB DESTINATION

OTHER

(See Schedule)

10. PLEASE FURNISH QUOTATIONS TO THE

ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)

IMPORTANT: This is a request for information and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or service. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

12. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations are are not attached.

13. NAME AND ADDRESS OF QUOTER

a. NAME OF QUOTER

b. STREET ADDRESS

c. COUNTY

d. CITY e. STATE f. ZIP CODE

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.

UNDER BDSA REG. 2

AND/OR DMS REG. 1

RATING

5a. ISSUED BY 6. DELIVER BY (Date)

5b. FOR INFORMATION CALL (NO COLLECT CALLS)

NAME TELEPHONE NUMBER

AREA CODE NUMBER

Section A - Solicitation/Contract Form

Fuel Tank Removal and Replacement, Colebrook River Lake, Colebrook, CTInstrument Name:

Product Service Code : Y1QA

W912WJ26QA164

Section B - Supplies or Services & Prices or Costs

Additional Information/Notes

Item Supplies/Service Quanti ty

Unit Unit Price Amount

0001 Contractor shall provide all labor, materials, equipment, and transportation to remove and replace an existing 600-gallon fuel tank and associated components with two (2) new 275-gallon insulated, double walled fuel tanks and associated components in the gatehouse at Colebrook River Lake, Colebrook, CT in accordance with the Statement of Work.

Product Service Code: Y1QA

North American Industry Classification System (NAICS):

237120

Pricing Arrangement: Firm Fixed Price

1 Job

Section C - Description/Specifications/Statement of Work

INTERESTED VENDORS SHALL REVIEW SECTION L AND SECTION M OF THE

SOLICITATION FOR INSTRUCTIONS AND EVALUATION CRITERIA. VENDORS ARE

RESPONSIBLE FOR ENSURING THEIR QUOTE SUBMISSION MEETS ALL REQUIREMENTS.

FAILURE TO DO SO MAY RESULT IN QUOTES BEING DEEMED NON-RESPONSIVE AND

REMOVED FROM CONSIDERATION.

THE MANDATORY SOLICITATION SURVEY ISSUED FOR THE SOLICITATION SHALL BE

COMPLETED IN ITS ENTIRETY AND RETURNED WITH QUOTES. FAILURE TO DO SO MAY

RESULT IN QUOTES BEING DEEMED NON-RESPONSIVE AND REMOVED FROM

CONSIDERATION. USE OF A SOLICITATION SURVEY NOT ISSUED FOR THE RELEVANT

SOLICITATION WILL RESULT IN QUOTES BEING DEEMED NON-RESPONSIVE AND

REMOVED FROM CONSIDERATION.

STATEMENT OF WORK:

FUEL TANK REMOVAL & REPLACEMENT

U.S. ARMY CORPS OF ENGINEERS

COLEBROOK RIVER LAKE

COLEBROOK, CT 06021

STATEMENT OF WORK

I. GENERAL

1. Scope:

The Contractor shall furnish all labor, materials, and equipment necessary to remove and dispose of one existing 600 gallon fuel tank with a catch basin filled with roughly 300 gallons of fuel, a 10 gallon day tank, fuel transfer pump, and the respective fuel/supply lines, and replace with two (2) new 275 gallon insulated, double walled fuel tanks, a new 10 gallon day tank, as well as dedicated grounding systems, fuel transfer pump, vent pipes, fill whistle, crossover/manifold kit, fill caps, fuel level gauges, tie down kit, and install new fuel/supply return lines in the Colebrook River Lake gatehouse.

All work will be performed in a timely manner to the satisfaction of the Technical Point of Contact and in accordance with the following Statement of Work and in accordance with local, state, and federal laws.

2. Location:

The work area is in the gatehouse of Colebrook River Dam, located at 426A Colebrook River Road, Colebrook, CT 06021. The work area will be open to the Contractor from 7:00 am to 3:00

pm. No work shall be performed on weekends or holidays unless approved by the Technical Point of Contact.

3. Site Visit:

Site visits are strongly recommended to gauge the full scope of work and provide an accurate quote. No extra payment will be considered for perceived additional work caused by unfamiliarity with the site conditions and requirements. Contact the Technical Point of Contact to arrange a site visit. To arrange a site visit, contact the Technical Point of Contact, Park Ranger Tyler Chaivanik at Tyler.A.Chaivanik@usace.army.mil or (978) 551-3818.

4. Schedule:

The period of performance shall be 120 days from Contract award. The project area will be open to the contractor Monday through Friday 7:00 AM to 3:00 PM and all work must be done during those hours unless additional hours are approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.

5. Submittals:

All pre-construction submittals shall be submitted within 21 days of contract award. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall be resubmitted to the Government in an acceptable form within 14 days of the Government's response, unless additional time is granted by the Government in writing. No field work may proceed prior to the acceptance of pre-construction submittals.

6. Safety Requirements:

a. General:

All work shall be conducted in accordance with the U.S. Army Corps of Engineers (USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at the following link:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE% 2015March2024.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

b. Accident Prevention Plan (APP):

The Contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.

The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.pdf

A preparatory meeting shall be conducted by the Prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

Daily safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact upon request.

c. Activity Hazard Analysis (AHA):

An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf

d. Site Safety and Health Officer (SSHO) Requirements:

The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.

b and 2-4.b.

Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.

The SSHO shall be present at the project site and be responsible for overseeing the implementation of the Prime Contractor's SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf

e. First-Aid and CPR Personnel Requirements:

For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employees work alone, they must be certified in First Aid and be provided with an effective means of communication to call for assistance in the event of an emergency. Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.

f. Additional Personnel Requirements:

Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385-1-1 and/or other sections of this Scope of Work, based on the definable features of work for this project.

g. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor and reported to the Technical Point of Contact in accordance with EM 385-1-1, Table 2-1.

The mandatory ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within seven (7) days of an incident: https://www.publications.usace.army.mil/Portals/76 /Publications/EngineerForms/Eng_Form_3394_2021Aug.pdf

h. Employee Exposure Data:

The Contractor shall electronically report total employee work hours (including subcontractors) to the Technical Point of Contact by close of business on the 10th calendar day of the following month.

i. Electrical

i. General Requirements (EM385-1-1, Para. 11-8):

All electrical work must comply with EM 385-1-1 (Chapters 11 & 12) and applicable American National Standards Institute (ANSI), ASTM International Standards, Electrical and Electronics Engineers Association (IEEE), National Fire Protection Association (NFPA), National Electric Safety Code (NESC), Occupational Health and Safety Administration (OSHA), Underwriters Laboratories (UL), Unified Facilities Criteria (UFC), and those regulations outlined in 29-CFR-1910 and 29-CFR-1926. In circumstances where a discrepancy between the codes and regulations listed above, or an omission exists, the most stringent regulations shall apply.

All electrical wiring and equipment must be a type listed by a Nationally Recognized Testing Laboratory (NRTL) for the specific application for which it is to be used. For equipment not listed by a NRTL, the Authority Having Jurisdiction (AHJ) must determine if use is allowable.

ii. Roles and Responsibilities:

1. Qualified Persons (QPs) Electrical: QPs must demonstrate the skills and knowledge related to the construction, operation, and maintenance of electrical equipment and installations, and receive relevant safety training to recognize, avoid, and control associated hazards that might be present.

(EM 385-1-1, 11-3.b). QPs will meet requirements in accordance with EM 385-1-1, Chapters 11-3 and 11-4.

2. Personnel that install and/or remove electric conductors, equipment, or raceways, or manipulate cables must have verifiable credentials and be familiar with applicable code and electrical safety requirements. Verifiable credentials consist of national, state, or local certifications or licenses of a Master or Journeyman Electrician.

iii. Establishing an Electrically Safe Work Condition (ESWC):

All equipment and circuits must be placed into an ESWC by a Qualified Person (QP) before work is performed, in accordance with EM 385-1-1, 11-8.d.

j. Cranes and Load Handling Equipment (LHE):

i. General: All load handling equipment (LHE) operations are required to be completed in accordance with EM 385-1-1, Chapter 16. The requirements apply to all LHE with a hoisting or lifting capacity over 2,000 lbs. (907.2 kg). LHE includes cranes, derricks, hoists, and power-operated equipment (excavators, forklifts, rough terrain equipment) when used with rigging that can raise, lower, and horizontally move a suspended load.

ii. Operator Requirements: Only properly trained, certified, and qualified personnel that are designated in writing by the employer may operate LHE. Prior to designating any LHE operator, the employer must obtain the intended operational functions and proof of qualifications for the operator in accordance with EM 385-1-1, Chapter 16-3.

iii. Certification: Crane operators must be trained, tested, and certified by a nationally accredited testing organization. The training must address applicable ASME B30 requirements and include a successful completion of written and practical/operational examinations.

Physical Qualifications/Examination: Class I operators must receive a physical exam, at a minimum of every three years, meeting the requirements of ASME B30.5.

Designation: The employer is responsible for designating operators and verifying all their required documents are completed in accordance with the applicable requirements.

iv. Signal Person Requirements: Signal Persons shall meet the minimum qualifications and requirements of EM 385-1-1, Chapter 16-3.i.

v. Qualified Rigger Requirements: Qualified riggers shall meet the minimum qualifications and requirements of EM 385-1-1, Chapter 15-3 and 15-4.

vi. Minimum Plan Requirements: A lift plan is required to be submitted and accepted by the Technical Point of Contact prior to any lifting operations. Non-mandatory, lift plan templates are available for use. However, contractors are permitted to submit their own lift plans, in accordance with EM 385-1-1, Chapter 16-7.

1. ENG Form 6203, Crane Standard Lift Plan (SLP):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6203_Crane%20Standard%20Lift% 20Plan_2024%2009%2013%20-%20Final.pdf

2. ENG Form 6213, Load-Handling Equipment Crane Operation Critical Lift Plan (CLP):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6213_Load%20Handling% 20Equipment%20Crane%20Operation%20Critical%20Lift%20Plan%202024%20Aug%20-% 20FINAL.pdf

vii. Other Mandatory Forms:

1. ENG Form 6209, Certificate of Compliance (CoC) for Load Handling Equipment (LHE) and Rigging:

https://www.publications.usace.army.mil/LinkClick.aspx?fileticket=kzvU4YyG1yU% 3d&tabid=16438&portalid=76&mid=43543

7. Pre-Construction Conference:

Prior to the start of any work, the Technical Point of Contact will schedule and conduct a "Pre- Construction Conference". The Contractor's Project Manager and Quality Control Personnel will be physically present to attend this meeting. The Contractor shall directly oversee all work on the project, and the Project Manager and Quality Control Personnel shall have the authority to act on behalf of the Contractor. This conference will be held at the time and location agreeable to the Government and Contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's administration and inspection of contract work or obtain other pertinent information that might be required.

At the Preconstruction Conference the Contractor shall provide the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Pre-Construction Conference:

a. Authority of the Technical Point of Contact and Quality Assurance Inspectors

b. Contractor's Safety Program (including sub-contractors)

c. Mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) and Activity Hazard Analysis for each Definable Feature of Work (DFOW)

d. Safety Meetings

e. ENG Form 3394 (Mandatory if needed for Accident Reporting)

f. Safety Data Sheet (SDS) requirements

g. Correspondence, Communication and Administrative Procedures

h. Invoice and Payment

8. Permits:

The Contractor shall, without additional expenses to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

9. Security:

The Contractor shall comply with all established security policies at Colebrook River Lake. If applicable, Contractor shall comply with Projects Key Control Management Program. Due to periods of heightened security, which may affect access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor's ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent work in an area. The Contractor shall be given at least a 24-hour notice of any such closure.

10. Contractor's Personnel:

a. Employee Conduct: Contractor and employees must comply with CFR 36 Rules and Regulations. The Contractor shall be responsible for seeing that the Contractor's employees strictly comply with all Federal, State, and Municipal laws. Any personnel activity, which, in the opinion of the Government, is deemed detrimental to the performance of the contract may result in the removal of Contractor employee/employees.

Examples of unbecoming actions or conduct include but are not limited to the following:

i. Cursing, harassment, or discrimination of and/or unwarranted physical contact with visitors, USACE personnel, or other contractors.

ii. Recurring written and/or verbal complaints from visitors, USACE personnel, or other contractors.

iii. Unsafe operation of vehicles while on USACE property.

b. Removal of Contractor's Employees:

The Technical Point of Contact may require the Contractor to immediately remove from the work site any employee of the Contractor or subcontractor, who, in the opinion of the Technical Point of

Contact, endangers persons or property, or whose physical or mental condition is such that it would impair the employee's ability to satisfactorily perform assigned work. Notification to the Contractor shall be promptly made in writing if time and circumstances permit. Otherwise, notification shall be verbal or by telephone and shall be confirmed in writing as soon as possible.

No such removal, however, will reduce the Contractor's obligation to perform all work required under this contract, and immediate replacement will be made as required. This requirement shall not be made the basis of any claim for compensation or damages against the United States or any of its officers or agents.

Note: At least one of the Contractor employees on site shall be able to communicate effectively and efficiently with all project staff.

11. Payment:

After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact that includes the name of Contractor invoice date, contract number, description of work completed, and total amount due. Final payment is made within 30 days to the appropriate Technical Point of Contact. For jobs greater than 30 days, the Contractor may request multiple payments.

All invoices may be mailed to:

U.S. Army Corps of Engineers

Colebrook River Lake

P.O. Box 58

Riverton, CT 06021

Or sent via email (preferred) to Tyler.A.Chaivanik@usace.army.mil

II. Technical Requirements:

1. Submittals:

Although the Government reviews submissions required by this Statement of Work, it is emphasized that the Contractor's work must be completed using proper internal controls and review procedures. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government in an acceptable form within 14 days of the Government's response, unless additional time is granted by the Government in writing.

The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and must be accepted by the Government.

Pre-Construction Submittals: Submitted within 21 days of contract award. Submittals must be accepted by the Government prior to the commencement of any field work.

a. ENG Form 6293 (Accident Prevention Plan Worksheet)

b. Activity Hazard Analysis; non-mandatory template available: ENG Form 6206

c. ENG Form 6282 (Site Safety and Health Officer Designation Letter)

d. First-Aid and CPR Personnel requirements

e. Environmental Protection Plan: The Contractor shall submit an Environmental Protection Plan for review and approval by the Technical Point of Contact.

f. ENG Form 6209, Certificate of Compliance for Load Handling Equipment and Rigging (If applicable)

g. ENG Form 6203, Crane Standard Lift Plan (SLP) (If applicable)

h. ENG Form 6213, Load-Handling Equipment Crane Operation Critical Lift Plan (CLP), (If Applicable).

i. Safety Data Sheet (SDS) for any non-Government-furnished materials

j. Safety Inspection for all Heavy Equipment: The Contractor shall submit a current written safety inspection for all heavy equipment proposed for use on this contract.

k. Work Site Plan: Prior to the start of on-site work, the Contractor shall submit a site plan with description of how fuel and tanks will be removed.

l. Work Plan and Schedule: The Contractor shall submit a written Work Plan describing the methods and equipment required to accomplish the work and provide the required environmental and worker protection; this plan will include a schedule of work.

2. Clean Up:

The Contractor shall practice good housekeeping to maintain a safe job site. The Contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials.

Upon completing work in an area, the Contractor shall remove any tools, equipment, and materials that are not the property of the Government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

3. Government Resources:

The Contractor is responsible for providing all materials to complete the project. Upon request, the Government will provide the use of the 5-ton hoist that is in the Colebrook Dam gatehouse, given that the equipment is inspected before and after use. The Contractor must provide proper submittals regarding the use of the load handling equipment listed above. Unless otherwise specified in the contract, the Government will not provide any other equipment, telephone services, or other resources.

4. Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable and functional product.

5. Quality Assurance:

The Contractor is responsible for the quality control of the contract work. The Government has the right to inspect and test all items called for by the contract, to the extent practicable always and at all places during the term of the contract.

6. Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other contractors and Government employees. The Contractor shall not commit or permit any act, which will interfere with the performance of work by another contractor or by Government employees.

7. Environmental Protection:

Containers for excess and/or waste materials shall be provided by the Contractor at the site, and the site will be inspected and cleaned daily when working onsite. Water, air, and land resources shall not be adversely impacted while the work occurs. The Contractor will take necessary steps to ensure all Federal, State, and Local environmental regulatory requirements are met at no additional cost to the Government. Assurance of compliance with this section by subcontractors shall be the responsibility of the Contractor. No burning is permissible.

8. Sustainability:

All products provided by the contractor must meet the recycled content requirements set forth by the Environmental Protection Agency. Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplies under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm /comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels. Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.

Furthermore, the contractor should also meet the BioPreferred Program requirements. The United States Department of Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio-based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio-based content level. Visit the BioPreferred website https://www.biopreferred.gov /BioPreferred/faces/pages/AboutBioPreferred.xhtml for the complete list of designated products and the associated minimum bio-based content level requirements.

9. Storage Area:

The storage area for use by the Contractor, for work and storage of equipment, materials, and trailers during the life of this contract will be determined at the Pre-Construction Conference. The storage area will be located at Colebrook River Lake.

The Contractor shall confine its storage area to the limits as designated or approved by the Technical Point of Contact and shall be responsible for the security of the area. Upon completion of the contract, and at no additional cost to the Government, remove all equipment and materials, except as otherwise specified, and restore the site to its original condition as approved by the Technical Point of Contact.

Trailers, equipment, or materials must not be open to public view except for those items which are in support of ongoing work on any given day. Do not stockpile materials outside the storage area in preparation for the next day's work, without approval from the Technical Point of Contact. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the storage area at the end of each workday.

10. Existing Conditions:

a. The existing 600-gallon oil tank and 10-gallon day tank are in the Colebrook River Lake dam operating tower, which is located across the dam, behind a locked access gate. Access is limited;

therefore, the Contractor must coordinate with the Technical Point of Contact.

b. Contractor must navigate a service bridge that is approximately 300 feet from the dam to the tower. The bridge is approximately 12 feet wide.

c. The main fuel tank is located on the floor below the main entrance of the gatehouse. The approximate footprint of the tank within the rupture basin is 78" x 34" x 85 1/2". There is one (1) 2" NPT threaded pipe connection for the tank fill, one (1) 1 1/2" NPT threaded pipe connection for the tank vent, and four (4) 1" NPT threaded pipe connections. Existing oil tank weight is estimated at approximately 575-750 lbs. empty. There is roughly 300 gallons of fuel remaining in the tank. The estimated weight of the half full tank is 2600-2900 lbs. There is a 1/2" flexible copper supply line running from the fuel tank to the furnace. The distance between the two is roughly 10.5'.

d. The day tank unit is 120VAC hard-wired and located on the floor above the main entrance of the gatehouse. The approximate footprint of the tank is 12" x 24" x 20". The transfer pump for the day tank is 120V hard-wired and located to the immediate right of the main fuel tank. The tank is fitted with four (4) 1" NPT threaded pipe connections, one (1) 1 1/4" NPT threaded connection for the pipe vent, and an additional fitting for the fuel inlet. There are two 3/8" flexible supply and return lines running from the tank to the generator.

e. The generator floor can only be accessed via a fixed ladder. All other levels are accessible via elevator, hatchway, or fixed ladder. Elevator cab measures 3' x 3' and rated for a maximum capacity of 1200 lbs. Elevator opening measures 32" W x 70" H.

f. A USACE-owned overhead hoist is in the tower and is available for use by the contractor, if needed. The maximum capacity load of the hoist is 5 tons. If the contractor chooses to use this overhead crane, the contractor is responsible for completing an inspection to certify use, as well as a post operation inspection.

g. Overhead crane use requires the setup of fall protection barricades and the removal of three steel floor plates, each measuring 2'6" x 5' and weighing approximately 100 lbs. After panels are removed, the total floor opening measures 7'6" x 5'. Access to the furnace level floor (floor below the main level) via hatchway requires the removal of three steel floor plates.

11. Product Specifications:

a. Two (2) 275-gallon oil storage tanks

i. Double-walled steel

ii. Weld-free galvanized steel outer tank

iii. Seamless high-density polyethylene inner tank

iv. Fuel gauges (for both tanks)

v. Visual leak indicators

vi. Steel fill and vent pipes

vii. Crossover/manifold kit

viii. Filling whistle

ix. Tie down kit

x. 3/4" crossovers and fuel line encased in non-metallic protective sleeve.

xi. New 1/2" Type L copper lines are to be installed to run from the tank to the furnace

b. One (1) 10-gallon day tank

i. Constructed of heavy-duty steel, no less than 16 gauge

ii. Unit shall be equipped with a "Press to Test Pump" switch and a "Pump Running Indicator Light"

iii. Equipped with a rupture basin capable of holding a minimum of 150% of primary tank volume.

iv. Provide flexible connector fuel supply and return lines.

1. 1/4" inside diameter with swivel couplings

c. One (1) Fuel transfer pump

i. Motor shall be heavy duty, 1/3 horsepower, 115-volt AC, single phase, and 60 hertz. Shall be a bronze gear pump rated for 2 GPM.

d. Appropriate gap filler/sealant

e. Appropriate electrical wiring and conduit in accordance with NFPA 780, API 2003, and API 651 (if replacement is deemed necessary by Contractor).

f. No. 2 Heating Oil

III. Execution

1. General:

a. Contractor shall install all products to manufacturer recommendations and in accordance with all electrical codes and federal, state, and local building codes and laws, and safety standards.

b. Only new, unused materials will be installed. Used or damaged materials will not be installed.

c. Activities including - but not limited to - removal and installation work, shall be scheduled so weather-related events will not damage new or existing materials or equipment.

d. Contractor must be able to cover and protect all work areas, materials and equipment that would otherwise be exposed to the elements during a weather event, expected or unexpected.

2. Safety Equipment:

It is the Contractor's responsibility to furnish and supply personnel with the proper personal protective equipment when and where necessary (Example: Hardhats, Hand Protection, Eye Protection).

3. Contractor Qualifications:

All work shall be performed by Qualified Personnel with verifiable credentials who are familiar with applicable code requirements. Verifiable credentials consist of State, National and/or Local Certifications or Licenses that a Master or Journeyman Professional may hold, depending on work being performed.

4. Removal/Demolition:

a. The contractor will take proper spill containment measures and have enough absorbent materials onsite to contain the existing oil contained in the tanks.

b. All fuel handling equipment must be bonded and grounded before transferring fuel out of the existing tanks.

c. The contractor will transfer all fuel out of the tanks for proper disposal and recycling. The extracted fuel and any sludge material present becomes the property of the contractor. Fuel that was pumped out of these tanks shall not be reused for the new installation.

d. Disconnect and remove existing tanks, transfer pump, fill pipe, vent pipe and corresponding hard-wired electrical hookups, crossovers, and supply/return fuel lines of both the oil tank and day tank. If deemed reusable, the vent pipe and electrical connections may be kept in place.

e. Recycle old tanks and all piping off-site in accordance with all local, state, and federal laws.

5. New Fuel Tank Installation:

a. New fuel tanks and transfer pump shall be placed in the same location as the previously installed units. Tie down kits are to be installed at this time.

b. Fill pipe, vent pipe, crossover/manifold kit, filling whistle, and all corresponding electrical hookups shall be installed. Vent pipes shall be run through exterior concrete wall. If old vent pipe and electrical hookups can be reused, it is recommended. For new vent pipe, usage of existing holes is strongly encouraged due to location; however, it may be necessary to modify the existing hole. Any voids surrounding the pipes shall be sealed with exterior weatherproof sealant to prevent weather intrusion.

c. New fuel supply and return lines shall be run from the tank to furnace and generator. Lines shall be neatly run and fastened to the wall/areas where the old lines were previously run (changes to this layout must be approved in advance by the Technical Point of Contact).

d. All tanks shall require dedicated grounding systems and shall be bonded and grounded in accordance with NFPA 780 and API 2003 & 651.

e. Contractor shall communicate with the Technical Point of Contact once the tanks are installed, and the Government will coordinate and pay for the heating fuel delivery to fill the new tanks

f. Furnace and generator shall be individually run for a period of thirty minutes and monitored to ensure proper fuel flow through the systems.

*** END OF NARRATIVE ***

Requirements Fuel Tank Removal and Replacement, Colebrook River Lake, Colebrook, CT

Section E - Inspection and Acceptance

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.246-12 Inspection of Construction. 1996-08

Section F - Deliveries or Performance

0001 Delivery Schedule From date of lead time event to completion of performance 120 Calendar Days

Date of Award 1 JobQuantity

Address and POC Place of Performance DoDAAC: 961108 CountryCode: USA

CORPS OF ENGINEERS NEW ENGLAND DIST

PROJECT MANAGER, COLEBROOK RIVER LAKE RIVERTON, CT 06065 UNITED

STATES

TYLER ANTH CHAIVANIK, DELIVER_TO_EMP_ID_NO

Section G - Contract Administration Data

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

2018-12

252.236-7000 Modification Proposals--Price Breakdown.

1991-12

DFARS Clauses Incorporated by Full Text

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.232-7006 Wide Area WorkFlow Payment Instructions.

2023-01

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause-

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall-

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web- Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC ____ Issue By DoDAAC ____ Admin DoDAAC ____ Inspect By DoDAAC ____ Ship To Code ____

Ship From Code ____ Mark For Code ____ Service Approver (DoDAAC) ____ Service Acceptor (DoDAAC) ____ Accept at Other DoDAAC ____ LPO DoDAAC ____ DCAA Auditor DoDAAC ____ Other DoDAAC(s) ____ (*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

SECURITY REQUIREMENTS:

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures -this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

WAGE DETERMINATIONS:

The Wage Determination for this project can be found at:

https://sam.gov/wage-determination/CT20260019/2

W912WJ26QA164

https://sam.gov/wage-determination/CT20260019/2

Wage Determination No.: CT20260019

Modification No.: 2

Revised Date: 18 May 2026

*** END OF NARRATIVE ***

Section I - Contract Clauses

UAI 5152.249-9000 Basis for Settlement of Proposals

Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under Federal Acquisition Regulation (FAR) 49.206-2(b). In evaluating a termination settlement proposal using total cost basis, the following principles will be applied to determine allowable equipment costs.

(a) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.

(b) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.

(c) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.

(d) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of Federal Acquisition Regulation (FAR) 31.205-11).

(e) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.

(End of Clause)

52.211-10 Commencement, Prosecution, and Completion of Work.

The Contractor shall be required to (a) commence work under this contract within 21 calendar days after the date the Contractor receives the contract award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than from contract award. * The 120 calendar days time stated for completion shall include final cleanup of the premises.

(End of clause)

52.236-27 Site Visit (Construction).

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Tyler Chaivanik

Address: 426A Colebrook River Road, Colebrook, CT 06021

Telephone: 978-551-3818

(End of Provision)

MAGNITUDE OF PROJECT

The estimated cost of the work is .less than $25,000

*** END OF NARRATIVE ***

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.

2017-01

52.204-9 Personal Identity Verification of Contractor Personnel.

2011-01

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (Deviation 2026-O0038)

2026-02

52.204-13 System for Award Management- Maintenance. (Deviation 2026- O0038)

2026-02

52.204-19 Incorporation by Reference of Representations and

2014-12

Certifications.

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.

(Deviation 2026-O0038)

2026-02

52.219-6 Notice of Total Small Business Set-Aside. (Deviation 2026- O0038)

2026-02

52.222-3 Convict Labor. (Deviation 2026- O0038)

2026-02

52.222-6 Construction Wage Rate Requirements. (Deviation 2026- O0038)

2026-02

52.222-7 Withholding of Funds. (Deviation 2026-O0038)

2026-02

52.222-8 Payrolls and Basic Records.

(Deviation 2026-O0038)

2026-02

52.222-9 Apprentices and Trainees.

(Deviation 2026-O0038)

2026-02

52.222-10 Compliance with Copeland Act Requirements. (Deviation 2026- O0038)

2026-02

52.222-11 Subcontracts (Labor Standards).

(Deviation 2026-O0038)

2026-02

52.222-12 Contract Termination-Debarment. 2014-05

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.

2014-05

52.222-14 Disputes Concerning Labor 2026-02

Standards. (Deviation 2026- O0038)

52.222-15 Certification of Eligibility. 2014-05

52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation 2026- O0038)

2026-02

52.222-50 Combating Trafficking in Persons. (Deviation 2026-O0038)

2026-02

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation 2026-O0038)

2026-02

52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation 2026- O0038)

2026-02

52.222-90 Addressing DEI Discrimination by Federal Contractors.

(Deviation 2026-O0040, Revision 1)

2026-04

52.223-2 Reporting of Biobased Products Under Service and Construction Contracts. (Deviation 2026- O0038)

2026-02

52.223-5 Pollution Prevention and Right-to- Know Information.

2024-05

52.223-23 Sustainable Products. (Deviation 2026-O0038)

2026-02

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.

2024-05

52.232-23 Assignment of Claims. 2014-05

52.232-27 Prompt Payment for Construction Contracts.

2017-01

52.232-33 Payment by Electronic Funds Transfer-System for Award Management.

2018-10

52.232-39 Unenforceability of Unauthorized Obligations.

2013-06

52.232-40 Providing Accelerated Payments to Small Business Subcontractors.

2023-03

52.233-1 Disputes. (Deviation 2026- O0038)

2026-02

52.233-3 Protest after Award. (Deviation 2026-O0038)

2026-02

52.233-4 Applicable Law for Breach of Contract Claim. (Deviation 2026- O0038)

2026-02

52.236-2 Differing Site Conditions.

(Deviation 2026-O0038)

2026-02

52.236-3 Site Investigation and Conditions Affecting the Work. (Deviation 2026-O0038)

2026-02

52.236-5 Material and Workmanship.

(Deviation 2026-O0038)

2026-02

52.236-6 Superintendence by the Contractor. (Deviation 2026- O0038)

2026-02

52.236-7 Permits and Responsibilities.

(Deviation…