Solicitation_Checklist_Summary_5.18.26.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Mill & Replace Asphalt Resurfacing
Solicitation number
ITB 26-070
Issued by
Lee County, Fort Lauderdale City, Florida

About this file

This file is a Solicitation Checklist Summary document used by the City of Fort Myers, Florida to manage the procurement process for state and local contract opportunities, specifically for the Mill & Replace Asphalt Resurfacing project. The checklist provides a comprehensive framework for both Invitation to Bid (ITB) and Request for Proposal/Request for Qualifications (RFP-RSQ) procurements. The City of Fort Myers requires asphalt roadway resurfacing improvements at various street locations within the city, divided into Package 1 (Mill and Replace Asphalt Resurfacing) and Package 2 (Mill and Replace Asphalt Paving), with an alternate bid option for Full Depth Reclamation Method. Work is anticipated to begin after City Council approval and issuance of the Purchase Order, with all authorized work to be completed within four months of the Purchase Order date. The checklist includes mandatory steps such as obtaining Independent Cost Estimates, conducting pre-submittal meetings (recorded via Teams), establishing selection committees for RFP-RSQ procurements, recording solicitation openings, performing vendor verification checks through SAM.gov and state suspended vendor lists, and obtaining grant source approval and concurrence prior to contract execution.

The checklist emphasizes specific procedural requirements for grant-funded projects, requiring notification to Minority, Women, and Veteran-owned Business Enterprises (MBE/WBE/VBE) certified vendors sourced from the Florida Marketplace, newspaper advertisement placement (with specific email notification to ganlegpubnotice4@gannett.com), and mandatory approval from the funding source, with FDOT projects requiring document upload to the Grants Administration Portal (GAP). Internal approvals must be obtained from Procurement, Department Manager, Department Director, Risk, Legal, and Grants Manager through the OpenGov system. All work shall be performed in accordance with City of Fort Myers standards, Florida Department of Transportation requirements, and applicable project specifications. The checklist was last revised on April 23, 2026 for ITB procedures and April 28, 2026 for RFP-RSQ procedures, with items marked in red indicating requirements specific to grant-funded projects.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB- incl Grants checklist

Date completedTitle:
Intake request received
Obtain grant and read entire Agreement
Obtain a Independent Cost Estimate (ICE) from the department
Create documentation of determing what contract type to use"Federal Funding Procurement & Contract Checklist" (separate file) found under H:/Checklist
Create H:/Checklists/Determination of Procurement-Contract Type
Create solicitation in OpenGov
__if grants funding is used that is not FEMA, remove all instances where FEMA is used and replace with proper term.
Meet with Proj Mgr to discuss any questions/review contract
Go through the "Federal Funding Procurement & Contract Checklist" (separate file) found under H:/Checklist
Send for internal approvals (in OpenGov)
*Procurement
*Dept Manager
*Dept Director
*Risk
*Legal
* Grants Manager
Email solicitation grant source for approval (have Thaddeus upload to GAP if FDOT)
Receive concurrance from the grant source
Finalize timeline
Send calendar invites to Project Manager for prebid, question deadline, and opening
* create Teams links for pre-submittal, opening, & selection committees
Send email to Bernice Vono, Lily Baker, and Mary Hagemann annoucing public meetings (prebid, opening, Selection committee)
Email newspaper ad to (ganlegpubnotice4@gannett.com)
receive and pay for ad - place in bid file (need to grant documentation)
Pay for ad by calling in your P-Card
Mark GL account on receipt (see intake) and send to Kim Beaber
Set up solicitation to auto release on desired date/time
Send email to all MBE's in the County and save in bid file. Search for MBE's at - https://vendor.myfloridamarketplace.com/search/vendor

The Minority supplier list requires 3 separate searches. One for Veteran, one for women and one for minority designation (only choose certified).

Create Pre-Submittal paperwork
* print out sign-in sheet
*create agenda (H:/Procurement Solicitation Templates/Pre-Submittal Meeting)
Conduct Pre-Submittal meeting
*record meeting through Teams link (during the meeting)
*save recording in file file
*save and post sign-in sheet, agenda, & recording to bid file and OpenGov
If site Visit, record, save in bid file and post to OpenGov as a Notice
Answer Questions in OpenGov/send to Proj Mgr if you cannot answer
Send Q&A to funding source for approval. ( Zoe.Giannopoulos@dot.state.fl.us)
Record the Solicitation Opening via Teams and post to Notices in OpenGov
Save submittals & recording in bid file
Mark pass/fail for each response in OpenGov
Save bid tabulation (after pass/fail selection) in bid file
Post tabulation & recording under Notices in OpenGov
Check SAM.gov and State Suspended Vendor list for each responsive proposal
If a Citywide continuing contract that Procurement is heading, check references.
meet virtually or in-person with departments that will utilize contract
Send external email to project Manager and committee with bidtab and submittal link, asking for recommendation
When recommendation is received…
Document why other respondents are being excluded (Grant)
Create a Cost/Price Analysis and save to bid file
Create contract and send to grant source for approval (have thaddeus upload to GAP)
Once concurrance is received from grant source, send to Contractor for signature
Create a Notice of Intent in OpenGov / save NOI to bid file.
Send/save "Dear John" letters to those proposers who aren't awarded (in OpenGov) & save sent email as proof when sent in the bid file
Check SAM.gov (prior to contract execution)
Simutaneously, create an agenda item (green sheet)
Once signed, attach to agenda item and print copy for the Clerk's office.
* in upper right of cover, write the Peak # and meeting date
* hand deliver to the Clerk's office
Once executed, Clerk's office will send link & save executed contract by "Contract_exec" in bid file
Send a copy of the executed contract to the grant source
See "H:/FDOT/FDOT docs to upload to GAP" and send Thaddeus those docs to upload to GAP
Send a copy of the fully executed contract to the Supplier and the Project Manager
Post under Contract Management in OpenGov
ITB COMPLETED
Obtain/save a copy of the PO for this purchase
Obtain /save a copy of the Notice to Proceed & proof of being sent

ITB Checklist revised 4/23/26

&Z&F &KFF0000items in red are required by Grants

RFP-RSQ Grants checklist

Date completedTitle
Intake request received
Obtain grant and read entire Agreement
Obtain an Independent Cost Estimate (ICE) from the department/save to bid file
Create H:/Checklists/Determination of Procurement-Contract Type
Create documentation of determing what contract type to use"Federal Funding Procurement & Contract Checklist" (separate file) found under H:/Checklist
Create solicitation in OpenGov
__if grants funding is used that is not FEMA, remove all instances where FEMA is used and replace with proper term.
Meet with Proj Mgr to discuss any questions/review contract
Go through the "Federal Funding Procurement & Contract Checklist" (separate file) found under H:/Checklist
*Procurement
*Dept Manager
*Dept Director
*Risk
*Legal
* Grants Manager
Email solicitation grant source for approval (have Thaddeus upload to GAP if FDOT)
Receive concurrance from the grant source
Finalize timeline
Before publishing, setup a meeting with the Selection Committee to review responsibilities, the scope, and send them "Evaluation Committee Requirements" to sign beore publishing. found in H:/Procurement Solicitation templates/selection committee templates (copy entire file to bid file)
* add title and bid number to "Evaluation Committee Requirements" and attached to meeting invite
* add any notes to "Pre-Selection committee agenda" and use at this meeting
Send calendar invites to committee and Project Manager for prebid, opening, selection committee
attach Evaluation Committee requirements form to the invite
* create Teams links for pre-submittal, opening, & selection committees
Send email (1 week prior) to Bernice Vono, Lily Baker, and Mary Hagemann annoucing public meetings (prebid, opening, Selection committee)
Email newspaper ad to (ganlegpubnotice4@gannett.com), if over $200k or grant funded
Email newspaper ad to (ganlegpubnotice4@gannett.com) regardless of amount
receive and pay for ad - place in bid file (need to grant documentation)
Set up solicitation to auto release on desired date/time
If Grant funded, Send email to all MBE's in the County and save in bid file. Search MBE's at - https://vendor.myfloridamarketplace.com/search/vendor

The Minority supplier list requires 3 separate searches. One for Veteran, one for women and one for minority designation (only choose certified).

Create Pre-Submittal paperwork
* print out sign-in sheet
*create agenda (H:/Procurement Solicitation Templates/Pre-Submittal Meeting)
Conduct Pre-Submittal meeting
*record meeting through Teams link (during the meeting)
*save recording in file file
*save and post sign-in sheet, agenda, & recording to bid file and OpenGov
If site Visit, record, save in bid file and post to OpenGov as a Notice
Answer Questions in OpenGov/send to Proj Mgr if you cannot answer
Send Q&A to funding source for approval. ( Zoe.Giannopoulos@dot.state.fl.us)
OPENING: Record the Solicitation Opening via Teams and post to Notices in OpenGov
Save submittals & recording in bid file
Mark pass/fail for each response in OpenGov
Save bid tabulation (after pass/fail selection) in bid file
Post tabulation & recording under Notices in OpenGov
Check SAM.gov and State Suspended Vendor list for each responsive proposal (See SAM.gov SOP under H:/Procurement Policy/SOPs/SAM.gov check)
Set up evaluation in OpenGov (see intake for list of selection committee members)
Broadcast Evaluation to committee members
Send sharepoint link of downloaded submittals to committee members. Reminding them the when/where the selection committee in scheduled.
Send external email to project Manager and committee with bidtab and submittal link
Selection committee Prep: copy documents from H:/Procurement Solicitation Documents/Selection committee templates to bid file
verify all "Evaluation Committee Requirement" forms have been turned in
* Modify "Agenda script" for the meeting and print for meeting
* Modify "Sign-In Sheet" and print for meeting
Selection Committee: record the meeting through a teams link
*record meeting through Teams link (during the meeting)
* discuss Pros and cons
* reveal scoring / make recommendation to Council (at least 3)
Create a Notice regarding who is moving forward (if no Presentations)
Schedule presentations on Council Chambers (If Committee wants presentations)
Send Invitation for Presentation (if committee wants presentations)
create an agenda (greens sheet) giving approval to negotiate
Document why other respondents are being excluded (Grant)
Memo attesting to any protests being file or not
Procurement staff will be included, record all negotiation meetings, & save recording in bid file
Documentation of negotiations
Create a Cost/Price Analysis and save to bid file
Notice of Intent to award (OpenGov) & proof it was sent
Send/save "Dear John" letters to those participants who aren't awarded (in OpenGov) /save email of sent items to prove when sent in bid file
Create contract and send to grant source for approval (have thaddeus upload to GAP, if FDOT)
Once concurrance is received from grant source, send to Contractor for signature
SAM.gov for selected bidder (pulled again prior to contract execution)
Simutaneously, create an agenda item (green sheet)
Once signed, attach to agenda item and print copy for the Clerk's office.
* in upper right of cover, write the Peak # and meeting date
* hand deliver to the Clerk's office
Once executed, Clerk's office will send link & save executed contract by "Contract_exec" in bid file
Send a copy of the executed contract to the grant source
If FDOT, See "H:/FDOT/FDOT docs to upload to GAP" and send Thaddeus those docs to upload to GAP
Send a copy of the contract to the Supplier and the Project Manager
Post under Contract Management in OpenGov
Obtain a copy of the PO
Obtain a Copy of the Notice to Proceed from the Department
RFP-RSQ COMPLETED

RFP/RSQ Checklist revised 4/28/26

&Z&F &KFF0000items in red are required by grants