Sol_140P2024R0181.pdf

PDF 499 KB Posted

Attached to
SEKI 342662 - REMOVE GRANT GROVE RANGER OFFICE DAM
Solicitation number
140P2024R0181
Issued by

About this file

This document is a Solicitation for Invitation for Bid/Request for Proposal (IFB/RFP) for the demolition and removal of a Ranger Station at Sequoia & Kings Canyon National Parks in California. The North American Industry Classification System (NAICS) code is 238910 with a small business size standard of $19M.

The key details are:

  • The estimated magnitude of the project is between $250,000 - $500,000.
  • There will be a mandatory pre-bid meeting on September 4, 2024.
  • Proposals are due by September 20, 2024 at 5:00pm Mountain Time.
  • The project includes demolition of the Ranger Station and site restoration to a buildable condition.
  • Award will be made to the lowest priced, technically acceptable offer.
  • Options for Hazmat Remediation are included.
  • The contract will be a Firm-Fixed Price task order under the BIA Demolition MATOC.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

NPS, DSC Contracting Services Div

12795 W. Alameda Pkwy

P.O. Box 25287 Denver CO 80225-0287

PDS

Mark Barber 721-621-7310

1x 08/27/2024

140P2024R0181

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

SEKI 342662 Demolish Ranger Station, Sequoia & Kings Canyon National Parks, California

a) This acquisition is being conducted via the BIA Demolition MATOC. The North

American Industrial Classification System (NAICS) code and the associated small business size standard are noted in clause 52.204-8 in section "K" of this solicitation.

b) Estimated Magnitude: Between $250,000.00 - $500,000.00

c) on-site prebid meeting to be held at SEKI on Wed 4 Sept 2024, at 09:30am. NPS is requesting attendees to RSVP to Ryan Walker, Maintenance Mech Lead Email: rwalker@nps.gov; Phone: (559) 565-4363 by COB on Tuesday, September 3, 2024.

d) Information and requirements stated in sections "B" through "J" & attachments noted in section "J" apply to this solicitation and the subsequent contract.

e) Refer to section "L" for proposal submittal requirements.

f) This is currently an unfunded requirement with a high expectation that funds will be available. When and if funds become available a contract will be awarded at that time.

Continued ...

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 90 calendar days and complete it within ________________ ________________ calendar days after receiving

09/20/2024

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Mark Barber

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 23

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140P2024R0181

g) Offerors shall submit proposals and questions, and acknowledge solicitation amendments as stated in section "L" of this solicitation

00001 Hazmat Report 1 LS

Product/Service Code: P400

Product/Service Description: SALVAGE- DEMOLITION

OF BUILDINGS

Period of Performance: 10/01/2024 to 12/31/2024

00002 Demolish and removal of Ranger Station 1 LS

Product/Service Code: P400

Product/Service Description: SALVAGE- DEMOLITION

OF BUILDINGS

Period of Performance: 10/01/2024 to 12/31/2024

00003 Hazmat Remediation 1 LS

(Option Line Item)

Anticipated Exercise Date 60

Product/Service Code: P400

Product/Service Description: SALVAGE- DEMOLITION

OF BUILDINGS

Period of Performance: 10/01/2024 to 12/31/2024

CO: Mark A Barber

PM: Andrew Reese

PS: Elisabeth Jackson

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

United States Department of the Interior

NATIONAL PARK SERVICE

DENVER SERVICE CENTER ‐ CONTRACTING SERVICES

12795 WEST ALAMEDA PARKWAY POST OFFICE (P.O.) BOX 25287

DENVER, COLORADO 80225‐0287

Refer to:

D5215 (DSC-CS)

SEKI 342662

January 24, 2024

Reference: Request for Quote, Demolish Non-Historic Structure and Miscellaneous

Debris, SEKI 342662, Sequoia & Kings Canyon National Parks, California

Subject: Request for Quote (RFQ)

Your firm, along with others who have a current Bureau of Indian Affairs contract, awarded under Multiple Award Contract (MAC), Demolition Services, is requested to provide a quote for the demolition services noted in the attached Scope of Services (SOS). The National Park Service (NPS) anticipates selecting a single firm for a firm fixed price task order award, based upon the evaluation criteria noted below. The anticipated Period of Performance for this project is 90 calendar days from the date of task order award.

SECTION B – CONTRACT PRICE SCHEDULE

The National Park Service requires the demolition of a Government-owned structure that is no longer usable or needed by Sequoia & Kings Canyon National Parks (SEKI). The project will also include restoration of the site to a buildable condition compacted and sloped for drainage so that ponding does not occur.

Propose your best prices projects in accordance with the Statement of Work (SOW) and attachments. Price Proposals must be submitted following the price schedule/format herein. Incomplete price proposals will not be considered for award.

Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total corrected amounts govern. Round totals and extended prices to whole dollars. Refer to solicitation section “H” for additional information regarding contract options.

CONTRACT

LINE ITEM

NUMBER

(CLIN)

CONTRACT LINE ITEM

(CLI) TITLE QUANTITY UNIT OF

MEASURE TOTAL PRICE

PMIS 342662 BASE PROPOSAL

1 Hazmat 1 LS

2 Demo Ranger Station 1 LS

TOTAL BASE PRICE PMIS 342662 (CLINs 1 through 2) ------------------------

PMIS 342662 PROPOSAL OPTIONS

3 Proposal option 1: HAZMAT Remediation 1 LS

TOTAL PROPOSAL OPTION PRICE PMIS 342662 (CLIN 3) -----------------

TOTAL BASE AND PROPOSAL OPTIONS PRICE FOR ALL CLINs (CLINs 1 through 3) -------------------------

All measurement and payment information is included in the project specifications and/or SOW.

Miscellaneous Work: The contractor shall not perform any of contingent sum work, until the Contracting Officer issues a contract modification authorizing performance of work in accordance with FAR Clause 52.243- 04, Changes; and subject to availability of funds, FAR Clause 52.232-18, Availability of Funds.

The Contractor shall promptly notify the Contracting Officer, in writing, of subsurface or any physical conditions different from those indicated in this contract or unknown unusual physical conditions at the site before proceeding with the work.

The change orders request shall be forwarded to the Contracting Officer by memorandum outlining the need and a justification for the change order. Upon receipt of a change order request, the Contracting Officer will request a cost proposal from the Contractor. All cost proposals shall be in detail and itemized, showing price breakdown in sufficient detail to permit an analysis of cost for material, labor, equipment, hours, taxes, insurance, bonds, overhead costs, profit, and complete description of work involved in the change order, including any time extension.

In an emergency, a telephone approval may be granted by the Contracting Officer, and immediately the Contractor shall follow through by submitting a written cost proposal to the Contracting Officer. The Contracting Office will issue a contract modification to authorize the work for the "emergency".

SECTION C – STATEMENT OF WORK

See Section J for the Statement of Work.

SECTION D – PACKAGING AND MARKING

A. All shipments of materials, equipment and/or supplies to the project site shall be addressed to the Contractor and not the Government. Preservation, packaging and packing shall be in accordance with standard practices for commercial packaging.

B. Government personnel are not authorized to accept deliveries for the contractor, nor are they responsible for off-loading shipments. A contractor representative must be present to accept deliveries.

SECTION E – INSPECTION AND ACCEPTANCE

E.1. DAILY REPORTING REQUIREMENT

A. The Contractor shall prepare and file a "Contractor's Daily Report", for each day of contract performance. Description must include contract number and work being performed. These reports shall be delivered to, or if directed, mailed to the Contracting Officer’s Representative on Fridays.

The daily report shall include the name of Contractors and Subcontractors on-site, the number of workers and their labor categories employed on-site, the work being performed, the type of equipment on-site, any change order work being performed, and whether the work being performed is on schedule. Reports shall be numbered, dated and signed by the Contractor or his Project Manager. Failure to submit the daily reports could result in payments being withheld until such time as all daily reports are current.

E.2. FINAL INSPECTION

A. Contractor Self-Inspection. Prior to the completion date, the Contractor’s Quality Control

Manager shall conduct a self-inspection of the site and document all items needing correction by means of a punch list. The corrected punch list shall be provided to the Contracting Officer’s Representative at the same time the pre-final inspection is requested. All punch list items must be corrected prior to requesting the pre-final inspection.

B. The Contractor and the Contracting Officer’s Representative will jointly conduct a pre-final inspection prior to requesting a final inspection. Any item needing correction shall be noted on the Pre-Final Inspection Punch List. Any discrepancies noted will be corrected prior to any final inspection. The Contracting Officer Representative may schedule more than one pre-final inspection if he determines it necessary.

C. When the Contractor is ready for final inspection, he will request final inspection in writing to the Contracting Officer and Contracting Officer’s Representative (COR). A copy of the Pre-Final Punch List shall be attached to this request with the corrective action taken noted. The final inspection will be requested at least 48 hours before the desired date.

D. The final inspection shall be performed with the Contractor by the COR, Contracting Officer, Safety Officer, and representatives of the using activity. Any discrepancies noted will be

Coney, Romorno Representatives of the using activity: Should this be clarified to be GOIS Park staff or Park representative in case someone mistakes this to be any public person or visitors?

corrected within the time specified in the contract for the completion of work.

1. Prior to close-out and final payment of the contract, the following are required:

2. All submittals to be submitted as required by the contract and may include product submittals, as-built drawings (completed in AutoCAD), manuals, etc.

3. All warranties; to be submitted with the request for Final Inspection.

4. Contractor’s Release; to be submitted with the Contractor’s final invoice.

SECTION F -- DELIVERIES OR PERFORMANCE

F.1. CONTINUITY OF FACILITIES OPERATION

Schedule work to minimize interference with any on-site housing residents and the facilities normal operations. Notify the Contracting Officer and Project Manager 24 hours in advance of any shutdowns.

Perform all on-site work between the hours of 7:00 AM and 7:00 PM, Monday through Friday (Federal Holidays excluded), unless otherwise approved by the Contracting Officer.

F.2. RECYCLING AND DISPOSAL OF REFUSE

With the exception of materials specifically indicated or specified to be salvaged for reuse in construction/services, or turned over to the Government, all refuse, excess or waste materials resulting from construction/services operations shall become the property of the Contractor and shall be recycled and/or disposed of off Government property. All disposal shall be done in accordance with federal, state, and local laws and regulations.

SECTION G – CONTRACT ADMINISTATION DATA

G.1. 1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment. The government may also employ the services of a construction management representative (CMR), who will be on-site daily to represent the COR in the technical monitoring of the contractor's performance and deliveries.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

Coney, Romorno Here or within the specs, we want to add that final as-built drawing shall be prepared in AutoCad and electronic file submitted with the matching hard copy markups. (Most contractors can easily hire a CAD Tech that can prep the as-builts since we always give them the original AutoCad files to work from.

Coney, Romorno These work hours seems ok. The specs should allow the contractor to request approval to change if needed.

Should we mention the project will have a CMR here or wait until pre-con?

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers having been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph

(d) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph

(d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

SECTION H -- SPECIAL CONTRACT REQUIREMENTS

H.1. WORK OUTSIDE REGULAR WORK HOURS

If the contractor desires to perform work under this contract outside regular work hours or on Saturdays, Sundays or holidays, he shall apply, in writing, to the Contracting Officer no less than 10 calendar days prior to the planned start of such work. Regular work hours are, for the purpose of this clause, those hours the activity or Command where the work is to be performed normally works on a day-by-day basis.

Application by the Contractor does not imply consent by the Government. Each application will be considered, and a decision made, on the potential benefit of permitting such work. Approval of a Contractor's application under this clause will be, unless otherwise agreed in writing, at no additional cost to the Government.

H.2. REQUIRED INSURANCE

The contractor shall procure and maintain insurance for each task order during the entire period of performance consistent with FAR 52.228-5, DIAR 1452.228-70, and FAR 28.307.

H.3 OPTION FOR ADDITIONAL SERVICES—SEPARATELY PRICED LINE ITEMS

The Government may require the delivery of the numbered line items identified in the Schedule as option items at the price stated in the Schedule. The Contracting Officer may unilaterally exercise the option by written notice to the Contractor within 60 days after contract award. Performance of added line-item tasks shall be at the price negotiated in the contract Schedule.

(End of clause)

H.4 WORKING IN FEDERAL BUILDINGS OR FEDERALLY CONTROLED INDOOR

WORKSPACES

In order to take steps to prevent the spread of COVID-19 and to protect the health and safety of all Federal employees, onsite contractors, visitors to Federal buildings or Federally controlled indoor workspaces, and other individuals interacting with the Federal workforce, employees under the subject contract who are required to work on site in Federal buildings or Federally controlled indoor worksites must comply with requirements located at https://www.saferfederalworkforce.gov/overview/.

H.5 MISCELLANEOUS WORKS:

The contractor shall not perform any of contingent sum work, until the Contracting Officer issues a contract modification authorizing performance of work in accordance with FAR 52.243-4 Changes; and subject to availability of funds, FAR Clause 52.232-18, Availability of Funds.

The Contractor shall promptly notify the Contracting Officer, in writing, of subsurface or any physical conditions different from those indicated in this contract or unknown unusual physical conditions at the site before proceeding with the work.

The change orders request shall be forwarded to the Contracting Officer by memorandum outlining the need and a justification for the change order. Upon receipt of a change order request, the Contracting Officer will request a cost proposal from the Contractor. All cost proposals shall be in detail and itemized, showing price breakdown in sufficient detail to permit an analysis of cost for material, labor, equipment, hours, taxes, insurance, bonds, overhead costs, profit, and complete description of work involved in the change order, including any time extension.

In an emergency, a telephone approval may be granted by the Contracting Officer, and immediately the Contractor shall follow through by submitting a written cost proposal to the Contracting Officer. The Contracting Office will issue a contract modification to authorize the work for the "emergency".

H.6 KEY PERSONNEL

The Contractor shall assign the following key personnel.

Project Manager: ________ Job-site Superintendent:

Quality Control Manager:

Safety Manager/Officer:

http://www.saferfederalworkforce.gov/overview/

During the first 60 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 60-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.

H.7 KEY SUBCONTRACTORS

(a) The Contractor shall identify firms that will perform the following work under this contract. If Key

Subcontractors will be self-performed, note “self-performed” in the appropriate trade; otherwise provide the name(s) of assigned subcontractors.

Demolition Subcontractor:________________________________

(b) The assignments above are permanent for the contract duration. The Contractor shall make no substitutions of the above listed Key Trade assignments unless the substitution is approved or directed by the Contracting Officer. The Contractor shall send requests for substitutions to the Contracting Officer a minimum of 15 calendar days prior to any substitution and provide the information required by paragraph c below.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete qualification statements for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes shall have comparable qualifications to the firm being replaced. The Contracting Officer will approve or deny substitution requests within 15 calendar days after receipt of all required information. This clause will be modified to reflect any approved changes.

H.8 LIABILITY INSURANCE

1452.228‐70 Liability Insurance. (JUL 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$______each person* $______each occurrence* $______property damage*

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

*Refer to page 13 MATOC contract 140A1621D0015 for amounts

SECTION I – CONTRACT CLAUSES

See base IDIQ contract for list of contract clauses. It is important to note that the Service Contract Act (FAR 52.222-41- Service Contract Labor Standards (Aug 2018)) is applicable to this task order.

SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

ATTACHMENT TITLE OF DOCUMENT OR FORM PAGES

0 Statement of Work/Program of Requirements 19

1 Appendix A – Building Demo Location Maps 11

2 Appendix B – Photos 2

3 Appendix C – General Management Summary 69

4 Appendix F-Vehicle Inspection Location Map 2

5 Appendix G- Building Floor Plan 1

6 Appendix H – Map of Utilities 1

7 Appendix I – Letter of Compliance Completion - PEPC 6

8 SCA Wage Rates 11

9 Proposal Submission Package 7

SECTION K – REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF

BIDDERS

52.204-8 Annual Representations and Certifications (MAR 2023)

(a)

(1) The North American Industry Classification System (NAICS) code for this acquisition is____238910______________

(2) The small business size standard is ___19M__________.

(3) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519 if the acquisition—

(i) Is set aside for small business and has a value above the simplified acquisition threshold;

(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or

(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(b)

(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

(i) □ Paragraph (d) applies.

(ii) □ Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)

(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless–

(A) The acquisition is to be made under the simplified acquisition procedures in part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or https://www.acquisition.gov/far/part-52#FAR_52_204_7 https://www.acquisition.gov/far/part-52#FAR_52_204_7 https://www.acquisition.gov/far/part-52#FAR_52_203_2 https://www.acquisition.gov/far/part-13#FAR_Part_13

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions.

This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that-

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.204-26, Covered Telecommunications Equipment or Services-Representation. This provision applies to all solicitations.

(vii) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations-Representation.

(viii) 52.209-5, CertificationRegarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(ix) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. This provision applies to all solicitations.

(x) 52.214-14, Place of Performance-Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(xi) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xii) 52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.

(C) The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS code assigned.

https://www.acquisition.gov/far/part-52#FAR_52_203_11 https://www.acquisition.gov/far/part-52#FAR_52_203_18 https://www.acquisition.gov/far/part-52#FAR_52_204_3 https://www.acquisition.gov/far/part-52#FAR_52_204_7 https://www.acquisition.gov/far/part-52#FAR_52_204_5 https://www.acquisition.gov/far/part-52#FAR_52_204_26 https://www.acquisition.gov/far/part-52#FAR_52_209_2 https://www.acquisition.gov/far/part-52#FAR_52_209_5 https://www.acquisition.gov/far/part-52#FAR_52_209_11 https://www.acquisition.gov/far/part-52#FAR_52_214_14 https://www.acquisition.gov/far/part-52#FAR_52_215_6 https://www.acquisition.gov/far/part-52#FAR_52_219_1 https://www.acquisition.gov/far/part-19#FAR_Part_19 https://www.acquisition.gov/far/part-19#FAR_19_000

(xiii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract is for supplies to be delivered or services to be performed in the United States or its outlying areas, or when the contracting officer has applied part 19 in accordance with 19.000(b)(1)(ii).

(xiv) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xvi) 52.222-38, Compliance with Veterans’ Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial products or commercial services.

(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA–designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA–designated items.

(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals-Representation. This provision applies to solicitations that include the clause at 52.204-7.)

(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225- 1.

(xxi) 52.225-4, Buy American-Free Trade Agreements-Israeli Trade Act Certificate. (Basic, Alternates II and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $50,000, the basic provision applies.

(B) If the acquisition value is $50,000 or more but is less than $92,319, the provision with its Alternate II applies.

(C) If the acquisition value is $92,319 or more but is less than $100,000, the provision with its Alternate III applies.

(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan-Certification. This provision applies to all solicitations.

(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications. This provision applies to all solicitations.

(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation. This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

https://www.acquisition.gov/far/part-52#FAR_52_219_2 https://www.acquisition.gov/far/part-19#FAR_Part_19 https://www.acquisition.gov/far/part-19#FAR_19_000 https://www.acquisition.gov/far/part-52#FAR_52_222_22 https://www.acquisition.gov/far/part-52#FAR_52_222_26 https://www.acquisition.gov/far/part-52#FAR_52_222_25 https://www.acquisition.gov/far/part-52#FAR_52_222_26 https://www.acquisition.gov/far/part-52#FAR_52_222_38 https://www.acquisition.gov/far/part-52#FAR_52_223_1 https://www.acquisition.gov/far/part-52#FAR_52_223_2 https://www.acquisition.gov/far/part-52#FAR_52_223_4 https://www.acquisition.gov/far/part-52#FAR_52_223_22 https://www.acquisition.gov/far/part-52#FAR_52_204_7 https://www.acquisition.gov/far/part-52#FAR_52_225_2 https://www.acquisition.gov/far/part-52#FAR_52_225_1 https://www.acquisition.gov/far/part-52#FAR_52_225_1 https://www.acquisition.gov/far/part-52#FAR_52_225_4 https://www.acquisition.gov/far/part-52#FAR_52_225_3 https://www.acquisition.gov/far/part-52#FAR_52_225_6 https://www.acquisition.gov/far/part-52#FAR_52_225_5 https://www.acquisition.gov/far/part-52#FAR_52_225_20 https://www.acquisition.gov/far/part-52#FAR_52_225_25 https://www.acquisition.gov/far/part-52#FAR_52_226_2

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[Contracting Officer check as appropriate.]

__ (i) 52.204-17, Ownership or Control of Offeror.

__ (ii) 52.204-20, Predecessor of Offeror.

__ (iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

__ (iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment- Certification.

__ (v) 52.222-52, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services-Certification.

__ (vi) 52.223-9, with its Alternate I, Estimate of Percentage of Recovered Material Content for EPA– Designated Products (Alternate I only).

__ (vii) 52.227-6, Royalty Information.

__ (A) Basic.

__ (B) Alternate I.

__ (viii) 52.227-15, Representation of Limited Rights Data and Restricted Computer Software.

(d) The offeror has completed the annual representations and certifications electronically in SAM website accessed through https://www.sam.gov. After reviewing the SAM information, the offeror verifies by submission of the offer that the representations and certifications currently posted electronically that apply to this solicitation as indicated in paragraph (c) of this provision have been entered or updated within the last 12 months, are current, accurate, complete, and applicable to this solicitation (including the business size standard applicable to the NAICS code referenced for this solicitation), as of the date of this offer and are incorporated in this offer by reference (see FAR 4.1201); except for the changes identified below [offeror to insert changes, identifying change by clause number, title, date]. These amended representation(s) and/or certification(s) are also incorporated in this offer and are current, accurate, and complete as of the date of this offer.

FAR Clause # Title Date Change

Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.

(End of provision)

Alternate I (MAR 2023). As prescribed in 4.1202 (a), substitute the following paragraph (a) for paragraph (a) of the basic provision:

https://www.acquisition.gov/far/part-52#FAR_52_204_17 https://www.acquisition.gov/far/part-52#FAR_52_204_20 https://www.acquisition.gov/far/part-52#FAR_52_222_18 https://www.acquisition.gov/far/part-52#FAR_52_222_48 https://www.acquisition.gov/far/part-52#FAR_52_222_52 https://www.acquisition.gov/far/part-52#FAR_52_223_9 https://www.acquisition.gov/far/part-52#FAR_52_227_6 https://www.acquisition.gov/far/part-52#FAR_52_227_15 https://www.sam.gov/ https://www.acquisition.gov/far/part-4#FAR_4_1201 https://www.acquisition.gov/far/part-4#FAR_4_1202

(a)(1) The North American Industry Classification System (NAICS) codes and corresponding size standards for this acquisition are as follows; the categories or portions these NAICS codes are assigned to are specified elsewhere in the solicitation:

[Contracting Officer to insert NAICS codes and size standards].

(2) The small business size standard for a concern that submits an offer, other than on a construction or service acquisition, but proposes to furnish an end item that it did not itself manufacture, process, or produce, (i.e., nonmanufacturer), is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—

(i) Is set aside for small business and has a value above the simplified acquisition threshold;

(ii) Uses the HUBZone price evaluation preference regardless of dollar value, unless the offeror waives the price evaluation preference; or

(iii) Is an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

A. GENERAL

1. Submit, at a minimum, an offer that conforms to the solicitation documents. By submission of an offer, the offeror unconditionally assents to the terms and conditions in this solicitation and in any solicitation attachments. Proposals offering alternative stipulations to the requirements of this solicitation will NOT be considered or accepted.

2. In accordance with FAR 36.209, all firms, prime contractors or subconsultants, involved in developing the design or specifications for this demolition solicitation are not eligible and prohibited from receiving any part of this award. Proposals from or containing firms under these circumstances will not be considered for award.

B. QUESTIONS

Pre-proposal questions shall be submitted a minimum of 14 days prior to the due date and time for proposals. Submit questions only though email to the following:

Contracting Officer, Mark A Barber mark_barber@nps.gov

C. OFFER DUE DATE AND LOCATION

1. To be considered for award, proposals must be received no later than the date and time noted in Block 13.a of the SF1442 contained in this solicitation. Offerors are responsible for confirming their proposals are received by the due date and time.

mailto:mark_barber@nps.gov

D. SUBMISSION REQUIREMENTS

1. Proposals shall be submitted via email. Proposals submitted via any means other than email shall not be accepted.

2. Proposals shall be sent to both of the following:

a. Contracting Officer, Mark Barber Mark_Barber@nps.gov

3. Title subject line for all proposal submissions shall contain the solicitation number, Park- PMIS, and number of total emails, per the following example:

Subj: 140P2024R0181, SEKI 342662, email 1 of 3

4. Submit proposals in separate VOLUMES (I and II) in the FORMATS specified, containing CONTENTS required. Each volume shall be submitted in separate email attachments.

5. Size limits:

a. Individual email attachments shall be no larger than 10 MB.

b. Each email shall be no larger than 38 MB

6. Offerors shall verify receipt of proposals.

E. VOLUME I, TECHNICAL PROPOSAL – FORMAT, ORGANIZATION, CONTENTS

1. FORMAT: Submit (1) one electronic copy. No hard copies shall be submitted.

ORGANIZATION: Include folders and files for electronic formats named as follows:

FACTOR 1 – PROJECT EXPERIENCE

FACTOR 2 – TECHNICAL APPROACH

FACTOR 3 – SCHEDULE

FACTOR 4 – KEY PERSONNEL

2. CONTENTS:

FACTOR 1 – PROJECT EXPERIENCE Submit the attached "Project Experience" form addressing the specific aspects below for up to 1 relevant project completed in the last 7 years. Key Subcontractors, if evaluated, are subject to substitution requirements in Section H of this solicitation and resulting contract.

• Key Subcontractors: Describe experience and capability for the following Key Subcontractors identified in Section H of this solicitation and listed below. Indicate whether or not you have previously worked with these firms on previous projects. All firms proposed here are subject to substitution requirements contained in this solicitation. If all demolition work will be completed in-house, please indicate this.

• List Key Subcontractors: Demolition Subcontractor

FACTOR 2 – TECHNICAL APPROACH

Technical approach is your means and methods to complete a technical aspect of required work in this solicitation. Submit a written narrative limited to 8 pages describing your technical approach for the specific ASPECTS below. Pictures can be included and will count towards the page limitation. There is no preprinted form for this submittal.

mailto:Mark_Barber@nps.gov

• Logistics, Coordination, Process: Submit a project-specific written detailed technical approach for performing this demolition project. Address the successful execution of the project while protecting the park's resources, maintaining park and partner operations, coordinating with archeological monitors (if applicable). Consider any unique considerations relating to project scope, and creative and innovative ideas to execute the project in an expeditious manner while managing and minimizing negative impacts of technical risks such as unforeseen conditions.

Demonstrate clear understanding of the project scope, seasonal considerations and project site conditions and offer realistic strategies and methods for addressing the overall project scope.

Include a brief schedule narrative describing the phasing/sequencing of the project and showing how it can be completed within the required contract period of performance.

FACTOR 3 – SCHEDULE

Submit your proposed schedule for THIS SPECIFIC PROJECT showing completion within the required period of performance contained in this solicitation with accompanying schedule narrative. Assume a Notice to Proceed date of 1 October 2024. Schedules can be submitted in any format, Gantt Chart is not required. There is no preprinted form for this submittal.

FACTOR 4 – KEY PERSONNEL

Submit resumes for key personnel as identified in this solicitation at Section H and listed below. All personnel proposed are subject to substitution requirements contained in this solicitation. There is no preprinted form for this submittal. Limit resumes to two pages per key personnel.

List of Key Personnel: Project Manager, Job-Site Superintendent(s), Safety Officer, Quality Control Manager.

End of Volume 1 – Technical Proposal Requirements.

F. VOLUME II, BUSINESS AND PRICE PROPOSAL – FORMAT, ORGANIZATION,

CONTENTS

1. FORMAT: Submit (1) one electronic copy. No hard copies shall be submitted.

2. CONTENTS:

SF1442: Standard Form 1442, Solicitation, Offer, and Award: Complete blocks 14 through 20C only. An official having the authority to contractually bind the offeror's company must sign the SF 1442 in accordance with the procedures prescribed in FAR 4.102.

AMENDMENTS: DO NOT acknowledgement amendments through FedConnect. Acknowledge all solicitation amendments using one of the methods set forth in Block 11 of Standard Form 30.

SECTION B CONTRACT PRICE SCHEDULE: Enter the proposed dollar amount for each line item in the Price Schedule, including any optional items, if applicable.

SECTION K REPRESENTATIONS AND CERTIFICATIONS: Submit a completed copy of provision

52.204-8 shown in section “K” of this solicitation. Complete all required representations and certifications if they are not available at www.SAM.gov. Your firm must maintain current, active registration at www.SAM.gov to be eligible for award and you are encouraged to complete SAM registration before submitting your offer.

GENERAL REFERENCES: Complete and submit the attached "General References," form. Information will be used in determining Responsibility pursuant to FAR 9.103.

End of Volume II – Business and Price Proposal requirements.

FAR 52.216-32 Task-Order and Delivery-Order Ombudsman (SEPTEMBER 2019)

a. In accordance with 41 U.S.C. 4106(g), the Agency has designated the following task-order and delivery-order Ombudsman for this contract. The Ombudsman must review complaints from the Contractor concerning all task-order and delivery-order actions for this contract and ensure the Contractor is afforded a fair opportunity for consideration in the award of orders, consistent with the procedures in the contract.

b. Consulting an ombudsman does not alter or postpone the timeline for any other process (e.g., protests).

c. Before consulting with the Ombudsman, the Contractor is encouraged to first address complaints with the Contracting Officer for resolution. When requested by the Contractor, the Ombudsman may keep the identity of the concerned party or entity confidential, unless prohibited by law or agency procedure.

d. Contracts used by multiple agencies.

(1) This is a contract that is used by multiple agencies. Complaints from Contractors concerning orders placed under contracts used by multiple agencies are primarily reviewed by the task-order and delivery-order Ombudsman for the ordering activity.

(2) The ordering activity has designated the following task-order and delivery-order Ombudsman for this order:

Chief of Contracting, Contracting Services

U.S Department of the Interior, National Park Service – Denver Service Center 12795 W.

Alameda Parkway Lakewood, CO 80228 Shannon_blackburn@nps.gov

(3) Before consulting with the task-order and delivery-order Ombudsman for the ordering activity, the

Contractor is encouraged to first address complaints with the ordering activity's Contracting Officer for resolution. When requested by the Contractor, the task-order and delivery-order Ombudsman for the ordering activity may keep the identity of the concerned party or entity confidential, unless prohibited by law or agency procedure.

http://www.sam.gov/ http://www.sam.gov/ mailto:Shannon_blackburn@nps.gov

SECTION M – EVALUATION FACTORS FOR AWARD

A. BASIS FOR AWARD

1. The Government is conducting this procurement pursuant to the Fair Opportunity guidelines in FAR 16.505, and ordering procedures described in the MATOC.