This document is a solicitation for the Norman Project Recreation Improvements at Lake Thunderbird State Park in Oklahoma, issued by the Department of the Interior Bureau of Reclamation. The project involves comprehensive recreational area upgrades across three primary locations: Little Sandy Day Use Area, Little Sandy Camp Sites, and Post Oak RV Site & Group Shelter. Key construction activities include demolition, site preparation, concrete work, installing accessibility features, constructing day use shelters, playgrounds, camping pads, parking areas, water utilities, electrical infrastructure, fencing, and landscaping.

The solicitation is structured as a fixed-price construction contract with base and optional pricing schedules totaling multiple line items across different project areas. The contract has a 365-calendar day completion period and includes specific requirements for Indian Small Business Economic Enterprise set-aside provisions. The work encompasses detailed improvements to enhance recreational facilities, including ADA-compliant features like accessible tables, parking, sidewalks, fire rings, and site markers. Pricing is itemized by specific construction elements such as concrete work, shelters, utilities, grading, and installation of recreational amenities, with separate schedules for different project locations.

View the file

Other files for this federal contract opportunity

Other files attached to Norman Recreation Improvements, newest first.
File Type Posted
Sol_140R6025R0008_Amd_0003.pdf PDF
140R6025R0008_0003_0003.pdf PDF
Sol_140R6025R0008_Amd_0002.pdf PDF
140R6025R0008_0002_0002.pdf PDF
Sol_140R6025R0008_Amd_0001.pdf PDF
140R6025R0008_0001_0001.pdf PDF
Drawings_0001.pdf PDF
Sol_140R6025R0008.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior April 2025 Bureau of Reclamation

Region

Norman Project Recreation Improvements Lake Thunderbird Norman Project, Oklahoma

Norman Project Recreation Improvements

Norman Project, Oklahoma

Table of Contents 00 01 10 - 1

SECTION C - DESCRIPTION / SPECIFICATIONS

TABLE OF CONTENTS

SECTION A – Solicitation, Offer, and Award Form, Standard Form 1442

SECTION B – Schedule

SECTION C – Specifications

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 14 10 Use of Site 01 14 12 Work Restrictions 01 14 30 Interruption of Service 01 31 19 Project Management and Coordination 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractors Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents

DIVISION 02 – DEMOLITION AND STRUCTURE MOVING

02 41 00 Demolition

DIVISION 03 - CONCRETE

03 11 10 Concrete Forming 03 20 00 Concrete Reinforcing

Norman Project, Oklahoma

00 01 10 - 2

03 20 30 Grouted Anchor Bars 03 20 60 Concrete Anchor Bolts 03 30 00 Cast-In-Place Concrete

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 92 00 Joint Sealants

DIVISION 10 – SPECIALTIES

10 14 00 Signage

DIVISION 12 - FURNISHINGS

12 90 01 Furnishings

DIVISION 13 – SPECIAL CONSTRUCTION

13 34 20 Metal Shelters 13 34 30 Playgroup

DIVISION 22 – Plumbing 22 00 00 Plumbing, General Purpose

DIVISION 26 – ELECTRICAL

26 05 02 Basic Electrical Materials and Methods 26 05 10 Conductors and Cables 26 05 20 Grounding and Bonding 26 05 33 Electrical Conduit

DIVISION 31 - EARTHWORK

31 02 10 Water for Dust Abatement 31 11 00 Clearing and Grubbing 31 23 02 Compacting Earth Materials 31 23 11 Earthwork for Structures 31 23 22 Pipe Trench Earthwork 31 23 39 Disposal of Excavated Materials 31 32 32 Geotextile 31 37 00 Riprap

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 22 Asphalt Pavement, Crack Filling, and Seal Coat 32 15 10 Aggregate 32 17 20 Painted Traffic Lines and Markings 32 31 30 Fencing 32 32 21 Segmented Retaining Wall 32 91 19 Placing Topsoil 32 92 20 Sod and Minor Grading

Norman Project, Oklahoma

Table of Contents 00 01 10 - 3

DIVISION 33 - UTILITIES

33 11 10 Pipeline General Requirements 33 42 30 Corrugated Metal Pipe Culverts

DIVISION 52 - DRAWINGS

52 00 00 Drawings

SECTION D – NOT USED

SECTION E – INSPECTION AND ACCEPTANCE

E.1 Inspection of Construction …………………………………………………………… E-1 E.2 Inspection-Dismantling, Demolition, or Removal of Improvements …………………E-2

SECTION F – DELIVERIES OR PERFORMANCE

F.1 Commencement, Prosecution, and Completion of Work ……………………………..F-1 F.2 Variation in Estimated Quantity ………………………………………………………F-1 F.3 Suspension of Work …………………………………………………………………...F-1

SECTION G – CONTRACT ADMINISTRATION DATA

G.1 Authorities and delegations …………………………………………………………. .G-1 G.2 Contracting Officer’s Representative Authorities and Limitations …………………..G-2 G.3 Electronic Invoicing and Payment Requirements – Invoicing Processing Platform …G-3 G.4 Notice to Contractors-Contractor Performance Assessment Reporting System … …..G-4

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 Schedule of Values …………………………………………………………………... H-1 H.2 Site Security ……………………………………………………………………...….. H-1 H.3 Payment of Bonds …………………………………………………………………… H-2 H.4 Postaward Conference – Bureau of Reclamation …………………………………… H-3

PART II – CONTRACT CLAUSES

I.1 Clauses Incorporated by Reference …………………………………………………... I-1 I.2 Basic Safeguarding of Covered Contractor Information System …………………….. I-3 I.3 Federal Acquisition Supply Chain Security Act Orders-Prohibition ………………… I-5 I.4 Updates of Publicly Available Information Regarding Responsibly Matters ………..I-10 I.5 Prohibition on Contracting with Inverted Domestic Corporations ………………….. I-12 I.6 Variation in Estimated Quantities …………………………………………………… I-12 I.7 Order of Precedence-Uniform Contract Format ……………………………………...I-13 I.8 Limitations on Subcontracting (Deviation) ………………………………………….. I-13 I.9 Hazardous Material Identification and Material Safety Data ALT I …………...…… I-16 I.10 Estimate of Percentage of Recovered Material Content for EPA-Designated Items ...I-18 I.11 Privacy Act …………………………………………………………………………...I-19 I.12 Buy American-Construction Materials …………………………………………...…. I-20 I.13 Additional Bond Security ……………………………………………………………. I-25 I.14 Prospective Subcontractor Requests for Bonds ……………………………………... I-25 I.15 Performance and Payment Bonds-Construction……………………………………... I-26

Norman Project, Oklahoma

Table of Contents 00 01 10 - 4

I.16 Payments under Fixed-Price Construction Contracts ………………………………...I-27 I.17 Prompt Payment for Construction Contracts ………………………………………... I-30 I.18 Payment by Electronic Funds Transfer-System for Award Management ……………I-39 I.19 Providing Accelerated Payments to Small Business Subcontractors ………………... I-41 I.20 Disputes ALT I ……………………………………………………………………….I-41 I.21 Differing Site Conditions ……………………………………………………………. I-43 I.22 Site Investigation and Conditions Affecting the Work …………………………….... I-43 I.23 Operations and Storage Areas ……………………………………………………….. I-44 I.24 Accident Prevention …………………………………………………………………. I-44 I.25 Availability and Use of Utility Services …………………………………………….. I-45 I.26 Schedule of Construction Contracts ………………………………………………….I-45 I.27 Specifications and Drawings for Construction ALT I ………………………………. I-46 I.28 Changes ……………………………………………………………………………… I-47 I.29 Changes and Changed Conditions ……………………………………………………I-48 I.30 Warranty of Construction ……………………………………………………………. I-49 I.31 Default (Fixed-Price Construction ) ALT I ………………………………………….. I-50 I.32 Authorized Deviations in Clauses …………………………………………………… I-52 I.33 Restrictions on Endorsements—Department of the Interior ………………………… I-52 I.34 Release of Claims—Department of the Interior ……………………………………... I-52 I.35 Examination of Records by the Department of the Interior …………………………. I-52 I.36 Privacy Act Notification (Deviation) ………………………………………………... I-52 I.37 Liability Insurance—Department of the Interior ………………………………….... I-52 I.38 Prohibition Against Use of Lead-Based Paint ………………………………………..I-53 I.39 Indian Economic Enterprise Subcontracting Limitations ………………………….... I-54 I.40 Prohibition on Release of Information—Bureau of Reclamation …………………… I-54 I.41 Incorporation of Technical Proposal—Bureau of Reclamation ……………………... I-54 I.42 Asbestos Free Warranty—Burau of Reclamation …………………………………… I-54 I.43 Safety and Health—Bureau of Reclamation ………………………………………… I-55 I.44 Payment for Mobilization and Preparatory Work, Bureau of Reclamation ALT III I-55 I.45 Other Invoice Requirements ………………………………………………………….I-55 I.46 Claims Accounting—Bureau of Reclamation ………………………………………..I-56 I.47 Preservation of Cultural Resources …………………………………………………..I-57 I.48 Security Requirements ALT III ………………………………………………………I-59 I.49 Modification Proposals—Bureau of Reclamation ALT II …………………………...I-68

PART III – DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

PART IV – REPRESENTATIONS AND INSTRUCTIONS

Norman Project, Oklahoma

00 01 10 - 5

SECTION K – REPRESENTATIONS, CERTIFICATIONS, AND OTHER

STATEMENTS

K.1 Solicitation Provisions Incorporated by Reference ………………………………….. K-1 K.2 Certificate of Independent Price Determination …………………………………….. K-1 K.3 Predecessor of Offeror ………………………………………………………………. K-2 K.4 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment ………………………………………………………………. K-3 K.5 Covered Telecommunications Equipment or Services Representation ………………K-5 K.6 Federal Acquisition Supply Chain Security Act Orders

—Representation and Disclosures ……………………………………………………K-6 K.7 Certification Regarding Responsibility Matters ……………………………………... K-7 K.8 Information Regarding Responsibility Matters ……………………………………… K-9 K.9 Representation by Corporations Regarding Delinquent Tax Liability or A Felony Conviction under any Federal Law ……………………………………….K-10 K.10 Violation of Arms Control Treaties or Agreements-Certification …………………..K-11 K.11 Postaward Small Business Program Rerepresentation ……………………………... K-13 K.12 Previous Contracts and Compliance Reports ………………………………………. K-17 K.13 Public Disclosure of Greenhouse Gas Emissions and

Reduction Goals-Representation …………………………………………………… K-17 K.14 Preparation of Proposals-Construction ……………………………………………... K-18 K.15 Notice of Indian Small Business Economic Enterprise Set-Aside …………………. K-18 K.16 Indian Economic Enterprise Representation ……………………………………….. K-18

SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS

L.1 Solicitation Provisions Incorporated by Reference …………………………………... L-1 L.2 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 …………………. L-1 L.3 Availability of Defense Specifications, Standards, and Data Item Descriptions In the Acquisition Streamlining and Standardization Information System (ASSIST) Website …………………………………………………………………….L-1 L.4 Instructions to Offerors-Competitive Acquisition …………………………………… L-2

L.5 Type of Contract ……………………………………………………………………... L-6 L.6 Notice of Buy American Requirement-Construction Materials ………………………L-6 L.7 Bid Guarantee …………………………………………………………………………L-7 L.8 Individual Surety Pledge of Assets (Bid Guarantee) ………………………………… L-8 L.9 Site Visit (Construction) ALT I ……………………………………………………… L-8

L.10 Preparation of Proposals—Construction ……………………………………………. L-11 L.11 Authorized Deviations in Provisions ……………………………………………….. L-12 L.12 Use and Disclosure of Proposal Information—Department of the Interior ………… L-12 L.13 Service of Protest—Department of the Interior (Deviation) ………………………... L-14 L.14 Notice of Indian Small Business Economic Enterprise Set-Aside …………………. L-14 L.15 Proposal Instructions—Bureau of Reclamation ……………………………………..L-14 L.16 Intent to Incorporate Technical Proposal—Bureau of Reclamation ………………...L-19 L.17 Instruction for Mobilization and Preparatory Work …………………………………L-20

Norman Project, Oklahoma

Table of Contents 00 01 10 - 6

SECTION M – EVALUATION FACTORS FOR AWARD

M.1 Source Selection Evaluation Procedures—Bureau of Reclamation ………………… M-1 M.2 Evaluation Factors for Award—Quality Predominance-Bureau of Reclamation ……M-1

PART I – THE SCHEDULE

SECTION A

Solicitation, Offer, and Award

(Standard Form 1442)

04/11

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. {Include aree coda)

16. REMITTANCE ADDRESS {Include only If cl/fferenl than item 14.)

COOE FACILITY COOE

17. The offeror agrees to perform the work required at the prices specified below In strict accordance with the terms of this sollcltatlon, lfthls offer Is accepted by the Government in writing within _______ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum n,quitement staled in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

AMOUNTS ►I

18. The offeror agrees to fumish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

{The offeror acknowledges receipt of amendments to the so/iciletion - give number and dale of each)

AMENDMENT NO.

DATE.

208. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMSACCEPTED:

Continued ...

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless othelwise specified)

25. OTHER THAN FULL AND OPEN COMPETITION PURSLl'\NT TO THE UNITED STATES COOE AT

26. ADMINISTERED BY COOE IR 6 0

D 10 U.S.C. 3204(a) D 41 u.s.c. 3304(a)

27. PAYMENT WILL BE MADE BY

Invoice Processing Platform System US Department of Treasury https://www.ipp.ogv

----------------1

Bureau of Reclamation Missouri Basin Regional Office

2021 4th Avenue North

Billings MT 59101

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

□ 28. NEGOTIATED AGREEMENT (Contractor is n,quired to sign this document 029.AWARD (Contractor is not required to sign this document.) Your offer on this and retum copies to issuing office.) Contractor agrees to furnish solicitation is hereby acceptad as to the items listed. This award consummates the ----and deliver all items or perform all worl< requirements identified on this fonn and contract, which consists of (a) the Government solicitation and your offer, and (b) any continuation sheets for the consideration stated in this contract. The rights this contract award. No further contractual document Is necessary.

and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations.certifications, and soecifications incomnrated bv reference in or attached to this contract.

308. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN {Type or print) 31a. NAME OF CONTRACTING OFFICER {Type or print)

Darlene Dillon

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

STANDARD FORM 1442 (REV. 12/2022) BACK

SECTION B

The Schedule

Norman Project, Oklahoma

Price Schedule B - 1

CONTINUATION OF SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

Norman Project Recreation Improvements Lake Thunderbird

Norman Project, Oklahoma

B.1 PRICE SCHEDULE

Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.

Offers are subject to the terms and conditions of this solicitation.

See the contract clause at WBR 1452.232-81 , Payment for Mobilization and Preparatory Work, for CLIN 1

Definitions:

CLIN – Contract Line Item Number

BASE PRICE SCHEDULE A – Little Sandy Day Use

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

1 WBR

1452.232 -81

Mobilization and Preparatory Work lump sum $

2 01 14 10 Silt Fence 932 lin ft $ $

3 01 46 20 Concrete Tests – Fresh Concrete Properties

11 ea $ $

4 01 46 20 Concrete Tests – Compressive Strength

11 ea $ $

5 01 71 20 Surveying lump sum $

Norman Project, Oklahoma

Price Schedule B - 2

BASE PRICE SCHEDULE A – Little Sandy Day Use

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

6 02 41 00 Demolition lump sum $

7 03 30 00 Cast-In-Place Concrete- Parking Slab

35 cubic yards

8 03 30 00 Cast-In-Place Concrete- ADA Compliant Concrete

178 cubic yards

9 10 14 00 ADA Parking Sign 4 ea $ $

10 12 90 01 Precast Parking Bumper 4 ea $ $

11 12 90 01 6 foot ADA Accessible Table

15 ea $ $

12 12 90 01 10 foot ADA Accessible Table

5 ea $ $

13 12 90 01 Pedestal Grill 20 ea $ $

14 12 90 01 Table Top 20 ea $ $

15 13 34 20 Day Use Shelter 5 ea $ $

16 22 00 00 Water Hydrant with Drain 2 ea $ $

17 31 11 00 Tree Removal 16 ea $ $

18 31 23 11 Supplemental Fill 238 cubic yards

19 31 23 11 Playgroup Cut 198 cubic yards

20 31 23 11 Ditch with Berm 1,874 lin ft $ $

21 31 32 32 Filter Fabric 4,244 square feet

22 31 37 00 6 inch Rip Rap 310 tons $ $

23 32 12 22 Removal of Asphalt Concrete Pavement

295 square yards

24 32 15 10 Compacted Crushed Base Course (c.c.b.c.)

486 tons $ $

25 32 15 10 Aggregate Trail 895 lin feet $ $

Norman Project, Oklahoma

Price Schedule B - 3

BASE PRICE SCHEDULE A – Little Sandy Day Use

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

26 32 17 20 Traffic Lines 321 lin ft $ $

27 32 31 30 Steel Post and Cable Fencing

858 lin ft $ $

28 32 32 21 Segmented Retaining Wall 563 square feet

29 32 92 20 Sod and Minor Grading 26,548 ft2 $ $

30 33 11 10 Water Utility Line 90 lin ft $ $

31 33 42 30 Corrugated Metal Pipe Culvert 73 lin ft $ $

TOTAL for BASE CONTRACT PRICE SCHEDULE A: Little Sandy Day Use $

OPTIONAL PRICE SCHEDULE B – Little Sandy Camp Sites

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

WBR

1452.232

-81

Mobilization and Preparatory Work lump sum $

01 46 20 Concrete Tests – Fresh Concrete Properties

7 ea $ $

01 46 20 Concrete Tests – Compressive Strength

7 ea $ $

01 71 20 Surveying lump sum $

Norman Project, Oklahoma

Price Schedule B - 4

OPTIONAL PRICE SCHEDULE B – Little Sandy Camp Sites

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

02 41 00 Demolition lump sum $

03 30 00 Cast-in-Place Concrete – ADA Compliant Concrete

60 cubic yards

10 14 00 ADA Parking Sign 2 ea $ $

12 90 01 Precast Parking Bumper 2 ea $ $

12 90 01 6 foot ADA Accessible Table

3 ea $ $

12 90 01 Fire Ring (Ground Grill with Steel Riser)

3 ea $ $

12 90 01 Lantern Holder 3 ea $ $

12 90 01 Accessible Marker (Campsite Marker)

3 ea $ $

31 23 11 Supplemental Fill 40 cubic yards

31 32 32 Filter Fabric 495 ft2 $ $

31 37 00 6 inch Rip Rap 22 tons $ $

32 15 10 Compacted Crushed Base Course (c.c.b.c.)

54 tons $ $

32 15 10 Compacted Crushed Granular Fill (c.c.g.f.)

82 tons $ $

32 17 20 Traffic Lines lump sum $

32 91 19 31 23 39

Topsoil 82 tons $ $

32 92 20 Sod and Minor Grading 6,000 ft2 $ $

TOTAL for OPTIONAL PRICE SCHEDULE B - Little Sandy Camp Sites $

Norman Project, Oklahoma

Price Schedule B - 5

OPTIONAL PRICE SCHEDULE C – Post Oak RV Site & Group Shelter

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

WBR

1452.232

-81

Mobilization and Preparatory Work lump sum $

01 46 20 Concrete Tests – Fresh Concrete Properties

4 ea $ $

01 46 20 Concrete Tests – Compressive Strength

4 ea $ $

01 71 20 Surveying lump sum $

02 41 00 Demolition lump sum $

03 30 00 Cast-in-Place Concrete – ADA Compliant Concrete

27 cubic yards

10 14 00 ADA Parking Sign 1 ea $ $

12 90 01 Precast Parking Bumper 1 ea $ $

12 90 01 6 foot ADA Accessible Table

1 ea $ $

12 90 01 10 foot ADA Accessible Table

8 ea $ $

12 90 01 Group Shelters Gutters & Downspouts

156 lin ft $ $

12 90 01 Fire Ring (Ground Grill with Steel Riser)

1 ea $ $

12 90 01 Lantern Holder 1 ea $ $

12 90 01 Accessible Marker (Campsite Marker)

1 ea $ $

Norman Project, Oklahoma

Price Schedule B - 6

OPTIONAL PRICE SCHEDULE C – Post Oak RV Site & Group Shelter

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

22 00 00 Water Hydrant 1 ea $ $

22 00 00 Water Hydrant with Drain 1 ea $ $

26 05 02 RV Electric Pedestal 1 ea $ $

31 23 11 Supplemental Fill 68 cubic yards

31 32 32 Filter Fabric 900 ft2 $ $

32 12 22 Asphalt Concrete Drive 40 cubic yards

32 15 10 Compacted Crushed Base Course (c.c.b.c.)

24 tons $ $

32 15 10 Compacted Crushed Granular Fill (c.c.g.f.)

17 tons $ $

32 17 20 Traffic Lines lump sum $

32 91 19 31 23 39

Topsoil 66 tons $ $

32 92 20 Sod and Minor Grading 3,000 ft2 $ $

TOTAL for OPTIONAL PRICE SCHEDULE C - Post Oak RV Site & Group Shelter $

PRICE SCHEDULE D – Little Sandy Playgroup

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

13 34 40 Playgroup lump sum $

TOTAL for OPTIONAL PRICE SCHEDULE D – Little Sandy Playgroup $

Total for Base Price Schedule A and Optional Price Schedules B, C, & D: $__________________________

END OF SECTION

Norman Project, Oklahoma

Summary of Work 01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located approximately 12 miles east of Norman, Oklahoma in Cleveland County.

Project is at two (2) locations at recreational areas of Lake Thunderbird State Park:

1. Little Sandy Beach Area (Latitude 35°14'29.76"N; Longitude 97°14'23.12"W)

2. Post Oak RV Site and Group Shelter (Latitude 35°14'32.67"N; Longitude 97°13'18.89"W)

1.02 PRINCIPAL COMPONENTS OF WORK

A. The principal components of work to be performed under this Contract consist of:

1. Demolition of existing features including utilities, earthwork, and small structures

2. Construct day use sites

3. Construct ADA sidewalks

4. Provide, orient, and install playgroup equipment and furnishings

5. Provide, orient, and install day use site furnishings

6. Provide, orient, and install shelters at day use sites

7. Construct water utility lines

8. Provide, orient, and install water hydrants

9. Construct ADA parking

10. Construct drainage berms

11. Construct aggregate trails

12. Construct post and cable fencing

13. Construct gravel tent sites

14. Construct gravel, asphalt and concrete drives

15. Place Rip Rap

Norman Project, Oklahoma

Summary of Work 01 11 00 - 2

16. Provide gutters and downspouts for existing Group Shelter

17. Construct RV Site

18. Install electric utility

B. This Contract is characterized by the following:

1. Drawings 763-514-1400 through 763-514-1433 and drawings 763-514-1435 through 763-514-1459 show location of the work and specific work requirements.

2. There are no on-site borrow locations planned for the project.

3. Schedules to be used for pricing the work provided in Section 00 00 50 – Section B.

4. There are no applicable Government-furnished Products.

5. Surveys for Clear Bay will utilize established control points as shown in drawings 763-514-1401, 763-514-1436 and 763-514-1446.

1.0 CONSTRUCTION COMPLETION

A. Construction period is 365 calendar days from the receipt of the Notice to Proceed, for all

1.0 PRE-WORK CONTACT

A. Contact Ms. Susie Snyder with Lake Thunderbird State Park at 405-360-3572, prior to beginning work at the site.

1.0 SPECIFICATIONS REQUIREMENTS

Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

Norman Project, Oklahoma

Summary of Work 01 11 00 - 3

PART 2

PART 3

PRODUCTS

Not Used

EXECUTION

Not Used

Summary of Work

01 11 00 - 4

This page intentionally left blank.

Use of Site 01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

B. Silt Fence:

1. Measurement: Length of silt fence constructed.

2. Payment: Unit price offered in the Price Schedule. Includes:

a. Labor and materials to install silt fence.

b. Excavation of material.

c. Haul of necessary material.

d. Compaction of materials.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. Cleaning Manual-2012 Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at:

http://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site on Government land.

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.

2) Parking areas, temporary roads, and haul routes.

01 14 10 - 2

3) Utilities including air, power, and water lines; fire hydrants; and compressor station.

4) First-aid and medical facilities.

5) Areas for processing, storing, and disposing of waste materials from construction operations.

6) Temporary fences.

b. Describe methods to preserve, protect, and repair, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.

c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.

d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.

2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.

1.04 PROJECT CONDITIONS

A. Government land at locations specified in drawings may be used for required construction facilities.

B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.

D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

E. Areas on Government land which will be obliterated by permanent construction or inundated by reservoir may be used where use of such land will be discontinued and construction facilities, materials, equipment, and rubbish and waste materials will be removed to avoid interference with work in such areas or with filling of reservoir.

F. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by COR.

PART 2 PRODUCTS

01 14 10 - 3

PART 3 EXECUTION

3.01 CLEANING

A. Construction equipment:

1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.

3. COR will inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.

3.02 RESTORATION

A. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.

B. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.

C. Unless otherwise instructed, seed disturbed areas of Government land used for construction purposes and not required for completed installation in accordance with section 32 92 20 – Seeding and Soil Supplements with species of native plants, or other approved perennial species, as recommended by an experienced local horticulturist.

01 14 10 - 4

Work Restrictions

01 14 12 - 1

SECTION 01 14 12

WORK RESTRICTIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 WORK RESTRICTIONS

A. Migratory Birds:

1. Nesting season: March 1 - August 31.

2. Work in accordance with Section 31 11 00 - Clearing and Grubbing.

B. Work hours:

1. Monday through Friday, 7 am to 7 pm.

2. Additional hours as determined by COR. Request in writing and be approved 7 days in advance.

3. Additional days as determined by COR. Request in writing and be approved 21 days in advance.

C. Contractor shall not work on any Federal recognized holiday listed below:

1. New Year’s Day

2. Birthday of Martin Luther King, Jr.

3. Washington’s Birthday

4. Memorial Day

5. Juneteenth

6. Independence Day

7. Labor Day

8. Columbus Day

9. Veteran’s Day

10. Thanksgiving Day

11. Christmas Day

Work Restrictions

01 14 12 - 2

D. Contractor shall not perform on site work during the Recreation Season. Recreation Season is defined as the time between Memorial Day and Labor Day of each year. If work is started prior to the Recreation Season, the work shall be completed by the start of the Recreation Season. If it is anticipated that the work will not be completed by the start of the Recreation Season, the Contractor shall wait to the end of that year’s Recreation Season to start the onsite work.

E. Minimize park access roads usage to greatest extent possible.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Interruption of Service

01 14 30 - 1

SECTION 01 14 30

INTERRUPTION OF SERVICE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for items of work for which interruption of services are required.

1.02 SUBMITTALS

A. Submit in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 30-1, Interruption of Service Request:

1. Area where work will be done (by number or other description).

2. Outline procedures for accomplishing work including:

a. Specific safety precautions to be taken.

b. Type and location of barricades.

c. Warning signs.

d. Protective grounds and devices to be used.

3. Commencement time of work.

4. Duration of work.

5. Number of personnel and their classification.

6. Description of equipment to be used.

7. Information indicating that required materials are on site or data indicating shipping dates of materials not on site.

1.03 PROJECT CONDITIONS

A. Coordinate and schedule interruption of services with COR:

1. Coordinate work with Government operations.

2. No specific interruption of service request will be considered unless:

a. COR has reasonable assurance that materials and equipment required for work will be onsite.

b. Contractor will be prepared to perform work on date and during period of time requested for specific interruption of service.

Interruption of Service

01 14 30 - 2

3. Allowable time and available interruption of service periods will govern interruption of service requests, work scheduling, onsite delivery of materials, and required drawings and data submittals.

B. When work cannot be performed during an approved interruption of service period, notify COR that interruption of service is not required.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Project Management and Coordination

01 31 19 - 1

SECTION 01 31 19

PROJECT MANAGEMENT AND COORDINATION

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include cost in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.

html

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 PROJECT COORDINATION

A. The following meetings are considered significant, but do not relieve Contractor from the responsibility of other meetings required outside this section.

B. Site Visits:

1. Meet as necessary with COR at work site to review work, progress made, difficulties in performing work, and resolution necessary to meet specifications requirements.

C. As-built Drawing Review:

1. Update in accordance with Section 01 78 30 - Project Record Documents.

2. Review as-built drawings with COR monthly.

Project Management and Coordination

01 31 19 - 2

Submittals

01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-14 United States National CAD Standards, Version 6

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement Units: US Customary Units.

C. Samples Submittals:

1. Label with complete manufacturer’s product and color identification.

2. Include type and quantity of materials specified in the referenced section in each “set” of samples.

3. Samples: Representative of product to be installed.

Submittals

01 33 00 - 2

4. Label each sample, sample kit with contract number and title.

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

E. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

F. Manuals:

1. Copies:

a. Printed copies: Bound and indexed.

b. Electronic copies: Adobe pdf on CD or DVD discs.

1) Bookmark longer files to assist in navigating file.

2. Contents:

a. Parts identification lists, lists of special tools, and accessories.

b. Schematics and wiring diagrams.

c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.

d. As-built drawings, photographs, and test records or reports if required by the specifications.

G. Samples and Color Selection Submittals:

1. Label with complete manufacturer's product and color identification.

2. Include type and quantity of materials specified in the referenced section in each “set” of samples.

3. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.

4. Color Chips: Sample paint chips. Ink color reproductions are not acceptable.

Norman Project, Oklahoma

Submittals 01 33 00 - 3

5. Label each sample, sample kit, set of color chips, or color chart with contract number and title.

6. The Government will select architectural color and pattern after product approval.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit number of sets specified in “Sets to be sent to:” columns in Table 01 33 00A - List of Submittals.

1. Electronic submittals:

a. In Portable Document Format (.pdf).

b. Include RSN transmittal letter.

c. Do not include Personally Identifiable Information (PII) in electronic submittals.

d. Submittal method (size based):

1) Government can receive e-mails up to 10 MB. Receipt of e-mails exceeding 10 MB (extra-large) may be possible. E-mailing of extra-large electronic submittals may occur only after size limit for transmittal of extra-large email has been verified.

2) Electronic media for submittals too large for e-mail: CD or DVD.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 7 days after receiving comments, unless otherwise directed.

Norman Project, Oklahoma

Submittals 01 33 00 - 4

4. Requirements for initial submittals apply to resubmittals.

F. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned for resubmittal.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.

a. Time extension will be to extent that excess review time caused delay to contract completion date.

b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.

2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to extent that:

a. Approval was required under contract,

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.

C. Submittal response:

1. Response letter will indicate whether submittal is approved, approved subject to identified changes, or not approved.

a. Revise and resubmit submittals not approved.

b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.

Norman Project, Oklahoma

Submittals 01 33 00 - 5

1.07 TRANSMITTAL

Address for codes submittals too large to email listed in Table 01 33 00A -List of Submittals:

Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:

Submit in accordance with this section.

Submit to COR, unless otherwise specified.

PART 2

PART 3

PRODUCTS

Not Used

EXECUTION

Norman Project, Oklahoma

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative.

Submittals 01 33 00 -

RSN

Clause or

Section Title

Submittals required Due date or delivery time

Responsible code

Sets to be sent: **

CO COR

1 Performance and Payment Bonds - Construction 52.228-15

Performance and Payment Bonds

Within 10 calendar days after award

CO 1

electronic

2 Evidence of Increase Within 10 calendar CO 1 0 Additional Bond Security 52.228-2 in Bond Security days after electronic modifications increasing contract value

3 Insurance-Work on a Government Installation 52.228-5

1) Written certification that the required insurance has been obtained

Before commencing onsite work

CO 1

electronic

2) Current certification of insurance for each subcontractor electronic

4 Liability Insurance 1452.228-70

Acceptable Certificate of Liability Insurance

Prior to commencement of work under the contract

CO 1

electronic

5 Site Security WBR 1452.237-80

List of contractor and subcontractor employees

At least 10 days prior to arriving at worksite

COR 1

electronic

6 52.223-3 A I Hazardous Material

Listing of Hazardous Material delivered to the jobsite

COR 0 1

electronic

7 Reporting Executive Certification that Within 10 days of CO 1 0 Compensation executive each report being electronic and First Tier compensation and submitted Subcontract Awards subcontract awards 52.204-10 were reported

8 Labor Standards Data 52.222-11

1) List of subcontractors

2) Statement and acknowledgement Form (SF-1413) for each subcontract

Within 14 days after award of contract

COR 1

electronic electronic electronic electronic

9 Payrolls and Basic Records 52.222-8

Copies of all payrolls Weekly for each week of contract performance

COR 1

electronic

Norman Project, Oklahoma

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative.

Submittals 01 33 00 -

10 Release of Claims 1452.204-70

Release of Claims

(DI-137)

After completion of the work and prior to final payment

CO & COR 1

electroni electroni

11 Estimate of Percentage of Recovered Material Content for EPA- Designated Items, 52.223-9

Provide Estimate of Percentage of Recovered Material Content for EPA Designated Items

After completion of the work and prior to final payment

CO & COR 1

electronic electronic

12 Site Security

WBR 1452.237-80

List of vehicles and equipment to be brought onsite

At least 10 days prior to arriving at worksite

COR 0 1

electronic

01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan

At least 28 days before use of Government land

COR 1

electronic

01 14 30-1 Interruption of Service

Interruption of Service Request

At least 14 days before interruption of service

COR 0 1

electronic

01 35 10-1 Safety Data Sheets Complete LHM and

SDS

At least 14 days before jobsite delivery of hazardous material

COR 0 1

electronic

01 35 10-2 Safety Data Sheets Updated LHM and

SDS

At least 14 days before jobsite delivery of hazardous material not previously listed

COR 1

electronic

01 35 20-1 Safety and Health Safety Program Submitted and accepted before commencing onsite work. See Section 3 of RSHS

COR 0 1

electronic

01 35 20-2 Safety and Health Monthly Accident Summary Report

First day of every month

COR 0 1

electronic

01 35 20-3 Safety and Health Respirator User Documentation

At least 28 days before beginning onsite work

COR 0 1

electronic

01 35 20-4 Safety and Health Exposure Assessment Form

At least 28 days before beginning onsite work

COR 0 1

electronic

01 35 20-5 Safety and Health Other Training Certificates

At least 28 days before beginning onsite work

COR 0 1

electronic

01 35 30-1 Contractors Onsite Safety Personnel

Qualifications At least 28 days before starting onsite work

COR 0 1

electronic

01 46 20-1 Testing Agency Services

Testing Agency Services Plan

At the time of the preconstruction conference

COR 0 1

Norman Project, Oklahoma

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative.

Submittals 01 33 00 -

01 55 20-1 Traffic Control Traffic Control Plan At least 14 days before beginning onsite work

COR 0 1

electronic

01 57 30-1 Water Pollution Control

Stormwater Pollution Prevention Plan

At least 28 days before delivery or storage of oil

COR 0 1

electronic

01 71 20-1 Surveying Resumes At least 35 days before beginning survey work; At least 35 days before personnel change

COR 0 1

electronic

01 74 00-1 Cleaning and Waste Management

Waste Production and Disposal Plan

At least 28 days before starting onsite work

COR 0 1

electronic

01 74 00-2 Cleaning and Waste Management

Waste Production and Disposal Records

Within 7 days of waste disposal

COR 0 1

electronic

01 78 30-1 Project Record Documents

Extra Materials: List of Extra Materials

Within 14 days of completion of work

COR 0 1

electronic

01 78 30-2 Project Record Documents

Warranties Within 14 days of completion of work

COR 0 1

electronic

01 78 30-3 Project Record Documents

Final As-built Drawings

Within 14 days of completion of work

COR 0 1

electronic

03 20 60-1 Concrete Anchor Bolts

Approval Data At least 28 days before installation

COR 0 1

electronic

03 20 60-2 Concrete Anchor Bolts

Instructions At least 28 days before installation

COR 0 1

electronic

03 30 00-1 Cast-In-Place Concrete

Approval Data At least 28 days before placing concrete

COR 0 1

electronic

03 30 00-2 Cast-In-Place Concrete

Cementitious Materials Certification and Test Reports

At least 28 days before placing concrete

COR 0 1

electronic

03 30 00-3 Cast-In-Place Concrete

Test Reports As soon as available COR 0 1 electronic

03 30 00-4 Cast-In-Place Concrete

Delivery Ticket Within 14 days after placing concrete

COR 0 1

electronic

10 14 00-1 Signage Approval Data At least 28 days prior to procuring

COR 0 1

electronic

12 90 01-1 Furnishings Approval Data At least 28 days prior to procuring furnishings

COR 0 1

electronic

13 34 20-1 Metal Shelters Approval Drawings and Data

At least 28 days prior to procuring furnishings

COR 0 1

electronic

13 34 20-2 Metal Shelters Certification At least 28 days prior to procuring furnishings

Norman Project, Oklahoma

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative.

Submittals 01 33 00 -

13 34 20-3 Metal Shelters Erection Plans and Manual

At least 28 days prior to procuring furnishings

COR 0 1

electronic

13 34 30-1 Playgroup Approval Drawings and Data

At least 28 days prior to procuring

COR 0 1

electronic

13 34 30-2 Playgroup Certification At least 28 days prior to procuring

COR 0 1

electronic

13 34 30-3 Playgroup Erection Plans and Manual

At least 14 days before beginning onsite work

COR 0 1

electronic

22 00 00 General Purpose Plumbing

Product Data At least 28 days prior to procuring

COR 0 1

electronic

26 05 02-1 Basic Electrical Materials and Methods

Approval Data At least 28 days prior to starting electrical work

COR 0 1

electronic

31 23 11-1 Earthwork for Structures

Product Data At least 28 days prior to placing topsoil

COR 0 1

electronic

31 23 11-2 Earthwork for Structures

Supplier Information At least 28 days prior to placing topsoil

COR 0 1

electronic

31 23 11-3 Earthwork for Structures

Delivery Ticket Within 14 days after placing material

COR 0 1

electronic

31 32 32-1 Geotextile Product Data At least 28 days before placing geotextile

COR 0 1

electronic

31 37 00-1 Riprap Supplier Information At least 28 days prior to procuring

COR 0 1

electronic

31 37 00-1 Riprap Delivery Ticket Within 14 days after placing gravel

COR 0 1

electronic

32 15 10-1 Aggregate Certification At least 28 days before placing surfacing

COR 0 1

electronic

32 15 10-2 Aggregate Delivery Ticket Within 14 days after placing gravel

COR 0 1

electronic

32 17 20-1 Painted Traffic Lines and Markings

Certification At least 28 days prior to procuring paint

COR 0 1

electronic

32 17 20-2 Painted Traffic Lines and Markings

Instructions At least 28 days prior to procuring paint

COR 0 1

electronic

32 31 30-1 Fencing Approval Data At least 28 days prior to procuring materials

COR 0 1

electronic

32 32 21-1 Segmented Retaining Wall

Approval Data At least 28 days prior to procuring materials

Norman Project, Oklahoma

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative.

Submittals 01 33 00 -

32 32 21-2 Segmented Retaining Wall

Certification At least 28 days prior to procuring materials

COR 0 1

electronic

32 32 21-3 Segmented Retaining Wall

Instructions At least 28 days prior to procuring materials

COR 0 1

electronic

32 92 20-1 Sod and Minor Grading

Sodding Plan At least 28 days prior to beginning work

COR 0 1

electronic

32 92 20-2 Sod and Minor Grading

Sod Certifications At least 28 days prior to beginning work

COR 0 1

electronic

33 11 10-1 Pipeline General Requirements

Approval Data At least 28 days prior to beginning work

COR 0 1

Norman Project, Oklahoma

Safety Data Sheets 01 35 10 - 1

SECTION 01 35 10

SAFETY DATA SHEETS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 DEFINITIONS

A. LHM: List of Hazardous Materials.

B. SDS: Safety Data Sheet.

1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous Material Identifications and Material Safety Data - Alternate 1.

1.03 APPLICATION

A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes materials:

1. Delivered to Government.

2. Incorporated into work.

3. Used by Contractor during contract performance at the jobsite.

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 10-1, Complete LHM and SDS.

C. RSN 01 35 10-2, Updated LHM and SDS:

1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.

1.05 DELIVERY

A. Do not deliver hazardous materials to jobsite which are not included on original or previously updated LHM and SDS before receipt of updated LHM and SDS by COR.

Safety Data Sheets

01 35 10 - 2

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Safety and Health

01 35 20 - 1

SECTION 01 35 20

SAFETY AND HEALTH

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include the cost of complying with this section in the prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR):

1. RSHS- Reclamation Safety and Health Standards including revisions posted.

a. Available on the internet at:

http://www.usbr.gov/ssle/safety/RSHS/rshs.html.

2. FIST 1-1 (2012) Hazardous Energy Control Program.

a. Available on the internet at: www.usbr.gov/power/data/fist_pub.html.

B. Occupational Safety and Health Administration (OSHA):

1. 29 CFR Part 1910 Occupational Safety and Health Standards.

2. 29 CFR Part 1926 Safety and Health Regulations for Construction.

3. Available on the Internet at www.osha.gov.

C. American Conference of Governmental Industrial Hygienists (ACGIH), Threshold Limit Values (TLVs):

1. Available at www.acgih.org.

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 20-1, Safety Program:

1. Submit a comprehensive, job-specific safety and health program in accordance with Section 01 33 00 – Submittals and in accordance with the requirements of Section 3.3 of the Reclamation Safety and Health Standards (RSHS) and these specifications.

01 35 20 - 2

2. Cover aspects of onsite and applicable off-site operations and activities associated with this contract.

3. Follow the outline in Appendix B of the RSHS.

4. The Safety Program will not be accepted for review by the COR unless it addresses, in order, lettered and numbered per Appendix B of the RSHS, a comprehensive narrative for each applicable item in the outline and program elements contained in these specifications.

5. Generic company safety programs are not acceptable. The Safety Program must be site specific for this contract.

6. The Contractor’s Safety Program must be submitted and accepted by Reclamation prior to commencing onsite work, including mobilization.

7. The Safety Program Statement of Responsibility must state that “the contractor is responsible for ensuring that all work will be in compliance with Reclamation Safety and Health Standards and these specifications.”

8. The Safety and Health Program shall include, but not be limited to, the following program elements but the outline in Appendix B of the RSHS shall be followed:

a. Safety and Health Program Guidance--General Requirements (in accordance with Appendix B as per these specifications, Section 01 35 20 1.03.B.4.). Comply with RSHS, local safety programs, and any other referenced safety and health standards. Perform work in accordance with the specific safety program elements and referenced standards.