Solicitation 1605AE-26-B-00001 - New Hampshire Replace siding IFB.pdf
PDF 1 MB Posted
- Attached to
- Construction Services for Replace Siding on All Buildings at the New Hampshire Job Corps Center
- Solicitation number
- 1605AE-26-B-00001
About this file
This is an Invitation for Bid (IFB) for construction services to replace exterior siding on seven buildings at the New Hampshire Job Corps Center operated by the Department of Labor. The contractor must furnish all labor, supervision, materials, equipment, transportation, permits, disposal, and incidental services necessary to complete the siding replacement work on Buildings A through G in accordance with the provided Statement of Work, specifications, drawings, and all applicable federal, state, and local codes and regulations.
The contract is structured as a firm-fixed price award, meaning the bid price shall include all labor, materials, equipment, services, transportation to site, storage, insurance and bond premiums, permits, licenses, inspection fees, taxes, profit, overhead, and any other items necessary for contract performance. A public bid opening will be conducted via Microsoft Teams video teleconference on October 7, 2026, at 2:00 PM Eastern. Interested parties must email the Contracting Officer (Paul M. Seivert at Seivert.Paul.M@dol.gov) and Contract Specialist (Kabir A. Saka at Saka.Kabir.a@dol.gov) no later than one business day prior to the bid opening to request meeting access. Contract price adjustments are permitted only through written modifications signed by the Contracting Officer.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
NEGOTIATED (RFP) REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF
SEALED BID (IFB) INVITATION FOR BID
9. FOR
INFORMATION CALL
PAGES
1605AE-26-B-00001
US Department of Labor Job Corps Acquisition Services 200 Constitution Ave, NW N-4643 Washington DC 20210
U.S. Department of Labor, (OSPE) 200 Constitution Avenue NW, Washington, DC 20210
1631-OJC-26-CDC-0098 4310
JCAS
Kabir Saka 202-413-4042
09/03/2026
10/05/2026
0 435
12:00 P.M.
New Hampshire JCC 4310 - Replace Siding on All Buildings, including the specifications/drawings and all solicitation documents.
1 97
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Continued...
AMENDMENT
NUMBER
DATE.
US Department of Labor Job Corps Acquisition Services 200 Constitution Ave, NW C5508-C5510 Washington DC 20210
JCAS
Paul M. Seivert
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
1605AE-26-B-00001
Delivery: 435 Days After Notice to Proceed
Delivery Location Code: ETA (DFAM)
US DEPARTMENT OF LABOR
200 CONSTITUTION AVE, NW
ROOM N4464 - OFFICE OF JOB CORPS
ATTN: PERRYN GIVENS & HEEJUNG CHUN
ATTN: MARC-OLIVIER TSCHIBELU
Washington Dc DC 20210 US
0001 New Hampshire JCC 4310 - Replace Siding on All
Buildings
The work involves construction services for the removal and replacement of the existing wood siding with fiber cement planks on all seven
(7) buildings (A, B, C, D, E, F, and G) at the
New Hampshire Job Corps campus
Product/Service Code: Z2CZ
0002 Payment and Performance Bonds. Contractors shall provide required payment and performance bonds in accordance with the solicitation requirements.
Anticipated Award Type: Cost
Product/Service Code: Z2CZ
Table of Contents
PART I – THE SCHEDULE
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
SECTION D – PACKAGING AND MARKING
SECTION E – INSPECTION AND ACCEPTANCE
SECTION F – DELIVERIES OR PERFORMANCE
SECTION G – CONTRACT ADMINISTRATION DATA
SECTION H – SPECIAL CONTRACT REQUIREMENTS
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
PART III-LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J – LIST OF ATTACHMENTS
PART IV-REPRESENTATIONS AND INSTRUCTIONS
SECTION K – REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF
OFFERORS OR RESPONDENTS
SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
PART I – THE SCHEDULE
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 OVERVIEW OF JOB CORPS.
Job Corps is a no-cost education and vocational training program administered by the U.S.
Department of Labor that helps young people ages 16 through 24 improve the quality of their lives through vocational and academic training. Funded by Congress, the Job Corps has been training young adults for meaningful careers since 1964. The Job Corps is committed to offering all students a safe, drug-free environment where they can take advantage of the resources provided. Through a nationwide network of campuses, the Job Corps offers a comprehensive array of career development services to young women and men, ages 16 to 24, to prepare them for successful careers. The Job Corps employs a holistic career development training approach which integrates the teaching of academic, vocational, employability skills and social competencies through a combination of classroom, practical and book-based learning experiences to prepare youth for stable, long-term, high-paying jobs. The Job Corps is currently authorized by the Workforce Innovation and Opportunity Act (WIOA) of 2014.
B.2 BRIEF DESCRIPTION OF SERVICES
The Contractor shall furnish all labor, supervision, materials, equipment, transportation, permits, disposal, and incidentals necessary to replace the exterior siding on Buildings A, B, C, D, E, F, and G at the New Hampshire Job Corps Center in accordance with the Statement of Work, specifications, drawings, and all applicable federal, state, and local codes and regulations.
B.3 CONTRACT LINE ITEMS
CLIN Description Quantity Unit Price
Construction- Replacement of Siding on Buildings A, B, C, D, E, F & G at the New Hampshire Job Corps Center
1 JOB $
0002 Payment & performance bonds1 1 LS $
TOTAL PRICE ALL CLINS $
1 These items are cost reimbursable items and will be reimbursed on a dollar per dollar basis
(actual expenses) upon receipt of bonds and proof of payment to the surety.
B.4 PRICING
As a firm-fixed price contract, the price shall include all labor, materials, equipment and services necessary to accomplish the construction required by the contract, including applicable customs duties, transportation to the site, storage, premiums for insurance and bonds required by the solicitation documents and/or the contract documents, permits, license and inspection fees, taxes, profit, overhead and all other items called for by the contract or otherwise necessary for performance of the contract. The contract price may be adjusted only by a written contract modification signed by the Contracting Officer (CO).
The contractor shall complete all work, including furnishing all labor, material, equipment, and services as called for and required by the terms and conditions of this contract document and all attachments hereto. The maximum time allowable for performance has been identified in Section
F.4, Period of Performance.
B.5 TYPE OF CONTRACT
The resulting contract will include Contract Line-Item Numbers (CLINs) that are Firm Fixed-
Price, except for Bonds Reimbursement costs. No additional sums will be payable on account of any escalation in the cost of materials, equipment, services, or labor, or because of the contractor’s failure to properly estimate or accurately predict the cost or difficulty of achieving the results required by this contract. Changes in the contract price or time to complete will be made only due to changes made by the Government in the work to be performed, or by delays caused by the Government.
B.6 COST OF MATERIALS/EQUIPMENT
The cost of any materials or equipment required in conjunction with the services rendered herein shall be included in the proposed firm fixed price.
B.7 DELIVERABLE – RELEASABLE COPIES – FREEDOM OF INFORMATION ACT
The Freedom of Information Act (FOIA) permits withholding information under several exemptions, including Exemption 4 which protects "trade secrets and commercial or financial information obtained from a person [that is] privileged or confidential," 5 U.S.C. 552(b) (4).
Within five business days of contract award, the contractor shall provide a statement that the contract is available for full disclosure under the FOIA or provide a scanned PDF of the redacted copy of the contract identifying the specific potions the contractor believes are covered by the particular exemption requested. Any redactions must be fully supported under the FOIA. In the event the Government notifies the contractor that it does not agree with a proposed redaction, the contractor shall have five business days to submit additional information to support the requested redaction. For subcontracts, within 5 business days of the contractor's award of any subcontract over $500,000 the contractor shall provide the Government a scanned PDF copy of the subcontract with a statement that the copy is either available for full disclosure, or identifying the specific portions believed to be covered by the particular exemption requested. Redactions should be limited to those protections provided under the FOIA. Following the procedures above, the Government has the right to notify the contractor of any disagreement with proposed redaction or exemption requests.
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 SUMMARY OF WORK
GENERAL
SCOPE BACKGROUND
1. The New Hampshire Job Corps Center is located on a 20.13-acre site in the City of
Manchester. The facility is leased by the U.S. Department of Labor (Department) and is operated by (Adams and Associates).
2. This property is not classified as an historic site.
SCOPE INTENT
1. The intent of this Scope of Work is to outline the work needed to replace the entire exterior wood siding throughout the campus with fiber cement siding at the New Hampshire Job
Corps Center.
2. A more detailed description of the work may be found in Section IV- EXTENT OF
WORK
SPECIFIC REQUIREMENTS
LEGALLY MANDATED STANDARDS
1. The Contractor shall conform to:
a. Code of Federal Regulations
b. Safety and Health OSHA CFR Part 1926
c. Life Safety Code NFPA-101
1) The Contractor’s shall adhere to the current National Fire Protection Agency requirements as they related to this project.
2) The Contractor’s responsibility for safety related requirements extends to all impacted areas and access ways affected by the work.
2. National and State Building Codes
a. The Contractor shall conform to all applicable construction codes, ordinances, and regulations including the national building code used in the local area, laws and local ordinances.
Deviations and interpretations shall be subject to the approval of the Contracting Officer (CO).
b. All work must conform to the current regulations of the Environmental Protection
Agency (EPA) and the Occupational Safety and Health Administration (OSHA) (29CFR1926).
The regulations of the State of New Hampshire shall prevail if they are more stringent than those of the Federal Government.
c. The Contractor shall not submit plans or specifications to any local authority without the prior approval of the New Hampshire Job Corps Center Director or designated representative.
3. Permits and Licenses
a. The New Hampshire Job Corps Center is leased by the U.S. Department of Labor
(Department) and is operated by (Adams and Associates).
b. The Contractor shall be responsible for obtaining all regulatory permits and licensing requirements required to perform this work in Manchester, New Hampshire.
SPECIFIC REQUIREMENTS
1. Center Operations
a. The center and its buildings shall remain in operation throughout construction.
b. The Contractor shall, as part of this contract, coordinate with the Department and the
Engineering Support Contractor (ESC) to develop a work plan that will minimize disruption of center operations during construction.
c. The Contractor shall also propose a sequencing of the work in coordination with the
Center to minimize potential disruption to Center operations.
d. Proper scheduling and phasing of the construction work is required to allow the Center to operate in a normal fashion during construction.
e. Although this scope of work may identify specific elements of construction, it is the
Contractor’s responsibility to provide all elements that are incidental to provide a fully complete and functional facility.
1) The Contractor and all persons employed under the contract:
2) Shall observe all security regulations in effect at the center;
3) Shall not be permitted to use the food service facilities at the center;
4) Shall not fraternize with the students or staff of the center;
5) Shall not consume or transport any alcoholic beverages or drugs on the center; and shall not transport any firearms on the center.
f. Persons violating the above shall be subject to disciplinary actions as set forth by the center.
g. Any proposed interruption to Center operations during construction must have prior approval from the Center Director after a minimum of 72 hours’ notice.
h. The Contractor shall NOT proceed with utility interruptions without written permission from the Center Director.
2. Submittal Requirements
a. The Contractor shall, at a minimum, submit the following for approval before commencing construction:
1) Schedule, CPM in Microsoft Project or Primavera P6, with electronic files:
2) Safety Plan
3) Quality Plan
4) Construction Phasing and Layout Plan
5) Manufacturer’s Product Data, catalog cut sheets, and shop drawings for all material, equipment, and systems to be incorporated into the work.
6) Safety Data Sheets for materials as applicable
b. The Contractor shall allow a 14-calendar day review period by the Government for all submittals.
3. Web Based Project Management System
a. During the construction phase, the Department shall provide, and requires the Contractor to use, the secure online construction management system, Submittal Exchange© (SE), that will expedite submittal information and management exchanges between members of the GC, the
ESC, the Department, and other designated project stakeholders.
b. Submittal Exchange will be provided at the Department’s expense, and the Contractor and the Contractor shall be required to attend a 1-hour orientation and overview of SE provided by the Department’s Engineering Support Contractor (ESC) which will be scheduled once the
Contractor has been given a notice to proceed.
c. Submittal Exchange offers unlimited online information exchange, as well as a repository for electronic closeout documentation for the project. The program features a comprehensive online system for sharing, reviewing, and archiving project documentation and construction communications between stakeholders.
d. The extent of use of Submittal Exchange shall be determined by the Department and the
General Contractor during the Pre-Construction Conference.
e. The following features of Submittal Exchange may be utilized:
1) ASI’s
2) Closeout
3) Commissioning
Documents
4) Compliance Documents
5) Construction Photos
6) Construction Submittals
7) Construction Videos
8) Coordination Drawings
9) Design Submittals
10) Meeting Minutes
11) Monthly Executive Reports
13) Product Data
12) O & M Manuals
14) Shop Drawings
15) Reports
16) RFI’s*
17) Schedules / SOVs*
18) Substantial Completion
Documentation
19) Tests & Inspections
20) Warranties
f. Schedules, SOVs, Quality and Safety Plans, and RFIs having time and cost impacts, and other submissions such as those listed below will be responded to by the Department through formal correspondence.
g. The following items should not be uploaded to Submittal Exchange unless otherwise instructed by the CO. These items shall be submitted directly to the Department as follows:
Submission Item Submission by Email to the Following:
1. Monthly Payment Applications /
Invoices Email to: JCASinvoice@dol.gov
2. Schedule Updates Include with monthly Payment
Applications
3. Final Inspection Request Email directly to:
1) the DOL Contracting Officer (CO)
2) the DOL Contracting Officer's Rep.
(COR)
3) the DOL Contracts Specialist (CS)
4) the ESC Project Manager (PM)
5) the ESC Regional Project Manager
(RPM)
6) the ESC Contracts Specialist (CS)
*Email addresses can be found under the
'Project Team' tab in Submittal Exchange.
4. Key Personnel Substitution
Request
5. Notice of Delay
6. Notice of Differing Site
Conditions
7. RFCs / Proposals / REAs / Claims
8. Punchlist
9. Substantial Completion Request
10. Substantial Completion Certificate
11. Accident / Incident Reporting
h. For electronic files uploaded directly into Submittal Exchange, the maximum file size for a single file is 100MB. Files up to 2GB can be uploaded indirectly via the end-user account library in Submittal Exchange©.
i. For files that exceed the above size limitations, contact the ESC PM for instructions.
j. When the Contractor’s submission consists of multiple files (such as drawings, specifications, calculations, etc.) individual zip files not exceeding 100MB each can be created for uploading to Submittal Exchange©.
k. Multiple zip files are acceptable if necessary and should be uploaded and properly identified as part of a single submission (i.e., “...File 1 of 4; File 2 of 4; File 3 of 4, etc.”).
Contact the ESC PM for guidance when more than one file or zip file is required to be submitted against a single item in Submittal Exchange©.
l. Files that cannot be separated into files of 100 MB or less (such as video files) that exceed 2 GB in size can also be posted to the Department’s External Share site or submitted on flash or thumb drive media directly to the CO at the address below. Contact the ESC PM for guidance and assistance.
Department of Labor Contracting Officer c/o Engineering Support Contractor
2101 Wilson Blvd, 4th Floor
Arlington, VA 22201
m. A transmittal cover can be uploaded to Submittal Exchange as a placeholder noting an electronic copy of the submission was sent under separate cover. Include tracking number(s) on transmittal cover or in email notification for submissions sent via UPS, FedEx, etc.
mailto:JCASinvoice@dol.gov
4. Existing Construction Documents: As-built drawings are available for informational purposes only and can be viewed and downloaded at:
www.solicitationattachments.com/nh_asbuilts
5. Site Visits and Construction Observation
a. The Department Contracting Officer’s Representative (COR) and/or a representative of the Department’s Engineering Support Contractor (ESC) will conduct a site visit at least once a month.
b. During this visit, the Contractor’s payment application will be quantified and verified by the COR or delegated ESC representative.
c. The Contractor will be responsible for verification of all dimensions, layout, and conditions in and around the construction area involved.
d. The Contractor shall be responsible for all cutting and patching incidental to the work described herein.
e. The Contractor shall be responsible for identifying the location of existing utilities and for avoiding damage to same in the completion of this work.
f. The Contractor shall promptly repair/replace any damage to structures, elements, utilities, finishes, etc., occurring due to construction, the cost of which shall be incurred by the Contractor.
Restoration of damaged elements or surfaces shall be promptly executed in like materials, as a part of this contract.
g. Although this scope of work identifies specific elements of construction, it is the
Contractor’s responsibility to provide any and all elements which are incidental to the functioning of the work to be provided.
h. It is not intended that other deficiencies not related to the work identified in this Scope be corrected. The Contractor shall limit its efforts only to the work that has been identified in this
Scope of Work, including affected areas.
i. The Contractor shall maintain a clean and safe work area throughout the period of construction.
j. The Contractor shall be responsible for receiving, storing, and securing of all materials, equipment and other items to be used in accomplishing the work.
k. The Contractor shall remove all devices/fixtures from the old siding and reinstall the same to the new siding and restore pre-construction condition and functionality.
l. The Contractor is responsible for removing all cameras attached to the wood siding, storing them in a safe place, and reinstalling the cameras in the same locations and ensuring they are functioning properly.
m. The Contractor will coordinate with the Center for locations of staging areas and vehicle parking.
n. Electricity will be made available by the Center. Connections to existing power shall be by the Contractor.
o. Upon completion, the Contractor shall return the site conditions to their original state.
6. Progress Meetings
a. Once construction commences, in coordination with the Department, the Contractor shall organize, prepare agenda, and conduct weekly construction progress meetings to include recording and preparing meeting minutes; and distribution to team members and attendees within
3 days after the meeting.
http://www.solicitationattachments.com/nh_asbuilts
b. Attendees to weekly progress meetings shall include representatives from the Contractor, the Engineering Support Contractor (ESC), the Department, and others as determined by the CO.
c. Meetings may be held at the construction site in conjunction with ESC site visits and/or attended by conference call. The ESC will provide the teleconference platform.
USE OF THE SITE
SITE ACCESS
1. Access to the construction site will be from the road located on the South side of the site.
2. The Contractor will maintain this road during construction and repair the road as necessary at the completion of the project.
STAGING AREA
1. The primary laydown and staging area will be located on the west side of Dormitory F.
The Contractor shall coordinate with and obtain approval for the Center and the CO for use of additional laydown and staging locations as necessary (see Section V - SKETCHES).
2. The Contractor shall restore the laydown area to its current condition after completion of the project.
SCHEDULE AND DELAYS
1. The Contractor shall immediately notify the Center of any expected delays in the acquisition of materials, as well as any unforeseen conditions, such as water damage, mold, wood rot, etc. which may delay the completion of the project.
2. Should this impact on the approved construction sequence schedule the Contractor shall adjust the schedule and resubmit it to the CO for approval.
3. No extensions in time will be granted unless the modified schedule is approved by the
CO.
SITE SAFETY, CONDITIONS, AND SECURITY
1. The Contractor must maintain site safety and minimize disruptions affecting building occupants and Center operations.
2. The Contractor must cover and protect all nearby surfaces from dust and debris and protect surroundings of any work area to ensure the safety of all students and employees on campus.
EXTENT OF WORK
SPECIFIC WORK REQUIREMENTS
1. The work involves the phased removal of the existing wood siding system and installation of new fiber cement plank siding system. Targeted areas of replacement include all existing wood siding on Buildings A through G.
2. All work includes necessary surface preparation, underlayment wrap, and finishing touches. All products used shall be compatible with the siding manufactures products.
3 Buildings A, B, C, D, E, and F consist of two levels and Building G is one level. The approximate square footage of the total elevations is 58,000 SF.
Building
Approximate Square
Footage of Wood Siding
A 5,000 SF
B 10,000 SF
C 9,000 SF
D 12,000 SF
E 9,000 SF
F 12,000 SF
G 1,000 SF
Total 58,000 SF
4. Before construction begins, the Contractor must provide storage for all materials for each phase. Location of storage containers/trailers shall be coordinated with the Center prior to start of work.
5. The Contractor is also responsible for the disposal of all removed material after demolition. Dumpsters must be provided by the Contractor and coordinated with the Center for the most suitable location during construction, for every building. Reduce waste disposed of in landfills and incineration facilities by recovering, reusing, and recycling materials.
6. Weather Protection
a. The Contractor shall incorporate into the project schedule reasonable allowances for typical regional weather impact based on historical weather data.
b. The Contractor must provide weather protection over exposed surfaces during construction to safeguard exposed areas.
c. No elevation shall be left unprotected overnight or during forecast adverse weather conditions.
7. Site Operation and Occupant Protection
a. The Contractor shall coordinate daily work areas with the center operations to:
1) Maintain required egress routes
2) Protect entrances and pedestrian pathways.
3) Limit noise, dust, and debris migration
4) Provide barricades and overhead protection as needed.
b. Work shall be planned to avoid blocking entrances, windows, and other openings required for ventilation or emergency exits.
c. Work must comply with all applicable building codes, manufacturer installation requirements and project specifications.
CONSTRUCTION PHASING
1. Proper scheduling, phasing, and sequencing of the work is required to enable the Center to operate in normal fashion during construction.
2. Each building shall be treated as an individual phase of construction.
3. Work shall be sequenced by building to maintain continued workflow while limiting building exposure and operational impact.
4. Phasing of the work shall be performed as identified below:
a. Phase 1 – Building G - WELCOME CENTER complete removal and disposal of old siding and install new siding. In parallel, during installation of the last side of Building G, the
Contractor may perform removal of old siding of Building A on one side of the structure.
b. Phase 2 – Building A - ADMIN-WELLNESS complete removal and disposal of old siding and install new siding. In parallel, during installation of the last side of Building A, the
Contractor may perform removal of old siding of Building B on one side of the structure.
c. Phase 3 – Building B – EDUCATION complete removal and disposal of old siding and install new siding. In parallel, during installation of the last side of Building B, the Contractor may perform removal of old siding of Building C on one side of the structure.
d. Phase 4 – Building C – CAFETERIA complete removal and disposal of old siding and install new siding. In parallel, during installation of the last side of Building C, the Contractor may perform removal of old siding of Building D on one side of the structure.
e. Phase 5 – Building D – DORMITORY complete removal and disposal of old siding and install new siding. In parallel, during installation of the last side of Building D, the Contractor may perform removal of old siding of Building E on one side of the structure.
f. Phase 6 – Building E - RECREATION CENTER complete removal and disposal of old siding and install new siding. In parallel, during installation of the last side of Building E, the
Contractor may perform removal of old siding of Building F on one side of the structure.
g. Phase 7 – Building F – DORMITORY complete removal and disposal of old siding and install new siding.
ARCHITECTURAL WORK
1. Demolition
a. The Contractor must remove the existing cedar siding as outlined under each phased section above.
b. Inspect and repair any damaged substrate and install sheathing as needed and match existing.
c. For bidding purposes, include 100 SF of sheathing per building. Sheathing material is
Glass-Mat Gypsum Sheathing Board. Type X, 5/8 inch thick.
d. The Contractor shall inspect all security cameras and document their operational status prior to removal.
e. The Contractor shall safely remove and store all cameras for reinstallation on the new siding to ensure cameras are in the same condition and function properly. Camera count is as follows:
Building A B C D E F G Total
Security Camera 3 8 3 6 5 8 3 36
g. Prior to removing old siding, uninstall all existing exterior utility fixtures and devices from each building’s siding and store securely until reinstallation.
h. The Contractor shall reinstall all existing fixtures and devices on the new siding. Devices and fixtures located on wood sides are as follows:
Building A B C D E F G Totals
Electric Wall Pack Lighting 5 5 6 13 12 12 1 54
Hose Bibb (Frost Free, Secure
Handle) 2 2 5 3 6 18
Steel Trim Frame Penetrations 30 30
Public Address Horns + Box 1 3 1 4 2 11
Natural Gas Line/Meter 1 1 1 3
Main Electrical
Distribution/Meter 4 4
HVAC Electric Disconnect
Boxes 2 1 1 4
Fire Department Connection
(FDC)
1 1 1 1 4
Misc. Plumbing Drain/Vent Pipe 3 1 2 6 8 6 26
Misc. Small Electric Device 6 7 6 11 3 8 10 51
GFCI Outlet 4 2 2 3 8 1 2 22
Misc. Signage 2 2 2 6 6 10 10 38
Gutter Downspouts 7 1 1 9
Scupper Openings 2 2
Small Motion Light + Box
(Solar) 13 3 10 26
Motion Light, Wired 1 1
Exterior Wi-Fi Booster 1 1 1 3
Roof Access Ladder, Mounted 1 1
Totals 60 38 24 70 52 66 33 343
i. The Contractor shall coordinate with the appropriate utility services companies (electric, gas, water, etc.) as required prior to removal of devices, specifically with service entrance equipment, such as the main disconnect switch and meter on Building G, and gas meters in
Buildings A, D, and F.
j. De-energize power by turning off at the associated building electrical panel feeders serving disconnect switches and enclosed circuit breakers serving and protecting HVAC equipment on exterior of Buildings A, C, and G.
k. Carefully remove existing siding, trim, flashing, and deteriorated sheathing as needed.
l. Properly dispose of all demolition debris offsite in accordance with local regulations.
m. Inspect underlayment sheathing, framing and insulation for damage or deterioration.
k. The exposed area must be sufficiently dry, free of any wood rot, and adhere to manufacturer's specifications for new coverings.
2. Fiber Cement Siding
a. Subject to compliance with requirements, available manufacturers offering fiber cement siding products that may be incorporated into the work include, but are not limited to:
1) James Hardie
2) Nichiha
3) or approved equal
b. Siding shall be in compliance with specifications under the following standards:
1) ASTM C1185 – Warm Water/Freeze/Thaw Resistance
2) ASTM C177 – Thermal Resistance
3) ASTM G23 – UV Accelerated Weathering Test
4) ASTM E84 – Surface Burning Characteristics
5) ASTM E136 – non-combustibility
6) ASTM E119 – Fire Resistance Rated Construction
5) NFPA Class – A
6) Minimum Thickness: 5/16”
c. Preparation
1). Ensure the surface is clean, dry, and free of debris.
2) Ensure all necessary materials are on site and ready.
3) Repair/replace damaged sheathing, insulation, wood rot, cracks, holes, or uneven spots with appropriate materials, and framing if any.
4) Furnish and install new fiber cement siding system per the manufacturer’s instructions as outlined in phasing sections above.
d. Building Wrap
1) Install proper underlayment/building wrap (weather resistant barrier).
2) Building Wrap: ASTM E 1677, Type I air retarder; with flame-spread and smoke-developed indexes of less than 25 and 450, respectively, when tested according to ASTM E 84;
UV stabilized; and acceptable to authorities having jurisdiction.
3) Subject to compliance with requirements, available products that may be incorporated into the work include, but are not limited to the following:
a) Dow Chemical Company (The); Styrofoam Weathermate Plus Brand Housewrap.
b) DuPont (E. I. du Pont de Nemours and Company); Tyvek CommercialWrap.
c) Raven Industries Inc.; Rufco-Wrap.
d) Reemay, Inc.; Typar HouseWrap.
e) Or approved equal.
4) Allowable UV Exposure Time: Not less than three months.
5) Building-Wrap Tape: Pressure-sensitive plastic tape recommended by building-wrap manufacturer for sealing joints and penetrations in building wrap.
3. Sheathing
a. Glass-Mat Gypsum Sheathing Board: ASTM C 1177.
b. Install sheathing as needed and include 100 SF per building for bidding purposes.
c. Subject to compliance with requirements, available products that may be incorporated into the work include, but are not limited to, the following:
1) CertainTeed Corp.; GlasRoc.
2) Georgia-Pacific Gypsum LLC; Dens-Glass Gold.
3) National Gypsum Company; Gold Bond, e2XP.
4) USG Corporation; Securock.
d. Type and Thickness: Type X, 5/8 inch thick.
4. Cleaning and Protection
1) Comply with manufacturer's written instructions for cleaning and protecting fiber cement siding.
2) Clean the site daily and ensure property safety protocols are followed.
3) Conduct a walkthrough after each building installation. Address any surface defects, or inconsistencies before project completion.
4) Provide the Center with maintenance guidelines for long-term durability.
ELECTRICAL WORK
1. General
a. For buildings in all phases, follow the outlined phasing sequence and de-energize all electrical/fire alarm/safety equipment before removal of siding.
b. Remove and safely store all electrical equipment and install new siding with necessary penetrations.
c. Re-install all removed equipment for each building after siding installation is completed.
d. Test all removed and re-installed systems for operation.
e. Reconnect exterior lights to photocells and time clocks for control.
f. Check exterior lights and photocells for operation.
g. Check GFCI receptacles, disconnects, and HVAC equipment for operation.
h. After siding replacement is completed in all buildings, coordinate with the Job Corps
Data Center (JCDC) to retain the services of a licensed security contractor to test all security cameras, horns, loudspeakers, and other equipment for proper operation.
2. Electrical Work (Phase 1-Building G WELCOME CENTER)
a. Existing Condition
1) Welcome Center Building G has its exterior service entrance equipment, including a
200A, 120/240V, 1-phase service disconnect switch and secondary utility meter, both located on the front exterior wall.
2) A 200A automatic transfer switch (ATS) connecting the building to the 38/39 kVA gas-powered standby generator is located next to the service disconnect.
3) In addition to the above-mentioned electrical equipment, the following components are also located on the building exterior:
(a) Large Junction Box
(b) Conduit System Connecting the Service Disconnect
(c) Automatic Transfer Switch (ATS)
(d) Panelboards (inside the building)
(e) Disconnect Switch (serving and protecting condensing unit)
(f) Security Camera with Associated Junction Box
(g) Building-Mounted Light Fixture
(h) Receptacle Outlet.
b. Removal & Reinstallation
1) Prior to removal of the siding at Welcome Center Building the Contractor must:
(a) Coordinate with the utility for deenergizing the service entrance equipment.
(b) Provide a new Unistrut post in the vicinity of the building and existing generator.
(c) Locate Unistrut post such that the post will not be in the way of construction.
(d) Relocate the existing ATS to the new/temporary Unistrut post.
(e) Provide a 3x3/0 THWN feeder+#6 GND conductor in 2-inch conduit from the generator to the temporary location of the ATS and from the ATS to the 200A MCB panelboard inside the building.
(f) Provide code required temporary grounding (ground rod) at the generator.
2) During the construction, the Contractor shall serve the building from the existing gas-operated generator. As an alternative consider request from the utility for temporary service.
3) Remove the 200A disconnect switch, utility meter, conduit, wiring, and junction box associated with the service entrance equipment.
4) The Contractor should de-energize all branch circuits by turning off and locking all circuit breakers serving electrical/fire alarm, and security components mounted on the side before removal of the electrical/fire alarm, and security equipment.
5) Safely store all removed electrical components, fire alarm, and security equipment and re-install them after new siding installation is completed.
6) Reinstall the existing service entrance disconnect switch and utility meter, ATS, junction box/boxes, conduit and wiring.
7) When installation is completed, contact the utility company to energize the service.
8) Restore grounding and feeders to original condition following NEC requirements.
9) Re-connect ATS to the feeders from generator and service disconnect and to the feeder to panelboard.
MECHANICAL
No Mechanical work has been included except that which is incidental to the rest of the work.
SKETCHES
*Drawings and Sketches Not to Scale and for Reference and Bidding Purposes Only
LOCATION MAP
VICINITY MAP
SITE PLAN
AERIAL VIEW
Legend:
1 = Building A:
Admin/Wellness
5 = Building E: Recreation
Center
2 = Building B: Education 6 = Building F: Dormitory
3 = Building C: Cafeteria 7 = Building G (Welcome
Center)
4 = Building D:Dormitory 8 = Laydown / Staging Area
Dunburton Road
PROJECT SCHEDULE
Activity Description Duration (Calendar Days)
CONSTRUCTION ADMINISTRATION # days
1. Construction Notice to Proceed (NTP) TBD
2. Substantial Completion Phase 1 45 days
3. Substantial Completion Phase 2 60 days
4. Substantial Completion Phase 3 60 days
5. Substantial Completion Phase 4 60 days
6. Substantial Completion Phase 5 60 days
7. Substantial Completion Phase 6 60 days
8. Substantial Completion Phase 7 60 days
9. Final Completion 30 days
TOTAL PERIOD OF PERFORMANCE 435 days
SECTION D – PACKAGING AND MARKING
[THERE ARE NO CLAUSES IN THIS SECTION]
SECTION E – INSPECTION AND ACCEPTANCE
E.1 CONTRACT CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are hereby incorporated by reference (by
Citation Number, Title, and Date) in accordance with the clause at Revolutionary FAR Overhaul
(RFO) 52.252-2 “CLAUSES INCORPORATED BY REFERENCE” in Section I of this contract.
See RFO 52.252-2 for an internet address (if specified) for electronic access to the full text of a clause.
NUMBER TITLE DATE
RFO 52.246-12 Inspection of Construction AUG 1996
E.2 SUBSTANTIAL COMPLETION
Definitions.
E.2.1. “Substantial Completion” means the stage in the progress of the work as determined and certified by the Contracting Officer (CO) or Contracting Officer’s Representative (COR) in writing to the Contractor, on which the work or a portion thereof designated by the Government is sufficiently complete and satisfactory, in accordance with the requirements of the contract documents, that it may be occupied or utilized for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which (1) do not interfere with the intended occupancy or utilization of the work and (2) can be completed or corrected within the time period required for final completion.
E.2.2 “Date of Substantial Completion” means the date determined by the Contracting Officer
(CO) or Contracting Officer’s Representative (COR) of which substantial completion of the work has been achieved. This date shall be contingent on the Contractor completing certain general construction work.
Substantial Completion is further dependent upon the Contractor providing all required training on operations and maintenance to the designated Center personnel. Unless indicated otherwise, the Date of Substantial Completion, as acknowledged by the Government, is also the commencement date of all warranties and guarantees required by the contract documents.
When the Contractor feels that the work is substantially complete, they shall notify the CO and the COR requesting a substantial completion walk thru inspection. Attached to the request must be a list of items to be corrected/completed (punch list). An inspection of the work shall be conducted by the Department of Labor (DOL) or its designated representative to review the punch list and verify its accuracy; should the Contractor’s punch list prove to be inaccurate or incomplete, Contractor shall provide revised punch list. At the time of the inspection, the
Contractor shall be required to submit to DOL or its designated representative all inspection reports, test results, operation and maintenance manuals, keys, and keying schedules for the substantially complete work. This information will then be turned over to the Center Operator.
Upon successful completion of the inspection, the CO shall provide Certification of Substantial
Completion.
Not until the date and Certificate of Substantial Completion have been fully acknowledged, by the Department of Labor’s CO and COR, will the Contractor be relieved of the responsibility for the security and maintenance of the work, except for punch list items. Following acknowledgment by the Department of Labor, the Contractor shall provide any required additional training to designated Center Personnel and shall also complete the punch list items in accordance with the Schedule identified in the Certificate of Substantial Completion. Failure to complete the punch list items within the schedule may be a breach of contract and will be subject to the sanction of the contract.
E.3 USE OF EQUIPMENT BY THE GOVERNMENT
E.3.1 Right to use The Government may take over and operate, with Government employees, such equipment as necessary for heating or cooling such areas of the building that require the service, and other equipment such as elevators, electrical, plumbing, and mechanical systems as soon as the installation is sufficiently complete to permit operation.
E.3.2 Pursuant to Revolutionary FAR Overhaul (RFO) clause 52.236-11, Use and Possession
Prior to Completion, the Government will advise the Contractor in writing of the Government’s intent to the use of the equipment prior to substantial completion, which items of equipment will be taken over and operated, in addition to the date and time such operation shall begin.
E.3.3 Effect on warranties. Government operation of equipment will not relieve the Contractor of warranty or correction obligations elsewhere provided for in this contract. The applicable warranty period, elsewhere provided for in this contract, for each piece of equipment, shall be in accordance with the applicable provisions of this contract.
E.4 FINAL COMPLETION AND ACCEPTANCE
E.4.1 Definitions.
E.4.1.1 “Final Completion and Acceptance” means the stage in the progress of the work as determined and certified by the CO or COR, in writing to the Contractor, on which work required under the contract has been completed in an acceptable manner in accordance with the contract requirements, subject to the discovery of latent defects after final completion and except for items specifically excluded in the notice of final acceptance. The contractor shall reference
Section G.13 entitled Final Completion/Closeout for documentation required prior to final acceptance.
E.4.1.2 “Date of Final Completion and Acceptance” means the date determined by the CO as of which final completion of the work has been achieved, as indicated by written notice to the
Contractor. Documentation indicating Final Acceptance has been achieved will be issued upon satisfactory review of the Final Completion/Closeout package required in Section G.13.
E.5 INSPECTION AND ACCEPTANCE
(a) The CO or the CO's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at:
New Hampshire Job Corps Center
943 Dunbarton Rd
Manchester, New Hampshire 03102
The Government shall perform inspections and tests, as may be applicable, in a manner that does not unduly delay the work.
SECTION F – DELIVERIES OR PERFORMANCE
F.1 CONTRACT CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are hereby incorporated by reference (by
Citation Number, Title, and Date) in accordance with the clause at RFO 52.252-2 “CLAUSES
INCORPORATED BY REFERENCE” in Section I of this contract. See RFO 52.252-2 for an internet address (if specified) for electronic access to the full text of a clause.
NUMBER TITLE DATE
RFO 52.211-13 Time Extensions SEP 2000
RFO 52.242-14 Suspension of Work APR 1984
RFO 52.247-34 F.o.b. Destination JAN 1991
F.2 [RESERVED]
F.3 RFO 52.211-12 LIQUIDATED DAMAGES – CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the
Contractor shall pay liquidated damages to the Government in the amount of $332.93 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
F.4 PERIOD OF PERFORMANCE
Project Name Project Duration Substantial
Completion
Final Acceptance
Date
Replacement of Siding on
Buildings A, B, C, D, E, F & G at the New Hampshire Job
Corps Center
435 Calendar
Days
*The Date for Substantial Completion shall be accomplished within 405 calendar days following receipt of a Notice to Proceed (NTP). (See Section/Paragraph E.2 SUBSTANTIAL
COMPLETION)
**The Date for Final Acceptance shall be the Date for Substantial Completion + 30 days or longer period as agreed and authorized by the CO.
F.5 PLACE OF PERFORMANCE
New Hampshire Job Corps Center
943 Dunbarton Rd
Manchester, New Hampshire 03102
F.6 SCHEDULES
These schedules shall include but are not limited to construction, product data, major material, equipment fabrication, delivery, samples and other submittals required by the contract to be submitted for acceptance.
Deliverables shall be in the English language, unless otherwise provided hereunder, and any system of dimensions (i.e., English or metric) shown shall be consistent with that used in the contract. No extension of time shall be allowed on account of a delay by the Government in approving such deliverables if the Contractor has failed to act promptly and responsively in submitting its deliverables. Each deliverable shall be identified as required by the contract.
The Contractor shall revise such schedules (1) to account for the actual progress of the work, (2) to reflect approved adjustments in the performance schedule, and (3) as required by the COR to achieve coordination with work by the Government and separate contractors employed by the
Government. The Contractor shall submit schedules on the last day of the preceding month for the next month’s work. The schedule shall sequence work to minimize disruption at the jobsite.
F.7 EXCUSABLE DELAYS
The Contractor will be allowed time, not money, for excusable delays as defined in RFO 52.249-
10, Default. Examples of such cases include (l) acts of God or of the public enemy; (2) acts of the United States Government in either its sovereign or contractual capacity; (3) acts of the government of the host country in its sovereign capacity; (4) acts of another contractor in the performance of a contract with the Government; (5) fires; (6) floods; (7) epidemics; (8) quarantine restrictions; (9) strikes; (l0) freight embargoes; and (11) unusually severe weather.
In each instance, the failure to perform must be beyond the control and without the fault or negligence of the Contractor, and the failure to perform furthermore (1) must be one that the
Contractor could not have reasonably anticipated and taken adequate measures to protect against,
(2) cannot be overcome by reasonable efforts to reschedule the work, and (3) directly and materially affects the date of final completion of the project.
F.8 DELIVERABLES/SUBMITTALS
The Contractor shall furnish the following deliverables/submittals listed below as well as other identified documents under this contract.
This is the start of the file's text. The full file is on GovTribe.