Amendment_000002_SOL-114-13-000003.pdf
PDF 81 KB Posted
- Solicitation number
- SOL-114-13-000003
About this file
Amendment 000002 to the SOL-114-13-000003
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_1_to_Amendment_000002_.docx | DOCX document | |
| Attachment_2-_Answers_to_Additional_Questions_.docx | DOCX document | |
| AMP_Final_Presentation_(24Apr).ppt | PPT presentation | |
| Answers_to_questions_(2).docx | DOCX document | |
| Amendment_000001_to_the_SOL-114-13-000003.pdf | ||
| AMP_Summary_Evaluation.mht | MHT file | |
| SOL-114-13-000003_(4).doc | DOC document | |
| SOL-114-13-000003_(4).pdf | ||
| DCN_2013_GEO_010_REAP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
SOL-114-13-000003
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
GEORGIA
Tbilisi 0131 Georgia 11, George Balanchine Street Regional Contracting Office
04/30/2013000002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/05/2013
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of the amendment 000002 is to provide the following revisions to the RFP
SOL-114-13-000003, shown in the revised change pages in Attachment 1 to this Amendment:
1. P.75, Section L.5 GENERAL INSTRUCTIONS TO OFFERORS, (a) (i) : delete "2 MB limit" and insert "5MB limit" in lieu thereof.
2.P.76 Section L.6 INSTRUCTIONS FOR THE PREPARATION OF THE TECHNICAL PROPOSAL, (b) (1)
Technical Approach: Add the following wording at the end of the first bullet:
"the implementation timeline should span the entire life of the Activity and outline the proposed timing and sequence of major activities (plan and timing of issuing grants, building capacity, providing training, etc.) proposed by the Offeror to achieve high level
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Sarah R. Bueter
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 9
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
SOL-114-13-000003/000002
objectives and intended results of REAP"
3.P. 76, Section L.6. INSTRUCTIONS FOR THE PREPARATION OF THE TECHNICAL PROPOSAL, (b) 2.
Management Approach: Delete bullet one and insert the following in lieu thereof:
"• The proposed staffing pattern, including illustrative position titles, location, and names of identified individuals (resumes may be submitted in an annex). NOTE: USAID requests offerors to not enter into exclusive agreements with local personnel. USAID would expect the contractor to establish regional offices where the proximity to a sufficient concentration of grant recipients and direct and indirect beneficiaries provides sufficient benefit to offset the infrastructure and operating costs of a regional office."
4. Answers to Additional Questions from the prospective offerors can be found in attachment 2 to this Amendment.