Solicitation 47PC5326R0004 Hanley VBA 5th Floor Construction.pdf

PDF 238 KB Posted

Attached to
SOLICITATION NOTICE - Syracuse, New York 5th Floor Construction
Solicitation number
47PC5326R0004
Issued by
Not on record

About this file

This is a GSA Solicitation for a firm-fixed-price construction contract for interior office renovations at the Hanley VBA facility in Syracuse, New York.

The solicitation is set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) and is being conducted as a Lowest Price Technically Acceptable (LPTA) acquisition. The project involves the relocation and renovation of the fifth floor at the Hanley VBA building. Proposals must be received by May 26, 2026 at 5:00 PM EST via email to kyle.cole@gsa.gov. The Contracting Officer is Kyle Cole, located at 100 State Street, Rochester, NY 14614. A pre-proposal conference is scheduled for April 16, 2026 at 9:00-11:00 AM EST at 100 S Clinton Street, Syracuse, NY 13261. Offerors must provide a bid guarantee equal to 20 percent of the bid price or $3,000,000, whichever is less.

Technical proposals must include three completed building construction projects (each with minimum $1,000,000 construction cost) performed within the past ten years as prime contractor; resumes for a Project Manager (minimum six years experience) and Construction Superintendent (minimum six years experience); and three past performance questionnaires from project owners or contracting officers for renovation/modernization projects within the past six years. The evaluation is on a pass/fail basis for technical factors (Experience, Past Performance, and Key Personnel), with award made to the responsible offeror submitting the lowest evaluated price among technically acceptable proposals. Proposals must comply with Buy American construction material requirements, construction wage rate requirements, and various FAR and GSAR clauses related to security prohibitions, arms control certifications, and environmental compliance. SAM registration must be active at time of proposal submission.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GSA Solicitation No. 47PC5326R0004

Document: C201-SB LPTA/DECEMBER 2025 (The Solicitation)

Table of Contents

I. General Information A. The Solicitation and Contract B. List of Solicitation Documents C. Authorized Representatives D. Pre-Proposal Conference E. FAR 52.228-1 Bid Guarantee F. Receipt of Offers

II. Proposals

A. Proposal Contents B. Proposal Format C. Price Proposal D. Technical Proposal E. Other Information to be Submitted with Proposal F. Requirements of Joint Venture Offerors

III. General Provisions

A. Availability of Funds B. Requests for Clarification or Interpretation C. Notice to Small Business Firms D. Information Concerning the Disclosure of Solicitation Results E. Notice Concerning Preparation of Proposals F. Bond Requirements G. Contractor Performance Information H. Safeguarding and Dissemination of Controlled Unclassified Information

(CUI) Building Information

IV. FAR/GSAR Solicitation Provisions

FAR 52.209-7 Information Regarding Responsibility Matters (GSA Class Deviation RFO-2025-09) FAR 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (GSA Class Deviation RFO-2025-09) FAR 52.216-1 Type Of Contract (GSA Class Deviation RFO-2025-16) FAR 52.222-5 Construction Wage Rate Requirements-Secondary Site of WorkBuy American Requirements Buy American Exceptions FAR 52.233-2 Service of Protest (GSA Class Deviation RFO-2025-33) FAR 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (GSA Class Deviation RFO-2025-09) FAR 52.252-1 Solicitation Provisions Incorporated by Reference GSAR 552.102 Incorporating Provisions and Clauses by Reference

V. Instructions to Offerors and Clauses A. FAR 52.215-1 Instructions to Offerors – Competitive Acquisition (GSA

Class Deviation RFO-2025-15) B. Additional Clauses

VI. Method Of Award

A. Evaluation of Offers – Lowest Price Technically Acceptable B. Lowest Price Technically Acceptable Process C. Determination of Responsibility D. Price Reasonableness/Price Realism E. Unbalanced Price F. Total Evaluated Prices G. Non Price Factors H. Evaluation of Joint Ventures

I. General Information

I.A. The Solicitation and Contract

(1) This Solicitation is set-aside for Service-Disabled Veteran-Owned Small Businesses, in accordance with FAR 19 (GSA Class Deviation RFO-2025-19). This Solicitation sets forth requirements for proposals for a Contract to construct the Project described in the attached Agreement. Proposals conforming to the Solicitation requirements will be evaluated in accordance with the Method of Award set forth herein. The Government will award the Contract to the selected Offeror, subject to the conditions set forth herein.

(2) Neither the Solicitation nor any part of an Offeror's proposal shall be part of the Contract except to the extent expressly incorporated therein by the Contracting Officer.

(3) The Offeror's proposal submitted in response to this Solicitation shall constitute a firm offer. No contract shall be formed unless and until the Contracting Officer has countersigned the SF 1442 submitted by an Offeror, and delivered to the Contractor a copy of the SF 1442 with original signatures together with the Agreement reflecting the Offeror's proposed prices.

I.B. List of Solicitation Documents

The Solicitation Documents are comprised of:

(1) The Solicitation

(2) Offeror Representations and Certifications Form

(3) Standard Form (SF) 1442 – Solicitation Offer and Award

(4) The Agreement and Attachments to the Agreement

(5) Other Forms Required For Submission with Proposals

a) Attachment 4 Experience on Similar Projects Offeror Form

b) Attachment 5 PBS Past Performance Questionnaire

c) Attachment 6 Key Personnel Form

d) Attachment 7 Bid Bond SF24-23a

e) Attachment 8 Contractors Qual and Financial Info GSA527-21a

(6) Other Attachments

a) Attachment 1 Construction SOW Hanley VBA

b) Attachment 2 CUI DRAWINGS Hanley VBA 5th Flr Relocation

c) Attachment 3 CUI SPECIFICATIONS Hanley VBA 5th Flr Relocation

d) Attachment 9 WD NY20260026 Onondaga County 22326

e) Attachment 10 Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information

I.C. Authorized Representatives

The following individuals are designated as the authorized GSA representatives under this Solicitation:

Authorized Representative Information:

Contracting Officer’s Information

Name: Kyle Cole

Address: 100 State St, Rochester, NY 14614

Telephone: (720) 481-7787

Email: kyle.cole@gsa.gov

I.D. Pre-Proposal Conference

Date: April 16th, 2026

Time: 9-11am EST

Location: 100 S Clinton St, Syracuse, NY 13261, 5th floor elevator lobby

RSVP: email kyle.cole@gsa.gov at least one business day prior of the pre-proposal conference to confirm your attendance.

I.E. FAR 52.228-1 Bid Guarantee (Sep 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids;

and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

I.F. Receipt of Offers

(1) In order to be considered for award, offers conforming to the requirements of the Solicitation must be received at the following office no later than 5:00 pm local time on the following date and at the following address.

Date: May 26th, 2026 Address: must be sent via email ONLY to kyle.cole@gsa.gov

II. Proposals

II.A. Proposal Contents Proposals shall consist of the following documents, completed and executed in accordance with this Solicitation:

1. Price Proposal

a) 47PC5326R0004 Form

2. Technical Proposal

a) Attachment 4 Experience on Similar Projects Offeror Form

b) Attachment 5 PBS Past Performance Questionnaire

c) Attachment 6 Key Personnel Form

3. Representations and Certifications

4. Standard Form 24, Bid Bond

a) Attachment 7 Bid Bond SF24-23a

5. GSA Form 527 – Contractor’s Qualification and Financial Information

a) Attachment 8 Contractors Qual and Financial Info GSA527-21a

6. Other Documents as Required

II.B. Proposal Format

Proposals submitted shall include all of the contents referred to in II.A. along with additional copies as noted. Proposals shall not exceed any page limits included in their respective sections as discussed in section II of this solicitation.

II.C. Price Proposal

(1) Contents

The Price Proposal shall consist of the SF 1442 and the Agreement, with prices and/or rates indicated for each price element shown on the pricing form included in Section II of the Agreement. Indicate the Base Contract Price, or if no such distinction is made, the Contract Price, in Block 17 of the SF 1442, which must be fully executed by the Offeror.

(2) Qualifications, Exclusions and Conditions

If the Offeror communicates in its proposal any qualifications, exclusions, or conditions to the proposed prices not provided for in the Contract Documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.

(3) Additional Proposal Requirements

As noted earlier, all proposals must be submitted electronically via email to kyle.cole@gsa.gov.

II.D. Technical Proposal

The Technical Proposal shall include the information requested below for the non-price factors described in Section VI.

(1) Experience on Similar Projects

This factor will consider the extent of the contractor’s experience with the construction of interior office renovations.

Contractors shall submit Attachment 4 –Experience on Similar Projects Offeror Form for three (3) completed contracts/task orders (government or commercial) for building construction projects performed within the past ten

(10) years. All three projects must have a minimum construction cost of one million dollars ($1,000,000) each. All must have been successfully and substantially completed within the past ten (10) years and be similar in size, complexity and scope as this project. The Offeror must have served as the Prime contractor on the submitted projects. Projects determined to be not relevant or only partially relevant will receive no credit resulting in an unacceptable rating for this factor. If the contractor provides more than three contracts/task orders, the SSEB will only review the first three submitted based on chronology starting with the most recent contract/task order completion date.

Similar size, Complexity and Scope is defined as: Building construction described earlier under Description of the Work [see paragraph 1], with equipment similar in complexity. This includes major modernization of office buildings, courthouses, or acceptable institutional buildings. Acceptable institutional buildings are buildings built for schools, colleges, hospitals, laboratories and airports. Construction within an occupied and operational site, campus or multi-story building. Complexity includes schedule constraints, management and administrative requirements, security requirements, coordination requirements, local conditions, as well as technical complexity.

(2) Key Personnel

This factor evaluates the Offerors’ demonstrated qualifications of the key personnel.

The offeror shall submit resumes for each of the key personnel listed below.

Resumes shall include all pertinent information that clearly exhibits the qualifications of the proposed personnel. Resumes for everyone shall summarize the qualifications, professional designation, experience, education, skills and professional background information. Resumes must list the key personnel’s roles/responsibilities for the projects listed. An example resume format is provided as Attachment 6. If subcontractors are to be used, indicate what work will be subcontracted and the names of the proposed subcontractors, including commitments that have been made with them.

Provide resumes indicating relevant experience for the proposed subcontractors. Submit resumes for the following positions:

• Project Manager

• Construction Superintendent

Expected Qualifications for Key Personnel:

• Project Manager: The Project Manager shall have at least six (6) years of construction project management experience having managed projects similar in size, complexity, and scope.

• Construction Superintendent: The Construction Superintendent shall have a minimum of six (6) years of construction experience as a superintendent on projects of similar size, complexity and scope.

(3) Past Performance of Offeror

The Past Performance will be evaluated based on the degree to which the contractor's:

a. Past Performance reflects performance of projects similar in size, scope, and complexity to the requirements contained in the drawings and specifications. In conducting the past performance assessment, the Government may use data obtained from other sources, as well as that provided in the proposal.

b. Past Performance references are current (within the last six years) and the degree to which the contractor's role and responsibilities under the projects are similar in size, scope and complexity to the requirements contained in the drawings and specifications.

c. Past Performance references reflects that the contractor consistently meets or exceeds performance standards regarding meeting work schedules, providing specified services, meeting contract terms without failure or resolving issues immediately.

d. It is encouraged, although not required, that the past performance references provided are associated with the projects provided under Technical Evaluation Factor 1, Experience.

e. In the case of a contractor without a record of past performance, the contractor will be evaluated neither favorably nor unfavorably on past performance, resulting in a neutral rating.

Independent References:

Each offeror will be required to provide three (3) completed past performance questionnaires (see attachment 5) prepared by the Owner or the Contracting Officer (CO)/Contracting Officer’s Representative (COR) for each contract/task order (Government or commercial) for renovation and/or modernization contracts/orders performed within the past six years in facilities similar in size, scope and complexity as this project. The contractor must have been the prime contractor of these contracts/task orders. Contractors are required to submit reliable** references for all submitted contracts/task orders.

Similar size, Complexity and Scope is defined as: Building construction described earlier under Description of the Work [see paragraph 1], with equipment similar in complexity. This includes major modernization of office buildings, courthouses, or acceptable institutional buildings. Acceptable institutional buildings are buildings built for schools, colleges, hospitals, laboratories and airports. Construction within an occupied and operational site, campus or multi-story building. Complexity includes schedule constraints, management and administrative requirements, security requirements, coordination requirements, local conditions, as well as technical complexity.

The Offeror must submit a Past Performance Questionnaire (PPQ) (included in the solicitation as Attachment 5, completed by the applicable client, for each project included in its proposal for Factor 3. Completed PPQs should be submitted with the proposal. Ensure correct phone numbers and email addresses are provided for the client point of contact. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the Offeror is unable to obtain a completed PPQ from a client for a project before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the project. If the client requests, the client may submit a questionnaire directly to the Government's point of contact, via email at kyle.cole@gsa.gov prior to proposal closing date. Offerors may resubmit questionnaires previously submitted with other proposals or may obtain an updated/new PPQ from a client for any submission. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs.

Also include performance recognition documents received within the last six (6) years such as awards, award fee determinations, customer letters of commendation, and any other forms of performance recognition. In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the Offeror's proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), previously submitted PPQ information, and any other known sources not provided by the Offeror. While the Government may elect to consider data from a variety of sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror. GSA will not maintain database of PPQs submitted by Offerors.

II.E. Other Information to Submit with Proposal

(1) Representations and Certifications

Offerors are reminded their SAM registration status must be “Active”, at the time their offer is submitted, to be considered for award (see 52.204-7 (GSA Class Deviation RFO-2025-04)). Offerors submitting a proposal in response to this Solicitation shall complete electronic Annual Representations and Certifications in conjunction with required Entity registration in System for Award Management (SAM), accessed via System for Award Management. In accordance with FAR 52.204-90 (GSA Class Deviation RFO-2025-04), if an Offeror will not have an active Federal Government contracts registration in SAM when submitting its offer, it shall complete paragraphs (c) and (d) of FAR 52.204-90 and include its responses with its offer. Offerors shall also submit with their proposal the completed provisions identified in Section IV of this solicitation.

(2) Qualifications of Offerors

Offerors submitting a proposal in response to this Solicitation shall submit with their proposal evidence of their financial responsibility and capacity to perform the Contract.

Offerors shall submit this information on GSA Form 527 – Contractor’s Qualifications and Financial Information. Where applicable, point of contact, including names and telephone numbers, are required for all contracts listed.

(3) Proprietary Information Agreement

A contractor that gains access to proprietary information of other companies in performing advisory and assistance services for the Government must agree with the other companies to protect their information from unauthorized use or disclosure for as long as it remains proprietary and refrain from using the information for any purpose other than that for which it was furnished. The contracting officer must obtain copies of these agreements and ensure that they are properly executed.

II.F. Requirements of Joint Venture Offerors

(1) All offers submitted by joint ventures must include a copy of an executed joint venture agreement (with original signatures) which fully discloses the legal identity of each member of the joint venture, the relationship between the members, the form of ownership of each member, and any limitations on liability or authority for each member.

(2) An authorized representative of each member of the joint venture must sign the SF 1442 accompanying an offer regardless of any agency relationship established between the members.

(3) In the case of corporations that are joint venture members, the corporation secretary must certify that the corporation is authorized to participate in the joint venture, either by so certifying in the joint venture agreement, or by submitting a separate certification to the Government. The joint venture must also provide a certificate that identifies a principal representative of the joint venture with full authority to bind the joint venture.

(4) Representations and certifications, financial information, and past performance information must be submitted for each member of the joint venture.

III. General Provisions

III.A. Availability of Funds

Issuance of this Solicitation does not warrant that funds are presently available for award of a Contract. Award of the contract shall be subject to the availability of appropriated funds, and the Government shall incur no obligation under this Solicitation in advance of such time as funds are made available to the Contracting Officer for the purpose of contract award.

III.B. Requests for Clarification or Interpretation

The Government will attempt to answer all requests for clarifications or interpretations of the Solicitation Documents prior to the date set for receipt of offers, but do not warrant that all such requests will be answered within 15 calendar days. Prospective Offerors should make such requests not less than 15 calendar days prior to the date set for receipt of offers.

III.C. Notice to Small Business Firms

A program for the purpose of assisting qualified small business concerns in obtaining certain bid, payment, or performance bonds that are otherwise not obtainable is available through the Small Business Administration (SBA) (Small Business Administration). For information concerning SBA's surety bond guarantee assistance, contact your SBA District Office.

III.D. Information Concerning the Disclosure of Solicitation Results This acquisition is being conducted under the provisions of FAR Part 15 (GSA Class Deviation RFO-2025-15) as a negotiated procurement. In accordance with FAR 3.104 (GSA Class Deviation RFO-2025-04) and FAR 15 (GSA Class Deviation RFO-2025-15), after receipt of proposals, no information regarding the identity of those submitting offers, the number of offers received, or the information contained in such offers will be made available until after award except as provided by FAR 15 (GSA Class Deviation

RFO-2025-15).

III.E. Notice Concerning Preparation of Proposals Offerors are cautioned to carefully read the entire Solicitation and the Agreement to be included in the Contract contemplated by the Solicitation in order to be fully aware of all requirements and clauses in the contemplated Contract. Verify that all blanks requiring information to be supplied in an Offer have been properly filled out, that all pricing and other numerical data is accurately calculated, and that all copies of the Offer contain the same information.

III.F. Bond Requirements

If a bid guarantee is required to be submitted with your offer, any contract awarded will require a performance bond and payment bond as specified in the Agreement. Offerors who utilize individual sureties should note the requirement for a certified, audited, financial statement for each person acting as an individual surety under clause FAR 52.228-1 Bid Guarantee and the requirements of clause FAR 52.228-11 Pledge of Assets.

III.G. Contractor Performance Information

(1) Evaluating Contractor Performance: The General Services Administration is using the Contractor Performance Assessment Reporting System (CPARS) module as the secure, confidential, information management tool to facilitate the performance evaluation process. CPARS enables a comprehensive evaluation by capturing comments from both GSA and the contractor. The website for CPARS is Contractor Performance Assessment

Completed CPARS evaluations may then be used by the Federal acquisition community for use in making source selection decisions. CPARS assists acquisition officials by serving as the single source for contractor past performance data.

(2) CPARS Registration: Each award requiring an evaluation must be registered in CPARS. The contractor will receive several automated emails. Within thirty days of award, the contractor will receive an e-mail that contains user account information, as well as the applicable contract and order number(s) assigned.

Contractors will be granted one user account to access all evaluations.

a. Contractor CPARS Training: Contractors may sign up for CPARS training.

A schedule of classes will be posted to the CPARS training site (CPARS Training) and updated as needed.

b. Contractor Representative (CR) Role: All evaluations will be sent the Contractor Representative (CR) named on your award. The CR will be able to access CPARS to review and comment on the evaluation. If your CR is not already in the CPARS system, the contracting officer will request the name and email address of the person that will be responsible for the CR role on your award.

Once an evaluation is ready to be released the CR will receive an email alerting them the evaluation is ready for their review and comment. The email will indicate the time frame the CR has to respond to the evaluation; however, the CR may return the evaluation earlier than this date.

GSA shall provide for review at a level above the contracting officer (i.e., contracting director) to consider any disagreement between GSA and the contractor regarding GSA’s evaluation of the contractor. Based on the review, the individual at a level above the contracting officer will issue the ultimate conclusion on the performance evaluation.

Copies of the evaluations, contractor responses, and review comments, if any, will be retained as part of the contract file.

III.H. Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information

Certain information contained in the Solicitation Documents may have been designated as Controlled Unclassified Information (CUI) building information. With respect to such information, Offerors shall agree to the terms for receipt of such information, as set forth in the provision “Administrative Matters” in Section III of the Agreement, as a condition of receipt of such information.

IV. FAR/GSAR Solicitation Provisions

FAR 52.209-7 Information Regarding Responsibility Matters. (NOV 2025) (GSA Class Deviation RFO-2025-09)

(a) Definitions. As used in this provision—

Administrative proceeding means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals

Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.

Federal contracts and grants with total value greater than $10,000,000 means—

(1) The total value of all current, active contracts and grants, including all priced options; and

(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).

Principal means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).

(b) The offeror □ has □ does not have current active Federal contracts and grants with total value greater than $10,000,000.

(c) If the offeror checked "has" in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:

(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:

(i) In a criminal proceeding, a conviction.

(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.

(iii) In an administrative proceeding, a finding of fault and liability that results in–

(A) The payment of a monetary fine or penalty of $5,000 or more; or

(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.

(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.

(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.

(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).

(End of Provision)

FAR 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (NOV 2025) (GSA Class Deviation RFO-2025-09)

(a) This provision does not apply to acquisitions at or below the simplified acquisition threshold or to acquisitions of commercial products and commercial services as defined in Federal Acquisition Regulation 2.101.

(b) Certification. [Offeror shall check either (1) or (2).]

__ (1) The Offeror certifies that–

(i) It does not engage and has not engaged in any activity that contributed to or was a significant factor in the President's or Secretary of State's determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international-security-affairs/bureau-of-arms-control-verification-and-compliance/; and

(ii) No entity owned or controlled by the Offeror has engaged in any activity that contributed to or was a significant factor in the President's or Secretary of State's determination that a foreign country is in violation of its obligations undertaken in any arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. The determinations are described in the most recent unclassified annual report provided to Congress pursuant to section 403 of the Arms Control and Disarmament Act (22 U.S.C. 2593a). The report is available at https://www.state.gov/bureaus-offices/under-secretary-for-arms-control-and-international-security-affairs/bureau-of-arms-control-verification-and-compliance/; or

__ (2) The Offeror is providing separate information with its offer in accordance with paragraph (d)(2) of this provision.

(c) Procedures for reviewing the annual unclassified report (see paragraph (b)(1) of this provision). For clarity, references to the report in this section refer to the entirety of the annual unclassified report, including any separate reports that are incorporated by reference into the annual unclassified report.

(1) Check the table of contents of the annual unclassified report and the country section headings of the reports incorporated by reference to identify the foreign countries listed there. Determine whether the Offeror or any person owned or controlled by the Offeror may have engaged in any activity related to one or more of such foreign countries.

(2) If such activity might have occurred, review all findings in the report associated with those foreign countries to determine whether or not each such foreign country was determined to be in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or to be not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. For clarity, in the annual report an explicit certification of non-compliance is equivalent to a determination of violation.

However, the following statements in the annual report are not equivalent to a determination of violation:

(i) An inability to certify compliance.

(ii) An inability to conclude compliance.

(iii) A statement about compliance concerns.

(3) If so, determine whether the Offeror or any person owned or controlled by the Offeror has engaged in any activity that contributed to or is a significant factor in the determination in the report that one or more of these foreign countries is in violation of its obligations undertaken in an arms control, nonproliferation, or disarmament agreement to which the United States is a party, or is not adhering to its arms control, nonproliferation, or disarmament commitments in which the United States is a participating state. Review the narrative for any such findings reflecting a determination of violation or non-adherence related to those foreign countries in the report, including the finding itself, and to the extent necessary, the conduct giving rise to the compliance or adherence concerns, the analysis of compliance or adherence concerns, and efforts to resolve compliance or adherence concerns.

(4) The Offeror may submit any questions with regard to this report by email to NDAA1290Cert@state.gov. To the extent feasible, the Department of State will respond to such email inquiries within 3 business days.

(d) Do not submit an offer unless—

(1) A certification is provided in paragraph (b)(1) of this provision and submitted with the offer; or

(2) In accordance with paragraph (b)(2) of this provision, the Offeror provides with its offer information that the President of the United States has

(i) Waived application under 22 U.S.C. 2593e(d) or (e); or

(ii) Determined under 22 U.S.C. 2593e(g)(2) that the entity has ceased all activities for which measures were imposed under 22 U.S.C. 2593e(b).

(e) Remedies. The certification in paragraph (b)(1) of this provision is a material representation of fact upon which reliance was placed when making award. If the Government later determines that the Offeror knowingly submitted a false certification, in addition to other remedies available to the Government, such as suspension or debarment, the Contracting Officer may terminate any contract resulting from the false certification.

(End of provision)

FAR 52.216-1 Type of Contract (NOV 2025) (GSA Class Deviation RFO-2025-16)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

FAR 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror’s request for a wage determination for a secondary site of the work.

Buy American Requirements

FAR 52.225-9 Buy American-Construction Materials (FEB 2021)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph

(1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components.

Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic.

Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws. Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States.

Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements. "United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

none

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (Dollars)* Item 1: Foreign Construction Material Domestic Construction Material Item 2: Foreign Construction Material Domestic Construction Material

[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed.

Attach copy of response; if oral, attach summary.]

[Include other applicable supporting information.]

(End of clause)

FAR 25.602-1 Section 1605 of the Recovery Act

Except as provided in 25.603-

(a) None of the funds appropriated or otherwise made available by the Recovery Act may be used for a project for the construction, alteration, maintenance, or repair of a public building or public work unless the public building or public work is located in the United States and-

(1) All of the iron, steel, and manufactured goods used as construction material in the project are produced or manufactured in the United States.

(i) All manufactured construction material must be manufactured in the United States.

(ii) Iron or steel components.

(A) Iron or steel components of construction material consisting wholly or predominantly of iron or steel must be produced in the United States. This does not restrict the origin of the elements of the iron or steel, but requires that all manufacturing processes of the iron or steel must take place in the United States, except metallurgical processes involving refinement of steel additives.

(B) The requirement in paragraph (a)(1)(ii)(A) of this section does not apply to iron or steel components or subcomponents in construction material that does not consist wholly or predominantly of iron or steel.

(iii) All other components. There is no restriction on the origin or place of production or manufacture of components or subcomponents that do not consist of iron or steel.

(iv) Examples.

(A) If a steel guardrail consists predominantly of steel, even though coated with aluminum, then the steel would be subject to the section 1605 restriction requiring that all stages of production of the steel occur in the United States, in addition to the requirement to manufacture the guardrail in the United States. There would be no restrictions on the other components of the guardrail.

(B) If a wooden window frame is delivered to the site as a single construction material, there is no restriction on any of the components, including the steel lock on the window frame; or

(2) If trade agreements apply, the manufactured construction material shall either comply with the requirements of paragraph (a)(1) of this subsection, or be wholly the product of or be substantially transformed in a Recovery Act designated country; (b) Manufactured materials purchased directly by the Government and delivered to the site for incorporation into the project shall meet the same domestic source requirements as specified for manufactured construction material in paragraphs (a)(1) and (a)(2) of this section; and (c) A project may include several contracts, a single contract, or one or more line items on a contract.

FAR 25.602-2 Buy American statute

Except as provided in 25.603, use only unmanufactured construction material mined or produced in the United States, as required by the Buy American statute or, if trade agreements apply, unmanufactured construction material mined or produced in a designated country may also be used.

Buy American Exceptions

For Buy American exceptions, if any, see the applicable Buy American clause in Section IV of the Agreement

FAR 52.233-2 Service of Protest (NOV 2025) (GSA Class Deviation RFO-2025- 33)

(a) Protests, (as defined in FAR 33.102), that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), must be served on the Contracting Officer identified in the solicitation by obtaining written and dated acknowledgment of receipt from them.

(b) The copy of any protest must be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

FAR 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (NOV 2025) (GSA Class Deviation RFO-2025-09)

(a) Definitions. As used in this provision-—

Backhaul, covered article, covered telecommunications equipment or services, critical technology, FASCSA order, Intelligence community, interconnection arrangements, national security system, roaming, sensitive compartmented information, sensitive compartmented information system, source, and substantial or essential component have the meanings provided in the clause 52.240-91, Security Prohibitions and Exclusions.

Business operations means engaging in commerce in any form, including by acquiring, developing, maintaining, owning, selling, possessing, leasing, or operating equipment, facilities, personnel, products, services, personal property, real property, or any other apparatus of business or commerce.

Marginalized populations of Sudan means—

(1) Adversely affected groups in regions authorized to receive assistance under section 8(c) of the Darfur Peace and Accountability Act (Pub. L. 109-344) (50 U.S.C. 1701 note); and

(2) Marginalized areas in Northern Sudan described in section 4(9) of such Act.

Restricted business operations means business operations in Sudan that include power…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .