This is a Solicitation/Contract/Order for Commercial Items (Standard Form 1449) issued by the USDA Agricultural Research Service for roof replacement services at the Eastern Regional Research Center in Fargo, North Dakota.

The solicitation seeks a firm-fixed-price contract for the repair and replacement of the roof on Building 3 (animal care facility) at the Biosciences Research Laboratory, with a mandatory 120-day delivery period from award. The contract is set aside 100 percent for small businesses under NAICS code 238160. The solicitation number is 1232SA26Q0403, with an offer due date of April 23, 2026 at 1000 ET and an issue date of April 7, 2026. Questions must be submitted by April 15, 2026 at 1000 AM ET to osvaldo.rodriguez@usda.gov. A mandatory site visit is scheduled for April 16, 2026 at 1000 AM Central Time at the Biosciences Research Laboratory, 1616 Albrecht Blvd N, Fargo, ND 58102. Invoicing must be submitted electronically through the Invoice Processing Platform (IPP). Award will be made to the lowest-priced, technically acceptable offer based on evaluation criteria including a detailed technical narrative demonstrating knowledge of the work, at least two relevant references completed within the past two years, and a detailed price breakdown. The Government intends to make one award from this solicitation. Performance and payment bonds are required per FAR 52.228-15. The contract incorporates by reference extensive FAR and AGAR clauses including construction wage rate requirements, Buy American provisions for materials, and compliance with labor standards and anti-discrimination requirements.

View the file

Other files

File Type Posted
BRL B3 Roof Replacement SOW.pdf PDF
Davis-Bacon Act WD ND20260013.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

ARS-1232SA

BELTSVILLE MD 20705

RM 3-2102

5601 SUNNYSIDE AVENUE

USDA ARS ACQUISITION AND PROPERTY D

ARS-126612 CODE 16. ADMINISTERED BYCODE

X

X

X

238160

SIZE STANDARD:

100.00 % FOR:SET ASIDE:UNRESTRICTED ORARS-1232SA

REQUEST FOR

PROPOSAL

(RFP)

INVITATION

FOR BID (IFB)

10. THIS ACQUISITION ISCODE

REQUEST FOR

QUOTE (RFQ)

14. METHOD OF SOLICITATION

13b. RATING

NORTH AMERICAN INDUSTRY

CLASSIFICATION STANDARD

(NAICS):

SMALL BUSINESS

04/23/2026 1000 ET

04/07/2026

662-686-5415OSVALDO RODRIGUEZ

(No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME

4. ORDER NUMBER3. AWARD/ 6. SOLICITATION

1232SA26Q0403

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 15 1165207OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

TELEPHONE NO.

17a. CONTRACTOR/

FARGO ND 58102

1616 ALBRECHT BLVD NORTH

PA RED RIVER VALLEY AGRICULTURAL RE

15. DELIVER TO

BELTSVILLE MD 20705

RM 3-2102

5601 SUNNYSIDE AVENUE

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

$19

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

ISSUE DATE

DELIVERY FOR FREE ON BOARD

(FOB) DESTINATION UNLESS

BLOCK IS MARKED

11.

SEE SCHEDULEX

12. DISCOUNT TERMS THIS CONTRACT IS A RATED

ORDER UNDER THE DEFENSE

PRIORITIES AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

8(A)

USDA ARS ACQUISITION AND PROPERTY D

WOMEN-OWNED SMALL

BUSINESS (WOSB)

ECONOMICALLY DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

Delivery: 120 Days After Award

0001 Repair roof to animal care facility at ETSARC BRL Building

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

XX

DATED

OSVALDO J. RODRIGUEZ

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Government Use Only)

OFFER

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT: REFERENCE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 11/2021) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

15 2 of

Statement of Requirement - The USDA, Agricultural Research Service in Eastern Regional Research Center, Fargo, ND requires a roof replacement of Building 3. Refer to the Statement of Work for specific details to include project location.

Federal Acquisition Regulation (FAR) and United States Department of Agriculture Acquisition Regulation (AGAR) Clauses and Provisions

The clauses and provisions contained herein are applicable to any order awarded as a result of this solicitation. The terms and conditions set forth herein supersede all other terms and conditions.

Acceptance of the order in accordance with (IAW) FAR 12.201-1(b)(2) constitutes acceptance of all terms and conditions contained herein.

As part of the Revolutionary FAR Overhaul (RFO), system updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in this solicitation. Contracting officers will rely on representations from offers based on provisions in the solicitation. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

52.252-2 Clauses Incorporated by Reference (Feb 1998) This solicitation incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also the full text of the clause may be accessed electronically at Internet address https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2025) 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.222-50 Combating Trafficking in Persons (Nov 2025) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After Award (Sep 2025) 52.233-4 Applicable Law for Breach of Contract Claim (Sep 2025) 52.240-91 Security Prohibitions and Exclusions (Nov 2025) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Nov 2025)

The following clauses are applicable if checked:

☒ 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) with Alternate I (Nov 2021) of 52.203-6 ☒ 52.204-9 Personal Identity Verification of Contractor Personnel Jan 2011 ☒ 52.204-13 System for Award Management—Maintenance (Nov 2025) ☒ 52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Sep 2025) ☒ 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Sep 2025) https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

☒ 52.219-6 Notice of Total Small Business Aside (Nov 2025) ☒ 52.219-8 Utilization of Small Business Concerns (Nov 2025) ☒ 52.219-14 Limitations on Subcontracting (Nov 2025) ☒ 52.222-3 Convict Labor (June 2003) ☒ 52.222-19 Child Labor—Cooperation with Authorities and Remedies (Nov 2025) ☒ 52.222-35 Equal Opportunity for Veterans (Nov 2025) ☒ 52.222-36 Equal Opportunity for Workers with Disabilities (Nov 2025) ☒ 52.222-37 Employment Reports on Veterans (Nov 2025) ☒ 52.222-54 Employment Eligibility Verification (Nov 2025) ☒ 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) ☒ 52.232-33 Payment by Electronic Funds Transfer— System for Award Management (Oct 2018)

The Contractor shall comply with the following FAR Clauses for Commercial Construction.

52.222-6 Construction Wage Rate Requirements 52.222-7 Withholding of Funds 52.222-8 Payrolls and Basic Records 52.222-9 Apprentices and Trainees 52.222-10 Compliance with Copeland Act Requirements 52.222-11 Subcontracts (Labor Standards) 52.222-12 Contract Termination-Debarment 52.222-14 Disputes Concerning Labor Standards 52.222-15 Certificate of Eligibility 52.236-5 Material and Workmanship

The following clauses are applicable when checked:

☒ 52.225-9 Buy American-Construction Materials (Oct 2022) ☒ 52.228-15 Performance and Payment Bonds-Construction (Jun 2020) ☒ 52.236-2 Differing Site Conditions (Jul 2025) ☒ 52.236-3 Site Investigation and Conditions Affecting the Work (Jul 2025) ☒ 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Jul 2025) ☒ 52.336-10 Operations and Storage Areas (Jul 2025) ☒ 52.236-11 Use and Possession Prior to Completion (Jul 2025) ☒ 52.236-12 Cleaning Up (Jul 2025) ☒ 52.236-13 Accident Prevention (Jul 2025) ☒ 52.236-14 Availability and Use of Utility Services (Jul 2025) ☒ 52.236-15 Schedules for Construction Contracts (Jul 2025) ☒ 52.236-17 Layout of Work (Jul 2025) ☒ 52.236-21 Specifications and Drawings for Construction (Jul 2025) ☒ 52.242-14 Suspension of Work (Apr 1984) ☒ 52.248-3 Value Engineering (Oct 2025)

AGAR Clauses

452.203-71 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Compliance (Dec 2025)

(a) By entering into this contract, the Contractor certifies that:

1. It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution, and it will remain compliant for the duration of the contract.

2. Neither it nor any subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution, and the Contractor and any subcontractor or teaming partner will not do so for the duration of the contract.

(b) If the Contractor participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, the Contractor certifies that it will remain compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.

(c) The Contractor affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the Contractor is not eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to Contractor’s compliance with the above requirements and/or eligibility for the contract may subject the Contractor to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.

(f) The Contractor must include the provisions of this clause in all subcontract solicitations.

(g) Failure on the part of the Contractor or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate this contract for default.

(End of Clause)

452.204–70 Modification for Contract Closeout (Nov 2025)

(a) If unliquidated funds in the amount of $1000 or less remain on the contract, the Contracting Officer (Contracting Officer) shall issue a unilateral modification for deobligation. The contractor will receive a copy of the modification but will not be required to provide a signature. The Contracting Officer shall immediately proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(b) Upon contract closeout for contracts utilizing SAP: if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation.

The contractor will receive a copy of the modification and will be required to provide a signature.

(The Contracting Officer may also request a “Contractor Release of Claims” be completed by the contractor, although not required for contracts and orders using SAP.) If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 60 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(c) Upon contract closeout for contracts utilizing anything other than cost reimbursement, if unliquidated funds of more than $1000 remain on the contract, the Contracting Officer shall issue a bilateral modification for deobligation. The contractor will receive a copy of the modification and a ‘‘Contractor Release of Claims’’ and will be required to provide a signature on both forms. If the bilateral modification and Release of Claims are not returned to the Contracting Officer within 120 days, the Contracting Officer shall release the modification as unilateral and proceed with contract closeout upon completion of the period of performance, receipt and acceptance of supplies or services, and final payment.

(End of Clause)

452.232-71 Progress Payments for Commercial Construction Contracts (Dec 2025)

(a) Contractor entitlement to progress payments. The Contractor may request progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished that meets the standards of quality established under the contract, as approved by the Contracting Officer.

(b) Computation of amounts. Progress payments will be authorized when the payment requested is properly due in accordance with this contract; the work will be performed in accordance with the contract; and there has been no impairment or diminution of the Government’s security under this contract. The Contracting Officer may authorize consideration of:

3. Materials delivered on site and preparatory work;

4. Materials delivered to the Contractor at locations other than the site, if:

i. Specifically authorized by the contract; and

ii. The Contractor provides satisfactory evidence of title and intended use in the contract.

(c) Contractor request for progress payments. The Contractor’s request for progress payments shall include the following:

1. An itemization of the amounts requested, related to the various elements of work required by the contract;

2. A listing of the amount included for work performed by each subcontractor;

3. A listing of the total amount of each subcontract;

4. A listing of the amounts previously paid to each subcontractor; and

5. Additional supporting data in a form and detail required by the Contracting Officer.

(d) Contractor Certification. Each request for progress payment shall be accompanied by the following certification:

I hereby certify, to the best of my knowledge and belief, that—

1. The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

2. All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

3. This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

4. This certification is not to be construed as final acceptance of a subcontractor’s performance.

________________________________________________(name) ________________________________________________(title) ________________________________________________(date)

(e) Access for verification of payment entitlement. To verify the Contractor’s entitlement to progress payments under this contract, the Contractor shall provide the Government, upon request and during normal business hours, access to the following:

1. Records and Documentation:

(i) Certified progress payment requests and supporting documentation;

(ii) Subcontractor and supplier invoices, payment records, and lien waivers;

(iii)Updated schedule of values and progress schedules;

(iv) Quality assurance and inspection reports;

(v) Payroll records, if applicable under labor provisions.

2. Facilities and Worksite Access:

(i) Physical access to the construction site for inspection of work progress;

(ii) Access to off-site storage locations for materials billed but not yet incorporated into the work; or (iii)Access to any fabrication facilities where contract-related work is being performed.

3. Access to electronic invoicing or project management systems used to track progress and payments, if such systems are used in contract performance.

(f) Dates for payment. A progress payment under this clause is a contract progress payment under the Prompt Payment clause of this contract, and except as provided in paragraph (g) of this clause, approved requests shall be paid within 30 days of submittal of a proper request for payment.

(g) Liquidation of progress payments. Progress payments shall be liquidated by deducting from the payment of each item the total unliquidated amount of progress payments made for that separately priced unit of that line item. The liquidation amounts for each line item shall be clearly delineated in each request for progress payment submitted by the Contractor.

(h) Security for progress payments. In the event the Contractor fails to provide adequate security as required in this contract, no progress payment shall be made under this contract. Upon receipt of adequate security, progress payments shall be made, including all previous payments to which the Contractor is entitled, in accordance with the terms of the contract. If at any time the Contracting Officer determines that the security provided by the Contractor is insufficient, the Contractor shall promptly provide such additional security as the Contracting Officer determines necessary. In the event the Contractor fails to provide such additional security, the Contracting Officer may collect or liquidate such security that has been provided, and suspend further payments to the Contractor; the Contractor shall repay to the Government the amount of unliquidated progress payments as the Contracting Officer at his sole discretion deems repayable.

(i) Special terms regarding termination for cause. If this contract is terminated for cause, the Contractor shall, on demand, repay to the Government the amount of unliquidated progress payments. The Government shall be liable for no payment except as provided by the Termination for Cause paragraph of the clause at Federal Acquisition Regulation 52.212-4, Contract Terms and Conditions—Commercial Products and Commercial Services.

(j) Reservation of rights.

1. No payment, vesting of title under this clause, or other action taken by the Government under this clause shall-

(i) Excuse the Contractor from performance of obligations under this contract; or

(ii) Constitute a waiver of any of the rights or remedies of the parties under the contract.

2. The Government’s rights and remedies under this clause-

(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(k) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-

1. Notify the Contracting Officer of such performance deficiency; and

2. Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-

(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or

(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.

(l) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

(m) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-

1. Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or

2. Waiving the right of the Government to require the fulfillment of all the terms of the contract.

3. The Government’s rights and remedies under this clause-

(i) Shall not be exclusive, but rather shall be in addition to any other rights and remedies provided by law or this contract; and

(ii) Shall not be affected by delayed, partial, or omitted exercise of any right, remedy, power, or privilege, nor shall such exercise or any single exercise preclude or impair any further exercise under this clause or the exercise of any other right, power, or privilege of the Government.

(n) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (l) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

(o) Final payment. The Government shall pay the amount due the Contractor under this contract after-

1. Completion and acceptance of all work;

2. Presentation of a properly executed voucher; and

3. Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).

(p) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(End of clause)

Invoicing Instructions: To invoice, a vendor must first enroll in the Invoice Processing Platform (IPP) by visiting https://www.ipp.gov/vendors/index.htm. Once enrolled, all invoices must be submitted electronically through IPP. The IPP is a government-wide secure web-based payment information service offered free of charge to government agencies and their suppliers by the U.S.

Department of Treasury’s Financial Management Service (FMS). One-time enrollment in IPP means that you will receive a series of e-mails from Treasury services. The first email will have the IPP Logon ID and link to the IPP application. A second e-mail, containing the password will be sent within 24 hours. Once you receive these emails, please login to the IPP application and complete the registration process.

Benefits of registering with IPP include the ability for your company to create invoices directly from a contract award and submit them electronically, as well as:

• E-mail notification when invoice(s) are paid

• Online payment history

• Remittance download

E-mail notifications of payments are sent when a payment is distributed to your bank account and will include all pertinent payment information. The IPP Customer Support Desk is available to assist users Monday through Friday (excluding bank holidays) from 8:00AM - 6:00PM ET, including answering any questions related to accessing IPP or completing the registration process.

Their toll-free number is (866) 973-3131 or they can be reached at:

IPPCustomerSupport@fms.treas.gov.

Award Type

It is anticipated that a firm-fixed price contract will be awarded as a result of this combined synopsis/solicitation. The total duration of this contract shall not exceed 120 days from time of award.

http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3727&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section6305&num=0&edition=prelim

The Government intends to make one award from this solicitation. Therefore, to be considered responsive, contractors must submit pricing for all items.

Site Visit

Site visit participation is mandatory to inspect the site where the work will be performed. The site visit will be April 16, 2026, 10:00 AM Central Time, Location: Biosciences Research Laboratory 1616 Albrecht Blvd N, Fargo, ND 58102.

Questions

Questions shall be submitted via email to osvaldo.rodriguez@usda.gov and are due no later than 4/15/2026, at 10:00 AM Eastern Time. This will ensure enough time to respond before the solicitation period ends. Please include the solicitation name and number as the subject line of the email.

Evaluation and Basis for Award

The provision at Federal Acquisition Regulation (FAR) 52.212-2 Evaluation of Commercial Items is not applicable to this solicitation. In lieu of this provision, quotes will be evaluated in accordance with FAR 12.203 based on the criteria listed below. Award will be made to the offeror representing the best value to the Government.

All offerors must provide the following minimum information and documentation with their quotations to be considered responsive and have their offers evaluated:

· Provide a detailed description of how the requirements listed in the SOW will be completed. The vendor/quoter must demonstrate their knowledge and understanding of the required construction.

The written narrative must include sufficient detail to clearly and concisely address the proposed sequence of technical tasks and activities. Quotes that merely offer to provide the construction as described in the SOW will not receive further consideration for the contract award. A simple statement of capabilities will not suffice.

· Provide a list of at least two (2) references for work as described in the SOW. The work must have been completed within the last two (2) years. Include a brief narrative of the work completed to show relevancy to the work described in the SOW. It is desirable, but not required, that references be other Federal Agencies.

Reference information must include at a minimum, the following:

1. Location of installation

2. Contract Number/Reference No.

3. Period of Performance

4. Total cost

5. Name of Agency/Entity/Business

6. Point of Contact for Agency/Entity/Business (including phone numbers & email)

7. Complete and thorough description of the work performed

The description should include specifics about the scope of projects completed. This information is requested to assist in evaluation of relevancy to this project in terms of type, complexity, and magnitude. The point of contact will be asked to assess/evaluate past performance.

· Provide a detailed price breakdown similar to a schedule of values which includes all materials, labor, and equipment for the entire project as specified in the Statement of Work.

Evaluation Method

The Government will evaluate quotations based on the lowest price technically acceptable criteria.

Only the lowest priced offer will be evaluated for Technical Acceptability. Should the lowest priced offer not receive an acceptable technical rating, the process will continue in order of lowest priced offer until the lowest price, technically acceptable offer with acceptable or neutral past performance is identified.

The Government shall evaluate the vendor's quote on a pass/fail basis, assigning ratings of acceptable or unacceptable using the ratings and descriptions outlined as follows:

Rating Description Acceptable The quote meets the requirements of the solicitation. The vendor has relevant experience, which has been positively verified by the references. -and-

The vendor has the knowledge and understanding of the required construction.

Unacceptable The quote does not meet the requirements of the solicitation. The vendor has no relevant experience and/or the references have negatively verified the past work.

-and/or-

The vendor does not have the knowledge and understanding of the required construction.

Price- The total evaluated price shall be the sum of all Contract Line Item Numbers (CLINs). Quotes will be evaluated to determine whether it is fair and reasonable. The Government shall not award a contract that is not fair and reasonable. Vendors are encouraged to offer discounts beyond their current pricing.

52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998) This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017) 52.209-2 Prohibition on Contracting with Inverted Domestic Corporations - Representation (Sep 2025) 52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law (Sep 2025) 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Nov 2025)

The following provisions are applicable if checked: You can either leave all clauses and check the boxes of the ones that apply or delete the clauses that do not apply. If you delete lines, you will need to right-click on the box and select “remove content control” before it will delete.

☒ 52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions (Sep 2024) ☒ 52.204-7 System for Award Management—Registration (Nov 2025) ☒ 52.222-5 Construction Wage Requirements, Secondary Site of the Work (Nov 2025) ☒ 52.225-10 Notice of Buy American Requirement- Construction Materials (May 2014)

Other Applicable FAR Provisions

52.233-2 Service of Protest (Sep 2025)

AGAR Provisions

452.203-70 Anti-Discrimination and Diversity, Equity, and Inclusion (DEI) Certification (Dec 2025)

(a) By submission of its offer, the offeror certifies that:

4. It is compliant with all applicable Federal anti-discrimination laws and the Equal Protection principles of the U.S. Constitution.

5. Neither it nor any proposed subcontractor or teaming partner operates or funds any program, policy, or initiative that promotes DEI in a manner that violates any applicable Federal anti-discrimination laws, including but not limited to Title VI and VII of the Civil Rights Act of 1964, or the Equal Protection principles of the U.S. Constitution.

(b) If the offeror participates in, facilitates, or funds programs that implicate Title VI of the Civil Rights Act of 1964 or Title IX of the Education Amendments of 1972, as amended, including but not limited to grants to or for schools, colleges, universities, 4-H programs, non-governmental organization (NGO) programs, sports programs, and education-related grants to prisons or other detention facilities, by submission of its offer, the offeror certifies that it is compliant with those laws, including the requirements set forth in Executive Order 14168, Defending Women from Gender Ideology Extremism and Restoring Biological Truth to the Federal Government, and Executive Order 14173, Ending Illegal Discrimination and Restoring Merit-Based Opportunity.

(c) The offeror affirms that the above requirements are conditions of payment that go to the essence of the contract and are therefore material terms of the contract. Payments under the contract are predicated on compliance with the above requirements, and therefore the offeror will not be eligible for funding under the contract or to retain any funding under the contract absent compliance with the above requirements.

(d) This certification reflects a change in the Government’s position regarding the materiality of the foregoing requirements and therefore any prior payment of similar claims does not reflect the materiality of the foregoing requirements to this contract.

(e) Submission of a knowing false statement relating to offeror’s compliance with the above requirements and/or eligibility for the contract may subject the offeror to liability under the False Claims Act, 31 U.S.C. § 3729, and/or criminal liability, including under 18 U.S.C. §§ 287 and 1001.

(f) Failure on the part of the offeror or its subcontractors to comply with the terms of this clause may be grounds for the Contracting Officer to terminate the contract for default.

(End of Provision)

NOTICE FOR FILING AGENCY PROTESTS

United States Department of Agriculture (USDA) Ombudsman Program

The USDA is committed to issuing solicitations and awarding contracts in a fair and prompt manner.

The Ombudsman Program for Agency Protests (OPAP) was established to address protest issues within the agency, providing an alternative to costly and time-consuming litigation. Operating independently, OPAP offers relief comparable to that granted by the Government Accountability Office (GAO). Interested parties are encouraged to resolve concerns through USDA’s internal Alternative Dispute Resolution (ADR) process before pursuing external forums such as the GAO.

Concerns may be addressed informally or through a formal agency protest filed with either the Contracting Officer or the Ombudsman.

Informal Forum with the Ombudsman

1. Initial Point of Contact: Interested parties who believe a specific USDA procurement is unfair or otherwise defective should first direct their concerns to the applicable Contracting Officer.

2. Escalation: If the Contracting Officer is unable to address their concerns, interested parties are encouraged to contact the USDA Ombudsman for Agency Protests. Under this informal process, the agency is not required to suspend contract award performance. Utilization of the informal forum does not suspend any time requirement for filing a formal protest with the agency or other forums.

3. Required Information: To ensure a timely response, interested parties should provide the following information to the Ombudsman: solicitation/contract number, contracting office, Contracting Officer, and solicitation closing date (if applicable).

Formal Agency Protest with the Ombudsman

1. Effort to Resolve: Prior to submitting a formal agency protest, protesters must first use their best efforts to resolve their concerns with the Contracting Officer through open and frank discussions.

2. Independent Review: If the protester’s concerns remain unresolved, an Independent Review is available by the Ombudsman. The protester may file a formal agency protest with either the Contracting Officer or, alternatively, with the Ombudsman under the OPAP program. Contract awards or performance will be suspended during the protest period unless justified in writing for urgent and compelling reasons or determined in writing to be in the best interest of the Government.

3. Resolution Timeline: The agency’s goal is to resolve protests within 35 calendar days from the date of filing.

4. Required Information: Protests shall include the information set forth in FAR 33.104(a)(3).

Failure to submit the required information may result in a delay or dismissal of the protest.

5. Timeliness: Protests must be filed within the timeframes specified in FAR 33.104.

6. Submission: Formal protests under the OPAP program should be submitted electronically to SPE.inquiry@usda.gov and the Contracting Officer.

Election of Forum. By initiating a protest with the USDA, the protester agrees not to pursue the same matter with the Government Accountability Office (GAO) or any other external forum while the agency protest is pending. If a protest is filed externally, the agency protest will be dismissed.