This solicitation (W912BU25QA015) is for an overhaul of the Survey Vessel (S/V) RECONNAISSANCE by the U.S. Army Corps of Engineers Philadelphia District. The contract requires the contractor to furnish all engineering, design, labor, services, equipment, parts, and materials necessary to perform drydocking and repairs, including installing new 200 HP Yamaha engines, hull painting, surface preparation, audiogaging, and other vessel maintenance tasks.
Key details include a 30-calendar day performance period between July 1-August 1, 2025, a firm fixed-price contract type, and 100% small business set-aside under NAICS Code 336611 with a 1,300-employee size standard. Quotes are due via email to Domenic Sestito and Matthew Rhoads, with vendors required to be registered in SAM.gov. A unique mileage surcharge evaluation factor will be applied based on the vessel's round-trip distance from Atlantic City, NJ, calculated at $50 per nautical mile. Quotes will only be accepted from facilities along the Atlantic Coast between New York, NY and Baltimore, MD.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment W912BU25QA0150001 SF 30 (2).pdf | ||
| N47900-301 Rev 0 ELECTRICAL SYSTEMS (1).pdf | ||
| Wage Determination.txt | TXT text file | |
| N47900-101 REV 0 GENERAL ARRANGEMENT (1).pdf | ||
| 25RECON SECT B-recon (reworked).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
Created On:
17 Jun 2025, 07:18 AM Central Daylight Time
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Section A - Solicitation/Contract Form
FY25 Shipyard of S/V RECON
W912BU25QA015
Section B - Supplies or Services & Prices or Costs
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
0001 FY25 Shipyard of S/V RECON
Pricing Arrangement: Firm Fixed Price
1 Job
Section C - Description/Specifications/Statement of Work
SECTION C
DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
TABLE OF CONTENTS
TP TECHNICAL PROVISIONS
TP-1 SCOPE OF WORK
TP-2 DEFINITIONS
TP-3 STANDARDS
TP-4 CERTIFICATION AND CLASSIFICATION
TP-5 INSPECTIONS, TESTING AND TRIALS
TP-6 WORKMANSHIP AND CONSTRUCTION STANDARDS
H HULL SECTION ITEMS
H-101 DRYDOCKING
H-102 UTILITIES AND SERVICES (UNIT PRICE)
H-200 SURFACE PREPARATION, INSPECTION AND AUDIOGAGING
H-201 HULL PAINTING
H-202 HULL ANODE REPLACEMENT
H-203 APPLICATION OF ARMY STAR DECALS
H-214 INSPECTION AND REPAIR FOREPEAK VOID
M MACHINERY SECTION ITEMS
M-101 INSTALL NEW 200 HP YAMAHA ENGINES
SECTION C
TP TECHNICALPROVISIONS
TP-1 SCOPE OF WORK
Overhaul the SURVEY VESSEL (S/V)RECONNAISSANCE. The contractor shall furnish all engineering, design, labor,services, equipment, parts and materials necessary to perform the drydockingand repairs listed in this contract.
Drawings, equipment or materials to befurnished by the Government will be specifically listed in the appropriate section.Unless specifically listed, the contractor shall assume no drawings, equipmentor materials will be furnished by the Government and shall submit offeraccordingly.
TP-2 DEFINITIONS
The following definitions are applicableto phrases and acronyms used throughout this Statement of Work
(SOW):
- ContractingOfficer (KO) A person with authority toenter into, administer, and/or terminate contracts and make relateddeterminations and findings.
- ContractingOfficer's Representative (COR) A memberof the Philadelphia District contract management and quality assurance teamauthorized by the Contracting Officer to perform administrative and managerialduties. A copy of the COR's authorityletter will be furnished to the Contractor at the time of award.
- GovernmentFurnished Equipment (GFE) Equipment,materials, parts, supplies, or components furnished by the Government to thecontractor for installation on the vessel.
- USACE Acronym for the U.S. Army Corps ofEngineers.
- PSBr - Acronym forthe Physical Support Branch of the Philadelphia District Corps of Engineers.
- QC - QualityControl. Quality Control is a function of the contractor. Refer to clause E03.
- QA - QualityAssurance. Quality Assurance is a function of the Government.
- ABS Acronym for the American Bureau of Shipping
- USCG Acronym for the U.S. Coast Guard.
- CFR Acronym for the Code of Federal Regulations.
- ANSI Acronym for American National StandardsInstitute
- OSHA Acronym for Occupational Safety and HealthAdministration
- NFPA Acronym for National Fire ProtectionAssociation
TP-3 STANDARDS
All design, engineering, modifications andrepairs to the vessel shall be performed in accordance with the criteria setforth in the latest issues of the following standards:
- U.S. Army Corps ofEngineers, Publication No. EM 385-1-1, "Safety and Health RequirementsManual." Dated 15 March 2024.
- 46 CFR SubchapterT - "Rules and Regulations for Small Passenger Vessels (Under 100 Gross Tons)"[46 CFR 175 - 185].
- 46 CFR SubchapterS - "Subdivision and Stability Regulations" [46 CFR 170 - 171].
- United StatesPublic Health Service (USPHS), Publication No. 393 "Handbook on Sanitationof Vessel Construction".
- USCG, NavigationRules - Inland/International.
- Institute ofElectrical and Electronic Engineers Standards, Publication No. IEEE-45 -Recommended Practice for Electrical Installation on Shipboard.
- IlluminatingEngineering Society, "Recommended Practice for Marine Lighting."
- National ElectricCode (NEC).
Note that these standards apply only tothe engineering, design and workmanship performed by the contractor as part ofthis contract including removals, accesses and other work performed by thecontractor incidental to the work required by the contract.
TP-4 CERTIFICATION AND CLASSIFICATION
The vessel is not certificated by theUSCG.
The vessel is not classed by the ABS.
It is not intended as part of thiscontract that any classification or certifications be achieved.
TP-5 INSPECTIONS, TESTING AND TRIALS
The contractor shall perform tests, trialsand other operational performance demonstrations as necessary to validate thatthe work specified in this contract was completed in accordance with therequirements, and functions as it was intended.
The contractor shall provide reasonableadvance notice (not less than 1 full working day) to the COR prior to anytesting or trials. If the COR, afterhaving received such notification, is not present at the designated time andplace for the inspection or test, the contractor shall proceed with theinspection or test. Untimelynotification will result in postponement or repetition of the test. Lack of notification will requireretesting. All delays caused by impropernotification are the responsibility of, and to the account of, the contractor.
The contractor shall furnish a competentand authorized individual to witness and document the results of allinspections and/or tests.
TP-6 WORKMANSHIP AND CONSTRUCTION STANDARDS
GENERAL REQUIREMENTS FOR ACCESSA
After careful planning and subject to theapproval of the COR, the Contractor may cut and/or remove plating or framingmembers from the vessel for access to machinery, piping, wiring and equipment. Under the same conditions, the Contractor mayalso remove piping, wiring, fixtures, fittings, etc., for access and clearanceto perform required work.
All removed equipment shall be tested aspart of the Tests and Trials requirement in Section TP5 of this SOW.
Damages to parts, components and/or equipmentas a result of removals, is the responsibility of the contractor and shall berepaired/replaced in kind.
Any removalsfor access shall be temporarily supported if lack of such support could causefailure or damage to adjacent systems, distortion of adjacent framing orplating, or result in a safety hazard.
All removals shall be replaced oncerequired work is completed. Replacementshall consist of returning the removed equipment, piping, wiring, structuralmembers and plating to their original locations and reinstallation.
Installation shall be in accordance with theoriginal construction drawings or referenced standards (Refer to TP3). Fit and finish shall be restored and damagedpaint shall be renewed.
GENERAL REQUIREMENTS FOR HULL WORKB
All new hull plating shall be fabricatedfrom marine grade Aluminum plate 5086/5083.
Due regard shall be paid to details inboth the design and construction of all new and/or modified structures, toprevent structural discontinuities and other stress concentrations. Where openings must be provided in thestructure, adequate compensation shall be provided by the contractor.
Watertight integrity of all bulkheads anddecks shall be maintained. Openingscreated by permanent removal or addition of piping, wiring or other materialsshall be closed by means of watertight penetrations or insert plates of equalthickness flush welded to the bulkheads.
All welds shall be ground flush andsmooth.
Sections of stiffeners, beams, girders,etc., shall be welded to the bulkheads to maintain continuity of structure.
Openings cut into decks and bulkheadsshall be adequately compensated by bounding bar to maintain original strength.
All watertight, oil tight and weathertight work shall be tested for tightness prior to painting. Testing procedures, other than hydrostatic testing, shall be submitted to the COR forapproval. Submittals shall includecomplete particulars on the testing procedure(s) proposed and, if air testingis used, the method of controlling the air pressure. Water used for testing shall be potablequality to prevent contamination of the compartments and piping.
GENERAL REQUIREMENTS FOR FOUNDATIONSAND SUPPORTSC
Suitable foundations shall be providedunder all new units of machinery. Foundations shall be built up of plates and structural shapes to thedimensions required for satisfactory support, and shall assure rigidity, freedomfrom vibration and designed for secure containment of the equipment in event ofcrash stops.
Where dripping water or oil can beexpected, the top plates of foundations shall project beyond the edges of thebed plates or bases of units being supported and formed into spillcontainment/drip pans. Flat bars weldedaround the edges of the top plates may be used to retain any leakage. Valveddrains shall be provided at the ends or corners of the pans to facilitate fluidremoval or recovery.
Foundations shall extend beyond theequipment fore and aft or transversely to distribute the load and to avoidexcessive weight concentrations.
Doublers, insert plates, girders, headersand stanchions shall be fitted and under deck framing shall be reinforced tosupport units mounted on deck.
GENERAL REQUIREMENTS FOR MATERIALSD
All materials provided by the contractorshall be suitable for marine applications and shall be subject to approval ofthe COR/GTR.
All new hull plate shall be marine gradeAluminum plate 5086/5083.
All new extrusions, shapes and pipegreater than or equal to 3" shall be marine grade Aluminum 6061.
All new extrusions and pipe less than 3"shall be marine grade Aluminum 6063.
Fasteners shall be AISI type 304 or 316stainless steel.
All fasteners shall be installed using nonmetallic gasket material when placed against an aluminum surface.
GENERAL REQUIREMENTS FOR PIPINGE
All piping required in thesespecifications shall be designed and installed to obtain optimum operatingconditions, and shall be compatible with the machinery or equipment serviced.
All piping, valves and fittings shallcomply with material specifications of the design standards for that particularservice.
Piping shall be run as directly aspractical. Piping shall include valves, unions and fittings.
Unions and flanges shall be provided tofacilitate installation and subsequent removal.
Flexible connections to machinerycomponents shall be provided where vibration may be anticipated.
Piping shall not pass over switchboardsand be kept clear of switchgear, wiring, etc.
All work shall be templated from thevessel.
Piping shall be secured by supports andhangers so as to avoid excessive strains; avoid the weight of the piping beingtransmitted to valves and fittings; minimize the effects of vibration, shock,pitching and rolling of the vessel; and permit proper thermal expansion andcontraction. Provision may be made forexpansion and contraction by changes in direction of pipe runs or by use ofexpansion bends, joints, loops or offsets.
Exhaust piping shall be welded for allsizes.
All burrs shall be removed from the endsof all piping after any cutting or threading. Pipe ends shall be dressed with a reamer before installation.
Valve type shall be consistent with theservice. All valve materials shall be stainless steel.
An aluminum label plate shall be attachedto the hand wheel of all new valves to indicate its function.
Where pipes are carried through watertightbulkheads, decks or tank tops, the watertight integrity of the structure shallbe maintained.
Heat sensitive materials shall not be usedin piping systems which penetrate watertight subdivisions.
All fasteningsused to connect valves to shell connections shall be of stainless steel.
Where dissimilar metals occur, thecontractor shall insulate to prevent electrolytic action.
GENERAL REQUIREMENTS FOR MACHINERYSYSTEMSF
Where new machinery and equipment is to beinstalled, or when existing machinery and equipment is relocated, thecontractor shall mount the items on suitable foundations.
All fastenings, bolts, (fitted orotherwise) studs, nuts, washers, gaskets, etc., shall be installed using antiseize compound furnished by the contractor unless otherwise specified.
Any defective or missing fasteners shallbe renewed at Contractor's own expense.
Where detailed disassembly, assembly, orinstallation procedures appear in this specification, they are presented forthe contractor's information and convenience in estimating the possible extentof the work to be done. The inclusion ofthese detailed procedures does not relieve the contractor of responsibility fordoing all work necessary and in the proper manner for satisfactorilyaccomplishing the specified ultimate objective.
GENERAL REQUIREMENTS FOR ELECTRICALSYSTEMSG
All electrical installations as set forthin these specifications shall be in compliance with the referenced rules, regulations and standards, especially with regard to ambient and workingtemperature requirements.
Electric cable shall be capable ofhandling the required amperage.
Electrical installations shall be such soas to eliminate the possibility of mechanical injury or damage from theaccumulation of dust, oil, vapors, steam, dripping liquids, etc.
New cable runs shall be supported atintervals of not more than 18" apart where vertical and 14" apartwhere horizontal. Straps, hangers, and standoffs shall be steel with stainlesssteel fasteners. Plastic type straps arepermitted only behind sheathing/paneling. No cable runs will be permitted below the deck plates, except for bilgepump wiring. Cable penetrations, whererequired to be watertight, shall have approved kick plates, stuffing tubes,etc.
All electrical supplies and/orinstallations to meet CFR 46, Subchapters J and T, as well as all applicableNEMA, NEC and ANSI standards.
GENERAL REQUIREMENTS FOR HOT WORKH
Prior to any hot work commencing in anycompartment, the compartment shall be pumped dry, cleaned, gas freed and madesafe for entry and hot work in accordance with 29 CFR 1915, Occupational Safetyand Health Standards for Shipyard Employment, and other applicable standards.
The COR/GTR shall be furnished a MarineChemist certificate stating that each compartment gas freed by the contractorhas been tested by an approved certified Marine Chemist and that the space issafe for hot work.
All spaces that have been certified by aMarine Chemist as safe for hot work, shall be checked daily by a competentperson to ensure there continued state of being safe for hot work. A log containing the original Marine Chemistcertificate and Daily checklist shall be kept at the gangway so that all whoneed to enter the space will have easy access to the knowledge of their currentconditions.
The contractor shall provide and maintainproper ventilation of spaces in which hot work is required or men are requiredto enter. Disposal of materialaccumulated during gas freeing work shall be the responsibility of thecontractor and shall be in accordance with all federal, state and local lawsand all costs are to be included in the respective line item.
The contractor shall post and maintain afire watch whenever any hot work is being performed. If work is being performed on a bulkhead, afire watch shall be posted on both sides of the bulkhead and/or deck.
GENERAL REQUIREMENTS FOR WELDINGI
All welding under this contract shall bedone only by welders who have successfully passed the qualifications test ofthe ABS, the U.S. Navy or the USCG for steel welding.
The contractor shall bear the expense ofconducting these tests, and shall certify by name to the COR those welders whohave successfully passed the prescribed tests. The contractor shall require any welder to repeat these tests when, inthe opinion of the COR or his appointed representative, the work of the welderindicates a reasonable doubt of his efficiency. In such cases the welder shall be recertified as above.
The electrodes used throughout the workshall be suitable for use with the parent metal at each weld. Electrodes shall be received on the job inunbroken packages bearing the manufacturers' label or be otherwise marked.Certified statements shall accompany each shipment of electrodes to the effectthat sample pieces, representative of each kind and size in each shipment, havesatisfactorily passed the tests required by the ABS, the USCG, and/or the U.S.Navy for steel welding.
Welding in this contract shall be doneusing the MIG process. All welding shallbe smooth, tight and free from undercuts, porosity, craters and gas inclusions.
Shell and deck butts and flush seams shallbe back chipped or gouged to sound metal from the closing side before welding.
All sharp and/or rough edges shall beground smooth and all weld spatter shall be removed.
All welds for temporary dogs used duringmodifications are to be ground smooth.
Assemblyof all welded joints before welding shall be such as to secure proper gaps inbutt welds and metal contact in fillet welds. Welding shall not be used to close openings larger than stipulated foreach plate thickness by the ABS.
All watertight seal welds shall be of"bead" type; no "weave" welding will be permitted.
Welding procedures, as to direction,length and number and sequence beads shall be carefully planned to minimizedistortion and locked in stresses.
GENERAL REQUIREMENTS FOR WORKMANSHIPJ
All parts of the work intended to join orbear upon others shall be cut or trimmed to fit neatly.
All faying surfaces shall be clean andsmooth before bolting up. Shims orliners shall not be used for the purpose of overcoming a bad fit.
Lightening holes may be punched, sawn orsheared and all burrs and cutting slag shall be removed.
Weld spatter shall be removed from allplating and stiffeners.
All mounting holes shall be drilled andreamed. Holes in members having sharpcurvature shall be avoided whenever possible.
All frames and longitudinals shall havelimber holes and/or snipes of adequate size to allow water to flow to thelowest point of each compartment and to allow air to escape.
All joints or areas of connection betweensteel and dissimilar metals shall be properly insulated by gasket material.
All fastenings used for connecting steelshall be made of AISI type 304 or type 316 series stainless steel.
All labor shall be performed by competentindividuals skilled for each kind of work, thorough, first class in everyrespect and under competent direction.
Where work of one trade joins, passesthrough or is on other work, there shall be no discrepancy or misfit whencompleted. In engaging one kind of workwith another, marring or damaging of previously acceptable construction shallbe cause for rejection.
GENERAL REQUIREMENTS FOR PAINTINGK
The contractor shall seal off allventilation, antennas, engine room, exhaust, tank and fan vents or openings,and all other intake or exhaust venting/piping and cover all zinc anodes,transducers, windows, propellers, propeller shafts, shaft bearings, ruddersstocks, and other fixtures that could be damaged or introduce contaminationinto the vessel from the high pressure water washing, sandblasting, orpainting. This protection shall bechecked and maintained daily during performance of any blasting and paintingoperations.
All areas contaminated with grease, oil,lubricants or other foreign matter shall be cleaned with a solvent similar toDEVOE Devprep #88, 788 T 000, or equal.
Defective shell plate discovered duringblasting shall be reported to the COR/GTR immediately.
All paints shall be from a singlemanufacturer and the paint system shall be applied in strict accordance withthat manufacturer's guidelines and recommendations, including time betweencoats, proper application equipment, thinning and disposal of excess paint andthinner and cleaning of equipment.
All painting underwater surfaces shall becompleted and accepted by the COR/GTR prior to refloating the vessel.
The contractor shall furnish the COR/GTRwith a thickness gauge suitable for use on aluminum to verify proper wet/dryfilm thickness.
All paints used in the performance of thiswork shall be within the manufacturer's specified closed container and "pot"shelf life.
All overspray of any new paint ontoexisting finished surfaces shall be removed and all surface repaired tooriginal condition.
Colors shall conform to Federal Standard595, in accordance with the following schedule:
AREA COLOR AND FS595NUMBER
Hull Exterior Black/17038
Deckhouse Exterior Old Ivory/13695
Decks & Housetop Deck Red/10076
Hull & Deckhouse Interior White/27880
Deck Fittings Yellow/13655
Hull Markings White/27880
Exterior Deck Coaming Striping Red/11136
Handrails & Stair Rails Black/17038
Antifouling 1st Coat ManufacturerContrasting Color
Antifouling 2nd Coat Manufacturer's Red
GENERAL REQUIREMENTS FOR DISPOSAL OFFLUIDSL
All fluids, including, but not limited to,diesel fuel, lubricating oil, hydraulic fluid, antifreeze/coolant, bilgewastes, battery acid, penetrating and cutting oils, dye penetrants, and paintthinners removed from the vessel or generated by the contractor in the courseof performing the required work shall be disposed of by the contractor inaccordance with all Federal, State, Regional and Local laws, rules,regulations, and guidelines for the disposal of hazardous materials, this toinclude all fluids that shall be drained from equipment removed from the vesselfor disposal or other disposition. Allassociated costs shall be included in the appropriate line item.
This also applies to any rags, clothing,equipment or other materials exposed or contaminated with such fluids.
GENERAL REQUIREMENTS FOR CONFINED SPACESM
The contractor shall comply with allrequirements of Federal Law contained in 29 CFR 1910 and 29 CFR 1915 for entryinto, monitoring of, rescue from and closure of confined spaces during theperformance of the contract.
The contractor shall have a competentperson on site whenever any work is being performed in a confined space andshall post required certificates in the immediate vicinity of the confinedspace and maintain a log of all inspections and certificates.
GENERAL REQUIREMENTS FOR SAFETYN
The contractor shall comply with therequirements of EM 385 1 1, "U.S. Army Corps of Engineers Safety and HealthRequirements Manual" throughout the contract period. It can be found online athttp://www.usace.army.mil/publications /eng-manuals/em385-1-1/toc.htm.
The contractor shall maintain Safety,Fire, and Security programs as required by Section H of this contractthroughout the contract period.
PART I - SECTION C
H HULLSECTION ITEMS
H-101 DRYDOCKING
1. INTENT
It is the Intent of this work itemto haul the vessel from the water and block the vessel while performing theunderwater work outlined in the Statement of Work (SOW). The vessel will need to be fleeted on theblocks in order to achieve a 100% coating of the underwater painting system.
2. REFERENCES
Drawing N47900-101 - 'General Arrangement'
MIL-STD-1625 - 'Safety CertificationProgram for Drydocking Facilities and Shipbuilding Ways for US Navy Ships'
NAVFAC DM-29.1 - 'Graving Docks,Design Manual 29.1'
3. DESCRIPTION OF WORK
Provide all labor, services and materialsand perform the work required in this clause. Provide a certified marine railway, or a certified synchro-lift, etc.and qualified personnel and necessary equipment to dock the vessel. The Survey Vessel RECONNAISSANCE has thefollowing principal dimensions:
Overall Length: 31 feet - 11 inches
Overall Beam: 9 feet -3-1/2 inches
Displacement (light ship): 9,757 pounds
Draft: 2feet - 0 inches
Vessel is constructed entirely ofaluminum:
All plating 5086/5083
Angle, Box Tube and Pipe 3" andlarger - Aluminum 6061
Pipe 2-1/2" and smaller - Aluminum6063
Provide and set blocks to supportand distribute the weight of the vessel while out of water and to preventmovement of vessel. Blocks shouldprovide for a minimum of 36-inches clearance under the hull.
Haul the vessel out of water and set onthe blocks. Participate in the jointdocking inspection.
Immediately after drydocking the vessel,and before the hull and any marine growth has had a chance to dry, the entirehull from the keel to the top of the bulwarks shall receive a fresh water high pressurewash at no less than 5000 psi.
The vessel's underwater hull will bepainted in its' entirety. This will makeit necessary to adjust the blocking for the washing, blasting and applicationof the paint system specified in Line Item H-202 of this contract.
Upon completion of all underwater relatedrepairs and following the joint undocking inspection, return the vessel to thewater.
All lay days, demurrage and other dockcosts, including the costs of weekends and holidays, necessary to perform therepair work listed in this contract shall be included in the cost of this LineItem.
Estimate on 30 calendar days fordry-docking.
H-102 UTILITIES AND SERVICES (UNIT PRICE)
The contractor shall provide all labor,materials, and equipment necessary to maintain the drydock and pier sideutilities and services specified in this work item for the duration of thecontract.
2. REFERENCES
Drawing N47900-301 - 'ElectricalSystems'
Services shall be connected and operatingwithin 2 hours after arrival of the vessel at the contractor's facility andshall continue until the vessel is accepted by the COR.
Payment shall be made only for the actualnumber of days the vessel remains and utilizes services at the contractor'sfacility.
Unit price shall cover all costsincidental to and charged direct to the job, and not otherwise included asoverhead.
Utilities and Services consist of thefollowing:
- SHORE POWER: Provide necessary labor to connect, maintain and disconnect shore powerservice for initial hook-up, re-blocking and moving vessel to pierside. Provide electrical service for the durationof the repair period.
Shore power service to be 30 amps(minimum), 120/240 VAC, 60 Hz, single phase.
The vessel contains a number of componentsand systems that are sensitive to voltage fluctuations. The contractor shall beresponsible for removal, repair or replacement, reinstallation and testing ofelectrical equipment which fails while the ship is in the contractor'spossession due to voltage surge or fluctuation.
* NOTE: There shall be no welding on board the shipwhile the Surveying Equipment is connected to the vessel. Coordinate with the crew for removal ofSensitive Surveying Equipment to facilitate welding.
The vessel shall be grounded to earth viaa grounding conductor when operating on shore power. Ensure the vessel is galvanically isolatedfrom the shore (earth), using a galvanic isolator or an isolation transformer. Application and installation of this deviceshall be in accordance with ABYC E-8.20.
- TRASH REMOVAL: Provide receptacles, equipment and labor to collect and remove garbageand trash from the vessel. The trashbins shall be located near the gangway.
- CRANE SERVICE: Provide all crane or forklift service, labor and rigging equipment formoving supplies, provisions, spare parts, liferaft, and equipment on and offthe vessel, and to and from the storage area. All other crane or forklift service directly related to repair worklisted in this contract shall be included in the cost of that Work Item.
- GANGWAY: Provide a gangway (stairs or ladder) with safety net or ladder foraccess to and from the vessel.
Install (on opposite side of vessel fromgangway) and maintain a separate ladder from the ground to the main deck foremergency egress during the docking period.
Estimate on 30 calendar days. Price per day.
H-200 SURFACE PREPARATION, INSPECTION AND AUDIOGAGING
It is the intent of this work itemto prepare the vessel's underwater hull from keel to deep load line forpainting, since we are changing the entire Paint System.
It is also intended to prepare andmake available the entire hull of the vessel for taking audiogage readings,especially in any areas of concern.
2. DESCRIPTION OF WORK
SURFACE PREPARATION, INSPECTIONA.
Immediately after drydocking the vessel,and before the hull and any marine growth has had a chance to dry, the entirehull from the keel to the top of the bulwarks shall receive a high-pressurewash.
The high-pressure wash shall be performedwith fresh water only and shall be no less than 5000 psi. All washing to be performed shall be donefrom above (i.e. from the top of the drydock, scaffolds, etc.) with the nozzlespointed down to the floor of the dock to prevent the spread of water to theupper portion of the vessel and into any interior spaces.
After the Vessel hull has dried and within24 hours after drydocking the vessel, a joint inspection shall be conductedwith the COR and the contractor.
A written condition report withrecommendations shall be submitted by the contractor to the COR within 24 hoursafter performing the joint inspection. The report shall include a summary of the hull's condition, including anestimate of the total square-footage of the hull that requires a renewal of theanticorrosive system.
The paint on the entire hull from the keelto the deep load line shall be blasted using dry sand, hydro blast or shotblast to remove all paint in accordance with Steel Structures Painting CouncilSpecification SSPC SP 7.
Completelyremove all oil, grease, dirt, rubber streaks, paint and foreign matter. The surface should be sufficiently abraded toprovide good adhesion and bonding of paint. Blast overspray shall be kept to minimum.
All blasting shall be done from above with the nozzlespointed down toward ground to prevent the spread of blast or water to the upperportion of the vessel.
Scaffolds, cherry pickers or other means shall be providedfor use of personnel in blasting/power washing and painting.
Prior to abrasive blasting,precautions shall be taken to protect the hull, equipment, and machinery fromflying sand, dust and water discharge. This also applies to blasting on otherships in the vicinity.
All open fans, vents, doors, hatches, antennas and wiring,windows, nameboards, castle, ship's bell, electrical outlets, navigationlights, wipers, spotlight, davits, winches, machinery and deck gear shall besealed with plastic film or a suitable substitute prior to blasting andpainting operations. As an option, equipment may be removed prior to blastingand reinstalled after the last coat of paint has dried.
Special care shall be taken to mask and fully protect thetransducers, zinc anodes, and other underwater equipment against abrasion,damage, and painting.
Any damage to the vessel or itscomponents due to lack of or improper painting/blasting protection shall berepaired to original by the Contractor at no additional cost to the Government.The Contractor shall contact the COR to inspect and approve theblasting/painting protection prior to the start of the blasting process. Itshall be the responsibility of the Contractor to maintain the blasting/paintingprotection for the duration of the blasting /painting process. At no time shallthis be a cause for extension of contract time or additional cost to theGovernment.
B. AUDIOGAGINGOF SUSPECT AREAS
The contractor shall conduct withqualified technician or provide the services of a testing firm to take audiogage readings on the hull along the keel in the areas aft, where salt water hascaused corrosion and oxidation to be noticed from inside the vessel. The audio gauging is to be done by ultrasonictesting or any other non-destructive testing methods.
The contractor shall provide the COR witha sketch showing the audio gage readings in relation to their position on thehull of the vessel.
Audio gage 100 spots as directed shall betaken along the keel. Pits and areasshowing 25% or more wastage from original thickness shall be highlighted.
NOTE: Coordinate with line item No. H-201, Hull Painting.
H-201 HULL PAINTING
NOTE - All of the manufacturers (E-Paint) and USACEpreparation and environmental conditions must be met prior to beginning anyoperation.
Surface temperature, humidity, wind conditions, dew point andwet-bulb readings shall be checked and recorded at least twice daily.
It is the intent of this work item toreplace the original underwater paint coating system, in its entirety, with E-Paint SN-1 (Black), from the keel tothe deep load line, on the surface prepared underwater hull of the vessel.
2. GOVERNMENT FURNISHED MATERIAL
E-Paint SN-1 (Black) Qty - 15 gallons
E-Paint Primer Qty - 6 gallons
The contractor shall furnish all necessarylabor, materials, services, and equipment and prepare and paint the hull of theSurvey Vessel RECONNAISSANCE in accordance with the following specifications.
A. PREPARATIONS/PAINTING
All work is to be performed in accordancewith Technical Provisions section TP-6 (K).
Residue on unpaintedsurfaces resulting from overspray and/or lack of protection shall be removedfrom the vessel daily by whatever non-destructive methods necessary.
Artificial illumination shall be used onany area specified to be painted, which cannot be clearly seen otherwise, atany time the work is being performed.
All of the manufacturers and USACEpreparation and environmental conditions must be met prior to beginning anyoperation. Surface temperature, humidity, wind conditions, dew point andwet-bulb readings shall be checked and recorded at least twice daily.
B. PAINTING(Keel to Deep Load Line)
The hull from the keel to the deep loadline shall be prepared and painted in accordance with the followingspecifications:
After pressure washing/blasting the hullas required above in H-201(A) proceed with painting the hull as follows:
The primer EP Epoxy Primer 1000 shall beapplied in two-(2) contrasting coats after final surface preparation has beenachieved in accordance with Manufacturer's recommendations. Each application of this coating shall beapplied with a minimum thickness of at least 4 mils.
All atmospheric condition requirements, such asTemperature and Relative Humidity for application, shall be strictly adheredto.
A hard, smooth foul release coating E-PaintSN-1 (Black), shall be provided on hull, up to 6 inches above the full loadwaterline. This coating shall be applied as the final two coatings and shouldbe at least 4 mils dry, each coating. This application shall be applied over the recommended primer coats of EPEpoxy Primer 1000.
C. PAINTING(Remove & Reinstall Lower Rub Rail and Apply Paint System)
The Contractor shall remove the lower rubrail in its entirety, Port & Starboard (approximately 40 Linear feet), toallow access to paint the shell behind it.
The primer EP Epoxy Primer 1000 shall beapplied in two-(2) contrasting coats after final surface preparation has beenachieved in accordance with Manufacturer's recommendations. Each application of this coating shall beapplied with a minimum thickness of at least 4 mils.
All atmospheric condition requirements, such asTemperature and Relative Humidity for application, shall be strictly adheredto.
A hard, smooth foul release coating E-PaintSN-1 (Black), shall be provided on hulls and foils, up to 6 inches above thefull load waterline. This coating shall be applied as the final two coatingsand should be at least 4 mils dry, each coating. This application shall be applied over therecommended primer coats of EP Epoxy Primer 1000.
Upon completion of all work, thecontractor shall reinstall both sides with contractor-furnished stainless-steelhardware.
H-202 HULL ANODEREPLACEMENT
It is the intent of this work item toreplace all of the Vessel's underwater hull sacrificial anodes.
The contractor shall provide all labor,materials and equipment and accomplish the following:
Inspect all of the underwater hullsacrificial anodes and provide a condition report to the COR, noting theposition on the hull, size and type of anode and the approximate percentwastage. This is for historical recordsand analysis of the current cathodic protection scheme's effectiveness.
The Contractor shall then replace all ofthe sacrificial anodes located on the vessel's hull. All new anodes shall be the same size andmaterial as the original (Martyr CMZ03B).
Coordinate installation of anodes withLine-Item H-201, Hull Painting.
H-203 APPLICATIONOF ARMY STAR DECALS
The Department of the Army has a newrequirement to have every vessel in the fleet display the Army Star Decal. Theintent of this line item is to have the Government Furnished Army Star Decalsadhered to the vessel in the proper locations.
2.GOVERMENT FURNISHED MATERIAL
1. Two (2) Black Stars
2. Two (2) Black lettering "U.S. ARMY"
The Contractor shall provide all necessarylabor, materials, services and equipment to apply two (2) complete Army Star Decals to the shell of the vessel.Specific locations will be on the Port and Starboard side of the vessel's hullat or near the stern in a manner that does not diminish the prominence of thevessel's nameboard, the U.S. Army Corps of Engineers Castle insignia, or anyother authorized vessel markings or identification.
CHECKPOINT - Once all locations have been identified specifically bythe COR, the Contractor and the COR will meet on the vessel to ensure that theDecals will be installed in the proper locations and orientations.
Eachlocation will be properly prepared and made ready for the application of thedecals. Prior to application, wash and dry the locations to remove any dirt anddebris. Finish with a final cleaning using a solvent similar to DEVOE Devprep#88, 788 T 000, or equal. The Decal will be parallel with the gunwale of thevessel, Port and Starboard. Ensure a bubble-free application of all vinyl decals.
H-214 INSPECTION AND REPAIR FOREPEAK VOID
The intent of this line item is tohave the Forepeak Void cleaned, inspected, and painted.
The Contractor shall provide all necessary labor, materials, servicesand equipment to open, clean, inspect, make repairs and paint the Forward Voidin accordance with the Technical Provisions.
NOTE - Theforward void does not carry any fuels or lubricants and is expected to haveminimal quantities of water, dirt and possible rust inside. The contractorshall include the removal and the disposal of the contents of this space in thebid price.
Upon removalof all contents, the void shall be cleaned of all contents, including anymaterial that may be adhered to the inside surface and longitudinal andtransverse framing members of the void. The void may be cleaned by hand, powerwashing tools and/or detergent and degreasers and shall wiped down with cleanlint free rags to the satisfaction of the COR.
CHECKPOINT -Inform the COR that the FWD Void is ready for final inspection.
Uponcompletion of the inspection by the COR, any repairs that are deemed necessaryshall be made.
Once allrepairs to the FWD Void are completed, ensure the void continues to be in acondition to accept paint.
Apply onecoat of Rust grip or similar product and a final topcoat of Amercoat 385, Whiteor similar product.
Uponcompletion of all work, the contractor shall close and reseal the access hatchwith contractor-furnished sealant and stainless-steel hardware.
PART II - SECTION C
M MACHINERYSECTION ITEMS
M-101 INSTALL NEW 200HP YAMAHA ENGINES
It is the intentof the Government is to replace the existing two-(2) 200 HP Yamaha Engines withtwo-(2) GFM Yamaha 200 HP Engines.
2. GOVERNMENT FURNISHED MATERIAL
Two-(2) 200 HP Yamaha Engines
The contractor shall provide alllabor, materials and services to accomplish the replacement of the 200 HPYamaha Engines.
Remove the existing 200 HP Yamaha Engines.They are located on the stern of the vessel.
NOTE - The contractorshall provide the services of Yamaha technical representative to oversee theinstallation and sea trials of new 200 HP Yamaha Engines.
It is intended to keep all wiringharnesses and control systems in place for this installation, just changing outthe Engine Set and restoring mechanical and electrical connections.
For the Engine Set, upon completion ofinstallation the contractor shall accomplish the following:
- Ensureproper operation of all components.
- Demonstrateto the COR the proper functioning of the shutdowns and alarms.
- Verifyall gages and meters function properly and display the correct read-outs.
The aforementioned work shall beaccomplished in accordance with the manufacturer's installation, maintenance, and service requirements.
Requirements Overhaul the SURVEY VESSEL (S/V) RECONNAISSANCE. The contractor shall furnish all engineering, design, labor, services, equipment, parts and materials necessary to perform the drydocking and repairs listed in this contract.
Product Service Code: J998
Section E - Inspection and Acceptance
Overall Contract Inspection/Acceptance Locations
Inspection and Acceptance Location
Both Destination Instructions: Email POC
DoDAAC: W912BU CountryCode: USA
W2SD ENDIST PHILADELPHIA
1650 ARCH STREET, 7TH FLOOR
PHILADELPHIA, PA 19103-0000
UNITED STATES
Sarah Moore Email: sarah.e.moore@usace.army.mil
Section F - Deliveries or Performance
Overall Contract Delivery Period
From date of lead time event to beginning of performance 30 Calendar Days Date of Notice to Proceed Receipt
From date of lead time event to completion of performance 30 Calendar Days Date of Notice to Proceed Receipt
Line Item Delivery Schedule Quantity Address and POC
Delivery Schedule From date of lead time event to completion of performance 30 Calendar Days Date of Notice to Proceed Receipt
1 Job Place of Performance DoDAAC: W912BU CountryCode: USA
W2SD ENDIST PHILADELPHIA
1650 ARCH STREET, 7TH FLOOR
PHILADELPHIA, PA 19103-0000
UNITED STATES
Sarah Moore, DELIVER_TO_EMP_ID_NO Email: sarah.e.moore@usace.army.mil
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.247-34 F.o.b. Destination. Nov 1991
Section G - Contract Administration Data
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.201-7000 Contracting Officer's Representative. Dec 1991 252.217-7007 Payments. Dec 1991 252.217-7008 Bonds. Dec 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. Dec 2018
Section I - Contract Clauses
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. Jan 2017 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. Jun 2020 52.204-13 System for Award Management Maintenance. Oct 2018 52.204-18 Commercial and Government Entity Code Maintenance. Aug 2020 52.204-19 Incorporation by Reference of Representations and Certifications. Dec 2014
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities.
Dec 2023
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
Nov 2021
52.204-27 Prohibition on a ByteDance Covered Application. Jun 2023
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded
Jan 2025
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. Nov 2015 52.219-6 Notice of Total Small Business Set-Aside. Nov 2020 52.222-3 Convict Labor. Jun 2003 52.222-36 Equal Opportunity for Workers with Disabilities. Jun 2020 52.222-41 Service Contract Labor Standards. Aug 2018 52.222-50 Combating Trafficking in Persons. Nov 2021 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. Jan 2022 52.222-62 Paid Sick Leave Under Executive Order 13706. Jan 2022 52.223-23 Sustainable Products and Services. May 2024 52.225-13 Restrictions on Certain Foreign Purchases. Feb 2021 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving. May 2024 52.232-1 Payments. Apr 1984 52.232-8 Discounts for Prompt Payment. Feb 2002 52.232-11 Extras. Apr 1984 52.232-23 Assignment of Claims. May 2014 52.232-25 Prompt Payment. Jan 2017 52.232-33 Payment by Electronic Funds Transfer-System for Award Management. Oct 2018 52.232-39 Unenforceability of Unauthorized Obligations. Jun 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. Mar 2023 52.233-3 Protest after Award. Aug 1996 52.233-4 Applicable Law for Breach of Contract Claim. Oct 2004
52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities.
Nov 2024
52.243-1 Changes-Fixed-Price. Aug 1987 52.243-1 Changes-Fixed-Price. (Alternate I) Aug 1987 Alternate I Apr 1984 52.244-6 Subcontracts for Commercial Products and Commercial Services. Jan 2025 52.249-4 Termination for Convenience of the Government (Services) (Short Form). Apr 1984
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.203-7000 Requirements Relating to Compensation of Former DoD Officials. Sep 2011 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. Dec 2022 252.204-7003 Control of Government Personnel Work Product. Apr 1992 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. May 2024
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.
Jan 2023
252.204-7020 NIST SP 800-171 DoD Assessment Requirements. Nov 2023 252.217-7003 Changes. Dec 1991 252.217-7004 Job Orders and Compensation. May 2006 252.217-7005 Inspection and Manner of Doing Work. Jul 2009 252.217-7006 Title. Dec 1991 252.217-7009 Default. Dec 1991 252.217-7010 Performance. Jul 2009 252.217-7011 Access to Vessel. Dec 1991 252.217-7012 Liability and Insurance. Aug 2003 252.217-7013 Guarantees. Dec 1991 252.217-7014 Discharge of Liens. Dec 1991 252.217-7015 Safety and Health. Dec 1991
252.217-7016 Plant Protection. Dec 1991 252.225-7048 Export-Controlled Items. Jun 2013 252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime. Jan 2023 252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region. Jun 2023 252.232-7010 Levies on Contract Payments. Dec 2006 252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel. Jan 2023 252.243-7001 Pricing of Contract Modifications. Dec 1991 252.244-7000 Subcontracts for Commercial Products or Commercial Services.
This is the start of the file's text. The full file is on GovTribe.