B08_Attach_0_SOS_Demo_GG_Ranger_Office_SEKI__Bldg_Rev.pdf

PDF 307 KB Posted

Attached to
SEKI 342662 - REMOVE GRANT GROVE RANGER OFFICE DAM
Solicitation number
140P2024R0181
Issued by

About this file

This document is a Statement of Work (SOW) for the demolition of a government-owned structure, known as the Grant Grove Ranger Office, located at Sequoia & Kings Canyon National Parks (SEKI) in California. The key objectives are to complete a hazardous materials assessment, demolish the 2,000 square foot building and associated site improvements, and restore the site to a buildable condition with proper drainage.

The work will be delivered using the Bureau of Indian Affairs (BIA) Demolition Services Multiple Award Contract (Demo MAC). The contractor will be responsible for all planning, programming, administration, coordination, and management necessary to provide the work, which includes hazardous materials abatement, demolition and disposal, utility decommissioning, and site restoration. The project must be completed within 90 calendar days of task order award. Specified deliverables include a Hazardous Materials Assessment Report, Demolition Plan, Waste Management Plan, Accident Prevention Plan, and Utilities Identification and Removal/Decommissioning Plan.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROGRAM OF REQUIREMENTS (STATEMENT OF WORK)

Sequoia & Kings Canyon National Parks, California

REMOVE GRANT GROVE RANGER OFFICE DAMAGED IN WINTER STORM

PMIS 342662

August 26, 2024

I. INTRODUCTION

The National Park Service requires the demolition of a Government-owned structure that is no longer usable or needed by Sequoia & Kings Canyon National Parks (SEKI). The project will also include restoration of the site to a buildable condition compacted and sloped for drainage so that ponding does not occur.

In 2022, a high wind event toppled a 3-foot diameter tree onto the 2000 SF Building #1698 located at 83726 Lower Loop Road in the Grant Grove Residential Neighborhood. Although this was built as a residential building in 1988, it was being used as a Ranger Operations Building at the time of its destruction. This project will resolve numerous safety and health hazards associated with the abandoned building as well as prepare the site for a new prototype housing building for use by Park staff.

This Statement of Work (SOW) outlines the contracted work necessary for this project.

II. OBJECTIVES

1. The objective of this project is to complete the following:

i. Assessment of hazardous materials - Hazardous material survey (physical assessment and testing)

ii. Demolition and disposal of structure and accompanying site improvements to be outside of the park, including:

a) Abate hazardous materials, if necessary. Asbestos pipe insulation removal has been completed by the Park. Pex was installed and lead and copper were removed from the plumbing. No reports of lead paint.

b) Remove large tree that has fallen on the building, including the root ball and any exposed roots. Backfill, regrade to provide positive drainage, and restore site to a drainable condition with no ponding.

c) Demolish and dispose of entire building and all its components.

d) Remove and dispose of all appliances, furniture, and other items in or on the building.

e) Remove and dispose of concrete stem walls and footings, interior concrete footings, garage slab, concrete steps, and sidewalks.

f) Remove all pavement associated with the building (if any) and other permanent fixtures serving the buildings (if any), unless otherwise noted.

g) Remove all electrical panels, conduit, and wiring, water and sewer fixtures, piping, valves, and all other fixtures and utilities.

h) Disconnect, cut, cap, and abandon utility lines a minimum of one foot below grade to the nearest connection point or source.

i) Restore site to return to the natural contour. Slope to drain at minimum 4% to nearest existing drainage feature/area, and grade to prevent water ponding. Restoration includes reseeding. Re-seed disturbed sites as soon as possible following demolition activities and put down a layer of pine/conifer needles on top of the seed, no deeper than 2 inches. All seeding and mulch shall be certified weed free. Any imported material shall be shipped directly from the source to Sequoia Kings Canyon National Park without intermediary storage or staging. See other mitigations related to prevention of introducing non-native seed. See Appendix I – Letter of Compliance Completion - for compliance stipulations concerning seeding, erosion, mulching, etc.

III. SCOPE

1. This project will be delivered using the Bureau of Indian Affairs (BIA) Demolition Services Multiple Award Contract (Demo MAC). The Contractor shall furnish all materials, equipment, and personnel necessary to manage and accomplish the work. The Contractor shall provide licensed technical support and supervision, and project management to assure quality, accuracy of estimates, and timely completion of the project according to delivery requirements. The Government will rely on the Contractor's expertise in recognizing and addressing problematic issues and successful execution of each Task Order. It is the Government's clear expectation that projects executed against this contract shall exhibit superior quality, responsiveness, and customer service. The Contractor must follow the specifications presented in BIA Demo MAC Indefinite Delivery Indefinite Quantity (IDIQ) Statement of Work (SOW) unless noted otherwise in this document.

2. In case of conflict between this task order and the DSC DB Workflows website, this task order shall take precedence and shall be used in lieu of conflicting portions.

3. The contractor remains fully responsible for determining if the standards or provisions cited on the DSC DB Workflows website have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer’s Representative (COR).

4. The Contractor's work responsibility shall include all contractor planning, programming, administration, coordination, and management necessary to provide all work as specified. The work shall be conducted by the Contractor in strict accordance with the contract and all applicable Federal, State, and local laws, regulations, codes, or directives. The Contractor shall ensure that all work provided meets or exceeds critical reliability rates or tolerances specified or included in applicable documents. The Contractor shall provide related services such as pre-award project development, project management, quality control (QC), preparation, review, and submission of required deliverables, environmental permits, along with other administrative work required to satisfy the requirements specified under this contract.

5. The following general work requirements shall also apply:

i. Field verify all existing conditions, utilities, dimensions, and clearances impacted by the work.

ii. Notify the COR of any changes to the scope or deviations from what is presented, or other conditions encountered.

iii. The Contractor is responsible to determine access for the site/structure. Submit a plan to the COR for review and approval 30 days prior to mobilization.

iv. The Contractor is responsible to determine staging areas. If staging is within Park boundaries submit location to the COR for approval.

v. The Contractor work shall be confined to the Project Areas denoted on the maps in the appendices. The project areas are also considered the limits of disturbance.

Limits of work are typically 5’ offset from the structure and any pavement, trees, or other features to be removed, unless otherwise authorized by COR. Contractor shall verify LOW in field with NPS prior to demolition.

vi. Coordinate work with applicable codes and local requirements.

vii. The Contractor shall provide all labor and materials required to complete the work

– refer to Part IV, Task Identification.

viii. The Contractor shall carefully review the attached appendix labelled, “Letter of

Compliance Completion” and comply with all stipulations in the letter.

ix. The Contractor shall contact appropriate underground dig markers prior to commencing demolition work.

i. All waste materials shall be removed and disposed of in a manner as specified by Federal, State, and local regulations. Waste receipts, manifests, and final report shall be provided to the COR. Hazardous materials shall require a hazardous waste manifest completed with descriptions and quantities at the time of pickup and the signed at the licensed hazardous materials facility.

Transportation of hazardous materials shall be performed by a licensed hazardous materials transport contractor.

ii. The work will be accepted and completed at one final inspection. One week minimum request for final inspection is required.

iii. The project is in a residential neighborhood with a playground directly across the street. Workdays and hours shall be 7:00am to 7:00pm Monday – Friday.

No weekend or holiday work will be allowed. Avoid equipment use associated with high decibel noise generation before 9:00AM as the work occurs within a residential area. Safety fencing shall be required and protection of the residents, including small children, and public shall be a primary concern. Submit safety plan to COR for review by park safety officer.

No work shall begin until safety plan is approved.

IV. TASK IDENTIFICATION

The table below summarizes the site included in this task order. Quantities listed below are approximate and shall be verified by the Contractor. See other sections of this Statement of Work for additional requirements. Payment for this project should be in accordance with the Contract Price Schedule.

NOTE: No work may proceed without approval by the Contracting Officer (CO).

Facility Management Software System = FMSS

FMSS

FMSS Name Year

Built Appendix Notes Possible HAZMAT**

67111 Grant Grove Quarters #1698 83726 Lower Loop Road

1988 A, B, G Remove one-story wood siding with metal roof single-family residence (approx. 2000 sq. ft.), Remove foundation(s) and slabs in their entirety add weed free, park approved fill material, compacted to 95%, and grade at -4% to ensure drainage and lack of ponding. and mark all existing utilities, including existing sewer water, electric, and telecon and IT, and telephone. Remove all concrete and asphalt pavement associated with this building (if any).

Remove large tree that has fallen on the building back to and including roots that are above ground.

Archeological and natural resource monitoring will be required and provided by the Park and will need to be coordinated 2 weeks prior to start of demolition.

The Park installed pex piping and removed the lead and copper from the plumbing, it was the most “modern” of the mission 66 houses.

There are no reports of lead in the paint and has modern kitchen cabinets, so no abatement has been required. There are no tests, samples or surveys available.

Contractor shall be responsible for HAZMAT verification.

*The provided building information and utility location in the appendices should be considered approximate; where provided, dimensions are rounded, and square footages are approximate. Actual conditions may differ slightly, field verify as needed.

** The provided HAZMAT information is for contractor’s awareness only. The contractor is responsible to conduct a HAZMAT study to confirm the current conditions.

CLIN 0001

1. Task #1 Hazardous Materials Assessment and Report

General This element of work shall consist of the performance of a hazardous materials assessment and the preparation of a Hazardous Materials Assessment Report. Documents shall be prepared using the English System of Weights and Measurements.

Work performed shall comply with applicable laws, regulations and NPS policies and guidelines.

Hazardous Materials Assessment The hazardous material assessment is to be completed for the Grant Grove Quarters 1698. The primary concern is the existence of asbestos containing materials (ACM) relative to the demolition of the building. Lead within the building, mold, fluorescent light tubes, mercury light switches, and bio-hazards are also potential hazardous materials that must be considered. The scope of work will include:

A. Conduct a reconnaissance of all areas to identify potential asbestos-containing materials (ACM) and obtain representative samples of these materials. Any area may have ACM and not accessible should be reported as Assumed ACMs according to OSHA. The inspection of asbestos should be conducted pursuant to the requirements of AHERA (40 CFR Part 763, Subpart E).

B. Sampling should be conducted according to EPA's Guidance for Controlling Asbestos-Containing Material in Building, including the following:

• Collect at least three bulk samples for each homogeneous area of suspect asbestos containing material.

• The test, evaluation and sample collection shall be conducted by a State accredited inspector.

• Collect at least one Quality Control (QC) sample of each material that may include asbestos or lead or 1 QC sample per 20 samples, whichever is larger.

• Destructive sampling techniques may be used.

C. Laboratory analyses for the presence of asbestiform minerals utilizing Polarized Light Microscopy (PLM) coupled with Dispersion Staining as detailed in the EPA's "Interim Method for the Determination of Asbestos in Bulk Insulation Samples" (EPA 40 CFR 763, Subpart F, Appendix A). The analytical procedures for determining the percent of asbestos in bulk samples to permit the use of visual area estimation shall also follow the "National Emission Standard for Hazardous Air Pollutants" (NESHAP) regulations (40 CFR Part 61, dated November 20, 1990).

This item shall be paid based on actual number of tests performed on a Not-To- Exceed basis.

D. List and identify any other hazardous materials, including lead, mold, fluorescent light tubes, mercury, and bio-hazards that may be found during the inspection.

Hazardous Material Assessment Report:

The hazardous materials investigation report shall present appropriate project information, method of analysis utilized, and a summary of those samples/tests found to contain hazardous materials. The asbestos-containing materials shall be detailed with information concerning content, type, location, and estimated quantity. The asbestos containing materials shall be identified and located on drawings and attached to the report. ACM documentation to include photographic documentation of sample/test areas and unique friable and non-friable material conditions for asbestos.

The report shall include recommendations to control or eliminate potential exposure from each of the hazardous materials that were documented, characterize the waste stream for the abated material, and include applicable state and federal regulations and laws to be followed in removing and disposing of the hazardous materials.

CLIN 0002

2. Task #2 Building Demolition A. Removal to one foot below grade add weed free, park approved fill material, compacted to 95%, and graded at -4% to ensure drainage and lack of ponding. The methods and procedures of demolition and site clearance shall be in full compliance with all applicable Federal, State, and Local laws and regulations and appendices with this document.

B. HAZMAT remediation shall be complete prior to initiating demolition activities.

C. Prepare a Demolition Plan and submit proposed salvage, demolition, deconstruction, and removal procedures for approval before work is started. Append tracking forms for all removed materials indicating type, quantities, condition, destination, and end use. Coordinate with Waste Management Plan in Part VII, Section 1 below. Provide procedures for safe conduct of the work in accordance with ANSI/ASSP A10.6. Plan must be approved by Contracting Officer prior to work beginning. Demolition Plan shall include, but not be limited to, the following:

a) Contractor’s proposed staging and site access routes.

b) Removal of large tree with associated above ground roots, and backfill, compaction, and grading to restore site and provide positive drainage.

Demolition and disposal of noted structures and foundations, foundations, flatwork, sidewalks, and other permanent infrastructure and fixtures. A detailed description of methods and equipment to be used for each operation and of the sequence of operations.

c) Disconnect, cut, cap, and abandon all utilities serving the noted structure at the original point of connection to the main service line. Contractor shall verify location of utilities. A private utility locating service may be needed.

Provide a disconnection schedule of utility services. Coordinate with Part

VII, Section 6 Utility Identification and Removal/Decommissioning Plan below.

d) Identify components and materials to be salvaged for reuse or recycling.

Refer to Part VII, Section1 Waste Management below.

e) Restoration of site topography to match existing grading. Site shall be prepped and left in buildable condition, ready to receive a new prototype housing structure. All safety hazards shall be removed from site.

f) Abate, demolish, and dispose of building at licensed landfills. Provide landfill receipts and completed hazardous materials manifests. Final scope shall be part of the Contractor submittal and will be reviewed by the COR.

Scope shall include, but not be limited to, the following:

i. Provide a Level 1 & Level 2 hazardous materials study/survey.

D. Site restoration:

iv. Cap existing utilities one foot below grade. Mark locations with a metal post labeled with utility type, line size, type, and elevation. Test water lines for leakage. Including fill and compaction to 95% of weed free, park approved fill material, compacted to 95%, and graded at -4% to ensure drainage and lack of ponding, and protected with park approved pine mulch. Compaction testing reports shall be provided to the COR. The area to be restored

a) The area to be restored must be filled and compacted to 95% with certified weed free, park approved fill material, compacted to 95%, and graded at - 4% to ensure drainage and lack of ponding, and protected with certified weed free park approved pine mulch.. Final grades will conform to the natural contours of adjacent areas and must not pond water.

b) Restoration of site topography. Including fill and compaction to 95% of weed free, park approved fill material, compacted to 95%, and graded at -4% to ensure drainage and lack of ponding, and protected with pine needle mulch per Appendix I. Compaction testing reports shall be provided to the COR.

c) Seeding area must be certified weed free, free of debris piles, other organic mater and gullies, and rocks larger than 3-inches in length.

d) Seeding areas must be scarified to a minimum depth 3-inches and maximum depth of 4-inches.

e) The seedbed must be approved by the COR prior to seeding.

V. GENERAL NOTES:

1. A project schedule shall be provided to the COR for approval at least two weeks prior to start date. No work shall occur until the schedule has been approved.

2. Archeological monitoring – An NPS-provided archeologist must be present during excavations / earth disturbance (as NPS determines necessary) and the contractor must coordinate with the archeologist a minimum of 2 weeks prior to the NTP/start of demolition work to ensure that schedules can be aligned.

3. Care will be taken not to disturb any wildlife species (reptiles, migratory birds, raptors, bats, etc.) found nesting, hibernating, estivating, or otherwise living in, or immediately nearby, worksites. See Appendix I.

4. No additional fees will be paid for Project extension if the Contractor does not complete the Project before the LOP - Limiting Operational Period for any wildlife. Contractor to carefully review the Letter of Compliance Completion in Appendix for the dates of LOP for Wildlife.

5. All equipment shall be free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Equipment must be inspected by park resources staff for weeds, including invasive plants, soil, and other debris prior to park entry. A one-week notification is required. Equipment will also be inspected for any stage of Spotted Lantern Flies (SLF). All stages of living insects or egg masses must be removed and disposed of off-site. Inspections shall occur between 8:00 am and 4:00 pm Monday through Friday, excluding holidays. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area. Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required. Equipment inspection must be coordinated with COR and park staff at least one week in advance with proposed entry location, day, and time. See Appendix F – Vehicle Inspection Map.

6. Contractor shall carefully review and comply with all compliance stipulations as outlined in Appendix I – Letter of Compliance Completion.

7. To protect trees that will remain on site, install tree protection fencing around the drip line of all large-diameter trees to be preserved. Any tree to remain in place damaged by Contractor operations shall be replaced at no additional cost to the government. Protect tree root systems from soil compaction by avoiding driving and stockpiling materials atop tree roots (i.e., within the drip line of the tree) to the extent possible. All tree protection fencing shall be installed to the satisfaction of the COR. Do not cut tree roots greater than 2” in diameter without approval of park resources staff.

VI. TIME FRAMES AND DELIVERABLES

1. The project shall be completed within 90 calendar days of task order award. Please note that no Notice to Proceed will be associated with this service task order. Issuance of the task order begins the period of performance.

2. The period of performance stated herein includes time allocated for submittal reviews and contractor performance. The contractor is wholly responsible for managing the period of performance.

3. Complete a “Pre-demolition Checklist” for all structures and submit to CO at least 30 days prior to beginning demolition. Provide minimum 2 weeks notices before demolishing any structure as some sites have sensitive resources and will require archeological monitoring. NPS will provide archeological monitoring.

VII. DEMOLITION REQUIREMENTS

1. Waste Management Plan: Prior to scheduled Predemolition meeting, Contractor shall submit draft Waste Management Plan to COR for approval. Develop and implement according to ASTM E1609 and as required in contract documents. Plan shall include, but not be limited to:

a) List of recycling facilities, reuse facilities, municipal solid waste landfills, and other disposal area(s) to be used. Include name, location, and phone number.

b) List of proposed materials to be reused or recycled. Government goal is to salvage and recycle as much nonhazardous demolition waste as possible.

c) List of materials that cannot be recycled or reused with explanation or justification.

d) Storage and collection methods of waste and recyclables, handling procedures, and means of keeping recyclables free of contamination.

e) Describe means of transporting recyclable materials and estimate frequency of emptying bins.

f) Identity person or persons responsible for ensuring project recycling goals are achieved.

g) Revise and resubmit Plan per COR. Approval of Contractor’s Plan does not relieve the Contractor of complying with applicable environmental regulations.

h) Submit the following with each progress payment:

• An updated NPS waste management plan worksheet (See form Appendix

K).

• Records for donations and all waste manifests.

2. Soil Erosion Plan: Protect against erosion and topsoil depletion through the use of acceptable temporary erosion and sediment control measures as defined by local, state and federal regulations. National Park Service (NPS) Standards and Guidelines require water quality be protected to ensure compliance with Organic Act. Contractor shall prepare an Under-An-Acre Pollution Prevention Plan (UPPP) for each project resulting in less than 1 acre of soil disturbance if not otherwise subject to requirements of NPDES program. (UPPP Guideline). Erosion control measures shall consist of Best Management Practices for storm water discharges, including silt fencing, barrier protectors, temporary soil retention blankets, excelsior drainage filters, sediment traps and berms. Any rolled erosion product must be completely free of all plastic (including "biodegradable" and “photodegradable” plastic mesh and netting). Use erosion control products made of natural fibers, such as Curlex Net Free or approved equivalent.

Contractor shall note that biodegradable coir logs or temporary silt sock must be used instead of silt fence to avoid the excavation and trenching associated with silt fence.

See Appendix I – Letter of Compliance for more compliance requirements.

3. Project Submittals:

i. Digital Images

a) Provide a minimum five existing condition images and five images per week documenting demolition labeled with location, feature, time and date Include pre-demolition images. Upload digital images to NPS DSC project website, and identify sets of images with date, location, title, description, and other information pertinent to subject captured in photos. Compile all photo documentation in final report and submit with closeout documents.

4. Quality Control Plan

i. Quality Control Plan - plan shall include:

https://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=411516|

a) A list of personnel responsible for quality control and assigned duties.

Include each person's qualifications.

b) A copy of a letter of direction to CQC Supervisor outlining assigned duties.

c) Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

d) Methods of performing, documenting, and enforcing quality control of work.

e) Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

f) Other requirements as stipulated by BIA Demo MAC IDIQ.

5. Accident Prevention Plan: Prior to the Predemolition Meeting, submit accident prevention plan. Plan must be accepted by NPS before work on site begins and shall comply with Occupational Safety and Health Administration (OSHA) and project requirements. Include:

i. Name of responsible supervisor to carry out the program who shall be responsible for.

a) Implementation and enforcement of the APP.

b) Daily safety inspections.

c) Conducting and documenting weekly and monthly safety meetings.

d) Review of safety requirements at progress meetings.

e) Compilation and maintenance of Safety Data Sheets (SDS) and safety reference materials.

f) Tracking and resolution of safety violations.

g) Site personnel and visitor compliance with site safety and health requirements and APP.

h) Investigation and reporting of accidents and injuries.

ii. Protection of the public and residents. Note that many families live in the neighborhood, including small children, and a playground is immediately across the street and very near the project site. See site logistics plan below for further information.

iii. Map showing staging and equipment areas, fencing, and dumpsters.

iv. First aid and rescue procedures and identification of adequate facilities.

v. Job Hazard Analysis (JHA) - Outline for each phase of work, hazards associated with each phase, and methods proposed to ensure property protection and safety of the public, NPS staff, and the Demolition Contractor employees.

vi. Training – Provide training to personnel to ensure prompt and efficient first aid.

Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage.

vii. Planning for possible emergency situations – Post telephone numbers, addresses, and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at work site and within APP.

viii. Conduct daily safety inspections and maintain safety reports to include:

Area/operation inspected, date, identified hazards, and corrective actions taken.

ix. Comply with National Fire Protection Association (NFPA) 241 (Standard for

Safeguarding Demolition, Alteration, Demolition Operations).

x. Store Hazardous materials in accordance with manufacturer’s and OSHA Subpart

D requirements. Maintain Safety Data Sheets (SDS) for each chemical readily available on site

a) Immediately report spills of hazardous materials to the COR and Park Superintendent / Law Enforcement.

xi. Maintain a spill emergency response kit.

xii. Train employees how to respond to a spill and use emergency response kit.

xiii. Housekeeping and fire protection shall conform to all applicable codes.

xiv. Personnel Protective Equipment (PPE) shall conform to OSHA Subpart E

xv. Designate and post a Hard hat area. Require all persons working on or visiting site to wear hard hats and PPE in good repair at all times.

xvi. Infectious Disease Preparedness plan.

xvii. Conduct, at a minimum, one weekly 15-minute “toolbox” safety meeting conducted by a foreman or supervisor and attended by demolition personnel at worksite with topics coinciding with work for the following week.

xviii. Conduct monthly safety meetings for personnel, contractors, and subcontractors performing work at the site to review effectiveness of Contractor’s safety effort, resolve current problems, and plan upcoming safety measures. Invite the CO and COR to attend monthly meetings. Maintain record of minutes and submit to COR within 1-day of meeting.

xix. Contractor shall note that blasting is prohibited on this project.

xx. In the case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply.

xxi. Onsite equipment shall meet 20 CFR 1926 (Code of Federal Regulations)

(Occupational Safety and Health Administration (OSHA)) requirements.

xxii. Qualifications of Employees:

a) Physically and able to perform their assigned duties in a safe manner.

xxiii. Do not allow employees whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury to perform work.

xxiv. Provide operating instructions for equipment. Operators of vehicles, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, operating instructions, and be fully capable of operating such equipment. Retain copies of operator licenses and certifications on site.

xxv. No progress payments will be made or work shall begin unless the APP is accepted.

xxvi. Accident Reporting: Immediately Report the Following to the CO, COR, Park Superintendent, and Park Law Enforcement:

a) Accidents defined as death.

xxvii. Occupational disease.

xxviii. Traumatic injury to DB Demolition Contractor’s personnel, NPS employees, or the public.

xxix. Property damage of accidents in excess of $100

xxx. Fires of any kind.

xxxi. Complete DSC Contractor Accident/Property Damage Report (CM-22) and forward to CO and COR.

xxvii. Hazardous materials plan and contractor, personnel, transporter, and landfill qualifications in accordance with CA state laws and regulations.

6. Utility Identification and Removal/Decommissioning Plan – Prior to the start of work, the Contractor shall submit a utilities identification and removal / decommissioning plan to the COR for each property that includes, at a minimum, the following:

i. Location and types of all utilities. Utilities must be verified by the Contractor, including use of a private utility locating company as needed. Utilities as shown on NPS-provided aerial imagery are approximate and may not be inclusive of all utilities present.

ii. Name / contacts for utility companies.

iii. Decommissioning and/or removal plan for existing utilities specific to the property

(including septic and wells) per all applicable codes, regulations, and safety requirements.

iv. The Contractor shall develop a plan and schedule to address shutoff of any utilities to the building(s) during the work if necessary. Contractor shall provide the COR a minimum of two weeks’ notice prior to planned shutoff.

v. The Contractor shall arrange and pay for disconnecting, removing, capping, and plugging site utility services. Notify affected utility companies and agencies in advance and obtain approval before starting this work. Obtain all required permits.

It is the Contractor’s responsibility to obtain and pay for all permitting, inspection and connection fees.

vi. Methods and materials used to cap and mark existing utility lines.

7. Site Logistics Plan – Provide a site logistics plan that includes staging area(s), site protection measures, access, traffic control and phasing for the work. Show locations of temporary facilities, such as barriers, fencing, field offices, staging areas, sanitary facilities, demolition entrances and haul and access roads for review and approval by COR at least 30 days prior to mobilization. At a minimum, include the following on the plan:

i. Location(s) of Temporary Facilities - If temporary facilities are needed, provide incombustible pre-fabricated construction for offices, shops, and sheds located within demolition area. Comply with NFPA 241. Provide toilet and wash facilities that are sufficiently lighted and ventilated in weatherproof, sight proof, handicap accessible, sturdy enclosures with privacy locks. At a minimum, clean toilet facilities weekly, or more, as needed.

a) Coordinate with utility provider and NPS to install temporary service or connect to existing electric service. Acquire all necessary permits. No water or telephone service will be provided for Contractor use.

ii. Maintain support facilities until near Substantial Completion.

iii. Location (s) of Site Enclosure Fence: Before demolition operations begin, furnish and install barriers, including orange barricade fence and/or chain link fencing, in a manner that will control access points to each site and prevent people and https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=231291 animals from easily entering the site. Show extent and type of fencing and locate vehicular gates to avoid interference with traffic on public thoroughfares. Locate pedestrian entry gates as required to control access. Provide lockable entry points in coordination with NPS staff.

iv. Location (s) of Dumpster and Separation facilities for recycling.

a) Designate a specific area with approval from COR.

v. Place waste and recycling bins near each other, and close to point of waste generation but out of traffic pattern.

vi. Keep bin areas neat, clean, and clearly marked to avoid comingling of materials.

vii. Protect bins during non-working hours from off-site contamination.

viii. Check garbage dumpsters periodically for recyclables being thrown away.

ix. Location of Staging Area (s) –Contractor to verify staging areas with NPS upon award of contract:

x. Location(s) of demolition Access Routes and demolition Entrances for the property. Describe plan for minimizing earth disturbance, including materials planned to be used for demolition entrances (refer to Part IV Section 3.D - Site Restoration for requirements).

xi. Location(s) of Tree Protection Fencing: See Tree Protection requirements in Section E. General Notes, this document.

xii. Location(s) of Temporary Traffic Controls: Erect and maintain barricades, lights, danger signals, and warning signs in accordance with Manual on Uniform Traffic Control Devices (MUTCD), Part IV, latest edition.

a) Protect pedestrian traffic by guardrails or fences.

xiii. When pedestrian traffic is detoured onto a roadway, provide temporary walkways with protection as required, including at ends and overhead.

xiv. Note – If required, NPS will provide archeological monitoring for certain sites.

The Contractor must coordinate with NPS archeological monitor a minimum of 2 weeks before the start of work at any given site to schedule work where monitoring is needed.

a) Archeological Resources Protection Act (ARPA) of 1979 (Public Law (P.L.)

96-95; 93 United States Statues at Large (Stat.) 712): defines archeological resources as any material remains of past human life or activities that are of archeological interest and at least 100 years old; Section 4 of the statute describes the requirements that must be met before Federal authorities can issue a permit to excavate or remove any archeological resource on Federal or Indian lands; the curatorial requirements of artifacts, and other materials excavated or removed.

xv. If Archeological Monitor discovers resources, immediate relocation of work to a non-sensitive area may be required for Monitor to identify and document resources and, if necessary, develop appropriate mitigation plan. While Archeological Monitor is documenting resources in sensitive areas, Contractor shall relocate work to non-sensitive areas where monitoring is not normally required.

xvi. If resources are discovered while Archeological Monitor is absent, stop work immediately and report the discovery to the COR.

xvii. Contractor shall plan, schedule, and execute work to prevent stoppages at one area from stopping all work at demolition site.

8. Demolition materials:

i. Backfill material – source, weed free certification, gradation, and composition.

Park inspection and approval of soil source is required with a 30-day notice/submittal.

ii. Testing Agencies – Submit proposed compaction testing agency and qualifications of proposed personnel and lab.

9. The Contractor shall furnish and submit the following to NPS a minimum of one week prior to the pre demolition conference:

i. Letter Designating – Superintendent, Project Manager, and Quality Control Manager

ii. Project Schedule

iii. Schedule of Values, comprehensive breakdown, separated by CLINs

iv. Permit List

v. List of Subcontractors for this project (with written statements from subcontractors certifying compliance with applicable labor standard clauses)

vi. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contractor and all Subcontractors.

vii. Waste Management Plan

viii. Quality Control Plan

ix. Erosion and Sediment Control Plan, UPPP.

x. Accident Prevention Plan

xi. Utilities Identification and Removal/Decommissioning Plan.

xii. Site Logistics Plan.

xiii. Demolition Plan per BIA Demo MAC Contract Requirements

xiv. Pre-demolition Checklist

xv. Hazardous Materials Plan

10. Schedule and Progress Payments:

i. Schedule of values (SOV) shall break down lump-sum items into component work activities used in the schedule for which progress payments may be requested. Do not include mobilization, general condition costs, overhead or profit as a separate item. An acceptable SOV shall be agreed upon by the Contractor and CO before the first progress payment is processed.

ii. Demolition Baseline Schedule – Prepare using a computerized cost and resource-loaded, time-scaled CPM network analysis diagram for the Work so it can be accepted for use no later than 30 days after date established for Notice of Award.

Include activities, critical path activities, processing, and the sequence and interdependence of activities to complete the work.

a) Provide a 2 week look-ahead schedule, derived from the currently accepted schedule, before each weekly progress meeting.

iii. Monthly schedule updates shall be provided to the COR. Reports shall include the following: Identification of activities that have changed and changes in the following: early and late start/finish dates, activity durations in workdays, critical path, total float or slack time, Contract Time.

iv. An updated schedule must be provided as part of Progress Payment package in IPP. If the Contractor fails to provide schedule updates or revisions, then a portion of the monthly payment may be retained until such corrections have been made.

v. Submit an updated version of the following forms with each Progress Payment to IPP: Demolition Payment Request Checklist, Updated Schedule, Pay Estimate Form, Limitation on Subcontracting Report, and Project Waste Management Plan Worksheet (NPS standard forms can be downloaded here:

https://www.nps.gov/dscw/publicforms.htm).

11. The Contractor shall complete the following close-out tasks:

i. Provide Project Record Documents, final completion demolition digital images with index and descriptions, testing records, and similar final record information.

ii. Terminate and remove temporary facilities from Project site, along with demolition tools, and similar elements.

iii. Complete final clean up and restoration.

iv. Provide copies of daily reports, photographs, and warranties.

v. Copies of Final Inspection, as required.

vi. Final summary of solid waste disposal and diversion.

vii. Hazardous material disposal documentation: original copies of disposal verifications, manifests, quantities, and hazardous materials removal practices followed.

viii. As-built drawing copies documenting the final conditions, including the final location, size, depth and description of utilities and any decommissioning notes per BIA Demo MAC IDIQ.

12. Submit deliverables to:

i. Contracting Officer Representative (COR):

Andrew Reese, Project Manager Design and Construction Division National Park Service - Denver Service Center Work Phone (Cell): 303-907-1185 Email: andrew_reese@nps.gov

ii. Project Manager:

Elisabeth Jackson, Project Specialist Design and Construction Division National Park Service - Denver Service Center Work Phone (Cell): 720-960-3145 Email: elisabeth_jackson@nps.gov mailto:andrew_reese@nps.gov mailto:elisabeth_jackson@nps.gov

VIII. CODES AND STANDARDS

1. The Contractor shall provide a multi-disciplined team to furnish services required to complete the work. Each responsible team member must be knowledgeable of and provide work in compliance with the most current editions of all applicable codes, standards, and guidelines as adopted by BIA.

i. NFPA 5000 Building Construction - Life Safety and Fire Codes

ii. National Electrical Codes

iii. International Plumbing Code (IPC) and Mechanical Codes

iv. ASHRAE Standards, Handbooks, Journals, and Publications

v. Americans with Disabilities Act and Architectural Barriers Act Accessibility

Guidelines (ADAABAAG)

vi. Occupational Safety Health Administration (OSHA) - Federal Regulations

vii. Environmental Protection Agency (EPA) - Tribal, State, and Federal Regulations

viii. National Emissions Standards for Hazardous Air Pollutants (NESHAP)

ix. Clean Water Act (CWA) and Safe Drinking Water Act (SDWA)

x. Value Engineering DOI OMB Circular A-131

xi. International Building Code (IBC) - 2021.

xii. DOI – Guiding Principles for Sustainable Federal Buildings

xiii. Laws/Regulations/Policies/Guidance - (U.S. National Park Service) (nps.gov)

xiv. (U.S. National Park Service) (nps.gov)

xv. Design-Build (DB) - (U.S. National Park Service) (nps.gov)

xvi. Cultural & Natural Resources | DSC Workflows - (U.S. National Park Service) (nps.gov)

2. Where applicable, the Contractor shall adhere to all Federal and State statutes pertaining to archaeological, historical, and environmental clearances which may affect this project.

Strict adherence to the National Environmental Protection Act (NEPA) and the National Historic Preservation Act (NHPA), Section 106, will be mandatory.

3. The Contractor shall follow all applicable environmental laws.

4. The following specifications/guidelines shall be utilized work described. Definitions and

Acronyms:

i. "ADAABAAG" means "Americans with Disabilities Act and Architectural

Barriers Act Accessibility Guidelines"

ii. "NPS" refers to the National Park Service

iii. "FRSP" refers to Fredericksburg and Spotsylvania National Historical Park

iv. "CO" refers to the NPS Contracting Officer

v. "COR" refers to the Contracting Officer's Representative

vi. “CWA” refers to the Clean Water Act

vii. "DOI" refers to the U.S. Department of the Interior

viii. “DSC” refers to the Denver Service Center

ix. “EPA” refers to the Environmental Protection Agency

x. “GAOA” refers to the Great American Outdoors Act

xi. “IDP” refers to Inadvertent Discoveries Plan

xii. “LOP” refers to Limiting Operational Period https://www.nps.gov/dscw/laws-policies.htm https://www.nps.gov/dscw/index.htm https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/cultural-and-natural-resources.htm https://www.nps.gov/dscw/cultural-and-natural-resources.htm

xiii. “LOW” refers to Limits of Work

xiv. “MAC” refers to Multiple Award Contract

xv. “NEPA” refers to the National Environmental Policy Act

xvi. “SDWA” refers to the Safe Drinking Water Act

xvii. “SOW” refers to Statement of Work

xviii. “UPPP” Developed and implemented pollution prevention plan (including stormwater management measures, if needed) to protect environment from pollutants on construction projects with less than one acre of disturbance in conformance with NPS guidelines.

CLIN 0003

Task #3 Hazardous Materials Remediation (Option A) -

The performance of optional Task #3 will be based on the results of the Task #1 assessment. If HAZMAT is identified in Task #1 the cost to perform Task #3 will be negotiated and the agreed upon price definitized through a contract modification.

Preparation of Hazardous Materials Remediation Plan:

The work of this section consists of the preparation of an abatement plan for asbestos and other regulated materials (ORM) to be performed to allow for the safe demolition of the Grant Grove Quarters 1698. The abatement plan shall include but not limited to:

• Work Description including description of project conditions.

• Abatement management areas, material description, material location, and estimated material quantities to be removed.

• Governing state and federal regulations and laws.

• Codes and regulations.

• Regulated and appropriate engineering control requirements.

• Regulated waste disposal requirements.

• Personnel training and experience requirements.

• Contractor’s use of the premises.

• Special construction requirements.

• Required certifications.

• Quality Assurance requirements.

• Personal protection equipment, abatement equipment and products.

• Execution, work area preparation, decontamination, and documentation requirements.

• Air monitoring requirements.

• Safety requirements.

• Requirements for the re-establishment of work area.

• Provide licensed landfill receipts and completed hazardous materials manifests.

Submit the Hazardous Materials Remediation Plan for review and acceptance by the NPS.

Contractor Hazardous Materials Remediation Requirements

A. Personnel Training and Experience Personnel must be certified prior to gaining entry to the facility during remediation activities. Training must include all info related to asbestos hazards, PPE, and respirator requirements. Certification training consists of a 16-hour course (40 CFR 763.92(a)) and must include all info related to asbestos hazards and respirator requirements.

B. Contractor’s Use of the Premises The Contractor shall confine its apparatus, the storage of materials and the operations of its work staff to limits indicated by law, ordinances, permits or directions of the National Park Service representative and shall not exceed those established limits in their operations. The Contractor shall not load or permit any part of the structure to be loaded with a weight that will endanger its safety. The Contractor shall enforce the National Park Service representative’s instructions regarding signs, advertisements, fires, and smoking.

C. Special Demolition Requirements The contractor shall follow all federal, state, and local, guidelines and regulations for asbestos removal and waste disposal. The contractor shall gain permission to enter the premises from the national Park Service for the purposes of removing hazardous wastes from the building.

D. Submittals and Documentation Contractors shall submit proof of training to the NPS representative for all personnel performing tasks associated with hazardous materials within, or immediately surrounding the Grant Grove Quarters 1698. The contractor shall provide daily work reports documenting personnel and equipment onsite, tasks completed, and a description and location of containers with any remediated hazardous materials inside. The contractor shall ensure all staged hazardous materials containers are properly labeled, and are staged in an appropriate area, confirmed by the NPS representative. Subsequent to the remediation of hazardous materials, the contractors shall provide a summary report describing volumes of regulated ACM removed, transported, and disposed.

E. Certifications Certification is required by Title 8, California Code of Regulations, Article 2.6, Section 341.15 for individuals who contract to provide health and safety services for asbestos-related work (projects involving more than 100 square feet of asbestos-containing construction material). A certified asbestos consultant shall possess a valid and appropriate federal Asbestos Hazard Emergency Response Act [Subchapter II (commencing with Section 2641) of Chapter 53 of Title 15 of the United States Code] certificate, or its equivalent, as determined by the Division.

F. Quality Assurance Quality assurance is a firm’s process for improving the quality of its services or products. The abatement contractor(s) shall follow their company-specific quality assurance plan to ensure they are meeting their desired quality goals.

G. Personal Protective Equipment, Abatement Equipment, and Products Personal Protective Equipment (PPE) for Class I-III asbestos work requires a half-mask air purifying respirator fitted with HEPA filters, coveralls with head covering, gloves, and foot coverings. Disposable coveralls, gloves, and foot coverings are preferred.

H. Work Area Preparation Provide decontamination and containment facilities, PPE, containers/bags as specified in the Hazardous Materials Remediation Plan.

I. Re-Establishment of Work Area The contractor shall ensure they restore the work area to a safe condition at the end of each day and prior to returning to operations. The contractor shall follow safe working practices and shall maintain environmental compliance at all times.

J. Air Monitoring By OSHA regulation, air testing is required to be performed to determine asbestos exposure to the breathing zone of working personnel in the building during the remediation process. The Abatement contractor shall ensure that air sampling clearance tests are spaced appropriately in each area to ensure indoor air quality is accurately quantified.

K. Safety The contractor shall be knowledgeable of federal. state, and local regulations for handling, storing, transporting, and disposing of California hazardous wastes. The contractor shall perform daily safety tailboard meetings to remind personnel of the hazards they may encounter during remediation tasks. Personnel shall ensure they follow all laws, Sequoia National Park rules and regulations, and safety procedures as outlined in the daily safety tailboard meetings.