Sol_140G0125Q0186.pdf
PDF 361 KB Posted
- Attached to
- Removal & reinstall a centrifugal pump
- Solicitation number
- 140G0125Q0186
About this file
This document is a Request for Quote (RFQ) from the US Geological Survey (USGS) for pump replacement and infrastructure upgrades at the Columbia Environmental Research Center in Missouri. The solicitation (140G0125Q0186) requires a contractor to remove the existing centrifugal pump and install two redundant inverter-duty pumps with a Variable Frequency Drive (VFD), including comprehensive electrical and piping modifications. Specific requirements include installing circuits to electrical code standards, implementing BACnet-capable digital flow meters and pressure gauges, ensuring pump capacity of 200 gallons per minute with 120-200 feet of head, and creating a system with bypass functionality.
The procurement is a 100% small business set-aside with a contract value between $100,000-$250,000 and a performance period of 30 days after notice to proceed. Key dates include a mandatory site visit on August 7, 2025, proposal submission deadline of August 14, 2025, and anticipated contract award on August 22, 2025. Vendors must be registered in the System for Award Management (SAM) and can submit proposals via email to dparkin@usgs.gov. The NAICS code is 333914 with a size standard of 750 employees, and the contract will be awarded using a best-value tradeoff approach that considers technical capability and past performance as significantly more important than price.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0044015875
USGS OAG RESTON ACQUISITION BRANCH
205 NATIONAL CENTER
12201 SUNRISE VALLEY DRIVE
RESTON VA 20192
GRB
Dayna Parkin 703-648-7374
107/31/2025
140G0125Q0186
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
100% Small Business Set-aside
See Section L for Instructions and Section M for Evaluation Factors
***SITE VISIT SCHEDULED AND NOTED IN SECTION L, Reference FAR 52.236-27***
*Ref Section F for list of Deliverables*
*Payment Protection Required*
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
14 30 calendar days and complete it within ________________ ________________ calendar days after receiving
08/14/2025
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USGS OAG RESTON ACQUISITION BRANCH
205 NATIONAL CENTER
RESTON VA 20192
GRB
Dayna Parkin
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 56
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140G0125Q0186
Contractor shall perform in accordance with the
Statement of Work herein. Questions must be submitted by email only. In accordance with the solicitation requirement to submit questions no later than 5 calendar days before quotes are due.
Delivery: 30 Days After Notice to Proceed
Delivery Location Code: 0011277071
USGS Columbia Environmental Researc
4200 New Haven Road
Columbia MO 65201 US
Period of Performance: 09/12/2025 to 10/28/2025
00010 The contractor shall provide all materials, 1 EA labor, equipment, travel, and supervision necessary to remove and replace the existing centrifugal pump and install an appropriately sized VFD (Variable Frequency Drive) and supporting controls.
Work must be performed in accordance with the statement of work, wage decision, clauses, and all applicable federal, state, and local regulations.
Product/Service Code: 4320
Product/Service Description: POWER AND HAND PUMPS
For questions on this solicitation contact Dayna
Parkin, dparkin@usgs.gov
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SECTION B - Supplies or Services B.1 Supplies Or Services And Prices/Costs B.2 Contract Type B.3 Place of Performance B.4 Period of Performance
SECTION C - Description/Specifications C.1 52.211-18 Variation in Estimated Quantity. (APR 1984) C.2 52.223-23 52.223-23, Sustainable Products and Services (MAY 2024) (DEVIATION FEB 2025) C.3 GS0347 Indoor Air Quality During Construction (MAR 2008)
SECTION D - Packaging and Marking SECTION E - Inspection and Acceptance
E.1 52.246-12 Inspection of Construction. (AUG 1996) E.2 52.246-13 Inspection - Dismantling, Demolition, or Removal of Improvements. (AUG 1996)
SECTION F - Deliveries or Performance F.1 Deliverables F.2 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) F.3 52.236-2 Differing Site Conditions. (APR 1984) F.4 52.242-14 Suspension of Work. (APR 1984) F.5 GS0919 Legal Holidays (JUN 2021) F.6 GS1354 List of subcontractors (Construction) (JUL 2001)
SECTION G - Contract Administration Data G.1 GS0231 Technical Liaison-Technical Direction (NOV 2014) G.2 GS1126 Invoicing and Performance Statements (JUL 2001) G.3 GS1131 Unilateral Deobligation of Unexpended Funds (MAY 2013) G.4 DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (February 2021)
SECTION H - Special Contract Requirements H.1 52.246-21 Warranty of Construction. (MAR 1994) H.2 GS1326 Indemnity (JUL 2001) H.3 GS1338 Notice to Government of Delays (JUL 2001) H.4 GS1346 Compliance with OSHA-Govt owned Facilities/Equipment (APR 2003) H.5 GS1348 Accident Reporting (APR 2003) H.6 GS1440 Wage Determination Applicable (JUL 2001)
SECTION I - Contract Clauses I.1 52.204-13 System for Award Management Maintenance. (OCT 2018) I.2 52.204-18 Commercial and Government Entity Code Maintenance. (AUG 2020) I.3 52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014) I.4 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(NOV 2021)
I.5 52.204-29 Federal Acquisition Supply Chain Security Act Orders-Representation and Disclosures. (DEC 2023) I.6 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (JAN 2025) I.7 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015) I.8 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997) I.9 52.219-28 Postaward Small Business Program Rerepresentation. (JAN 2025) I.10 52.222-1 Notice to the Government of Labor Disputes. (FEB 1997) I.11 52.222-3 Convict Labor. (JUN 2003) I.12 52.222-6 Construction Wage Rate Requirements. (AUG 2018) I.13 52.222-7 Withholding of Funds. (MAY 2014) I.14 52.222-8 Payrolls and Basic Records. (JUL 2021) I.15 52.222-9 Apprentices and Trainees. (JUL 2005) I.16 52.222-10 Compliance With Copeland Act Requirements. (FEB 1988) I.17 52.222-11 Subcontracts (Labor Standards). (MAY 2014) I.18 52.222-12 Contract Termination - Debarment. (MAY 2014) I.19 52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014) I.20 52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
I.21 52.222-15 Certification of Eligibility. (MAY 2014) I.22 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts. (MAY 2024) I.23 52.223-3 Hazardous Material Identification and Material Safety Data. (FEB 2021) I.24 52.225-9 Buy American - Construction Materials. (OCT 2022) I.25 52.225-13 Restrictions on Certain Foreign Purchases. (FEB 2021) I.26 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran- Representation and Certifications. (JUN 2020) I.27 52.226-7 Drug-Free Workplace. (MAY 2024) I.28 52.226-8 Encouraging Contractor Policies To Ban Text Messaging While Driving. (MAY 2024) I.29 52.228-2 Additional Bond Security. (OCT 1997) I.30 52.228-5 Insurance - Work on a Government Installation. (JAN 1997) I.31 52.228-11 Individual Surety-Pledge of Assets. (FEB 2021) I.32 52.228-12 Prospective Subcontractor Requests for Bonds. (DEC 2022) I.33 52.228-13 Alternative Payment Protections. (JUL 2000) I.34 52.228-14 Irrevocable Letter of Credit. (NOV 2014) I.35 52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014) I.36 52.232-14 Notice of Availability of Progress Payments Exclusively for Small Business Concerns. (APR 1984) I.37 52.232-23 Assignment of Claims. (MAY 2014) I.38 52.232-27 Prompt Payment for Construction Contracts. (JAN 2017) I.39 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) I.40 52.236-5 Material and Workmanship. (APR 1984) I.41 52.236-7 Permits and Responsibilities. (NOV 1991) I.42 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984) I.43 52.236-12 Cleaning Up. (APR 1984) I.44 52.236-13 Accident Prevention. (NOV 1991) I.45 52.236-14 Availability and Use of Utility Services. (APR 1984) I.46 52.236-15 Schedules for Construction Contracts. (APR 1984) I.47 52.236-26 Preconstruction Conference. (FEB 1995) I.48 52.243-5 Changes and Changed Conditions. (APR 1984) I.49 52.252-6 Authorized Deviations in Clauses. (NOV 2020) I.50 52.253-1 Computer Generated Forms. (JAN 1991) I.51 1452.203-70 Restriction on Endorsements (JUL 1996) I.52 1452.204-70 Release of Claims (JUL 1996) I.53 1452.225-70 Use of Foreign Construction Materials (JUL 1996) I.54 1452.228-70 Liability Insurance (JUL 1996) I.55 1452.236-70 Prohibition Against Use of Lead-based Paint (JUL 1996) I.56 52.213-4 Terms and Conditions - Simplified Acquisitions (Other Than Commercial Products and Commercial Services) (Jan 2025) (DEVIATION FEB 2025) I.57 52.222-99 Combating Race and Sex Stereotyping. [(DEVIATION 20-09)] I.58 52.219-6 Notice of Total Small Business Set-Aside (DEVIATION 2019-01) I.59 -- Notice
SECTION J - List of Documents, Exhibits, and Other Attachments SECTION K - Representations, Certifications, and Other Statements of Bidders
K.1 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.
(NOV 2021)
K.2 52.204-8 Annual Representations and Certifications (Jan 2025) (DEVIATION FEB 2025)
SECTION L - Instructions, Conditions, and Notices to Bidders L.1 52.204-7 System for Award Management. (NOV 2024) L.2 52.204-16 Commercial and Government Entity Code Reporting. (AUG 2020) L.3 52.204-22 Alternative Line Item Proposal. (JAN 2017) L.4 52.216-1 Type of Contract. (APR 1984) L.5 52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. (MAY 2014) L.6 52.225-10 Notice of Buy American Requirement - Construction Materials. (MAY 2014) L.7 52.236-27 Site Visit (Construction). (FEB 1995) L.8 52.236-27 Site Visit (Construction). (FEB 1995) - Alternate I (FEB 1995) L.9 52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)
L.10 52.252-5 Authorized Deviations in Provisions. (NOV 2020) L.11 1452.215-71 Use and Disclosure of Proposal Information-Department of the Interior. (APR 1984) L.12 1452.233-2 Service of Protest L.13 Instructions Instructions, Conditions, and Notices to Bidders
SECTION M - Evaluation Factors for Award M.1 - Evaluation Factors
SECTION B - Supplies or Services
B.1 Supplies Or Services And Prices/Costs
Line Item Description UnitQtyUnit
Price
00010 The contractor shall provide all materials, labor, equipment, travel, and supervision necessary to remove and replace the existing centrifugal pump and install an appropriately sized VFD (Variable Frequency Drive) and supporting controls
1 Job
B.2 Contract Type
Firm Fixed-Price
B.3 Place of Performance
Columbia Environmental Research Center 4200 New Haven Road Columbia, Missouri 65201
B.4 Period of Performance
Completion 30 days after Notice to Proceed is issued
SECTION C - Description/Specifications
C.1 52.211-18 Variation in Estimated Quantity. (APR 1984)
C.2 52.223-23 52.223-23, Sustainable Products and Services (MAY 2024) (DEVIATION FEB 2025)
As prescribed in 23.109(a), insert the following clause:
52.223-23, Sustainable Products and Services (MAY 2024) (DEVIATION FEB 2025)
(a) Definitions. As used in this clause¿
Biobased product means a product determined by the U.S. Department of Agriculture (USDA) to be a commercial product or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products, including renewable domestic agricultural materials and forestry materials, or that is an intermediate ingredient or feedstock. The term includes, with respect to forestry materials, forest products that meet biobased content requirements, notwithstanding the market share the product holds, the age of the product, or whether the market for the product is new or emerging. ( 7 U.S.C. 8101) ( 7 CFR part 4270.2).
Recovered material means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process. ( 42 U.S.C. 6903).
Sustainable products and services means:
(1) Products containing recovered material designated by the U.S. Environmental Protection Agency (EPA) under the Comprehensive Procurement Guidelines ( 42 U.S.C. 6962) ( 40 CFR part 247) ( https://www.epa.gov/ smm/ comprehensive-procurement-guideline-cpg-program#products).
(2) Energy- and water-efficient products that are ENERGY STAR® certified or Federal Energy Management Program (FEMP)-designated products ( 42 U.S.C. 8259b) ( 10 CFR part 436, subpart C) ( https://www.energy.gov/ eere/ femp/ search-energy-efficient-products and https://www.energystar.gov/ products? s= mega).
(3) Biobased products meeting the content requirement of the USDA under the BioPreferred® program ( 7 U.S.C. 8102) ( 7 CFR part 3201) ( https://www.biopreferred.gov).
(4) Acceptable chemicals, products, and manufacturing processes listed under EPA's Significant New Alternatives Policy (SNAP) program, which ensures a safe and smooth transition away from substances that contribute to the depletion of stratospheric ozone ( 42 U.S.C. 7671l) ( 40 CFR part 82, subpart G) ( https://www.epa.gov/ snap).
(b) Requirements.
(1) The sustainable products and services, including the purchasing program and type of product or service, that are applicable to this contract, and any products or services that are not subject to this clause, will be set forth in the statement of work or elsewhere in the contract.
(2) The Contractor shall ensure that the sustainable products and services required by this contract are¿
(i) Delivered to the Government;
(ii) Furnished for use by the Government;
(iii) Incorporated into the construction of a public building or public work; and
(iv) Furnished for use in performing services under this contract, where the cost of the products is a direct cost to this contract (versus costs which are normally applied to the Contractor's general and administrative expenses or indirect costs). This includes services performed by contractors performing management and operation of Government-owned facilities to the same extent that, at the time of award, an agency would be required to comply if an agency operated or supported the facility.
(c) Resource. The Green Procurement Compilation (GPC) available at https://sftool.gov/ greenprocurement provides a comprehensive list of sustainable products and services and sustainable acquisition guidance. The Contractor should review the GPC when determining which statutory purchasing programs apply to a specific product or service.
End of clause
C.3 GS0347 Indoor Air Quality During Construction (MAR 2008)
(a) The contractor shall control contaminants at the source and/or operate the space in such a manner that the GSA indicator levels for carbon monoxide (CO), carbon dioxide (CO2 ), and formaldehyde (HCHO) are not exceeded. The indicator levels for office areas shall be:
CO - 9 parts per million (ppm) time-weighted average (TWA - 8-hour sample); CO2 - 1000 ppm (TWA); formaldehyde
- 0.1 ppm (TWA).
(b) The contractor shall make a reasonable attempt to apply insecticides, paints, glues, adhesives, and heating, ventilating and air conditioning (HVAC) system cleaning compounds with highly volatile or irritating organic compounds, outside of working hours. The contractor shall provide at least 72 hours advance notice to the Government before applying noxious chemicals in occupied spaces, and adequately ventilate those spaces during and after application.
(c) To the greatest extent possible, contractor shall sequence the installation of finish materials so that materials that will be high emitters of Volatile Organic Compounds (VOCs) are installed and allowed to cure before installing interior finish materials, especially soft materials that are woven, fibrous, or porous in nature, that may adsorb contaminants and release them over time.
(d) Where demolition or construction work occurs adjacent to occupied space, contractor shall erect appropriate barriers (noise, dust, odor, etc.) and take necessary steps to minimize interference with the occupants. This includes maintaining acceptable temperature, humidity and ventilation in the occupied areas during window removal, window replacement, or similar types of work.
(e) A final flush-out period of 48 to 72 hours should be provided before occupancy. Contractor shall ventilate with 100 percent outside air at the recommended air change rate (ASHRAE Standard 62) during installation of materials and finishes. If outside air would cause unacceptable inside temperature levels, humidity levels, and/or air quality, an alternate ventilation plan may be submitted to the Contracting Officer for approval.
(f) The contractor shall promptly investigate indoor air quality (IAQ) complaints and shall implement the necessary controls to address the complaint when requested to do so by the Contracting Officer.
(g) The Government reserves the right to conduct independent IAQ assessments and detailed studies in space it occupies, as well as in space serving the Government-leased space (e.g., common use areas, mechanical rooms, HVAC systems, etc.). The contractor shall assist the Government in its assessments and detailed studies by making available information on building operations and contractor activities, and providing access to space for assessment and testing, if required, and implement corrective measures required by the Contracting Officer.
SECTION D - Packaging and Marking
SECTION E - Inspection and Acceptance
E.1 52.246-12 Inspection of Construction. (AUG 1996)
E.2 52.246-13 Inspection - Dismantling, Demolition, or Removal of Improvements. (AUG 1996)
SECTION F - Deliveries or Performance
F.1 Deliverables
Deliverables Reference Due Delivery To All labor, materials, and equipment necessary to construct all items described in statement of work and attachments
Statement of Work NTP + 30 days USGS
Project Schedule and Timeline Project Schedule and Timeline Kick-off Meeting COR
Payment Bond or Irrevocable of Letter of Credit
Section I: 52.228-14 Section I: 52.228-13
Within 14 days after receipt of contract award
CO
Proof of Liability Section I: 1452.228-70 Within 14 days after receipt of contract award
CO
List of Subcontractors Section F: GS1354 Within 14 days after receipt of contract award
CO
Schedule of Contruction Section I: 52.236-15 Within 5 days after work commences
COR
CO
Monthly Contract Performance Statement Section G: GS1126, paragraph (c)
Submit at same time as invoice for progress payment
COR
Progress Meetings
Discuss
(1) Estimated project completion
(2) Value of completed work
- For each separately price line item
- For each of the significant construction categories contained in the approved Schedule of Prices;
(3) Difficulties encountered and remedial action taken during the reporting period and anticipated activity during the subsequent reporting period
Biweekly COR
CO
Invoices Section G: DOI Electronic Invoicing Section G: GS1126
No more often than monthly IPP Web Page
DI-137 Release of Claims Section G: 1452.204-70 Prior to submitting final invoice CO
Final Invoices N/A After submitting Release of Claims IPP
Certification of Progress Payment (if requesting progress payment) Section I: 52.232-5
As work proceeds
- No more often than monthly
COR
Weekly Payrolls for subcontractors and each subcontractor
The contractor is required to submit copies of all payrolls. The prime contractor is responsible for the submission of copies of payrolls by all subcontractors. This information may be submitted in any form. The optional form WH-347 form the Department of Labor may be used and is available at:
Date of payroll week covered
22.406(c) for examination of payrolls and statements.
Further compliance checking may http://www.doi.gov/whd/forms/wh347.pdf be done IAW
FAR 22.406-7
SF-1413 Statement and Acknowledgement (including the subcontractor's signed and dated acknowledgement that the clauses set forth in paragraph (b) of FAR 52.222-11 have been included in the subcontract)
Section I: 52.222-11
The contractor is required to submit statement and acknowledgement to the Contracting Officer on the Standard Form (SF) 1413.
Section I: 52.222-11 The contractor is required to submit statement and acknowledgement to the Contracting Officer on the Standard Form (SF) 1413.
CO
F.2 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 14 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30. The time stated for completion shall include final cleanup of the premises.
(End of clause)
* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
F.3 52.236-2 Differing Site Conditions. (APR 1984)
(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract or (2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.
(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.
(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in paragraph (a) above for giving written notice may be extended by the Contracting Officer.
(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.
(End of clause)
F.4 52.242-14 Suspension of Work. (APR 1984)
F.5 GS0919 Legal Holidays (JUN 2021)
The following legal holidays are observed by this Government agency:
New Year's Day January 01
Martin Luther King's Birthday 3rd Monday in January
Presidents Day 3rd Monday in February
Memorial Day Last Monday in May
Juneteenth National Independence Day June 19
Independence Day July 04
Labor Day 1st Monday in September
Columbus Day 2nd Monday in October
Veterans Day November 11
Thanksgiving Day 4th Thursday in November
Christmas Day December 25
When a holiday falls on Saturday or Sunday, it is observed on the adjacent Friday or Monday, respectively.
In addition to the holidays listed above, the contractor agrees to observe leave days or closures designated by Federal Statute, Executive Order, or Presidential Proclamation.
F.6 GS1354 List of subcontractors (Construction) (JUL 2001)
For purposes of monitoring compliance with the insurance and payroll reporting requirements of this contract, the contractor shall furnish a listing of all subcontractors to the Contracting Officer within 14 calendars days after contract award.
SECTION G - Contract Administration Data
G.1 GS0231 Technical Liaison-Technical Direction (NOV 2014)
(a) The performance required herein shall be subject to the technical direction of the Technical Liaison (TL) as identified below. As used herein, "technical direction" is defined as direction to the contractor that fills in details, suggests possible lines of approach, or otherwise supplements the scope of the work set forth herein and shall not constitute a new assignment, and does not supersede or modify any article or clause of this contract.
(b) The Technical Liaison is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the
Disputes Clause;
(4) Terminate, for any reason, the contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government. Only a warranted Contracting Officer is authorized to obligate funds on this or any other contract action.
(c) The contractor shall immediately notify the Contracting Officer in writing if the Technical Liaison has taken an action (or fails to take action) or issues direction (written or oral) that the contractor considers to exceed the above limitations.
(d) The Technical Liaison assigned for this contract is:
Name: TBD After Award
Telephone Number: []
Email: []
Address Line 1: []
Address Line 2: []
Address Line 3: []
(e) Only the Contracting Officer may designate a different Technical
Liaison.
G.2 GS1126 Invoicing and Performance Statements (JUL 2001)
Invoicing and Performance Statements (Construction)
(a) A copy of each invoice submitted with an IPP payment request must be submitted to:
U.S. Geological Survey TBD After Award
Attn: [ ]
(b) Invoices for progress payments may be submitted no more frequently than monthly.
(c) Invoices for progress payments must be accompanied by a contract Performance Statement, which shall show in detail the estimated percentage of completion and value of completed performance for each separately priced line item or, if applicable, each of the significant construction categories contained in the approved Schedule of Prices.
(d) See clause 52.232-5 for certification requirements.
G.3 GS1131 Unilateral Deobligation of Unexpended Funds (MAY 2013)
The contractor shall submit all invoices under the award no later than 90 calendar days after the period of performance has expired, unless a request for extension has been submitted to the Contracting Officer. After 120 days has passed since the expiration of the performance period, the government reserves the right to issue a unilateral modification deobligating any unexpended funds, and to initiate closeout procedures.
G.4 DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (February 2021)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice :
- Contractor generated invoice
- Payrolls
- Performance Statement if progress payment
- Release of Claims for final invoice
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
SECTION H - Special Contract Requirements
H.1 52.246-21 Warranty of Construction. (MAR 1994)
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.
(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of -
(1) The Contractor's failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished.
(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.
(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.
(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall -
(1) Obtain all warranties that would be given in normal commercial practice;
(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and
(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.
(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.
(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.
(End of clause)
H.2 GS1326 Indemnity (JUL 2001)
The contractor herein is "an independent contractor" and shall obtain all necessary insurance to protect himself from liability arising out of this contract. The contractor hereby agrees to indemnify and hold the Government harmless in connection with, any loss or liability from damage to or destruction of property or from injuries to or death of persons
(including the agents and employees of both parties) if such damage, destruction, injury or death arises out of, or is caused by performance of work under this contract, unless such damage, destruction, injury or death is caused solely by the active negligence of the Government, its agents or employees. The contractor agrees to include this clause, appropriately modified, in all subcontracts to be performed under this contract.
H.3 GS1338 Notice to Government of Delays (JUL 2001)
In the event the contractor encounters difficulty in meeting performance requirements, or when it anticipates difficulty in complying with the contract delivery schedule or date, or whenever the contractor has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this contract, the contractor shall immediately notify the contracting officer and the COR (if one has been designated), in writing, giving pertinent details.
This data shall be informational only in character. Notice under this provision shall not be construed as a waiver by the Government of any delivery schedule or date or of any rights or remedies provided by law or under this contract.
H.4 GS1346 Compliance with OSHA-Govt owned Facilities/Equipment (APR 2003)
Compliance with Occupational Safety and Health Act -- Government-Owned Performance of work hereunder shall comply with the provisions of the Occupational Health and Safety Act of 1970, as amended (OSHA). If, at any time during the performance of this contract, the Government-furnished facilities and/or equipment do not conform to OSHA standards, the contractor must so notify the Contracting Officer, in writing, including a recommendation of the corrective action needed.
H.5 GS1348 Accident Reporting (APR 2003)
If an accident occurs on Government-controlled facilities, a report must be provided to the Contracting Officer's Representative and the Contracting Officer within 48 hours. An accident is defined as an event which causes injury, illness, or loss or damage to Government-owned or private property. The contractor will cooperate with any ensuing Government accident investigation.
H.6 GS1440 Wage Determination Applicable (JUL 2001)
In the performance of this contract, the contractor shall comply with the requirements of U.S. Department of Labor Wage Determination Number MO20240084 dated 07/18/2025. The wage determination is incorporated into this contract as Attachment B03 Attachment 1
SECTION I - Contract Clauses
I.1 52.204-13 System for Award Management Maintenance. (OCT 2018)
I.2 52.204-18 Commercial and Government Entity Code Maintenance. (AUG 2020)
I.3 52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)
I.4 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021)
I.5 52.204-29 Federal Acquisition Supply Chain Security Act Orders-Representation and Disclosures. (DEC 2023)
(a) Definitions. As used in this provision, Covered article, FASCSA order, Intelligence community, National security system, Reasonable inquiry, Sensitive compartmented information, Sensitive compartmented information system, and Source have the meaning provided in the clause 52.204-30, Federal Acquisition Supply Chain Security Act Orders- Prohibition.
(b) Prohibition. Contractors are prohibited from providing or using as part of the performance of the contract any covered article, or any products or services produced or provided by a source, if the prohibition is set out in an applicable Federal Acquisition Supply Chain Security Act (FASCSA) order, as described in paragraph (b)(1) of FAR 52.204-30, Federal Acquisition Supply Chain Security Act Orders-Prohibition.
(c) Procedures. (1) The Offeror shall search for the phrase "FASCSA order" in the System for Award Management (SAM)(https://www.sam.gov) for any covered article, or any products or services produced or provided by a source, if there is an applicable FASCSA order described in paragraph (b)(1) of FAR 52.204-30, Federal Acquisition Supply Chain Security Act Orders-Prohibition.
(2) The Offeror shall review the solicitation for any FASCSA orders that are not in SAM, but are effective and do apply to the solicitation and resultant contract (see FAR 4.2303(c)(2)).
(3) FASCSA orders issued after the date of solicitation do not apply unless added by an amendment to the solicitation.
(d) Representation. By submission of this offer, the offeror represents that it has conducted a reasonable inquiry, and that the offeror does not propose to provide or use in response to this solicitation any covered article, or any products or services produced or provided by a source, if the covered article or the source is prohibited by an applicable FASCSA order in effect on the date the solicitation was issued, except as waived by the solicitation, or as disclosed in paragraph (e).
(e) Disclosures. The purpose for this disclosure is so the Government may decide whether to issue a waiver. For any covered article, or any products or services produced or provided by a source, if the covered article or the source is subject to an applicable FASCSA order, and the Offeror is unable to represent compliance, then the Offeror shall provide the following information as part of the offer:
(1) Name of the product or service provided to the Government;
(2) Name of the covered article or source subject to a FASCSA order;
(3) If applicable, name of the vendor, including the Commercial and Government Entity code and unique entity identifier (if known), that supplied the covered article or the product or service to the Offeror;
(4) Brand;
(5) Model number (original equipment manufacturer number, manufacturer part number, or wholesaler number);
(6) Item description;
(7) Reason why the applicable covered article or the product or service is being provided or used;
(f) Executive agency review of disclosures. The contracting officer will review disclosures provided in paragraph (e) to determine if any waiver may be sought. A contracting officer may choose not to pursue a waiver for covered articles or sources otherwise subject to a FASCSA order and may instead make an award to an offeror that does not require a waiver.
(End of provision)
I.6 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (JAN 2025)
I.7 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015)
I.8 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997)
I.9 52.219-28 Postaward Small Business Program Rerepresentation. (JAN 2025)
I.10 52.222-1 Notice to the Government of Labor Disputes. (FEB 1997)
I.11 52.222-3 Convict Labor. (JUN 2003)
I.12 52.222-6 Construction Wage Rate Requirements. (AUG 2018)
I.13 52.222-7 Withholding of Funds. (MAY 2014)
I.14 52.222-8 Payrolls and Basic Records. (JUL 2021)
I.15 52.222-9 Apprentices and Trainees. (JUL 2005)
I.16 52.222-10 Compliance With Copeland Act Requirements. (FEB 1988)
I.17 52.222-11 Subcontracts (Labor Standards). (MAY 2014)
I.18 52.222-12 Contract Termination - Debarment. (MAY 2014)
I.19 52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014)
I.20 52.222-14 Disputes Concerning Labor Standards. (FEB 1988)
I.21 52.222-15 Certification of Eligibility. (MAY 2014)
I.22 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts. (MAY 2024)
I.23 52.223-3 Hazardous Material Identification and Material Safety Data. (FEB 2021)
I.24 52.225-9 Buy American - Construction Materials. (OCT 2022)
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-
(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means-
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if-
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
NONE
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is…