This is a Request for Quotation (RFQ) for epoxy floor coating services at the Cold Regions Research and Engineering Laboratory (CRREL) in Hanover, New Hampshire. The U.S. Army Corps of Engineers, New England District is seeking quotes for the preparation and application of a polyaspartic epoxy floor coating system on eight rooms comprising approximately 3,242 square feet of the Cold Clean Laboratory. The work must be completed within 90 calendar days from contract award, with work performed Monday through Friday, 8:00 AM to 4:00 PM. The contract is issued under RFO Part 13 (simplified acquisition procedures) with a firm fixed price arrangement. The estimated cost range is between $25,000 and $100,000. No small business set-aside applies. Site visits are highly recommended and can be arranged by contacting the Technical Point of Contact, Eric Rosenberg, at (978) 318-8216 or Eric.C.Rosenberg@usace.army.mil.

The epoxy system must meet specific technical requirements including 96% solids content, VOC of 33 g/L, compressive strength of 12,500 psi, tensile strength of 4,000 psi, and a coefficient of friction exceeding 0.6. The system shall consist of primer, topping, basecoat, broadcast, grout, and topcoats achieving an overall thickness of 1/8 inch, with a six-inch integral cove base and aluminum termination strip at wall perimeters. The contractor must provide all labor, materials, equipment, and transportation; conduct mechanical floor preparation; apply the coating system per manufacturer specifications; and provide a one-year warranty from final acceptance. Responses must include signed SF18 forms, completed bid schedules, copies of material amendments, and a mandatory solicitation survey. Payment protection (payment bond or irrevocable letter of credit at 100% of contract price) is required for contracts at or above $150,000 and must be submitted within 10 days of award. Awards will be based on comparative evaluation of technical capability, price, and past performance factors.

View the file

Other files

File Type Posted
Amendment W912WJ26QA154-0001.pdf PDF
Additional Attachments 26QA154.pdf PDF
Attachments 26QA154.pdf PDF
Solicitation Survey 26QA154.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION

(THIS IS NOT AN ORDER)

THIS RFQ IS IS NOT A SMALL BUSINESS SET-ASIDE

15. DATE OF QUOTATION

16. SIGNER

a. NAME (Type or print)

c. TITLE (Type or print)

b. TELEPHONE

AREA CODE

NUMBER

STANDARD FORM 18 (REV. 6-95)

Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition not usable

8. TO:

b. COMPANYa. NAME

c. STREET ADDRESS

d. CITY e. STATE f. ZIP CODE

9. DESTINATION

a. NAME OF CONSIGNEE

b. STREET ADDRESS

c. CITY

d. STATE e. ZIP CODE

7. DELIVERY

FOB DESTINATION

OTHER

(See Schedule)

10. PLEASE FURNISH QUOTATIONS TO THE

ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)

IMPORTANT: This is a request for information and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or service. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

12. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations are are not attached.

13. NAME AND ADDRESS OF QUOTER

a. NAME OF QUOTER

b. STREET ADDRESS

c. COUNTY

d. CITY e. STATE f. ZIP CODE

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.

UNDER BDSA REG. 2

AND/OR DMS REG. 1

RATING

5a. ISSUED BY 6. DELIVER BY (Date)

5b. FOR INFORMATION CALL (NO COLLECT CALLS)

NAME TELEPHONE NUMBER

AREA CODE NUMBER

Section A - Solicitation/Contract Form

Epoxy Floor Coating, Cold Regions Research and Engineering Laboratory, Instrument Name:

Hanover, NH

Product Service Code : Y1QA

W912WJ26QA154

Section B - Supplies or Services & Prices or Costs

Additional Information/Notes

Item Supplies/Service Quanti ty

Unit Unit Price Amount

0001 Contractor shall provide all labor, materials, equipment, and transportation for the preparation and application of a polyaspartic epoxy floor coating system on eight

(8) rooms in the Cold Clean Laboratory located in the Cold Regions Research and Engineering Laboratory (CRREL), Hanover, NH in accordance with the Statement of Work.

Product Service Code: Y1QA

North American Industry Classification System (NAICS):

238330

Pricing Arrangement: Firm Fixed Price

1 Job

Section C - Description/Specifications/Statement of Work

INTERESTED VENDORS SHALL REVIEW SECTION L AND SECTION M OF THE

SOLICITATION FOR INSTRUCTIONS AND EVALUATION CRITERIA. VENDORS ARE

RESPONSIBLE FOR ENSURING THEIR QUOTE SUBMISSION MEETS ALL REQUIREMENTS.

FAILURE TO DO SO MAY RESULT IN QUOTES BEING DEEMED NON-RESPONSIVE AND

REMOVED FROM CONSIDERATION.

THE MANDATORY SOLICITATION SURVEY ISSUED FOR THE SOLICITATION SHALL BE

COMPLETED IN ITS ENTIRETY AND RETURNED WITH QUOTES. FAILURE TO DO SO MAY

RESULT IN QUOTES BEING DEEMED NON-RESPONSIVE AND REMOVED FROM

CONSIDERATION. USE OF A SOLICITATION SURVEY NOT ISSUED FOR THE RELEVANT

SOLICITATION WILL RESULT IN QUOTES BEING DEEMED NON-RESPONSIVE AND

REMOVED FROM CONSIDERATION.

STATEMENT OF WORK:

CONCRETE FLOOR POLYASPARTIC EPOXY COATING

U.S. ARMY CORPS OF ENGINEERS

COLD REGIONS RESEARCH AND ENGINEERING LABORATORY (CRREL)

HANOVER, NH

STATEMENT OF WORK

I. General:

1. Scope - Furnish all labor, materials and equipment necessary to provide a polyaspartic epoxy floor system on eight (8) rooms comprising the CRREL Cold Clean Laboratory in Hanover, NH.

The work includes the following:

a. Mechanical preparation of the concrete substrate in accordance with manufacturer's preparation recommendations.

b. Application of the polyaspartic floor coating system in accordance with manufacturer's application recommendations.

2. Location - CRREL is located at 72 Lyme Road Hanover, NH 03755.

3. Site Visit - Contact the Technical Point of Contact to arrange a site visit. The Technical Point of Contact (POC) for the project is Project Manager, Eric Rosenberg. The POC can be contacted at

(978) 318-8216 or Eric.C.Rosenberg@usace.army.mil.

4. Schedule - The work shall be completed no later than 90 days from the contract award date.

Work shall be performed Monday through Friday 8:00 AM to 4:00 PM, unless otherwise approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.

After-hours work is permitted with prior approval by the TPOC.

5. Safety Requirements - All work shall be conducted in accordance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, most recent edition), and all applicable OSHA, federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed at the project office or electronically at Headquarters USACE website under publications using the following link: http://www.publications.usace.army.mil/Portals/76/Publications /EngineerManuals/EM_385-1-1.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

a. Accident Prevention Plan:

The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include Activity Hazard Analyses (AHAs) as described below. A non-mandatory, fillable APP template is available upon request. However, the contractor is permitted to submit their own plan, at a minimum it must meet the requirements of EM 385-1-1, Appendix A, Section K.

A preparatory meeting shall be conducted by the prime contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

b. Activity Hazard Analysis (AHA):

An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work. The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level.

The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

c. Emergency Response:

Emergency procedures shall be documented in the Accident Prevention Plan and will include a map with directions to the nearest hospital, emergency contact numbers, and onsite First Aid/CPR responders.

d. Required Personnel:

Site Safety and Health Officer (SSHO)

The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.

b and 2-4.b.

Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.

The SSHO shall be present at the project site and be responsible for overseeing the implementation of the Prime Contractor's SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf

Competent Person (CP)

The Contractor shall designate one employee as the site's Competent Person (CP) who is responsible for ensuring a safe environment for all employees. The CP shall be present at the project site and report to the contractor's upper management. The CP is required to have related construction and/or service experience. The Prime Contractor can designate a subcontractor as the CP if all qualifications and certifications of EM 385-1-1 are met.

The Competent Person and SSHO can be one in the same.

For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employees work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency.

Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.

e. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the TPOC within four

(4) hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D shall be immediately reported to the TPOC. ENG Form 3394 shall be completed and submitted to the TPOC within five (5) working days of the incident.

The Contractor shall compile employee work hours (including subcontractors) and forward the total hours to the TPOC no later than close of business on the 10th calendar day of the following month.

The method of transmission by the prime contractor to the TPOC shall be electronically.

6. Pre-Construction Conference - Prior to the start of any work, the Technical Point of Contact will schedule and conduct a "Pre-Construction Conference". The Contractor's Project Manager and Quality Control Personnel will physically present to attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's administration and inspection of contract work or obtain other pertinent information that might be required. At the Pre-Construction conference the contractor shall provide the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Pre-Construction Conference:

i. Authority of the Technical Point of Contact and Quality Assurance Inspectors.

ii. Contractor's Safety Program (including sub-contractors).

iii. Accident Prevention Plan and Activity Hazard Analysis

(Submitted & accepted prior to start of work on site)

iv. Accident Reporting (ENG Form 3394)

v. Safety Data Sheet (SDS) requirements

vi. Contractor's Equipment

vii. Correspondence, Communication, Security and Administrative Procedures.

viii. Invoice and payment.

7. Permits - The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

8. Security - The Contractor will comply with all established security policies at CRREL. Due to periods of heightened security that may affect the access to the areas covered under this contract, the Government reserves the right to close any property or portion of property and reschedule and /or cancel any subsequent service. The Contractor shall be given at least 24-hour notice of any such closure.

9. Contractor Conduct - Alcohol and firearms are prohibited on project grounds. Contractor and employees must comply with CFR 36 Rules and Regulations.

10. Payment - After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. The invoice must also include the company letterhead and this must match the data that is registered in the System for Award Management (SAM) registry. For jobs greater than 30 days the contractor may request progress payment.

All invoices may be mailed to

U.S. Army Corps of Engineers

New England District

696 Virginia Rd.

Concord, Massachusetts 01742

Or Emailed to Eric Rosenberg at eric.c.rosenberg@usace.army.mil

II. Technical Requirements:

Part 1 General:

1. Summary - Furnish all labor, materials, and equipment to mechanically prepare, repair damaged substrate if necessary, and apply a polyaspartic epoxy system to eight rooms (approximately 3,242 square feet total) which comprise the CRREL Cold Clean Laboratory.

2. Submittals - Although the Government reviews submissions required by this Statement of Work, it is emphasized that the Contractor's work must be completed using proper internal controls and review procedures. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government in acceptable form within 14 days of the Government's response, unless additional time is granted by the Government in writing.

The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the Government.

Pre-construction Submittals: Submitted within 21 days of Contract Award. Submittals must be accepted prior to the commencement of any field work.

Accident Prevention Plan (APP) - Prior to the start of field work

Activity Hazard Analysis - to include mechanical floor preparation plan (barriers, ventilation, dust collection, protection of equipment or materials not being treated etc.) Prior to the start of field work

CPR and First Aid documentation

Epoxy flooring product and color sample

Manufacturer's product data sheets - Prior to ordering

Manufacturer's cut sheets for all new and replaced materials

Manufacturer's Warranty information

3. References - All work shall be in conformance with:

a. U.S. Army Corps of Engineers (USACE)

i. EM-385-1-1 2014 Safety and Health Requirements Manual, U.S. Army Engineering Manual

b. Other appropriate Federal, State, and Local codes for such an installation

4. Existing Conditions:

a. Cold Regions Research and Engineering Lab:

i. Cold Clean Laboratory Lab consists of eight (8) adjacent rooms.

Room 154 is approximately 706 square feet, and room perimeter is approximately 159'

Room 154A is approximately 42 square feet, and room perimeter is approximately 27'

Room 154B is approximately 1,993 square feet, and room perimeter is approximately 317'

Room 154E is approximately 34 square feet, and room perimeter is approximately 24'

Room 154F is approximately 35 square feet, and room perimeter is approximately 24'

Room 154H is approximately 27 square feet, and room perimeter is approximately 22'

Room 156 is approximately 95 square feet, and room perimeter is approximately 41'

Room 158 is approximately 310 square feet, and room perimeter is approximately 80'

Total is 3,242 square feet; 694 linear feet of perimeter walls.

The rooms are all bare concrete floors.

b. NOTE: The Government will move any non-fixed items off the floor surface prior to the start of work. Any existing floor coverings will be removed by the Government, and all rooms will be bare concrete at the start of work.

5. Clean Up and Waste Disposal - The Contractor shall practice good housekeeping to maintain a safe job site. The Contractor shall keep the work area, including any designated storage areas, free from accumulation of waste materials. Upon completing work in an area the Contractor shall remove any tools, equipment, and materials that are not the property of the Government. Any and all disturbed areas resulting from Contractor activities shall be restored by the contractor to the satisfaction of the Technical Point of Contact. All waste material will be disposed of offsite in accordance with all Federal, State, and Local regulations.

6. Environmental Protection - Containers for excess and/ or waste materials, rubbish, etc. shall be provided by the Contractor at the site, and the site will be inspected/ cleaned on a daily basis when working onsite. Water, air and land resources shall not be adversely impacted during the course of the work. The Contractor will take necessary steps to ensure all Federal, State, and Local environmental regulatory requirements are met at no additional cost to the Government.

Assurance of compliance with this section by subcontractors shall be the responsibility of the Contractor. CRREL strictly prohibits the use of products which contain Trichloroethylene (TCE).

7. Sustainability & Environmentally Preferred Products - The contractor shall provide Safer Choice labeled products under this contract, as applicable. The contractor is encouraged to visit https://www.epa.gov/saferchoice/products for updated lists of qualifying products. Products that are identified as "environmentally preferable" have a lesser or reduced effect on human health and the environment when compared with competing products that serve the same purpose, and bio-based will be selected over those which do not carry such designations. The United States Department of Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio-based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio-based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces /pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio-based content level requirements. Safer Choice or BioPreferred labeling is only required where an applicable designated product exists.

8. Reduced Volatile Organic Compounds - Provide products with reduced organic volatile compounds (VOC). The VOC content of adhesives, sealants, and sealant primers shall be determined and limited in accordance with SCAQMD Rule 1168. The VOC content of aerosol adhesives shall be determined and limited in accordance with Green Seal Standard GS-36, Section 3. For Construction submittal documentation, provide certifications or labels that demonstrate compliance with cited requirements.

9. Building Protection - Any involved building or structure, and all of its contents shall be protected from the elements during the duration of this contract. The Contractor shall keep on site the means to quickly cover and protect all areas open to the elements during an unforeseen weather related event that could cause damage to the building and or any of its contents during all phases of this contract.

10. Personal Protective Equipment - It is the Contractor's responsibility to furnish and supply personnel with the proper personal protective equipment necessary for performing the work.

11. Government Resources - The Government will supply any electricity necessary for the project work from points of existing outlets when available. The Contractor shall carefully conserve the use of electricity provided. There are several existing outlets (120V) available in the work area for the contractor's use. The Government can accommodate 240V electrical connections provided the contractor has equipment with a standard plug pattern or a "pigtail" device with a compatible amperage. All 240V or higher connections must be coordinated with the CRREL facilities staff. The Contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, water, telephone services, or other resources. The Contractor may use the sanitary facilities at CRREL but must proceed directly to and from the sanitary facilities.

12. Damage to Government and Private Property - The Contractor shall be responsible for restoring all Government facilities or structures damaged as a result of the Contractor's operation.

The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the Contractor's operation. The Contractor shall notify the Project Manager immediately of damage to Government and private property and injury to any person resulting from the Contractor's operation. Also, the Contractor shall notify the Technical Point of Contact of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed. Trucks and/or trailers will be driven on existing roads only and not across or through park areas to facilities. The Contractor shall also restore landscape features (shrubs, flowers, grasses, etc.), which are damaged or destroyed by the contractor's operation. Damaged or destroyed grass areas shall be re-planted as directed by the Technical Point of Contact, and shrubs and flowers which are damaged or destroyed shall be replaced from nursery stock of like size and kind.

13. Omissions - This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

14. Quality Assurance - The Contractor is responsible for the quality control of the contract work.

The Contractor shall establish and maintain a quality control system to assure compliance with the contract requirements. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

15. Other Contracts - The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other contractors and Government employees. The Contractor shall not commit or permit any act which will interfere with the performance of work by another contractor or by Government employees.

16. Receiving and Storing Materials - The Contractor is responsible for protecting any stored material until it is placed in service. The Contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive materials or supplies for the Contractor and will not be responsible for damage to the Contractor's equipment or materials.

A designated staging area will be coordinated in close proximity to the work area. All materials, equipment, and waste containers must be maintained daily to ensure safe circulation for personnel and emergency vehicles.

17. Requests for information - Requests concerning the work after award of this project should be directed to the Technical Point of Contact, Project Manager, Eric Rosenberg, at (978) 318-8216 or Eric.C.Rosenberg@usace.army.mil.

Part 2 Products:

All products shall be new, unused, and to the satisfaction of the Technical Point of Contact.

Products shall be approved by the Technical Point of Contact prior to installation.

1. Polyaspartic epoxy system shall meet the following requirements:

i. Will not chip, crack, or peel.

ii. Waterproof product intended to protect concrete from heavy traffic, oil, chemicals.

iii. Meets or exceeds slip resistance per coefficient of friction as listed in product requirements.

iv. The epoxy system must consist of primer, topping, basecoat, broadcast, grout and topcoats for an overall thickness of 1/8". All material must be from a single manufacturer or approved by the manufacturer for use on their epoxy system.

v. Product Requirements:

1. Epoxy Flooring:

a. Percent Solids 96 %

b. VOC 33 g/L3.

c. Compressive Strength, ASTM C579 12,500 psi

d. Tensile Strength, ASTM D638 4,000 psi

e. Service Temperature Up to 200F

f. Abrasion Resistance, ASTM D4060 25 mg

C-17 Wheel, 1,000 gm load, 1,000 cycles

g. Potlife @ 70 F 10-15 minutes

h. Film Hardness (ASTM D4366),

i. Seconds, ultimate 90

i. Gloss (ASTM D523) 60 91

j. Coefficient of Friction, ANSI B101.1 >0.6

k. Dynamic Coefficient of Friction -

Wet, ANSI A326.3 >0.42

vi. Colored paint chips must have 100% coverage with 50% white and 50% light grey.

vii. Provide a six-inch integral polyaspartic epoxy cove base with continuous top aluminum termination strip at wall perimeter.

2. Color shall be light to medium grey and approved by the Technical Point of Contact. (Color samples shall be submitted for approval.)

3. Flooring texture shall be an orange peel texture that is simple to clean up spills, chemically non-reactive, and has good traction. A sample provided shall be approved by the Technical Point of Contact.

Part 3 Execution:

1. Safety Equipment: It is the Contractor's responsibility to furnish and supply personnel with the proper personal protective equipment (Hardhats, Hand Protection, Eye Protection, Ventilation, etc.) when and where necessary.

2. Preparation:

The Contactor shall supply all materials, equipment and labor to prepare the floor surface for the coatings. Surface preparation shall include mechanically preparing the floor surface by grinding, shot blasting or other means as specified by the approved product. Floor must be clean and sound prior to application. This shall be done according to the best practice standards for installing epoxy flooring and polyaspartic coating. All rooms are currently bare concrete and no removal of residue is required. There are various cracks, spalls, and divots that are required to be filled before epoxy application. There are ~30 divots that are ~1/2" depth and 3" wide. There are also ~5 cracks that are 1/8" wide that must be repaired.

a. Appropriate Personal Protective Equipment (PPE) shall be utilized for each step of this job including protection from potentially hazardous airborne particulates that could be inhaled.

b. Industry standard containment barriers, dust collection mechanisms, and ventilation systems with dust collection capabilities shall be properly utilized and functioning during mechanical preparation of floor surfaces. The adjacent rooms will be occupied, and each work area must be sealed with poly sheeting meeting OSHA standards. Contractor shall provide equipment to achieve negative pressure to force air outside the building and ensure venting is away from occupied spaces and operable windows. There is existing ductwork in the work area which the contractor may utilize for the negative air system. The ductwork goes directly up through the roof. The contractor will NOT be permitted to temporarily isolate or protect HVAC returns/supplies in the work area during surface preparation and coating installation. Contractor shall tape off the doorways in the nearby offices/work areas.

c. Appropriate protection shall be incorporated around any wood surfaces, plumbing and electrical components, and any other surface that could be damages due to the mechanical preparation of the floor surface.

d. There is one (1) floor drain in room 154A. This drain shall be plugged and shall be protected throughout installation. If blasting, the recommended blasting media is glass beads or similar non-toxic blasting media to obtain an appropriate Concrete Surface Profile (CSP) recommended for the polyaspartic floor coating system.

e. NOTE: SILICA SAND MAY NOT BE USED ON FEDERAL INSTALLATIONS AS A BLAST

MEDIA.

f. The Contractor shall dispose of any paint, dust, and other waste materials according to Federal, State, and Local requirements regarding this type of material.

g. There is NO concrete moisture testing, relative humidity testing, calcium chloride testing, or pH testing required as part of the contact.

h. The contractor may perform the work across all rooms in one continuous sequence, and no work is required to be phased.

3. Application of Epoxy System:

The Contractor shall supply all materials, equipment, and labor necessary to properly apply the polyaspartic epoxy system to all eight (8) rooms.

a. The Contractor shall prepare the floor surface to receive topping per manufacturer's recommendation.

b. The Contractor shall furnish and apply topping per manufacturer's recommendation to provide an overall epoxy system thickness of 1/8". The floor coating shall be applied evenly to assure seamless coverage of the floor surface. Where the new floor meets existing flooring, the new epoxy flooring shall be flushed with existing. Provide 1/4" wide stainless-steel transition between differing floor types.

c. The Contractor shall apply two (2) coats of a polyaspartic flooring system. Second coat shall be applied according to the manufacturer's instruction for an orange peel texture.

d. The Contractor shall apply colored paint chips with 100% coverage and 50% of them white and 50% light grey.

e. The contractor shall apply a six-inch integral cove base where the floor meets every wall and column. Provide a top aluminum termination strip at all integral cove base locations. Miter aluminum termination joints at all outside and insider corner locations.

f. There is a floor joint in room 154. The floor joint shall remain exposed and functional. Do not cut, fill, or apply coating to the floor joint. The contractor will ensure the joint is protected during the painting process.

g. The Contractor shall follow all cure times and manufacturer recommendations regarding surface preparation, humidity, and temperature.

h. Mockups: Apply mockups to verify selections made under sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution. Do not cover up mockup area.

i. Apply full-thickness mockups at a minimum of 16 square feet floor area as selected by the TPOC. Mockup must also include cove base conditions for one inside corner and one outside corner.

ii. Approved mockups may become part of the completed work if undisturbed at time of Substantial Completion.

iii. Mockup shall demonstrate desired slip resistance for review and approval by the TPOC prior to installing in other project areas.

iv. Government review will occur within 24 hours once mockup is complete.

4. Disposal:

The Contractor shall dispose of all materials in the appropriate waste streams. Any new and unused epoxy product shall be mixed and cured before being disposed in required waste streams.

5. Warranty of Construction:

a. In addition to any other warranties in this contract, the Contractor warrants that work performed under this contract conforms to the contract requirements and is free from defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

b. The warranty shall continue for a minimum period of one (1) year from the date of final acceptance of the work.

*** END OF NARRATIVE ***

Requirements Epoxy Floor Coating, Cold Regions Research and Engineering Laboratory, Hanover, NH

Section E - Inspection and Acceptance

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.246-12 Inspection of Construction. 1996-08

Section F - Deliveries or Performance

0001 Delivery Schedule From date of lead time event to completion of performance 90 Calendar Days

Date of Award 1 JobQuantity

Address and POC Place of Performance DoDAAC: W913E5 CountryCode: USA

W2R2 COLD RGNS RSCH ENG LAB

KO CONTRACTING OFFICE VCCO, 72 LYME ROAD HANOVER, NH 03755-1290

UNITED STATES

ERIC C. ROSENBERG, DELIVER_TO_EMP_ID_NO

Section G - Contract Administration Data

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

2018-12

252.236-7000 Modification Proposals--Price Breakdown.

1991-12

DFARS Clauses Incorporated by Full Text

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.232-7006 Wide Area WorkFlow Payment Instructions.

2023-01

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause-

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall-

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web- Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC ____ Issue By DoDAAC ____ Admin DoDAAC ____ Inspect By DoDAAC ____ Ship To Code ____

Ship From Code ____ Mark For Code ____ Service Approver (DoDAAC) ____ Service Acceptor (DoDAAC) ____ Accept at Other DoDAAC ____ LPO DoDAAC ____ DCAA Auditor DoDAAC ____ Other DoDAAC(s) ____ (*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

SECURITY REQUIREMENTS:

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures -this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

All contract personnel requiring physical Physical security and access control requirements:

access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly known as "NCIC-III") and Terrorist Screening Database (commonly referred to as "TSDB"). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.

Escorting in classified and/or sensitive areas: In accordance with appliable regulations, all contract personnel who do not possess the appropriate security clearance or access privileges will be escorted in areas where they may be exposed to classified information or operations, sensitive information or activities, or restricted areas.

WAGE DETERMINATIONS:

The Wage Determination for this project can be found at:

https://sam.gov/wage-determination/NH20260018/1

Wage Determination No.: NH20260018

Modification No.: 1

Revised Date: 18 May 2026

*** END OF NARRATIVE ***

W912WJ26QA154

https://sam.gov/wage-determination/NH20260018/1

Section I - Contract Clauses

UAI 5152.249-9000 Basis for Settlement of Proposals

Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under Federal Acquisition Regulation (FAR) 49.206-2(b). In evaluating a termination settlement proposal using total cost basis, the following principles will be applied to determine allowable equipment costs.

(a) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.

(b) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.

(c) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.

(d) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of Federal Acquisition Regulation (FAR) 31.205-11).

(e) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.

(End of Clause)

52.211-10 Commencement, Prosecution, and Completion of Work.

The Contractor shall be required to (a) commence work under this contract within 21 calendar days after the date the Contractor receives the notice to proceed (contract award shall be considered notice to proceed if less than the bonding threshold), (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than from notice to proceed 90 calendar days (contract award shall be considered notice to proceed if less than the bonding threshold).* The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.236-27 Site Visit (Construction).

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) Site visits may be arranged during normal duty hours by contacting:

Name: Eric Rosenberg

Address: 72 Lyme Road, Hanover, NH 03755

Email Address: Eric.C.Rosenberg@usace.army.mil

Telephone: 978-318-8216

(End of Provision)

MAGNITUDE OF PROJECT

The estimated cost of the work is between $25,000 and $100,000.

*** END OF NARRATIVE ***

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.

2017-01

52.204-9 Personal Identity Verification of Contractor Personnel.

2011-01

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (Deviation 2026-O0038)

2026-02

52.204-13 System for Award Management- Maintenance. (Deviation 2026-

2026-02

O0038)

52.204-19 Incorporation by Reference of Representations and Certifications.

2014-12

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.

(Deviation 2026-O0038)

2026-02

52.219-6 Notice of Total Small Business Set-Aside. (Deviation 2026- O0038)

2026-02

52.222-3 Convict Labor. (Deviation 2026- O0038)

2026-02

52.222-6 Construction Wage Rate Requirements. (Deviation 2026- O0038)

2026-02

52.222-7 Withholding of Funds. (Deviation 2026-O0038)

2026-02

52.222-8 Payrolls and Basic Records.

(Deviation 2026-O0038)

2026-02

52.222-9 Apprentices and Trainees.

(Deviation 2026-O0038)

2026-02

52.222-10 Compliance with Copeland Act Requirements. (Deviation 2026- O0038)

2026-02

52.222-11 Subcontracts (Labor Standards).

(Deviation 2026-O0038)

2026-02

52.222-12 Contract Termination-Debarment. 2014-05

52.222-13 Compliance with Construction 2014-05

Wage Rate Requirements and Related Regulations.

52.222-14 Disputes Concerning Labor Standards. (Deviation 2026- O0038)

2026-02

52.222-15 Certification of Eligibility. 2014-05

52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation 2026- O0038)

2026-02

52.222-50 Combating Trafficking in Persons. (Deviation 2026-O0038)

2026-02

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation 2026-O0038)

2026-02

52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation 2026- O0038)

2026-02

52.222-90 Addressing DEI Discrimination by Federal Contractors.

(Deviation 2026-O0040, Revision 1)

2026-04

52.223-2 Reporting of Biobased Products Under Service and Construction Contracts. (Deviation 2026- O0038)

2026-02

52.223-5 Pollution Prevention and Right-to- Know Information.

2024-05

52.223-23 Sustainable Products. (Deviation 2026-O0038)

2026-02

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving.

2024-05

52.228-2 Additional Bond Security. 1997-10

52.228-11 Pledges of Assets (DEVIATION 2020-O0016)

2021-02 Deviation 2020- O0016

2020-04

52.228-12 Prospective Subcontractor Requests for Bonds.

2022-12

52.228-14 Irrevocable Letter of Credit. 2014-11

52.232-23 Assignment of Claims. 2014-05

52.232-27 Prompt Payment for Construction Contracts.

2017-01

52.232-33 Payment by Electronic Funds Transfer-System for Award Management.

2018-10

52.232-39 Unenforceability of Unauthorized Obligations.

2013-06

52.232-40 Providing Accelerated Payments to Small Business Subcontractors.

2023-03

52.233-1 Disputes. (Deviation 2026- O0038)

2026-02

52.233-3 Protest after Award. (Deviation 2026-O0038)

2026-02

52.233-4 Applicable Law for Breach of Contract Claim. (Deviation 2026- O0038)

2026-02

52.236-2 Differing Site Conditions.

(Deviation 2026-O0038)

2026-02

52.236-3 Site Investigation and Conditions Affecting the Work. (Deviation 2026-O0038)

2026-02

52.236-5 Material and Workmanship.

(Deviation 2026-O0038)

2026-02

52.236-6 Superintendence by the Contractor. (Deviation 2026- O0038)

2026-02

52.236-7 Permits and Responsibilities.

(Deviation 2026-O0038)

2026-02

52.236-8 Other Contracts. (Deviation 2026- O0038)

2026-02

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (Deviation 2026-O0038)

2026-02

52.236-10 Operations and Storage Areas.

(Deviation 2026-O0038)

2026-02

52.236-11 Use and Possession Prior to Completion. (Deviation 2026- O0038)

2026-02

52.236-12 Cleaning Up. (Deviation 2026- O0038)

2026-02

52.236-13 Accident Prevention. (Deviation 2026-O0038)

2026-02

52.236-14 Availability and Use of Utility Services. (Deviation 2026-O0038)

2026-02

52.236-21 Specifications and Drawings for Construction. (Deviation 2026- O0038)

2026-02

52.240-91 Security Prohibitions and Exclusions. (Deviation 2026- O0038)

2026-02

52.242-14 Suspension of Work. 1984-04

52.243-5 Changes and Changed Conditions. (Deviation 2026- O0038)

2026-02

52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation 2026-O0038)

2026-04

52.246-21 Warranty of Construction. 1994-03

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form).

1984-04

52.249-10 Default (Fixed-Price Construction).

1984-04

DFARS Clauses Incorporated by Reference

Date

Alternate Deviation

Variation Effective Date

252.203-7000 Requirements Relating to Compensation of Former DoD Officials.

2011-09

252.203-7002 Requirement to Inform Employees of Whistleblower Rights.

2022-12

252.204-7003 Control of Government Personnel Work Product.

1992-04

252.204-7004 Antiterrorism Awareness Training for Contractors.

2023-01

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. (DEVIATION 2024-

O0013 REVISION 1)

2024-05 Deviation 2024- O0013

2024-05

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.

2023-01

252.204-7020 NIST SP 800-171 DoD Assessment Requirements.

2023-11

252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials.

2014-09

252.223-7008 Prohibition of Hexavalent Chromium.

2023-01

252.225-7048 Export-Controlled Items. 2013-06

252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.

2023-01

252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region.

2023-06

252.232-7004 DoD Progress Payment Rates

(DEVIATION 2020-O0010)

2014-10 Deviation 2020- O0010

2020-03

252.232-7010 Levies on Contract Payments. 2006-12

252.243-7001 Pricing of Contract Modifications. 1991-12

252.244-7999 Subcontracts for Commercial Products or Commercial Services. (DEVIATION 2026- O0015)

2026-02…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .