Sol_140P6426Q0007.pdf

PDF 1 MB Posted

Attached to
Railroad Tie Replacement Federal contract opportunity
Solicitation number
140P6426Q0007
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This is a Request for Quote (RFQ) issued by the National Park Service (NPS) for a railroad tie replacement project at Cuyahoga Valley National Park in Ohio. The project involves replacing approximately 1,200 railroad ties between milepost 64-66, with the goal of bringing the track section back to minimum acceptable Federal Rail Administration (FRA) Class 1 track standards. The contract is a total small business set-aside with a project value between $100,000 and $250,000.

Key details include a site visit scheduled for January 14, 2026, at the Rockside Road Depot in Independence, Ohio, with quotes due by February 9, 2026. The contract will be a firm-fixed price with a 90-calendar day performance period after notice to proceed. Contractors must submit a comprehensive quote package including a technical questionnaire, prior experience documentation, bid guarantee, and pricing schedule. The government will evaluate quotes based on price, technical capability, and prior experience, with the intent to award to the offeror providing the best value to the government.

View the file

Other files for this federal contract opportunity

Other files attached to Railroad Tie Replacement, newest first.
File Type Posted
Sol_140P6426Q0007_Amd_0001.pdf PDF
RR_Tie_Replacement_-_Q_A_0001.pdf PDF
B09_Solicitation_-_Bid_Schedule_-_RR_Ties_-_Amendment_1_0001.xlsx XLSX spreadsheet
B08_Solicitation_-_Bid_Schedule_-_RR_Ties.xlsx XLSX spreadsheet
B08_Solicitation_-_Statement_of_Work_-_Railroad_Ties.pdf PDF
B08_Solicitation_-_DOL_Wage_Determination.pdf PDF
B08_Solicitation_-_Tech_Question.docx DOCX document
Experience_Questionnaire.xls XLS spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

NEGOTIATED (RFP) REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF

SEALED BID (IFB) INVITATION FOR BID

9. FOR

INFORMATION CALL

PAGES

140P6426Q0007

NPS, MWR - Ohio MABO 1113 West Aurora Road Sagamore Hills OH 44067-1678

0044034070

PMO

Christopher Bauer 3304682500

01/07/2026

02/09/2026

1 90

FAR CLAUSE 52.211-10

Scope of Work: Work will consist of providing all labor, materials, tools and other equipment necessary to replace approximately 1200 railroad ties between MP64-MP66 of the Cuyahoga Valley Railway. This section of railroad track is in very bad condition. This project will bring this section back into a condition to bring the track back to the minimum acceptable level to allow trains to pass over this section of track meeting Federal Rail Administration (FRA) regulations for Class 1 track standards.

Magnitude of Construction: Between $100,000 and $250,000

This project is subject to the Construction Wage Rate Requirements Statute.

Set Aside: Total Small Business Set Aside

Site Visit: An organized site visit has been scheduled for this project. See the solicitation Section L, Provision 52.236-27 Site Visit (Construction) for all site visit information.

Continued...

1 54

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Continued...

AMENDMENT

NUMBER

DATE.

NPS, MWR - Ohio MABO 1113 West Aurora Road Sagamore Hills OH 44067-1678

PMO

Christopher Bauer

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P6426Q0007

Type of Acquisition: A firm-fixed price contract will be awarded

Submission Requirements: See Section L of the solicitation.

Bid Guarantee will be required with your proposal -- See Provision 52.228-1 Bid

Guarantee of the solicitation.

Delivery: 90 Days After Notice to Proceed

Delivery Location Code: 0011283113

NPS, MWR, Cuyahoga Valley NP

15610 Vaughn Road

Brecksville OH 44141-3018 US

00010 1200 Railroad Ties Replacement

140P6426Q0007 Railroad Tie Replacement - CUVA Page 4 of 54

TABLE OF CONTENT

Part I – The Schedule SECTION A – Solicitation/Contract Form Special Notice for Contractors Submitting Quotes SECTION B – Price/Bid Schedule SECTION C – Specifications/Drawings SECTION D - Packaging and Marking SECTION E - Inspection and Acceptance 52.246-12 -- Inspection of Construction. Inspection of Construction (Aug 1996) SECTION F - Deliveries or Performance 52.211-10 -- Commencement, Prosecution, and Completion or Work (Apr 1984) 52.236-15 Schedules for Construction Contracts (Apr 1984) 52.242-14 -- Suspension of Work (Apr 1984) SECTION G - Contract Administration Data 1452.201-70 Authorities and Delegations (Sep 2011) Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Feb 2021) Construction Contract Administration

COMPLIANCE WITH RECENT EXECUTIVE ORDERS 14148/14208

Subject to Availability of Funds Addendum:

SECTION H - Special Contract Requirements Part II – Contract Clauses SECTION I - Contract Clauses 52.252-2 – Clauses Incorporated by Reference (Feb 1998) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) . 13 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan 2025) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.215-8 Order of Precedence -- Uniform Contract Format (Oct 1997) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) 52.222-3 Convict Labor (June 2003) 52.222-4 Contract Work Hours and Safety Standards- Overtime Compensation (Mar 2018) 52.222-6 Construction Wage Rate Requirements (Aug 2018) (DEVIATION Feb 2025) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (Jul 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) (DEVIATION Feb 2025) 52.222-12 Contract Termination-Debarment (May 2014) (DEVIATION Feb 2025) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certification of Eligibility (May 2014) 52.222-26 Equal Opportunity (Sep 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-50 Combating Trafficking in Persons (Oct 2025) 52.222-54 Employee Eligibility Verification (Jan 2025)

140P6426Q0007 Railroad Tie Replacement - CUVA Page 5 of 54

52.222-55 Minimum Wages Under Executive Order 13658 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.225-13 Restriction on Certain Foreign Purchases (Feb 2021) 52.226-7 Drug-Free Workplace (May 2024) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity- Construction Contracts (Dec 2007) 52.228-1 Bid Guarantee (Sep 1996) 52.228-2 Additional Bond Security (Oct 1997) 52.228-11 Individual Surety - Pledges of Assets (Feb 2021)(DEVIATION May 2023) 52.228-15 Performance and Payment Bonds- Construction (Jun 2020)(DEVIATION May 2023) 52.229-11 Tax on Certain Foreign Procurements – Notice and Representation (Jun 2020) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-18 Availability of Funds (Apr 1984) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management (Oct 2018) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 15 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-13 Accident Prevention (Nov 1991) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) 52.236-26 Preconstruction Conference (Feb 1995) 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities (Nov 2024) 52.243-5 Changes and Changed Conditions (Apr 1984) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Oct 2025) 52.246-21 Warranty of Construction (Mar 1994) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (Apr 1984) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991)

CLAUSES INCORPORATED BY FULL TEXT

1452.203-70 -- Restrictions on Endorsements (Jul 1996) 1452.204-70 -- Release of Claims – Department of Interior (Jul 1996) 1452.228-70 -- Liability Insurance—Department of the Interior (Jul 1996) 52.204-28 Federal Acquisition Supply Chain Security Act Orders – Federal Supply Schedules, Government Acquisition Contracts, and Multi-Agency Contracts (Dec 2023) 52.204-30 Federal Acquisition Supply Chain Security Act Orders – Prohibition (Dec 2023) 52.213-4 – Terms and Conditions – Simplified Acquisitions (Other Than Commercial Products and Commercial Services) (Oct 2025) 52.219-14 Limitations on Subcontracting (Oct 2022)(DEVIATION Oct 2022) 52.225-9 -- Buy American–Construction Materials (Oct 2022)

140P6426Q0007 Railroad Tie Replacement - CUVA Page 6 of 54

52.252-6 – Authorized Deviations in Clauses (Nov 2020) Part III – List of Documents, Exhibits, and Other Attachments SECTION J – List of Attachments Part IV – Representations and Instructions SECTION K - Representations, Certifications, and Other Statements of Offerors 52.252-1 – Solicitation Provisions Incorporated by Reference (Feb 1998) 52.203-18 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements - Representation (Jan 2017) 52.204-17 Ownership or Control of Offeror (Aug 2020) 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications (Jun 2020)

PROVISIONS INCORPORATED BY FULL TEXT

52.201-1 Acquisition 360: Voluntary Survey (Sep 2023) 52.204-8 -- Annual Representations and Certifications (Oct 2025) 52.204-24 Representation Regarding Certain Telecommunication and Video Surveillance Services or Equipment (Nov 2021) 52.204-26 Covered Telecommunications Equipment or Services-Representation (Oct 2020) 52.204-29 Federal Acquisition Supply Chain Security Act Orders – Representation and Disclosures (Dec 2023) 52.209-13 Violation of Arms Control Treaties or Agreements – Certification (Nov 2021) 52.222-23 -- Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction (Feb 1999) 52.252-5 – Authorized Deviations in Provisions (Nov 2020) SECTION L - Instructions, Conditions, and Notices to Offerors 52.252-1 – Solicitation Provisions Incorporated by Reference (Feb 1998) 52.204-7 System for Award Management (Nov 2024) 52.204-16 Commercial and Government Entity Code Reporting (Aug 2020) 52.204-22 Alternative Line Item Proposal (Jan 2017) 52.211-6 Brand Name or Equal (Aug 1999) 52.214-34 Submission of Offers in the English Language (Apr 1991) 52.214-35 Submission of Offers in U.S. Currency (Apr 1991)

PROVISIONS INCORPORATED BY FULL TEXT

52.216-1 – Type of Contract (Apr 1984) 52.222-5 -- Construction Wage Rate Requirements—Secondary Site of the Work (May 2014) 52.225-10 -- Notice of Buy American Requirement--Construction Materials (May 2014) 52.228-1 Bid Guarantee (Sep 1996) 52.233-2 Service of Protest Department of the Interior (Sep 2006) (DEVIATION) (Jul 1996) 52.236-27 – Site Visit (Construction) (Feb 1995)

INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS OR RESPONDENTS

SECTION M – EVALUATION FACTORS FOR AWARD

52.217-5 Evaluation of Options (July 1990)

140P6426Q0007 Railroad Tie Replacement - CUVA Page 7 of 54

Part I – The Schedule

SECTION A – Solicitation/Contract Form

This solicitation is a Request for Quote (RFQ), in accordance with the Specifications/Drawings and is issued on Standard Form (SF) SF1442. Award of this contract will be made according to FAR Part 13 Simplified Acquisition Procedures. All references to “proposal” or “bid” in this solicitation shall be understood to mean “quotation.” The Government will evaluate all Quotations in an impartial manner and consideration will be given to those with the highest perceived value to the government based on responses to the evaluation factors identified in Section M.

Reference Department of Interior Acquisition Regulation (DIAR) Part 1436, 1436.270-1 Uniform Contract Format.

Special Notice for Contractors Submitting Quotes Signing of the offer shall be deemed to be a representation by the quoter that contractor owns, operates, or maintains a place of business, regularly engaged in construction projects that include having staff with experience required to perform the work described in this solicitation. Quoted price must include all materials/labor/work/taxes to complete work outlined in the Specifications.

SECTION B – Price/Bid Schedule

Quote pricing shall be provided in accordance with Section L and is incorporated herein.

1. The contractor must furnish an itemized breakdown. Contractor shall use the Price/Bid Schedule referred to under SECTION J - LIST OF ATTACHMENTS.

SECTION C – Specifications/Drawings

Project work consists of: providing all labor, materials, tools and other equipment necessary to replace approximately 1200 railroad ties between MP64-MP66 of the Cuyahoga Valley Railway. This section of railroad track is in very bad condition. This project will bring this section back into a condition to bring the track back to the minimum acceptable level to allow trains to pass over this section of track meeting Federal Rail Administration (FRA) regulations for Class 1 track standards.

Additional requirements information is provided in the solicitation, specifications, supporting documents and other pertinent attachments.

“Specifications and other supporting documents are attached and incorporated herein. Refer to SECTION J.”

SECTION D - Packaging and Marking

No clauses included

SECTION E - Inspection and Acceptance

52.246-12 -- Inspection of Construction. Inspection of Construction (Aug 1996)

(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not --

140P6426Q0007 Railroad Tie Replacement - CUVA Page 8 of 54

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph

(i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may --

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

(End of clause)

140P6426Q0007 Railroad Tie Replacement - CUVA Page 9 of 54

SECTION F - Deliveries or Performance

Work shall be completed by skilled personnel per industry standards and manufacturer specifications.

52.211-10 -- Commencement, Prosecution, and Completion or Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days after receipt of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.236-15 Schedules for Construction Contracts (Apr 1984)

(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

(End of clause)

52.242-14 -- Suspension of Work (Apr 1984)

(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer's failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.

However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that

140P6426Q0007 Railroad Tie Replacement - CUVA Page 10 of 54 performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.

(c) A claim under this clause shall not be allowed—

(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and

(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.

SECTION G - Contract Administration Data

(a) Contact Information:

The Contracting Specialist administrating the Contract:

Christopher Bauer Contract Specialist

National Park Service 1113 W. Aurora Rd

Sagamore Hills, OH 44067 Telephone No. (330) 468-2500 ext: 5 Fax No. (330) 468-2507 Email: christopher_bauer@nps.gov

(b) The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely with the CO. In the event the contractor effects any such change at the direction of any person other than the CO, the change will be considered made without authority and no adjustment will be made in the contract price to cover increase in costs incurred as a result thereof.

(c) Contractual problems, of any nature, which might occur during the life of the contract, must be handled in conformance with very specific public laws and regulations (e.g., Federal Acquisition Regulation), and must be referred to the CO for resolution. Only the CO is authorized to formally resolve such problems. Therefore, the contractor is hereby directed to bring all such contractual problems to the immediate attention of the CO.

(d) Any request for contract changes/modifications shall be submitted to the CO.

(e) The contractor and the Government may agree to perform a no-cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated line items.

All field changes must be approved by the CO prior to execution.

(f) All correspondence concerning this contract, such as requests for information (RFI), explanation of terms, and contract interpretation, shall be submitted to the CO.

FINAL PAYMENT

Final payment will be made only after receipt of all payrolls to include subcontractors, SF 1413 Statement of

140P6426Q0007 Railroad Tie Replacement - CUVA Page 11 of 54

Acknowledgement for each subcontractor, project schedule, updated progress reports, material submittals, test reports, as-built drawings, warranty of construction, release of claims and any other documents requested by the contracting office as applicable. Contractor must provide a signed copy of the 'Release of Claims' to the Contract Administrator upon submittal of final invoice.

AVAILABILITY OF UTILITIES SERVICES

Notwithstanding the provisions of contract clause FAR 52.236-14, Availability and Use of Utility Services, all reasonable required amounts of water, gas, electricity, etc., essential to contract performance shall be made available, at no cost to the contractor, from existing systems, outlets, and supplies. All temporary connections, outlets, and distribution lines as may be required will be installed by the contractor at the contractor's own expense.

UTILITIES CONSERVATION

The contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the contractor.

OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) INSPECTIONS

The contractor shall be subject to inspections under the OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) program by inspectors of the Department of Labor.

INTERIM AND FINAL INSPECTIONS

1. Prior to covering, enclosing, or hiding any of type work, the Contractor must contact the Government representative to perform an interim inspection. Failure to contact the Government representative perform an interim inspection prior to concealment may result in the Contractor being required to uncover performed work sufficiently to allow for proper inspection.

2. When ready for final inspection, the Contractor shall notify the CO and COR, requesting a final inspection in writing to the CO. The final inspection shall normally be requested a minimum of three (3) calendar days before the desired date or as otherwise negotiated with the Contracting Officer.

3. The final inspection will be onsite with the Contractor, the Contracting Officer’s Representative, and Contract

Specialist/Contracting Officer (when possible).

1452.201-70 Authorities and Delegations (Sep 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

The COR for this contract will be:

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

140P6426Q0007 Railroad Tie Replacement - CUVA Page 12 of 54

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR’s appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.

(End of Local Clause)

Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Feb 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Copy of vendor invoice document in PDF format, completed on the pay application document provided by contracting, which shows pricing breakdown for all line items. Once all signatures (Contractor’s / COR / CO) and approvals are completed on the pay application, the vendor can then upload this document into IPP as their invoice attachment.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date.

Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

140P6426Q0007 Railroad Tie Replacement - CUVA Page 13 of 54

Construction Contract Administration

Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.

COMPLIANCE WITH RECENT EXECUTIVE ORDERS 14148/14208

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation, and paragraph

(t) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services.

Agencies will not consider or use these representations. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

Subject to Availability of Funds Addendum:

Notice to Offeror(s)/Supplier(s): Funds are not presently available for this effort, however there is a high expectation that funds will become available to make an award resulting from this solicitation. No award will be made under this solicitation until funds are available. The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs.

SECTION H - Special Contract Requirements

N/A

Part II – Contract Clauses

SECTION I - Contract Clauses

52.252-2 – Clauses Incorporated by Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.acquisition.gov

52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014)

140P6426Q0007 Railroad Tie Replacement - CUVA Page 14 of 54

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan 2025) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.215-8 Order of Precedence -- Uniform Contract Format (Oct 1997) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) 52.222-3 Convict Labor (June 2003) 52.222-4 Contract Work Hours and Safety Standards- Overtime Compensation (Mar 2018) 52.222-6 Construction Wage Rate Requirements (Aug 2018) (DEVIATION Feb 2025) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (Jul 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) (DEVIATION Feb 2025) 52.222-12 Contract Termination-Debarment (May 2014) (DEVIATION Feb 2025) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certification of Eligibility (May 2014) 52.222-26 Equal Opportunity (Sep 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-50 Combating Trafficking in Persons (Oct 2025) 52.222-54 Employee Eligibility Verification (Jan 2025) 52.222-55 Minimum Wages Under Executive Order 13658 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.225-13 Restriction on Certain Foreign Purchases (Feb 2021) 52.226-7 Drug-Free Workplace (May 2024) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity- Construction Contracts (Dec 2007) 52.228-1 Bid Guarantee (Sep 1996) 52.228-2 Additional Bond Security (Oct 1997) 52.228-11 Individual Surety - Pledges of Assets (Feb 2021)(DEVIATION May 2023) 52.228-15 Performance and Payment Bonds- Construction (Jun 2020)(DEVIATION May 2023) 52.229-11 Tax on Certain Foreign Procurements – Notice and Representation (Jun 2020) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-18 Availability of Funds (Apr 1984) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management (Oct 2018) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984)

140P6426Q0007 Railroad Tie Replacement - CUVA Page 15 of 54

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-13 Accident Prevention (Nov 1991) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) 52.236-26 Preconstruction Conference (Feb 1995) 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities (Nov 2024) 52.243-5 Changes and Changed Conditions (Apr 1984) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Oct 2025) 52.245-1 Government Property (Sep 2021) 52.246-21 Warranty of Construction (Mar 1994) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (Apr 1984) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991)

CLAUSES INCORPORATED BY FULL TEXT

1452.203-70 -- Restrictions on Endorsements (Jul 1996)

Restriction on Endorsements—Department of the Interior

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205–1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.

(End of clause)

1452.204-70 -- Release of Claims – Department of Interior (Jul 1996)

Release of Claims—Department of the Interior

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

(End of clause)

1452.228-70 -- Liability Insurance—Department of the Interior (Jul 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$200,000.00 each person

$500,000.00 each occurrence

140P6426Q0007 Railroad Tie Replacement - CUVA Page 16 of 54

$500,000.00 property damage

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

52.204-28 Federal Acquisition Supply Chain Security Act Orders – Federal Supply Schedules, Government Acquisition Contracts, and Multi-Agency Contracts (Dec 2023)

(a) Definitions. As used in this clause—

Covered article as defined in 41 U.S.C. 4713(k), means—

(1) Information technology, as defined in 40 U.S.C. 11101, including cloud computing services of all types;

(2) Telecommunications equipment or telecommunications service, as those terms are defined in section 3 of the Communications Act of 1934 ( 47 U.S.C. 153);

(3) The processing of information on a Federal or non-Federal information system, subject to the requirements of the Controlled Unclassified Information program (see 32 CFR part 2002); or

(4) Hardware, systems, devices, software, or services that include embedded or incidental information technology.

FASCSA order, means any of the following orders issued under the Federal Acquisition Supply Chain Security Act (FASCSA) requiring the removal of covered articles from executive agency information systems or the exclusion of one or more named sources or named covered articles from executive agency procurement actions, as described in 41 CFR 201–1.303(d) and (e):

(1) The Secretary of Homeland Security may issue FASCSA orders applicable to civilian agencies, to the extent not covered by paragraph (2) or (3) of this definition. This type of FASCSA order may be referred to as a Department of Homeland Security (DHS) FASCSA order.

(2) The Secretary of Defense may issue FASCSA orders applicable to the Department of Defense (DoD) and national security systems other than sensitive compartmented information systems. This type of FASCSA order may be referred to as a DoD FASCSA order.

(3) The Director of National Intelligence (DNI) may issue FASCSA orders applicable to the intelligence community and sensitive compartmented information systems, to the extent not covered by paragraph (2) of this definition. This type of FASCSA order may be referred to as a DNI FASCSA order.

Intelligence community, as defined by 50 U.S.C. 3003(4), means the following—

(1) The Office of the Director of National Intelligence;

(2) The Central Intelligence Agency;

(3) The National Security Agency;

140P6426Q0007 Railroad Tie Replacement - CUVA Page 17 of 54

(4) The Defense Intelligence Agency;

(5) The National Geospatial-Intelligence Agency;

(6) The National Reconnaissance Office;

(7) Other offices within the Department of Defense for the collection of specialized national intelligence through reconnaissance programs;

(8) The intelligence elements of the Army, the Navy, the Air Force, the Marine Corps, the Coast Guard, the Federal Bureau of Investigation, the Drug Enforcement Administration, and the Department of Energy

(9) The Bureau of Intelligence and Research of the Department of State;

(10) The Office of Intelligence and Analysis of the Department of the Treasury;

(11) The Office of Intelligence and Analysis of the Department of Homeland Security; or

(12) Such other elements of any department or agency as may be designated by the President, or designated jointly by the Director of National Intelligence and the head of the department or agency concerned, as an element of the intelligence community.

National security system, as defined in 44 U.S.C. 3552, means any information system (including any telecommunications system) used or operated by an agency or by a contractor of an agency, or other organization on behalf of an agency—

(1) The function, operation, or use of which involves intelligence activities; involves cryptologic activities related to national security; involves command and control of military forces; involves equipment that is an integral part of a weapon or weapons system; or is critical to the direct fulfillment of military or intelligence missions, but does not include a system that is to be used for routine administrative and business applications (including payroll, finance, logistics, and personnel management applications); or

(2) Is protected at all times by procedures established for information that have been specifically authorized under criteria established by an Executive order or an Act of Congress to be kept classified in the interest of national defense or foreign policy

Sensitive compartmented information means classified information concerning or derived from intelligence sources, methods, or analytical processes, which is required to be handled within formal access control systems established by the Director of National Intelligence.

Sensitive compartmented information system means a national security system authorized to process or store sensitive compartmented information.

Source means a non-Federal supplier, or potential supplier, of products or services, at any tier.

(b) Notice. During contract performance, the Contractor shall be required to comply with any…