PDF 719 KB Posted
- Attached to
- FRSP REPAIR CHANCELLORSVILLE WATER TOWER
- Solicitation number
- 140P4226R0019
About this file
This is a Solicitation, Offer, and Award (SF 1442) for construction services issued by the National Park Service, Northeast Regional Contracting Office in Philadelphia.
The Department of Interior's National Park Service seeks a contractor to perform repair and painting work on the Chancellorsville Water Tower at Fredericksburg & Spotsylvania National Military Park in Spotsylvania, Virginia. The solicitation number is 140P4226R0019, issued July 13, 2026, with offers due August 11, 2026. The contract will be awarded on a firm fixed price basis with a 90-day period of performance after issuance of Notice to Proceed and a contract period extending from August 31, 2026 to August 30, 2027. The base work involves cleaning, painting preparation, interior and exterior painting, disinfection, and safety upgrades to a 25,000-gallon above-ground potable water tank approximately 9 feet in height. Required work includes temporary potable water hookups for park facilities, blast media cleaning to SSPC-SP10/NACE 2 standards, NSF/ANSI 61-certified interior coatings with stripe coats and topcoats, exterior rust-inhibiting paint, bacteriological testing, new drain valves, ladder and safety system replacements, roof vents, shell manways, mixing systems to prevent thermal stratification, level switches with WiFi capabilities, confined space signage, and installation of government-provided Starlink equipment.
Five optional line items are available subject to funding availability: concrete crack repair and sealing at the foundation, bolt/nut tightening and weld repairs, windage rod adjustment, installation of a passive galvanic anode cathodic protection system, and installation of a mechanical float and tape/cable liquid level indicator system. All work must comply with AWWA, NACE, OSHA, NSF/ANSI, ASME, AWS, and Virginia regulations. The contractor must provide a five-year workmanship warranty, daily safety meetings, a comprehensive safety plan addressing fall protection and confined space entry, hot work permits, and a construction manager and site superintendent available during business hours. Work hours are 7:00 a.m. to 5:00 p.m. Monday through Friday, excluding federal holidays, with 72-hour advance written authorization required for weekend or holiday work. The location is Chancellorsville Battlefield Water Tower, 9100 Ranger Lane, Spotsylvania, Virginia 22553, with delivery location at Fredericksburg National Military Park, 120 Chatham Lane, Fredericksburg, Virginia 22405.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
NEGOTIATED (RFP) REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF
SEALED BID (IFB) INVITATION FOR BID
9. FOR
INFORMATION CALL
PAGES
140P4226R0019
DOI, NPS, NERO & NER SOUTH MABO
National Park Service Northeast Regional Contracting South/Philadelphia MABO 1234 Market Street, 20th Floor Philadelphia PA 19107
0044037423
PNC
Brian McCabe 2023397772
07/13/2026
08/11/2026
10 90 Section C.3
Section C- Scope of Work
Section D-I - Contract Clauses
Attachment 1 - Construction Wage - VA20260165 - 05.18.2026 - Building
Attachment 2 - Photo
Attachment 3 - Proposal Submission Package - 140P4226R0019
Sections K-M - Provisions and Evaluation Criteria
1 77
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Continued...
AMENDMENT
NUMBER
DATE.
DOI, NPS, NERO & NER SOUTH MABO
National Park Service Northeast Regional Contracting South/Philadelphia MABO 1234 Market Street, 20th Floor Philadelphia PA 19107
PNC
Brian McCabe
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
Fredericksburg & Spotsylvania National Military
Park (FRSP) - REPAIR & PAINT CHANCELLORSVILLE
WATER TOWER
Firm Fixed Price Contract
Delivery: 90 Days After Notice to Proceed
Delivery Location Code: 0011282867
NPS, Fredericksburg NMP
120 Chatham Lane
Fredericksburg VA 22405 US
Period of Performance: 08/31/2026 to
08/30/2027
00010 FRSP - Watertower Painting and Repairs (Total of A-E)
Product/Service Code: Z1NE
Product/Service Description: MAINTENANCE OF
WATER
SUPPLY FACILITIES
A - Temporary Potable Water
B - Cleaning and Paint Preparation
C - Painting/Coating
D - Disinfection/Sample Testing
E - Additional Work (See Section C.2 (E) for each specific items details)
00020 Optional Item 1 - Repair cracks/spalling concrete, grout/caulk seal foundations around base of water tower.
(Option Line Item)
Anticipated Exercise Date 10
Product/Service Code: Z1NE
Product/Service Description: MAINTENANCE OF
WATER
SUPPLY FACILITIES
00030 Optional Item 2 - Tighten Bolts/Nuts and weld anchors and base plates
(Option Line Item)
Anticipated Exercise Date 10
Product/Service Code: Z1NE
Product/Service Description: MAINTENANCE OF
WATER
SUPPLY FACILITIES
Continued...
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
00040 Optional Item 3 - Adjust windage rods
(Option Line Item)
Anticipated Exercise Date
Product/Service Code: Z1NE
Product/Service Description: MAINTENANCE OF
WATER
SUPPLY FACILITIES
00050 Optional Item 4 - Install new passive
(sacrificial) galvanic anode cathodic protection (CP) system
(Option Line Item)
Anticipated Exercise Date 10
Product/Service Code: Z1NE
Product/Service Description: MAINTENANCE OF
WATER
SUPPLY FACILITIES
00060 Optional Item 5 - Install new Mechanical Float and Tape/Cable Liquid Level Indicator
(Option Line Item)
Anticipated Exercise Date 10
Product/Service Code: Z1NE
Product/Service Description: MAINTENANCE OF
WATER
SUPPLY FACILITIES
REFERENCE NO. OF DOCUMENT BEING CONTINUED
140P4226R0019
PAGE OF
SECTION A - TABLE OF CONTENTS
SECTION DESCRIPTION PAGE
PART I – The Schedule A Solicitation/Contract Form 1 B Schedule of Items 6 C Specifications/Drawings 7 D Packaging and Marking 29 E Inspection and Acceptance 29 F Deliveries or Performance 30 G Contract Administration Data 31 H Special Contract Requirements 37
PART II – Contract Clauses I Contract Clauses 41
PART III – List of Documents, Exhibits, and Other Attachments J List of Attachments 56
PART IV – Representations and Instructions K Representations, Certifications, and Other Statements of Offerors 57 L Instructions, Conditions, and Notices to Offerors 65 M Evaluation Factors for Award 74
140P4226R0019
SECTION B – SCHEDULE OF ITEMS
19.
ITEM
NO.
20.
SCHEDULE OF ITEMS
21.
QTY
22.
UNIT OF
MEASURE
23.
UNIT
PRICE
24.
TOTAL
Base Items
00010 FRSP – Watertower Painting and Repairs (Total of A-E) 1 Lump Sum $ $
A Temporary Potable Water Hook-up 1 Lump Sum $ $
B Cleaning and Paint Preparation 1 Lump Sum $ $ C Painting/Coating 1 Lump Sum $ $ D Disinfection/ Sample Testing 1 Lump Sum $ $ E Additional Work (See Section
C.2 (E) for each specific item details)
1 Lump Sum $ $
Base Total $ Optional Items (Subject to the Availability of Funding)
00020 Optional Item 1 – Repair cracks/spalling concrete, grout/caulk seal foundations around base of water tower
1 Lump Sum $ $
00030 Optional Item 2 - Tighten Bolts/Nuts and weld anchors and base plates
1 Lump Sum $ $
00040 Optional Item 3 - Adjust windage rods 1 Lump Sum $ $
00050 Optional Item 4 - Install new passive (sacrificial) galvanic anode cathodic protection (CP) system
1 Lump Sum $ $
00060 Optional Item 5 - Install new Mechanical Float and Tape/Cable Liquid Level Indicator
1 Lump Sum $ $
Optional Items Total $ Base and Optional Items Total $
Note - the Requirement is being solicited under the Revolutionary FAR Updates (RFO) - Simplified Acquisition Procedures under RFO FAR 12 – Acquisition of Commercial Products and Commercial Services, which now includes Construction, as authorized by RFO FAR 12.200 (b). The requirement also includes original Federal Acquisition Regulations (FAR) that have not been implemented by the DOI under the RFO.
140P4226R0019
SECTION C – SCOPE OF WORK
C.0 NATIONAL PARK SERVICE
The National Park Service (NPS) is a bureau of the U.S. Department of the Interior (DOI) that has been entrusted with the care of our national parks since 1916. The National Park System currently has 433 units (often referred to as parks), covering more than 85 million acres in all 50 states, the District of Columbia, and US territories.
The NPS also has more than 150 related areas that are linked in importance and purpose to places managed directly by the National Park Service by preserving important segments of the nation's natural and cultural heritage. They are designated by acts of Congress or by the Secretary of the Interior (affiliated areas). The majority of related areas are not units of the National Park Service and are managed by other government agencies or non-government organizations and landowners.
The National Park Service is involved in related areas by directly managing the entire or sections of a related area, or by providing technical or financial assistance.
The NPS preserves unimpaired natural and cultural resources, and values of the National Park System for the enjoyment, education, and inspiration of this and future generations. The NPS cooperates with partners to extend the benefits of natural and cultural resource conservation and outdoor recreation throughout this country and the world.
The NPS – Business Service Contracting Division (BSCD) – Contracting Operations – Northeast Region – Philadelphia MABO. The NPS – BSCD-Northeast issues contracts through the Federal Acquisition Regulation’s (FAR) for supplies, services, construction, A&E for Northeast Regional Parks only.
C.1 FREDERICKSBURG & SPOTSYLVANIA NATIONAL MILITARY PARK (FRSP)
Fredericksburg & Spotsylvania National Military Park (FRSP) consists of approximately 7,600 acres and is an assemblage of four (4) battlefields, historic landscapes, and related sites that commemorate major Civil War events that occurred between December 1862 and May 1864. FRSP was home to four (4) major Civil War battles: Fredericksburg, Chancellorsville, the Wilderness, and Spotsylvania Court House
FRSP also contains nationally significant historic structures present at the time of the battles, including Chatham Manor used by the Union Army as a headquarters and hospital; Ellwood Manor used by the Union Army as a headquarters and by both sides as a hospital; Salem Church, a shelter for civilian refugees from Fredericksburg in 1862 and a focal point of battle in 1863; the Innis House on Fredericksburg Battlefield; and a plantation outbuilding at Guinea Station (Jackson Death Site) where the great Confederate Gen. Stonewall Jackson died in 1863, with far reaching consequences for the Confederacy.
FRSP also includes The Fredericksburg National Cemetery which honors more than 15,000 Union soldiers, who died in battle or from disease. The cemetery contains almost 85% unknown burials and is one of the largest Civil War national cemeteries in the Nation.
In addition to the historic battlefield and buildings, there are 23 miles of trails, 1,100 acres of open fields and 6,500 acres of forest throughout FRSP. FRSP also supports an eastern North American riparian and woodland habitat on a substrate of the Appalachian Piedmont and the Atlantic Coastal Plain. The park provides rich forest and wetlands, developed parkland, farmsteads, and historic landscapes and it lies in the Rappahannock and York River basins of central Virginia. For more information, please visits FRSP’s website at: Fredericksburg & Spotsylvania National Military Park (U.S. National Park Service)
C.2 TASKS
The DOI on behalf of the National Park Service (NPS) – Fredericksburg & Spotsylvania National Military Park (FRSP) – has a requirement to correct deficiencies of the Chancellorsville Battlefield Above-Ground Potable Water Tower, located https://www.nps.gov/frsp/index.htm https://www.nps.gov/frsp/index.htm
140P4226R0019 in Spotsylvania, VA. The work consists of removing pitting, scale, and sediment from the exterior and interior of the approximately 25,000 gallon above ground water tank that is approximately 9- ft in height as measured from the ground. The work also consists of providing temporary potable water hookups, repairs, repainting both the interior and exterior and upgrades and replacements for safety deficiencies to meet State of VA, National Sanitation Foundation (NSF), National Association of Corrosion Engineers (NACE), American National Standards Institute (ANSI), American Water Works Association (AWWA) regulations and standards for potable water tank standards.
A. Temporary Potable Water Hook-up:
The contractor shall provide ample treated water for public consumption (portable tank, pumps, etc. utilizing existing well as source water) for (2 park housing units, 1 administrative building, and 1 park visitor center) in lieu of the water that is going to be removed from the tower to permit the cleaning and painting of the interior, unless a possible alternative of valve openings and closings can be used to accommodate the water usage.
B. Cleaning and Paint Preparation
The contractor shall:
• Interior of Tank o Any/all sediment, scale, and debris shall be removed from tank and be disposed of properly and in accordance with applicable Local, State and Federal Regulations.
o Use Blast media that is compliant with AWWA D102 to remove all rust, corrosion, etc. to meet the Society for Protective Coating (SSPC)-SP10/NACE 2 – Near White Blast Cleaning standard that removes all loose rust, mill scale, oil grease, and foreign matter, leaving a clean, uniform surface profile that is required per NSF/ANSI 61
▪ Blast Media shall:
• Have an angular profile of 2.0 to 3.0 mils per ASTM D 4417, Method C or NACE Standard RP0287.
• Not be applied with pressures exceeding more than 3500 psi. @ 3.0 gpm.
▪ Any damage or holes created and/or discovered after the Blast Media application, shall be repaired per NSF/ANSI, AWWA and applicable State of VA standards for a potable water tank.
• If applicable, all new welds shall be ground to a smooth contour per NACE Standard SP0178, Designation D.
o Remove any remaining interior loose rust and scale with wire brushes and hand scrapers as necessary to prepare surface for primer/paint in accordance painting manufacturers recommendation and NSF/ANSI Standard 61 (NSF 61) for interior of potable water tank.
o After Blast Media, pressure wash with bio-degradable detergent throughout entire interior of the tank at no more than 3500 psi @ 3.0 gpm.
• Exterior of Tank and Support Structure o Exterior surface preparation of both tank and all exterior structural metal surfaces to at least SSPC-SP2: Hand Tool Cleaning standard and/or manufactures recommendations that removes all loose mill scale, rust, paint, and other detrimental matters.
▪ SSPC-SP3: Power Tool Cleaning is acceptable, but adherent rust, mill scale, or paint shall not be removed.
▪ Any areas where excessive rust, corrosion, or damage are present, that may require additional steps to reduce and/or eliminate further damage shall be addressed with COR/POC.
o Pressure wash exterior with a bio-degradable detergent at no more 3500 psi @ 3.0 gpm (no Blast Media shall be used on exterior).
• Care must be taken to prevent damage to pumps, electrical switches and sensors, etc.
o Any damage to existing equipment, not otherwise included for repair and/or replacement in
140P4226R0019 this contract shall be the contractors responsibility to replace/repair at no cost to Government.
C. Painting/Coating
1. Interior Water Tank Paint/Coating
• The contractor shall apply o One (1) primer coat over entire interior of the tank per manufacturer’s instructions
▪ Shall follow immediately after surface preparation and cleaning before rust bloom occurs or the same day, whichever is less.
▪ Any cleaned areas not receiving first coat within this period shall be recleaned at no expense to government prior to application of first coat.
▪ Dehumidifier may be used after written approval of COR/POC if necessary.
o One (1) stripe coat applied to all weld seams, edges, corners, bolts, nuts and other difficult to coat areas.
o Two (2) topcoats of paint/coating to the entire interior of the water tank.
• The Primer/Paint and/or coatings used on the interior of the water tank must be NSF/ANSI
Standard 61 (NSF 61) Certified.
o Contractor must provide NSF certification for any coating system that is proposed for inside of tank. This NSF-61 certification applies to all primers, intermediate coats and topcoats or linings that may be exposed to potable water.
• Discontinuity/Holiday (Pinhole) Testing – The integrity of interior coated surfaces shall be tested for holidays in accordance with NACE Standard SP0188-2024 (as amended).
o For dry films less than 20 mils, a non-destructive holiday detector shall not exceed 67.5 volts, nor shall destructive holiday detector exceed the voltage recommended by the manufacture of the coating system.
o All pinholes and/or holidays shall be marked and repaired in accordance with the manufacturer’s printed recommendations and retested.
o No pinholes or other irregularities shall be permitted in the final coating.
2. Exterior Water Tank and Support Structure Painting/Coating
• Apply one (1) primer coat and one (1) finish topcoat of paint to the entire exterior of the tower.
o The primer and paint shall be rust-inhibiting enamel or metal-specific paint that is designed for exterior metal surfaces o Exterior paint/coating DOES NOT need to be NSF-61 Certified.
• All new exterior paint shall be commercial grade and shall be applied evenly to ensure even color without flashing, and free from drips, over spray, etc.
• Color and sheen shall match existing exterior color; provide COR/POC with three (3) swatches for selection and approval. All swatches must be provided and applied on similar material to water tower.
D. Disinfection/ Sample Testing
After the painting and repairs are completed, the contractor shall ensure the finished water storage tank shall be satisfactorily disinfected in accordance with 12VAC5-590-1081 – Atmospheric Tank Storage (N) 12VAC5-590-1081. Atmospheric tank storage. and AWWA Standard C652-19 before being placed in operation. The disinfection of the storage facilities shall be repeated at least two (2) times until or until it is determined, by bacteriological testing, that the water is free of coliform bacteria.
• The Government does conduct monthly testing and will provide the contractor with most recent test results prior to work beginning, so there is an established base line.
• The contractor shall conduct and provide at least two (2) bacteria samples to a VA stated https://law.lis.virginia.gov/admincode/title12/agency5/chapter590/section1081/ https://law.lis.virginia.gov/vacode/52-19/
140P4226R0019 certified water testing laboratory.
• Each sample shall be taken 24 hours apart.
• The contractor must provide at least two (2) negative tests BEFORE the water tank can be used to provide potable water.
E. Additional work:
The contractor shall:
1. Remove existing 4” drain valve and install new 4" Drain valve to Tower in existing utility pit. New drain shall be at least compliant with:
• AWWA D103 or D100 (general tank requirements)
• NSF/ANSI 61 – Components in contact with potable water
• NSF/ANSI 372 – Lead-free compliance
2. New Exterior and Interior Tower Ladder/Standoffs, Cable Type Safety System and Handrails with Toe Boards. The contractor shall:
a. Remove and dispose of the existing ladders/standoffs.
b. Provide and install:
i. New exterior tower ladder with standoffs, anti-slip rungs and safety cable system.
ii. New interior bowl and riser ladders with standoffs, anti-slip rungs, new stay rod clips/bands on riser and new safety cable system.
iii. New intermediate rail/swing gates
iv. New swing gate at roof access
v. New secondary ladders with standoffs, anti-slip rungs and safety cable system
vi. New handrails system with toe boards on tank roof.
vii. New Secondary Roof Hatch
c. All hatches, manholes, or scuttles above the waterline shall be:
i. Framed at least four inches, preferably six inches, above the surface of the roof at the opening; on ground-level structures, manholes should be elevated 24 to 36 inches above finished grade;
ii. Fitted with a solid watertight cover that overlaps the framed opening and extends vertically down around the frame at least two inches (shoebox type);
iii. Hinged at one side; and
iv. Fitted with a locking device.
d. Contractor shall provide shop drawings of new interior and exterior ladders with standoffs, and cable type safety system for approval by COR/POC, prior to fabrication and construction for approval.
e. All new installations shall meet current NACE,AWWA/OSHA and 12VAC5-590-1081 requirements for safety.
f. All new installations shall be completed prior to painting/coating.
g. All welding shall be in compliance with industry standards as set by the American Society of Mechanical
Engineers (ASME) and the American Welding Society (AWS).
i. All new welds on interior of tank shall be compliant with NACE Standard SP0178 as amended and ground to a smooth contour per NACE Standard SP0178, Designation D.
3. Replace Existing Roof vent with a new roof vent. Per 12VAC5-590-1081 – Atmospheric Tank Storage the new roof vent shall:
a. Prevent the entrance of surface water.
b. Include screen that exclude birds, animals, and insects and be constructed of noncorrodible material.
c. Be designed to be frost-free or capable of relieving pressure or vacuum in the event of frosting or clogging.
4. Install (2) 30” Shell Manway’s 180 degrees apart with Davit slides on both Manway’s per current OSHA
140P4226R0019
Regulation and other applicable code and regulations.
5. Install new potable water mixing system to prevent thermal stratification, ensure uniform water quality, and protect against disinfection by-products and nitrification.
a. Mixing system shall be sized to meet existing 25,000-Gallon Tower that can be install at the bottom of tank or via manifold and is energy efficient and easy to maintain.
b. Must be NSF/ANSI 61 Certified for and compatible with above ground potable water tank.
c. Shall include install of appliable exterior rated conduit, wire and trenching/overhead wiring to the pumphouse including controls in pumphouse (location to be confirmed in writing with COR/POC).
6. Remove existing damaged high/low switches and install new high/low leveling switches and outside level alarm (audible and visible lights) with WIFI capabilities to include conduit and wiring from tower into the pump house and controls in pump house.
7. Provide and permanently install NEW confined space and fall protection signs per current AWWA and OSHA standards.
8. Install (2) Starlink apparatus (provided by the Government) on the top of tower and attach 2 cables with a grounding cable to leg of tower. Cables must stop roughly 12’ above ground on leg of tower and attach through the air to a mast on small building closest to tower. Ground cables shall go into ground. All Starlink and Starlink cable materials will be supplied by Government.
F. Optional Items (Subject to the Availability of Funding)
1. Optional Item 1 - Repair cracks/spalling concrete, grout/caulk and seal foundations around base of water tower.
The contractor shall repair cracks and spalling concrete on the foundation and base in order to ensure both structural integrity and waterproofing. All repairs must address the root cause (e.g., freeze-thaw cycles, water intrusion, differential movement) and use materials that meet durability and compliance standards.
a. Assessment & Preparation
• Inspect for active water entry, spalling patterns, and movement. Use ACI 562 guidelines for evaluation and repair design.
• Clean and dry all surfaces: remove loose debris, spalled material, and curing compound residues.
For vertical/overhead surfaces, use hand troweling or wet-spray mortars. Ensure the substrate is frost-free and free of oil/grease before sealing.
2. Optional Item 2 - Tighten Bolts/Nuts and weld anchors and base plates.
a. Tighten Bolts/Nuts
• Match torque to bolt size, grade, and material; use a NIST traceable certified calibrated torque wrench or impact wrench; follow a star/crisscross sequence in staged passes; lubricate as needed; and verify preload in critical joints. This ensures the bolted connection meets industrial safety and performance standards.
• Prior to tightening the contract shall inspect bolts for damage, corrosion, etc., all damaged bolts/nuts shall be replaced with bolts of same size and manufactured with same material grade as existing bolts.
• Replacement of bolt/nuts, if required, the materials may be priced separately after award through modification, once quantity, size and materials are identified. Labor costs shall be incorporated into tightening process, with no additional labor for replacement (if applicable).
• Avoid over-tightening, contractors shall be responsible for costs of replacement due to over tightening.
b. Weld Anchors and Base Plates
• Verify existing welds, checking for damage, cracks, etc.
140P4226R0019
• Repair all damage/cracks per industry standards.
3. Optional Item 3 - Adjust existing windage rods
The contractor shall adjust the existing windage rods per the manufacturer’s standards, so they are taut, free of sag, and resistant to movement when tested visually, by touch or by sound.
a. Recommended Inspection Methods
• Visual Inspection – Look for sagging, bowing, or movement. If a rod appears loose, move to the next test.
• Touch and Feel – Shake, knock, or push the rod. If it wiggles or moves easily, it’s too loose and needs tightening.
• Sound Test – Tap the rod; looser rods produce a deeper, longer reverberation, while tighter rods make a higher, shorter sound.
b. Adjustment Procedure
• Tools: Use the manufacturer’s recommended torque wrench or hydraulic adjuster.
• Method:
o Loosen the rod’s locking nuts or bolts.
o Adjust the rod length or tension until it is taut but not overstressed.
o Retighten locking nuts to the specified torque (check manufacturer specs).
o Recheck using all three inspection methods to ensure stability as necessary.
4. Optional Item 4 - Install new passive (sacrificial) galvanic anode cathodic protection (CP) system
a. Description The contractor shall provide a complete passive (sacrificial) galvanic anode cathodic protection (CP) system for corrosion protection of the interior steel surfaces of a ~25,000-gallon above-ground potable water tank. The system shall be self-regulating, require no external power, and be compatible with all coatings and repairs required under the project.
b. Standards The system shall comply with:
• AWWA D102 – Coatings for steel water tanks
• AWWA D100 (or D103 if bolted) – Welded steel water tanks
• AWWA C652 – Disinfection of water storage facilities
• NACE SP0169 / SP0388 – Cathodic protection criteria
• NSF/ANSI 61 & 372 – All materials in contact with potable water
• OSHA confined-space and working-at-height requirements (referenced in Section C.6)
c. Submittals Contractor shall submit:
• Product data sheets for all anodes and hardware
• Calculations showing anode sizing, quantity, and estimated life cycle
• Drawings showing anode placement, suspension method, and tank penetrations or brackets
• Material certifications (NSF 61/372)
• Maintenance documentation/Operation Manuals
• Warranty documentation at closeout
• As constructed/built drawings (if applicable)
5. Optional Item 5 - Install new Mechanical Float and Tape/Cable Liquid Level Indicator
a. Description
The contractor shall provide a new complete mechanical float-and-tape (or float-and-cable) liquid level indicator system suitable for continuous measurement of water level in a 25,000-gallon above-ground
140P4226R0019 potable water tank. The system shall provide reliable, accurate, and easily visible level indication without the need for power or electronics.
b. Standards The system shall comply with the following, as applicable:
• AWWA D103 or D100 (general tank requirements)
• NSF/ANSI 61 – Components in contact with potable water
• NSF/ANSI 372 – Lead-free compliance
• ASTM A240 – Stainless steel components
• OSHA requirements for working around tanks (referenced in Section C.6)
c. Submittals Contractor shall provide:
• Product data and cut sheets
• Material certifications (NSF 61/372)
• Maintenance Documentation/Operation Manuals
• Float buoyancy calculations and system range confirmation
• Shop drawings showing mounting locations, cable routing, indicator board layout
• Warranty documentation at closeout
• As constructed/built drawings (if applicable)
G. Material Requirements
1. General Requirements
a. All materials shall be lead-free as defined by the Consumer Product Safety Act, Part 1303.
b. All materials for the interior wetted portion of the tank shall meet the requirements of NSF/ASNI
Standard 61 for potable water contact.
c. No products containing MOCHA shall be allowed
d. No inorganic zinc-rich primers shall be permitted on the tank interior surfaces.
e. All zinc dust pigment contained in any zinc-rich material shall meet the requirements of ASTM D 520
Type III regarding zinc content and purity.
2. Material Preparation
a. Mix and thin materials according to manufacturer’s latest printed instructions.
b. Do not use materials beyond manufacturer’s recommended shelf life.
c. Do not use mixed materials beyond manufacturer’s recommended pot life
d. Do not split kits of multi-component products.
H. Warranty The contractor must submit in writing a five (5) year guarantee on workmanship to cover any resulting paint flaking or corrosion surfacing. The manufactures warranty must be submitted for the primer and the paint/coating and must be provided to the COR at closeout.
Additional warranty information is required under Section F above if any of the optional items are added at award and/or included after award.
I. Cleanup Contractor shall keep work area and remove all debris and materials daily.
J. Deliverables
The Contractor shall provide the COR/POC with the following:
140P4226R0019
• Temporary Potable Water as noted in C.2 (A)
• All work required in C.2 (A) through (E)
• Applicable shop drawings under Section E
• At least to negative bacteria tests from state certified water testing lab as required by C.2. (F).
• Daily logs and Certified Payrolls with Invoice (invoices will be rejected if not provided).
• SDS Sheets at Close-Out
• Before and After photos
• Warranty documentation as noted in C.2 (G) at closeout
• Provide all as-constructed/built drawings for all items constructed/installed under Sections E and F (as applicable) at close-out
C.3 PERIOD OF PERFORMANCE
The Period of Performance is 90 days after issuance of full Not-to-Proceed (NTP). The full NTP start date is based on actual mobilization date which will be established after submittals are approved. A partial NTP may be issued at the request of the Contracting Officer Representative (COR) and/or Point-of-Contact (POC) and/or Contractor for the submittal process after award but will not count towards the 90 days for the full NTP. If not requested, contractor shall assume submittal process begins immediately after award.
C.4 PLACE OF PERFORMANCE AND HOURS OF OPERATION
Fredericksburg & Spotsylvania National Military Park 120 Chatham Lane Fredericksburg, VA 22405
Specific Location Chancellorsville Battlefield Water Tower 9100 Ranger Lane Spotsylvania, VA 22553
Hours of Operation: Work shall be performed between the hours of 7:00 a.m. and 5:00 p.m., Monday through Friday, federal holidays excluded, unless authorized by the COR/POC in writing. Specific hours may be determined at award. If the NPS determines that the safety of visitors is threatened by the Contractor’s operations, all or part of the Contractor’s operations may be suspended until agreement is reached on additional safety measures and precautions. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
Additional requirements applicable to all locations:
A. Do not execute operations during:
1) Federal holidays, unless otherwise agreed to in advance by Park.
2) Weekends, unless otherwise authorized by Park.
3) Official ceremonies.
B. Weekend Hours: Do not perform Work, unless authorized by Government.
1) Request authorization 72 hours in advance, minimum, in writing.
C. Holiday Hours: Do not perform Work, unless authorized by Government.
1) Request authorization 72 hours in advance, minimum, in writing.
D. These are the following observed Federal Holidays:
140P4226R0019
• New Year’s Day – January 1st
• Martin Luther King Junior’s Birthday – Third Monday in January
• President’s Day – Third Monday in February
• Memorial Day – Last Monday in May
• Juneteenth – June 19th
• Independence Day – July 4th
• Labor Day – First Monday in September
• Columbus Day/Indigenous Peoples Day – Second Monday in October
• Veteran’s Day – November 11th
• Thanksgiving Day – Fourth Thursday in November
• Christmas Day – December 25th
Note - if any of the holidays stated above fall on a Saturday, the Friday before the actual day is the official day the Government takes for the holiday. If the holiday falls on a Sunday, the Monday after the actual day is the official day the Government takes for the holiday. These dates do not account for any other days or shorten days that may be added prior to any of the holidays mentioned above that may be added at the discretion of any Presidential Administration and implemented by the DOI.
C.5 GENERAL PERFORMANCE/PROJECT REQUIREMENTS
A. All worked shall be performed by skilled craftsmen qualified to perform the required work in a manner comparable with the best standards of practice.
B. Noise, Vibration, and Odors (when applicable):
1. When construction noise affects residences, it should be no more than five decibels above the background sound level from: 8 p.m. to 7 a.m. on weekdays. 8 p.m. to 8 a.m. on weekends
2. Coordinate operations that may result in high levels of noise and vibration, odors, dust or other disruption to
Government occupancy with Government and neighboring parties.
3. Notify Government not less than four days in advance of proposed disruptive activities.
4. Obtain Government written permission before proceeding (if applicable).
C. Nonsmoking Building:
1. Smoking is not permitted inside or upon structure or within 25 feet of entrances, operable windows, or outdoor-air intakes.
2. No litter from smoking shall be present on, near or adjacent to the Site.
3. Areas where smoking is allowed shall be at a location directed and approved by Government.
D. Controlled Substances:
1. Use of controlled substances within the existing building is not permitted.
E. Park Security:
1. Special security requirements for the Project(s) maybe required and will be announced at the Pre-Bid and Pre-
Construction meetings (when required).
F. Additional Restrictions:
1. Photographs, social media posts, online content, or any form of communication is strictly prohibited regarding all aspects of this requirement unless authorized in writing by the COR/POC.
2. Contractor must confine storage of equipment and supplies to areas designated by the COR/POC.
3. Contractor must confine all operations to work limits of the project to prevent damage to architectural features and natural surroundings. If damage does occur, Contractor shall restore damaged areas to original condition at no additional expense to the Government.
140P4226R0019
4. Contractor shall furnish, install, and maintain barriers to protect existing facilities and the public from construction operations. Fences and barriers shall be structurally adequate and neat in appearance. Contractor shall completely remove barriers no longer needed when approved by the COR/POC.
5. Contractor shall not remove, injure, or destroy trees or other plants without prior written approval from COR/POC. Contractor(s) must consult with the COR/POC before removing roots and branches that interfere with construction. All written requests for removal and/or trimming must be received no later than five (5) business days before work is to begin, and no work regarding removal and/or trimming shall begin until written approval is received from COR/POC.
6. If excavation, trenching, digging or in ground work that requires the disturbance and/or remove of existing landscaping, soil, etc. requires a written notice that must be received no later than ten (10) business days prior to work beginning, and this type of work requires an NPS Archeologist to be present during all excavation, trenching, digging, or in-ground work.
7. Contractor must not fasten ropes, cables, or guys to existing trees, and must carefully supervise construction operations near trees and plants to prevent damage.
8. Any work that must be performed by a licensed/certified technician (i.e. Electricians, Plumbers, etc.) shall be performed by state-licensed/certified technicians. The applicable state-license/certification must be from the State where the work is performed, no exceptions.
G. Existing Utility Interruptions:
1. Do not interrupt utilities serving facilities occupied by Government or others unless permitted by Government and those authorities having jurisdiction, and then only after providing temporary utilities per requirements indicated.
a. Two hours is the maximum time allowed for planned utility disruptions unless otherwise approved by
Government in writing.
b. An interruption beyond four hours shall require temporary services.
2. Notify Government not less than four days in advance of proposed utility interruptions.
3. Obtain Government written from COR/POC permission before proceeding.
4. Cite periods on construction schedule.
5. Locate and prevent damage to known utilities.
a. If any damage occurs, take relative action and repair utility at no additional expense to Government.
b. Repairs shall commence immediately and be carried out expeditiously and in a professional manner pursuant to and compliant with all federal, state and local codes and regulations as applicable.
c. No additional time shall be added to Contract for repairs from damages to utilities.
d. If damage occurs to an unknown utility, repair and reconnect utility immediately.
1) An equitable adjustment shall be made in accordance with the Changes clause of the Contract.
2) Repairs shall be executed as cited above.
C.6 SAFETY
A. Conduct all operations and procedures in a manner to ensure safety for all and to minimize inconveniences.
1. Methods shall be compliant all applicable regulations (as amended), including State and local bodies having jurisdiction, including, but not limited to:
• American Society for Testing and Materials (ASTM)
• American National Standards Institute (ANSI) with attention to:
o ANSI/ASC 29.4 Exhaust Systems – Abrasive Blasting Operations – Ventilation and Safe Practice
• American Water Works Association (AWWA)
• Consumer Product Safety Act, Part 1303
• National Sanitation Foundation (NSF)
• NACE International
• OSHA – Part 1926 – Safety and Health Regulations for Construction with attention to the specific
Subparts considered applicable to this requirement, o Subpart M – Fall Protection
140P4226R0019 o Subpart X – Stairways and Ladders o Subpart AA – Confined Spaces in Construction
B. Safety Meetings: Contractor shall conduct documented daily safety meetings.
C. Addition, during the execution of this contract, the Contractor must conform to the rules and regulations, as amended and as set forth by:
• National Park Service Occupational Safety and Health Program – Reference Manual 50B - Reference Manual 50B: NPS Occupational Safety and Health Program
• Most Recent Superintendents Compendiums as amended: Superintendent's Compendium - Fredericksburg & Spotsylvania National Military Park (U.S. National Park Service)
D. All Contractor or employee conduct is subject to park rules and regulations concerning: littering, wildlife harassment, collecting, resource damage and other topics as specified for the NPS in the Code of Federal Regulations title 36 (eCFR :: 36 CFR Part 2 -- Resource Protection, Public Use and Recreation).
E. Directors Orders - Director's Orders and Related Documents/NPS Office of Policy – which can have an impact on work performed, includes, but is not limited to:
• NPS Directors Order #83 – Public Health (as amended) - Director's Order #83: Public Health
F. Use of barricades, ropes, signs, or audible signals is required, and the contractor must take all necessary precautions for the protection of the work, property, and safety of the public.
G. All personnel shall wear high-visibility clothing, eye and hearing protection, gloves, and other appropriate PPE.
H. All scaffolding/ladders, etc. shall be properly secured per OSHA and other applicable regulations, which may also include securing site to prevent unauthorized access.
C.7 PERSONAL PROTECTIVE EQUIPMENT (PPE)
A. The Contractor shall furnish personal protective equipment (PPE) to crew members respective of the type of work being completed (i.e., hard hat, eye and hearing protection, leather gloves, etc.).
B. The contractor shall train workers in the safe operation and use of equipment that they will be using to accomplish the work under this contract. Occupation Safety & Health Administration (OSHA) standards PPE shall be followed; information can be found at OSHA PPE Standards.
C. PPE, including personal protective equipment for eyes, face, head, and extremities, shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered in a manner capable of causing injury or impairment in the function of any part of the body.
D. Defective or damaged PPE shall not be used and shall be either repaired or replaced.
C.8 ACCIDENT REPORTING
The contractor shall report emergency situations, such as accidents involving property and/or personal injury or other unforeseen circumstances and shall follow required emergency reporting procedures according to the CO/COR approved Safety Plan. In the event of an emergency the contractor shall dial 911.
A. Accident Reporting: Reportable Accidents: A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires.
1. Notify COR/POC and CO immediately in the event of a reportable accident.
2. Fill out and forward an Accident/Property Damage report Form (CM-22) to COR/POC and CO within 7 days of a reportable accident. Obtain form from COR/POC or CO.
https://www.nps.gov/frsp/learn/management/superintendent-s-compendium.htm https://www.nps.gov/frsp/learn/management/superintendent-s-compendium.htm https://npgallery.nps.gov/GetAsset/109bd8b164d846a8bb286130392a48c8/original
140P4226R0019
B. All Other Accidents: The Contractor shall report all other accidents to the CO as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
C.9 HOT WORK REQUIREMENTS
A. NPS Hot Work Permit – A permit is required for any operation involving open flame or producing heat and/or sparks, such as welding, brazing, cutting, and soldering. Coordinate permitting procedures with COR/POC. Here are the minimum elements regarding the permit:
• Designated Areas: Hot work must be performed in designated or permit-required areas, which are approved by the Park Structural Fire Coordinator.
• Precautions: Before starting, ensure all necessary precautions are taken, including isolating flammable materials and establishing a fire watch.
• Permit Requirements: A signed Hot Work Permit on Form HW-1 must be issued by the designated authority before any hot work operations begin.
• Safety Measures: Conduct thorough inspections, ensure proper isolation of the work area, and provide appropriate personal protective equipment.
B. Hot Work Plan - The Contractor shall prepare a compliant plan and submit it for review 14 days prior to the request to perform hot work. Perform and safeguard hot work operations in accordance with NFPA 51B and NFPA 241 as applicable. The Plan shall be prepared and submitted in conjunction with the Hot Work Permit to the COR/POC.
C.10 FIRE PREVENTION AND PROTECTION
• Any accidental fire starts shall be reported immediately to COR and/or FRSP Fire Management Fire Management. Should the fire exceed the size of a campfire and threaten workers safety, the contractor should depart the area and call 911 or FRSP Fire Management Fire Management immediately.
• Hazard Control: Take all necessary precautions to prevent fire during construction. Keep flammable substances or materials at a safe distance from use of volatile or noxious substances.
• Smoking is prohibited in the work areas in sites designated for the contractor’s use. Designate a space away from the work area be used for smoking. Cigarette butts must be disposed of properly.
• Protection Equipment Required: Furnish a minimum of one extinguisher for each 1,500 square feet of area or major fraction thereof and a sufficient number to meet the requirement that a travel distance from any workstation to the nearest extinguisher shall not exceed 75 feet. Fire extinguisher shall be of type and size appropriate for the work but no less than 10lb.
C.11 EQUIPMENT REQUIREMENTS
A. All equipment/tools shall only be used within the limits of the manufacturer’s recommendations.
B. All tools/machinery/equipment/vehicles shall be safeguarded from the public.
Tools/machinery/equipment/vehicles shall not be left unattended. All tools/equipment shall not be allowed to lie around except in the immediate work area.
C. Any tools not in immediate use shall be staged or stowed in such manner so as not to create a hazard. The government and contractor will agree on delineating the work area around the project.
D. Any damaged caused to NPS property through equipment use shall be restored and/or repair to original conditions at contractor expense.
E. All equipment must meet all federal OSHA, state and local safety requirements and must be properly licensed.
F. The name or logo of the contractor must be clearly displayed on all trucks used on the job.
C.12 SAFETY PLAN
140P4226R0019
The Contractor shall draft and provide a safety plan specific. The Safety Plan shall be available to all employees and subcontractors working on the contract and subsequent task orders. The Safety Plan should cover at a minimum:
a. All requirements stated in C.6 – Safety, especially OSHA 1926 Subpart M – Fall Protection and OSHA 1926 Subpart AA – Confined Space as required.
b. Personal Protective Equipment required for the work under the contract (see C.7)
c. Accident Reporting (see C.8 above)
d. Hot Work Permit Requirements (see C.9)
e. Fire Prevention and Protection (see C.10 above)
f. Equipment use (see C.11)
C.13 DRONES/UNMANNED AERIAL VEHICLE (UAV) USAGE
The use of drones and/or UAVs are not authorized at FRSP during performance of this contract, without specific written approval (refer to Superintendents Compendium noted in C.6 – Safety above).
C.14 TEMPORARY FACILITIES/WORK AREA
A. ACCESS: Access to Water Tower and related buildings will be provided by FRSP COR/POC. All other areas are open to general public.
B. PARKING: Contractor will have access to Parking in the areas at Chancellorsville Water Tower and on Ranger Lane; however, contractor vehicles shall not obstruct NPS Employee Traffic.
C. STORAGE: The NPS will provide on-site material storage and loading of materials, and the contractor shall coordinate with COR/POC. The contractor is responsible for securing all property, from loss, damage, and/or theft. The Government will not be held responsible for any loss, damage, and/or theft of any materials, equipment, etc. used and/or provided in performance of this contract.:
D. RESTROOMS: No private restroom facility is available onsite for the contractor’s use. The contractor will have to provide Port-a-Potties as needed.
If contractor elects to bring in portable toilets, this shall be approved in advance by COR/POC. Additionally:
• Location and placement shall be coordinated by COR/POC and shall be secured when not in use to prevent tipping due to weather and non-weather-related events.
• If the contractor elects to allow public use of portable toilets, excess cleaning, etc. shall be the responsibility of the contractor.
• If the contractor does not…