This document is a Schedule of Items for the Fairplay Office Rehabilitation project, which includes the following base items: Mobilization, Roof Replacement, Snow/Ice Melt System, Interior/Exterior Modifications, and Communications. There is also an optional item for Chain Link Fencing. The overall project cost is stated, with the base items totaling $______________ and the optional item total of $______________.
The related federal contract opportunity is for the South Park District Office Rehabilitation Project, which involves the rehabilitation of the South Park Ranger District Office. The project is being solicited as a 100% Total Small Business set-aside, with the intent to award a Firm-Fixed Price contract. The scope of work includes mobilization, quality control, roof replacement, snow/ice melt system installation, interior and exterior modifications, and the installation of additional communication outlets. An optional item for a chain link fence is also included. The period of performance is 60 days after Notice to Proceed, and construction must be completed by October 31, 2025. The estimated cost range for the project is between $100,000 and $260,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage Determination CO20240026 - Building - Park County CO.pdf | ||
| Contractor Experience Questionaire.docx | DOCX document | |
| Contractor Questions and Answers Template.doc | DOC document | |
| Drawings - South Park District Office Rehab .pdf | ||
| SOW - South Park District Office Rehab.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PSICC NFs AND NGs
FAIRPLAY OFFICE REHAB
Schedule of Items
FAIRPLAY OFFICE REHAB SCHEDULE OF ITEMS
PSICC NFs AND NGs
Item No. Description
Method of Measurement Total
BASE ITEMS
BI 1 Mobilization Lump Sum $_________
BI 2 Roof Replacement Lump Sum $_________
BI 3 Snow/Ice Melt System Lump Sum $_________
BI 4 Interior/Exterior Modifications Lump Sum $_________
BI 5 Communications Lump Sum $_________
$______________ BASE TOTAL:
OPTIONAL ITEMS
OI 1 Chain Link Fencing Lump Sum
OPTIONAL ITEM TOTAL:
TOTAL PROJECT COST (BASE PLUS OPTIONAL):