This is a Statement of Work (SOW) for the National Park Service at San Juan National Historic Site in San Juan, Puerto Rico (PMIS #173414) for the acquisition and installation of a replica Spanish Colonial cannon carriage.
The primary objective is to manufacture, deliver, and install one field-type cannon carriage designed to support an iron cannon (Catalog #SAJU-00031) weighing approximately 4,700 pounds with specific dimensions: 106 inches in length, 61 inches diameter at the back, and 5½-inch munions. The carriage must withstand harsh tropical marine environmental conditions including salt air, humidity, and high temperatures, and will be exhibited at the Main Plaza of Castillo San Cristóbal. The project is divided into three tasks: (1) develop design/construction drawings for NPS review and acceptance prior to construction; (2) reproduce a field-type cannon carriage using highest-quality, longest-lasting materials including hot-dipped galvanized steel fasteners, UV-resistant marine-grade black paint, and treated lumber with protective additives; and (3) deliver and install the completed carriage at the site. The contractor must be on-site for assembly or provide detailed step-by-step assembly and installation instructions. All work must be completed within 365 calendar days from the notice to proceed, with on-site work performed between May 2026 and May 2027, Monday through Friday, 8:00 a.m. to 5:00 p.m., excluding Federal holidays. The contractor is responsible for all project management, labor, tools, equipment, shipping, transport, materials, and insurance (workers' compensation and liability coverage valid in Puerto Rico). Deliverables include design/construction drawings, delivery and installation of the carriage, and as-built drawings. The Government will provide site access, park documentation, existing cannon and carriage access for reference, historic carriage drawings, and safety assistance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5426Q0023.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Acquire Replica Spanish Colonial Carriages to Improve Visitor Understanding (SAJU)
Acquire Replica Spanish Colonial Carriage to Improve Visitor Understanding (SAJU)
PMIS #173414
San Juan National Historic Site
San Juan, Puerto Rico
SECTION 1—STATEMENT OF WORK INTRODUCTION
1.1. Project Location and Identification. The location of this project for which these supplies are contracted is Castillo San Cristóbal, San Juan National Historic Site, San Juan, Puerto Rico. Reference numbers for this project are:
1.2. Site Background. San Juan National Historic Site is a unit of the National Park
Service, located in Old San Juan, Puerto Rico. This park unit was established in 1949 by the Secretary of the Interior to preserve the fortifications of San Juan as well as the objects contained in them for future generations. The park is 75 acres and contains two major fortifications: Castillo San Felipe del Morro and Castillo San Cristóbal; approximately 2.5 miles of walls and bastions surrounding Old San Juan;
a smaller but significant fortification across the San Juan Harbor, Fort San Juan de la Cruz (El Cañuelo) and several auxiliary buildings and structures that were once part of the military defensive system built by the Spaniards from 1539 to 1898. Both El Morro (1539) and San Cristóbal (1634), are masonry fortifications within the National Historic Site and form the cornerstone of the visitor experience within this National Park unit.
1.3. Required Supplies. The purpose of this contract is to provide supplies necessary for the reproduction of a field type cannon carriage for an iron cannon that is part of the museum collection (Catalog # SAJU-00031) and that will be exhibited at the park.
The carriage built as part of this requirement needs to be able to withstand the harsh environmental conditions at the historic site (salt-air, humidity, high temperatures, etc.). The carriage needs to support a cannon with the following dimensions (for more specifics see Appendix B):
• Length- 106 inches
• Diameter in the back- 61 inches
• Munions- 5 ½ inches
• Weight: approximately 4700 lbs.
The reproduction and installation of the carriage forms the base award supplies required under this Statement of Work (SOW).
Contractor shall be on-site for assembly of the carriage or provide detailed, step-by-step instructions for their assembly and installation. The Contractor shall provide all project management, labor, tools, equipment, shipping, transport, and materials required to execute the work as described in this SOW. The work area and work requirements for this contract are described herein.
1.4. Project Background.
In 2007, the park started a cannon conservation project. One of the issues affecting the cannon were related to them being placed on concrete blocks without any protection from the weather, visitors, and from the chemical reactions that occurred because of the contact of the metal of the cannon with concrete. The park decided that once treatment of the historic cannon was completed to relocate them on more accessible areas as well as in a carriage so they could be better interpreted. The carriages need to look similar to what the Spanish Ordnance regulations prescribed.
1.5. Situation Analysis as of 2026
Visitors have noticed that artillery pieces are missing from the park. While conservation work on the cannons is underway at the park, they are currently not accessible. The carriages will serve as interpretive tools to highlight the fortifications’ military significance. The park plans to place the cannons on carriages throughout the area, helping to protect them while presenting them in a historically accurate way.
1.6. Definitions
San Juan National Historic Site (Park and/or SAJU) Contracting Officer (CO) Contracting Officer’s Representative (COR)
1.7. Contractor Responsibilities:
A. Contractor shall provide, in writing, documentation of expertise and success in reproducing historic wooden and metal cannon carriages or similar equivalent;
B. Contractor shall provide necessary project management, labor, tools, equipment, shipping, transport, and materials and insurance, to perform work to reproduce and install a field type cannon carriage a (X) pound cannon.
C. Design/construction drawings will be submitted for NPS review and acceptance prior to the commencement of carriage construction; as built design drawings will be submitted at the completion of work.
1.8. PROJECT TASKS FOR BASE SUPPLIES–Necessary base supplies are divided into three primary tasks that noted below and detailed in Section 2.1 of this document.
Contractor shall successfully complete each task to the satisfaction of NPS SAJU
COR.
1.8.1. PROJECT TASK 1— MANUFACTURE AND INSTALL ONE FIELD TYPE
CANNON CARRIAGE FOR AN IRON CANNON (CAT #: SAJU-00031) AT
CASTILLO SAN CRISTOBAL.
1.9. Government Furnished Property, Materials & Supplies.
The Government shall provide:
A. Access to the fortifications, Monday through Friday, 8:00 am to 5:00 pm, barring Federal Holidays.
B. Access to park documents related to cannon carriages as necessary to ensure accurate reproduction carriages upon request of contractor.
C. Access to existing cannon and carriages on display at the park upon request of contractor.
D. Access to existing historic cannon carriage drawings upon request of contractor.
E. Assistance as needed to ensure safety for project implementation;
provide visitor information regarding project and restrict visitor access to work area during installation of cannon and carriages.
1.10. Work Restrictions.
A. WORK HOURS: Work may be performed on-site between 08:00 and 5 : 0 0 p m , Monday through Friday with the exception of Federal holidays
B. TERM OF CONTRACT: The term of this contract is for 365 calendar days from the date of award.
1.11. Management.
The Contractor shall manage the total work effort in accordance with effective and efficient management principles and safe working practices to ensure on-time completion of this contract.
1.12. Safety & Environmental Compliance.
A. The Contractor shall comply with pertinent provisions of the Occupational Safety and Health Act (OSHA), state, and local safety laws and regulations.
B. The Contractor shall comply with pertinent local, state, and federal environmental protection laws and regulations.
C. The Park safety officer has the authority to issue restraint or cease-and-desist orders to the Contractor when violations or unsafe acts are present and threaten Government and Contractor employees or damage to Government property
D. The Contractor shall immediately report to the COR all accidents resulting in employee injury or death or damage to property while performing this contract.
1.13. Insurance.
The Contractor shall be insured and insurance will be valid for work in the Commonwealth of Puerto Rico and meet the Commonwealth of Puerto Rico insurance requirements. The Government is not responsible for damage to Contractor’s equipment, vehicles, tools or materials or their employees and the personal property brought on-site. The Government will not accept any liability due to contractor employee negligence.
A. Workers Compensation: The Contractor shall furnish proof of workers compensation insurance to the Contracting Officer for those employees performing work related to this contract and shall comply with the Workman’s Compensation Laws
B. Liability: The Contractor shall maintain a level of insurance that will protect the Contractor and the Government from any claims as a result of bodily injury (including death) and property damage which may arise from and during the performance of this contract and shall submit proof of insurance to the Contracting Officer.
1.14. Field Verification.
The Contractor shall verify work conditions and design specifications to reproduce the carriage.
1.15. Replacement of Contractor Employee for Security Reasons.
The Government retains the right to request removal of the Contractor’s employee(s), regardless of prior clearances.
1.16. Non-Payment for Additional Work.
Any additional Contractor performed services not specified in contract, either at its own volition or at the request of an individual other than an appointed Contracting Officer, except as may be explicitly authorized in the contract, shall be performed at the financial risk of the Contractor. Only an appointed Contracting Officer is authorized to bind the Government to a change in specifications, contract terms, or conditions.
1.17. Contractor’s documentation deliverables.
The following deliverables are to be submitted with upon acceptance of offer:
A. Description of work plan activities and schedule to perform required services.
B. Contractor safety plan/accident prevention plan C. Contractor’s Quality Control Plan D. Letter designating job principal E. List of subcontractors if applicable F. Written labor law compliance letters G. Proof of Insurance–Business Liability & Workers Compensation.
1.18. Inspection.
The Government will conduct inspections periodically and upon completion of the required services. Final payment will be processed upon confirming that all noted contractor performance deficiencies have been satisfactorily corrected.
SECTION 2 - SUMMARY OF WORK (SOW) Details
2.0. SUMMARY
This Section includes the following:
• Work covered by the Contract Documents
• Contractor use of premises
• Public use of site
• Work Schedule
• Deliverables
SERVICE PRODUCT LOCATION CARRIAGE TYPE
TASK 1
SERVICES
One field type cannon carriage for iron cannon (Cat.
# SAJU-00031
Main Plaza at Castillo San
Cristóbal
Field
2.1. WORK COVERED BY CONTRACT DOCUMENTS
Project Location: San Juan National Historic Site, 501 Norzagaray St.
San Juan, PR 00901
PROJECT TASKS FOR TASK 1-- MANUFACTURE AND INSTALL A FIELD
TYPE CANNON CARRIAGES FOR ONE (1) XXXX-POUNDER CANNON TO BE
LOCATED ON MAIN PLAZA OF CASTILLO SAN CRISTOBAL.
TASK 1: DEVELOP DESIGN/CONSTRUCTION DRAWINGS.
Contractor shall develop design/construction drawings for reproduction of carriage. Construction drawings will be submitted to NPS for review and acceptance prior to commencement of construction of cannon carriages.
TASK 2: REPRODUCE A FIELD TYPE CANNON CARRIAGE FOR A HISTORIC
IRON CANNON
Contractor shall submit documentation of material specifications of highest quality and longest lasting materials as part of this task. Carriage is in a tropical marine environment under high heat and UV exposure. Material and construction specifications will include: as built construction drawings, type and treatment of lumber, metal fastenings of hot-dipped galvanized steel, paint types (UV, marine grade, rust-resistant-type) and black for all metal materials; submittal will be required for all materials. Provide additives for best long lasting wood materials, metal, and paint.
TASK 3: DELIVER COMPLETED REPRODUCTION CARRIAGE TO SITE, AND
INSTALL
Contractor shall deliver and install a reproduction cannon carriage to the site. The contractor shall coordinate with the park times and logistics required for installation in the place where the carriage will be exhibited.
CONTRACTOR USE OF SITE
General: Contractor shall have full use of the areas designated for construction operations during the construction period. Contractor's use of the areas designated for construction are limited only by the Government's right to perform work or to retain other contractors on portions of Project.
Storage of Materials: Confine storage of materials to areas designated by the CO and approved by COR at the preconstruction meeting. The National Park Service is not responsible for safety of stored materials or tools. The park will be open to the public during project.
Preservation of Historic Features: Historic Preservation Treatment Program: Describe in detail materials, methods, and equipment to be used to perform the work. Alternative Methods and Materials: If alternative methods and materials to those indicated are proposed for any phase of work, provide a written description including evidence of successful use on other, comparable projects, and program of testing to demonstrate effectiveness for use on this Project.
PUBLIC USE OF SITE
Contractor shall at all times conduct his operations to ensure the least inconvenience to the visiting public.
OCCUPANCY REQUIREMENTS FOR BUILDINGS
Existing Buildings: Castillo San Cristóbal
Partial Government Occupancy: The government may access the designated construction areas to retrieve necessary supplies and equipment, for security purposes, and to inspect work, and the government will have access to Castillo San Cristóbal during the period of construction for visitor fee area operations, NPS staff offices and public viewing.
WORK SCHEDULE
The contractor shall complete all on-site work between May 2026, -May, 2027, weather permitting.
All work shall be completed and final deliverables submitted within 365 days after the CO issues the notice to proceed.
On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:00 a.m. to 5:00 p.m., Monday through Friday (adjust days as necessary), except when otherwise indicated.
Evening and weekend hours: As approved by the CO only (adjust as necessary).
Holidays: No work will occur on Federal Holidays (adjust as necessary).
DELIVERABLES
• Design/construction drawings for carriage based on accepted bid.
• Delivery and installation of cannon carriage.
• As built drawings for carriages based on accepted bid.
Appendix A: Photograph of Iron Cannon, Cat. # SAJU-00031
Appendix B: Detailed Measurements for Iron Cannon Cat #: SAJU-00031
| SECTION 2 - SUMMARY OF WORK (SOW) Details |
| 2.0. SUMMARY |
| This Section includes the following: |
| Work covered by the Contract Documents |
| Contractor use of premises |
| Public use of site |
| Work Schedule |
| Deliverables |
| CARRIAGE TYPE |
| LOCATION |
| PRODUCT |
| SERVICE |
| Field |
| Main Plaza at Castillo San Cristóbal |
| One field type cannon carriage for iron cannon (Cat. # SAJU-00031 |
| TASK 1 SERVICES |
| 2.1. WORK COVERED BY CONTRACT DOCUMENTS |
| Project Location: San Juan National Historic Site, 501 Norzagaray St. San Juan, PR 00901 |
| CONTRACTOR USE OF SITE |
| General: Contractor shall have full use of the areas designated for construction operations during the construction period. Contractor's use of the areas designated for construction are limited only by the Government's right to perform work or to re... |
| Storage of Materials: Confine storage of materials to areas designated by the CO and approved by COR at the preconstruction meeting. The National Park Service is not responsible for safety of stored materials or tools. The park will be open to the ... |
| Preservation of Historic Features: Historic Preservation Treatment Program: Describe in detail materials, methods, and equipment to be used to perform the work. Alternative Methods and Materials: If alternative methods and materials to those indica... |
| PUBLIC USE OF SITE |
| Contractor shall at all times conduct his operations to ensure the least inconvenience to the visiting public. |
| OCCUPANCY REQUIREMENTS FOR BUILDINGS |
| Existing Buildings: Castillo San Cristóbal |
| Partial Government Occupancy: The government may access the designated construction areas to retrieve necessary supplies and equipment, for security purposes, and to inspect work, and the government will have access to Castillo San Cristóbal during t... |
| WORK SCHEDULE |
| The contractor shall complete all on-site work between May 2026, -May, 2027, weather permitting. |
| All work shall be completed and final deliverables submitted within 365 days after the CO issues the notice to proceed. |
| On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:00 a.m. to 5:00 p.m., Monday through Friday (adjust days as necessary), except when otherwise indicated. |
| Evening and weekend hours: As approved by the CO only (adjust as necessary). |
| Holidays: No work will occur on Federal Holidays (adjust as necessary). |
| DELIVERABLES |
| Design/construction drawings for carriage based on accepted bid. |
| Delivery and installation of cannon carriage. |
| As built drawings for carriages based on accepted bid. |
| Appendix A: Photograph of Iron Cannon, Cat. # SAJU-00031 |
| Appendix B: Detailed Measurements for Iron Cannon Cat #: SAJU-00031 |