SmartPGH_Early_Action_-_Technical_Specifications__(1).docx

DOCX document 48 KB Posted

Attached to
SMARTPGH Cable Installation
Solicitation number
2025-IFB-171
Issued by
Allegheny County, Philadelphia City, Pennsylvania

About this file

The document is a technical specifications file for the SmartPGH Early Action project issued by the City of Pittsburgh Department of Mobility and Infrastructure (DOMI) in Allegheny County, Pennsylvania. The project involves the installation of a 96-count fiber optic cable trunk line between the Traffic Management Center (TMC) and specified termination points in the Central Business District, including work at the City-County Building and Armstrong Tunnel. The project scope includes fiber optic cable installation, splicing, hub cabinet installation, and comprehensive testing, with a contract duration of 140 consecutive calendar days from the written Notice to Proceed.

The project will be performed entirely within public right-of-way, with an estimated total fiber optic cable installation of approximately 96 strands of single-mode fiber. The work includes complex technical requirements such as installing conduits, performing fusion splices, testing cable continuity and attenuation, and replacing existing fiber hub cabinets. Contractors must adhere to specific traffic management protocols, coordinate with Pittsburgh Regional Transit, and follow strict time restrictions for work, including limitations during holidays, sporting events, and city celebrations. The project involves detailed specifications for equipment, including IT racks, fiber optic termination panels, and splice enclosures, with precise technical requirements for each component.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL SPECIFICATIONS

SmartPGH Early Action - Central Business District City of Pittsburgh, Allegheny County, Pennsylvania Project Limits:

City of Pittsburgh Traffic Management Center (TMC) at 412 Boulevard of the Allies to Smithfield Street Bridge. TMC to City-County Building (CCB) via Boulevard of the Allies and Grant Street. CCB to Armstrong Tunnel north portal via Grant Street, Sixth Avenue, and Forbes Avenue.

1st and 2nd Wards

Pittsburgh, PA Scope of Work:

The scope of work under this contract shall consist of the following:

Installation of 96-count fiber optic cable trunk line between the TMC and indicated termination points. This work includes fiber optic splicing, hub cabinet installation, and testing.

It is intended that the work described in this Contract be complete in every detail, including furnishing, constructing, installing, removing, and testing all equipment, materials and products necessary for the aforementioned scope of work. All work is to be performed within Public Right of Way. Any work performed outside of Public Right of way will be the CONTRACTOR’s responsibility to coordinate with private property owners.

Plans and Specifications All work done and materials furnished under this Contract shall be in accordance with the Construction Plan, the Technical Specifications, City of Pittsburgh Department of Mobility and Infrastructure (DOMI) Standards of Construction, the Pennsylvania Department of Transportation Publication 408, Specifications, dated 2020, Pennsylvania Department of Transportation Civil and Structural Standard Drawings for Intelligent Transportation Systems Publication 647, Pennsylvania Department of Transportation Publication 148, Pennsylvania Department of Transportation Publication 213, and the Manual on Uniformed Traffic Control devices (MUTCD), where applicable.

Should any of the Technical Specifications or special notes on the drawings conflict with any of the provisions of the Standards of Construction of the City of Pittsburgh or the Pennsylvania Department of Transportation Specifications mentioned above, the Technical Specifications of this contract and/or notes on the final approved for construction drawings shall govern; followed by the City of Pittsburgh Specifications and Standards, then the Pennsylvania Department of Transportation Specifications.

Protection of Utilities and Structures Within the limits of this project, there may be existing aboveground and underground electric, telephone, gas, water, sewer and other public utility structures. It shall be the responsibility of the CONTRACTOR to discover and determine their location and to carry out his work carefully and skillfully so as to avoid damage to them. In the event any utility facility or structure is damaged, the repair of any such damage shall be made at the sole expense of the CONTRACTOR before the acceptance of the work, and the OWNER will not be required to compensate the CONTRACTOR for such damage in any manner whatsoever.

The CONTRACTOR shall be responsible for the preservation of all public and private underground and surface utilities and structures at or adjacent to the site of construction, insofar as they may be endangered by his operations. This shall hold true whether or not they are shown on the Contract Drawings. If they are shown on the drawings, their locations are determined from the best available sources, and in any event, others not shown may be encountered in the field. The CONTRACTOR shall give ample and reasonable notice to all private, corporate or municipal owners before work is done near their utility or structure, shall properly protect all utilities and structures encountered, shall at his own expense, repair or replace any that he damages and shall constantly proceed with caution to prevent undue interruptions to utility services.

The CONTRACTOR shall contact Duquesne Light Company (DLC) and follow all manhole entry process requirements and recommendations for working in underground facilities before entering any manhole.

Maintenance and Protection of Traffic The CONTRACTOR shall furnish all necessary labor and materials for the maintenance and protection of traffic during construction in accordance with PennDOT Publication 213, Temporary Traffic Control Guidelines. All required separate pay items shall be incidental to item 0901-0001.

Shop Drawing Submittal It shall be the CONTRACTOR'S responsibility to submit to the PROJECT MANAGER one (1) copy of the shop drawings, catalog data and material certifications for review and approval by the PROJECT MANAGER and OWNER. It is preferred that the number of submissions be kept to a minimum and made shortly after the "Notice to Proceed". On each shop drawing or catalog cut sheet the PennDOT approval number or provisional number shall be marked in a prominent place.

Building Access Coordinate access to the TMC and CCB with the PROJECT MANAGER and OWNER for locating and access to applicable storage rooms for fiber optic cable splicing and termination.

Condition of Work Area It shall be the CONTRACTOR'S responsibility to clear and clean the work area after each day's work and after the contract work has been completed.

Project Schedule:

Time being of the essence, the CONTRACTOR shall commence work after the "Notice to Proceed" has been given by the OWNER. After beginning work, the CONTRACTOR shall work continuously until completion and shall notify the OWNER and the PROJECT MANAGER of each instance and reasons therefore, of suspension of work. The work shall be substantially completed within 140 consecutive calendar days from the date in written “Notice to Proceed” by the OWNER.

Acceptance Prior to the OWNER'S acceptance of the work, a final inspection of items shall be conducted by the PROJECT MANAGER, ENGINEER, and the OWNER to determine if all equipment is acceptably installed. It shall be the CONTRACTOR'S responsibility to correct any deficiencies or omissions in the work to the satisfaction of the PROJECT MANAGER, ENGINEER, and the OWNER.

Schedule of Quantities Attached to these Technical Specifications is a schedule of quantities and prices for the project. This schedule shall be completed by the bidder and a copy shall be attached to the Bid. The quantities are approximate, and it is the responsibility of the bidder to verify the amounts before preparing his bid.

Special Provisions

CITY OF PITTSBURGH STANDARDS AND SPECIFICATIONS

Obtain any referenced City of Pittsburgh Standards and Specifications not included in the bid package from the following:

Leila Bouabdellaoui – Project Manager City of Pittsburgh Department of Mobility and Infrastructure City County Building, Suite 301 414 Grant Street Pittsburgh, PA 15219-2455 Phone: (412) 526-7105 Email: Leila.Bouabdellaoui@pittsburghpa.gov

NOTICE TO CONTRACTOR – PITTSBURGH REGIONAL TRANSIT

Notify Pittsburgh Regional Transit (PRT) of the construction start date and time 14 days prior to the start of any construction activities on the project site. Provide a construction schedule to PRT 14 days prior to the start of any construction activities on the project site. Any changes to the construction schedule shall be communicated to PRT on a bi-weekly basis. The schedule should display the type of work occurring and the work hours. Notify PRT if work will occur on the weekends.

Attend a minimum of one project planning and scheduling meeting with PRT to discuss the work schedule, activities, and the impact of those activities on PRT facilities.

Provide PRT with the contact information of your construction Project Manager or designated representative.

Maintain good communication and dialogue with PRT in order to successfully complete the project.

NOTICE TO CONTRACTOR – PROJECT COORDINATION

Coordinate all work activities, especially lane closures, with other projects in the area, including, but not limited to:

· SR 3027 Section A05 – Smithfield Street Bridge Preservation Project (ECMS 28525)

· Armstrong Tunnel Rehabilitation Project (ECMS 93922)

· PRT Bus Rapid Transit Project

NOTICE TO CONTRACTOR – STREET OPENING AND OBSTRUCTION PERMITS

Street Opening and Obstruction Permits for City sponsored jobs must be requested from City Project Managers. The info needed to create a permit is as follows:

1. Applicant - Project Manager Name, Email Address & Phone Number

2. Work Description

3. Location of Work - please be as descriptive as possible

4. Contractor Company - to be listed on the permit

5. Contractor Foreman Name, Phone Number & email address

6. Work start and anticipated end date

7. Traffic Obstruction Description- closure requests, PATA's and/or MPT plans

8. Project plans or other attachments (if applicable)

This information should be sent from the Project Manager to Sergey Brodskiy at sergey.brodskiy@pittsburghpa.gov at least 2 weeks before work is to begin. Fees are waived for City jobs when using this system. The information should not come directly from a consultant or contractor.

ITEM 0901-0001 – MAINTENANCE AND PROTECTION OF TRAFFIC DURING CONSTRUCTION

In accordance with Section 901 and as follows.

Section 901.1 DESCRIPTION – Revise the first sentence to read:

This work is the furnishing, installing, maintaining and protection of traffic adjacent to and within the Work Zone including the Active Work Zone, and relocating of traffic control devices.

Section 901.2 MATERIAL - Revise by adding the following sentence:

For all barricades, provide barricade rails constructed of non-metallic materials.

Section 901.3 CONSTRUCTION:

ADVANCE REQUIREMENTS

Provide two weeks advance notice to the City of Pittsburgh Department of Mobility and Infrastructure prior to beginning any work or imposing any traffic restrictions. Additionally, provide notification to all affected businesses and property owners four days prior to the erection of the Advance Construction Advisory signs and any work that may impact the businesses and property owners.

Obtain a Street Opening and Obstruction Permit from the PROJECT MANAGER.

Coordinate working schedule with any adjacent PennDOT, County, and/or local projects.

A workday is defined as any day from Monday through Friday except Holidays during normal DOMI office hours. The following official holidays and events will not be included as workdays. For a complete list of events, coordinate with the PROJECT MANAGER.

Holidays

· New Year’s Day

· Dr. Martin Luther King, Jr. Day

· Good Friday

· Memorial Day

· Independence Day

· Labor Day

· Veteran’s Day

· Thanksgiving Day

· Day after Thanksgiving Day

· Christmas Day

Events

· Pittsburgh Marathon

· Light Up Night

· Three Rivers Arts Festival

· EQT Pittsburgh 10 Miler Race

· EQT Three Rivers Regatta

· Pittsburgh Steelers home games

· Pittsburgh Pirates home games

· Pittsburgh Penguins home games

· Picklesburgh (Blvd of the Allies)

· St. Patrick’s Day Parade and other parades (Grant)

· Rush to Crush Cancer (Grant)

· Open Streets PGH (Forbes)

Section 901.3(a) General. – Revise the seventh paragraph to read:

Construct and erect all devices in an efficient manner. Maintain, clean, and properly operate the devices during the entire time they are in use. Traffic control devices must meet the acceptable or marginal standards of the Pennsylvania Quality Guidelines for Temporary Traffic Control Devices after the devices have been installed. Only place devices a maximum of two weeks prior to implementing restrictions. Remove all devices when no longer required or not used for a period of two weeks unless authorized, in writing, by DOMI or authorized representative. Where operations are performed in stages, keep only the necessary devices that apply to the present stage of construction.

TRAFFIC CONTROL/DEVICES REQUIREMENTS

The signs and traffic control devices listed or indicated in Publication 213 represent the minimum requirements for this item and as such, are for information only. The number and types of traffic control signs and devices for this project will be predicated on the number and location of work sites, the extent of repairs and the planned sequence of operations.

All vinyl roll up material used to overlay overhead and all type (A, B, C, D, E, and F) signs shall be reflectorized including the letters and shields.

Provide new traffic control signs and devices at the start of the project. Do not use reflective sheeting that is scratched, scarred, and dirty or shows evidence of loss of reflectivity. Do not use signs or devices that are cracked, bent, dented or broken. Replace reflective sheeting should it become damaged where retroreflectivity becomes defective or falls below the minimum retroreflectivity levels as per Chapter 2 of the Publication 46. Immediately repair or replace damaged, defaced or dirty signs, devices or barrier. Replace traffic control devices as necessary as per Appendix C in the Publication 213.

For long-term temporary traffic control set-ups, place an identification marker on the back of the sign listing the ECMS number so that the sign can be distinguished from other projects’ signs.

Mount all construction warning signs (W series), R11-2, R11-2-1, R11-3A, R11-4, and G20-1 for long-term operations on Type III barricades. Include one Type B light on each W series and R11-3A signs and two Type B lights on R11-2, R11-2-1, and R11-4 signs. If it is not possible to mount construction warning or other signing as indicated or specified, submit an alternate method for approval by DOMI or authorized representative.

Do not position construction warning signs on sidewalks unless the signs can be positioned to meet the minimum requirements stated in Publication 213. If construction warning signs cannot be positioned to meet the minimum requirements, then signs should either be field-adjusted per the Inspector-in-Charge’s approval or installed on “H” Bases per the TC-8717 Standards.

Provide additional channelizing devices and barricades at intersections, major driveways and ramps to prevent vehicles from turning onto any lane closed for construction. Space channelizing devices at 5-foot intervals or as directed by DOMI or authorized representative or the Inspector-In-Charge.

Use channelizing devices with Type C steady burn lights for all nighttime lane restrictions. Mount a light on each device used in transition areas and on every third device used in tangent sections.

For short term nighttime operations, place a Type B light on all W-series and R11-3A signs and two Type B lights on R11-2, R11-2-1, and R11-4 signs used in the traffic restrictions.

The contractor shall have a sufficient amount of the following signs available in case their use becomes necessary: W3-4 “BE PREPARED TO STOP” and W20-7 “FLAGGER SYMBOL”. These signs are not intended to be part of the required normal traffic control or a supplement thereto.

When flaggers are used, they must be properly attired. This includes, but is not limited to, vest, leggings, and hard hat.

Space channelizing devices in the tangent sections at one times the normal posted speed limit unless otherwise noted on the Traffic Control Plan or as directed by DOMI’s authorized representative or the Inspector-In-Charge. Channelizers used in the PATA Drawings from Publication 213 shall be spaced at one times the normal posted speed limit in tangent sections.

For overnight operations, if located within 500 feet of any residence or business use arrow panels that are electrically, solar or battery operated.

When working on entrance and exit ramp gore areas, the same Traffic Restrictions for main road SR's must be adhered to for ramp SR’s.

Erect "ROAD WORK AHEAD" (W20-1, W30-1-6) signs with Type B lights attached on each intersecting road and major drive, for the appropriate situation as shown in PennDOT Publication 213.

Post Act 229 signs in accordance with the requirements specified in PennDOT Publication 213 - PATA 003, 'Act 229 Guidelines'.

Provide a Traffic Control Supervisor or Supervisors and phone numbers where they can be reached on a 24 hour - 7 days a week basis for the duration of the project. The Traffic Control Supervisor must be knowledgeable of work zone traffic control including incident management. The Traffic Control Supervisor must have a thorough understanding of the Manual on Uniform Traffic Control Devices (MUTCD) and PennDOT Publications 212 and 213. The Traffic Control Supervisor shall attend the pre-job meeting. The Supervisor's responsibilities are as follows:

Notify DOMI and affected property owners of all traffic restrictions.

Implement and maintain traffic control schemes. Place and maintain all traffic control signs and devices used on the project.

Conduct daily reviews and document the performance of traffic control signs, devices, and off-duty uniformed police during the day and night, adverse weather conditions and active and inactive construction operations, as directed. The Traffic Control Supervisor will present all MPT problems and discrepancies in writing to the Inspector-in-Charge by Noon of each day.

Prepare and submit the proposed corrective action to the Inspector-in-Charge. Correct any deficiencies or damage discovered during the daily review immediately.

Maintain a daily written record of any crashes, work zone incidents, and maximum queue lengths for each traffic pattern for the life of the project. All feedback received from the public through phone calls, in person, or in writing shall also be captured. This information shall be submitted daily to the Inspector-in-Charge and will be logged and forwarded to DOMI when requested.

Maintain ongoing communication with the Inspector-in-Charge regarding operations that will impact transportation operations in the project area. The Contractor shall develop and maintain lists of phone, fax numbers and e-mail addresses for the affected stakeholders within the project area, including but not limited to: school districts, emergency services, major businesses, transit companies, nearby trucking firms, and other prominent traffic generators in the project vicinity. The Contractor is responsible for notifying these groups of changes in the traffic control phasing at least 48 hours in advance of the phase change or as directed by the Inspector-in-Charge in writing when this notification occurs.

During nighttime operations, all workers must wear hard hat, Class 3 vest and leggings unless operation is behind positive protection (barrier).

A minimum of one ingress and egress point for each property must be maintained for both travel directions provided they are not separated by a barrier or grass median.

Limit any lane closure to the length necessary to safely perform the required work.

When closing a lane at or within close proximity to a signalized intersection or having to shut off power to a signalized intersection, provide off-duty uniformed police officers to control and direct traffic at the intersection. Provide police officers to manually operate traffic signals or have the police officers place the signals in a flashing mode and direct traffic at the intersection. Give the City of Pittsburgh one-week advance notice prior to working within a signalized intersection. Prior to removing the police officer at the end of the workday, return the traffic signals to normal operation.

Open the specified roadway and/or ramps by the specified times, dates, and/or calendar day durations, or be assessed Road Users Liquidated Damages as specified in the Special Provisions entitled "Road Users Liquidated Damages."

TRAFFIC/CONSTRUCTION RESTRICTIONS

Do not cause intermittent traffic stoppages for longer than 5 minutes. When traffic stoppages are necessary, utilize the appropriate PATA in PennDOT Publication 213. Do not stop vehicular or pedestrian traffic between 7 A.M. to 6 P.M. Monday through Sunday. After any one 5-minute stoppage, all Queued Traffic shall be cleared and any succeeding 5-minute stoppage shall not occur until traffic has returned to "normal" pre-stoppage flow.

· TIME RESTRICTIONS

All streets, approaches, sidewalks, and driveways:

Do not restrict vehicular or pedestrian traffic weekdays from 7 A.M. to 6 P.M. Work may be performed in an available parking lane from 9 A.M. to 4 P.M. and 6 P.M. to 6 A.M. weekdays. Work may be performed in the travel lane from 9 A.M. to 4 P.M. weekdays with the presence of an off-duty uniformed police officer or from 6 P.M. to 6 A.M. with properly attired flaggers. Any deviation from this schedule must be approved in advance by the City Traffic Engineer.

Provide at least one 10-foot travel lane during working hours.

For long-term operations, maintain at least one 10-foot travel lane in each direction at all times.

Saturdays and Sundays –

Do not restrict vehicular or pedestrian traffic weekends from 7 A.M. to 6 P.M. Work may be performed in an available parking lane from 9 A.M. to 4 P.M. and 6 P.M. to 6 A.M. weekends. Work may be performed in the travel lane from 9 A.M. to 4 P.M. weekends with the presence of an off-duty uniformed police officer or from 6 P.M. to 6 A.M. with properly attired flaggers. Any deviation from this schedule must be approved in advance by the City Traffic Engineer.

Provide at least one 10-foot travel lane during working hours.

For long-term operations, maintain at least one 10-foot travel lane in each direction at all times.

· ADDITIONAL RESTRICTIONS

When ADA curb ramp closures are required, close only one ADA curb ramp corner (per intersection) at a time. Do not work on adjacent intersections concurrently.

Failure to adequately maintain driveway access will be subject to work zone liquidated damages. Driveway tie-ins shall be installed to the satisfaction of the Department and driveway owners.

· HOLIDAY RESTRICTIONS

· Labor Day (Including the Saturday and Sunday before Labor Day) - No work permitted affecting any travel lane or shoulder.

Fridays before Labor Day –

12 Midnight to 6 A.M.: Provide minimum number of travel lanes as indicated under TIME RESTRICTION section.

6 A.M. to 12 Midnight: No work permitted affecting any travel lane or shoulder.

· Veteran's Day (Including the Saturday and Sunday before Veteran’s Day) - No work permitted affecting any travel lane or shoulder.

Fridays before Veteran's Day –

12 Midnight to 6 A.M.: Provide minimum number of travel lanes as indicated under TIME RESTRICTION section.

6 A.M. to 12 Midnight: No work permitted affecting any travel lane or shoulder.

· Thanksgiving (Including Thanksgiving Day through the Sunday after Thanksgiving Day) - No work permitted affecting any travel lane or shoulder.

Wednesday before Thanksgiving –

12 Midnight to 6 A.M.: Provide minimum number of travel lanes as indicated under TIME RESTRICTION section.

6 A.M. to 12 Midnight: No work permitted affecting any travel lane or shoulder.

· Christmas through New Year's Day - No work permitted affecting any travel lane or shoulder on December 24, 25, 26, 27, 28, 29, 30 and 31 and January 1.

· Dr. Martin Luther King, Jr. Day - (Including the Saturday and Sunday before Dr. Martin Luther King, Jr. Day) - No work permitted affecting any travel lane or shoulder.

Fridays before Dr. Martin Luther King, Jr. Day –

12 Midnight to 6 A.M.: Provide minimum number of travel lanes as indicated under TIME RESTRICTION section.

6 A.M. to 12 Midnight: No work permitted affecting any travel lane or shoulder.

· Good Friday - No work permitted affecting any travel lane or shoulder.

Friday before Easter –

12 Midnight to 6 A.M.: Provide minimum number of travel lanes as indicated under TIME RESTRICTION section.

6 A.M. to 12 Midnight: No work permitted affecting any travel lane or shoulder.

· St. Patrick's Day (Including the Saturday before and/or after St. Patrick's Day) - No work permitted affecting any travel lane or shoulder. For the Saturday before or after restrictions, verify with DOMI which Saturday will have restrictions due to St. Patrick's Day celebrations.

Fridays before St. Patrick's Day –

12 Midnight to 6 A.M.: Provide minimum number of travel lanes as indicated under TIME RESTRICTION section.

6 A.M. to 12 Midnight: No work permitted affecting any travel lane or shoulder.

· Memorial Day (Including the Saturday & Sunday before Memorial Day) - No work permitted affecting any travel lane or shoulder.

Fridays before Memorial Day –

12 Midnight to 6 A.M.: Provide minimum number of travel lanes as indicated under TIME RESTRICTION section.

6 A.M. to 12 Midnight: No work permitted affecting any travel lane or shoulder.

· Independence Day - No work permitted affecting any travel lane or shoulder on July 2, 3, 4, and 5, 2021 and July 2, 3, and 4, 2022.

Event Restrictions:

In addition to the work limitations outlined above, no travel lane closures or restrictions affecting any streets, approaches, sidewalks, and driveways will be permitted during any of the following events. For a complete list of events, coordinate with the PROJECT MANAGER.

· Light Up Night: As directed when date is announced.

· Pittsburgh Marathon: As directed when date is announced.

· Three Rivers Arts Festival: As directed when date is announced.

· EQT Pittsburgh 10 Miler - As directed when date is announced.

· EQT Three Rivers Regatta - No work permitted affecting any travel lane or shoulder on Saturday and Sunday of Three Rivers Regatta weekend.

Friday before Three Rivers Regatta - 12 Midnight to 6 A.M.: Provide minimum number of travel lanes as indicated under TIME RESTRICTION section.

6 A.M. to 12 Midnight: No work permitted affecting any travel lane or shoulder.

· Steeler Home Games - No work permitted affecting any travel lane or shoulder on the day of the game within 4 hours of kickoff and 4 hours after the conclusion of the Steeler game.

· Pirates Home Games - No work permitted affecting any travel lane or shoulder on the day of the game within 4 hours of start and 4 hours after the conclusion of the Pirate game.

· Penguins Home Games - No work permitted affecting any travel lane or shoulder on the day of the game within 4 hours of start and 4 hours after the conclusion of the Penguin game.

· In accordance with Publication 408 Section 901.3(a), the Contractor must be aware that there may be instances where the PROJECT MANAGER may implement restrictions for other unforeseen major events (i.e., events scheduled subsequent to contract execution).

· PARKING RESTRICTIONS

When parking must be restricted during work hours, coordinate with the City and impacted business owners/residences four (4) days prior to the impending parking restrictions. Install no parking signs one (1) day prior to establishment of the work zone.

Open the roadway to all traffic at the end of each workday.

Do not use steel plates to bridge any trenching construction.

Remove or deactivate any warning lights during those periods when signs are covered or folded.

Dropoff conditions are in accordance with Section 901.3(j) except as follows:

General Conditions (Bullet Point 3) revise to read:

An approved Type C steady burn light shall be placed on each channelizing device throughout the drop-off condition.

General Conditions (Bullet Point 5) add the following:

A Type B light shall be installed on each W-series sign.

General Conditions revise by adding the following:

6. When the drop-off condition is less than 25 feet in length, place a channelizing device at each end of the drop-off condition.

Condition (1) Between Active Travel Lane & Non-Active Travel Lane or Shoulder Treatment revise to read:

Place channelizing devices throughout drop-off condition. Space all channelizing devices at a maximum distance of 25-foot spacing throughout a continuous or intermittent drop-off condition, unless otherwise directed.

Condition (1) Between Two Active Travel Lanes Treatment revise to read:

· Install Longitudinal Notched Wedge Joint during paving operations in accordance with RC-28M and during milling operations mill a 12:1 wedge. For Temporary Overlay Transitions during paving and milling operations follow RC-28M except for the paving notch, feather transition edge as much as mix will allow. Place channelizing devices throughout drop-off condition. Space all channelizing devices at a maximum distance of 25-foot spacing throughout a continuous or intermittent drop-off condition, unless otherwise directed.

OR

· End all lanes at the same grade longitudinally, install Temporary Overlay Transitions during paving and milling operations in accordance with RC-28M except for the paving notch, and feather transition edge as much as mix will allow. Space all channelizing devices at a maximum distance of 25-foot spacing throughout a continuous or intermittent drop-off condition, unless otherwise directed.

Condition (2) Footnote (D) revise the second sentence to read:

Space all channelizing devices at a maximum distance in feet, equal to the posted speed limit in miles per hour throughout a continuous or intermittent drop-off condition, unless otherwise directed.

Section 901.4(a) Maintenance and Protection of Traffic During Construction. Revise by adding the following:

Includes floodlights, shadow vehicles, truck mounted attenuators, and associated maintenance, fuel, relocations, and operating costs for the duration of the project.

Section 901.4(b) Separate Pay Items. Revise by deleting the 6th bullet and 26th bullet.

ITEM 4954-0013 – 3 INCH CONDUIT WITH WARNING TAPE

As specified in Section 954 and as follows:

Section 954.2 MATERIAL – Revise by adding the following:

a. Conduit - Polyvinyl Chloride (PVC) Schedule 40; 90°C (194°F) , UL-Listed conduit conforming to NEMA standard TC-2 (EPC-40-PVC), manufactured from compounds meeting the applicable requirements of ASTM D1784, listed in conformity with Article 347 of the National Electrical Code. Furnish conduit fittings, elbows, cleaner, and solvent produced by the same manufacturer.

b. Detectable Warning Tape - 5 mil overall thickness, with a solid aluminum foil core, double laminated tape. Orange in color and have a repeating warning message "Caution Buried Fiber Optic Cable Below" and laminated to foil core with a 3.75 mil clear film backing. Meet or exceed the American Public Works Association (APWA) AND OSHA standards. Detectable to a depth of 3 feet.

Section 954.3(c) Conduit. Revise by adding the following:

Provide positive drainage at the low point of each conduit run. Clean conduit runs after installation by pulling a stiff wire brush, the size of the conduit, through the conduit. Then test the conduit by pulling a ball mandrel, having a diameter of at least 85% of the inside diameter of the conduit, through each run. Where the mandrel fails to pass, either acceptably repair or replace conduit until mandrel passes. Place detectable warning tape 1 foot above the conduit.

ITEM 4954-0152 – TRENCH AND BACKFILL, TYPE II MODIFIED

As specified in Section 954 except as follows:

Section 954.3(a) Conduit Trench and Backfill. Revise by adding the following:

Replace full sidewalk slab.

Section 954.4(b) Trench and Backfill. Revise by adding the following:

Cement concrete sidewalk slabs replaced as a result of Type II trench and backfill are incidental to the trench and backfill payment. No separate payment will be made for cement concrete sidewalk.

Delete Section 954.4(i) Cement Concrete Sidewalks.

ITEM 5204-0100 – STANDARD FIBER OPTIC CABLE, 96 STRAND SINGLE-MODE

As specified in Section 1204 and as follows:

Section 1204.2(b)1. Fiber Optic Cable. Revise by adding the following:

· 96 Strand single-mode

ITEM 9000-0001 – CBD FIBER HUB REPLACEMENT

DESCRIPTION

This work includes the relocation of the existing equipment and fiber and electrical conduit splices from the existing CBD Fiber Hub Cabinet to the proposed CBD Fiber Hub Cabinet. This work also includes the removal of the existing Fiber Hub after all relocations have occurred.

MATERIAL

Section 1201.2(b) and as follows:

Provide shop drawings, showing proposed power/communications supply configuration to the Representative for approval. Shop drawings are to be signed and sealed by a Professional Engineer licensed in the Commonwealth of Pennsylvania.

Provide a hub cabinet large enough to accommodate double doors on both sides of the cabinet.

CONSTRUCTION

Section 1201.3(a) 1-9 and as follows:

Coordinate with City Traffic Engineer before disconnecting the existing TC7 CBD Network Hub.

Construct the foundation in accordance with TC-8802 of PUB 148. Take responsibility for the location of all subsurface structures and utilities in the construction area. If the presence of subsurface utilities prevents the construction of a foundation of the specified size, suspend work immediately and notify the Representative. Securely cover the excavation after completion and remain covered when no work is in progress. Keep the excavation reasonably dry and free of mud until placement of the concrete.

Install new termination panels. Termination panels to be paid for under a separate item.

Construct the new hub cabinet and foundation prior to remove the existing TC7 CBD Network Hub. Cutover to new Hub Cabinet shall not exceed 6 hours of downtime. Cut the existing CBD Fiber and remove from the existing Hub Cabinet. Pull the CBD fiber into the new hub and relocate existing Layer 3 Ruggedcom switch to new hub.

Terminate the old CBD fiber, new 96 count fibers from City Council Building, and new 96 count fibers from Armstrong Tunnel into new patch panels in new hub. Terminate fiber in accordance with the contract drawings.

Test connectivity with Layer 3 CBD network. Provide power to relocated Ruggedcom and Comnet ethernet switches and ensure fiber optic patch cables are configured to match the existing TC7 Hub Configuration. Verify Layer 3 connectivity to adjacent TC3 and TC4 hubs.

Relocate electrical cables into new Hub Cabinet. Test electrical connectivity inside new Hub Cabinet. Install new 120/240VAC, single phase electrical service for new hub cabinet in accordance with the contract drawings. Coordinate with Duquesne Light Company to de-energize existing TC7 Hub Cabinet. Ensure that upon completion of installation of the grounding and bonding systems the overall resistance of the grounding system does not exceed the maximum total resistance described in the NEC and recommended by the IEEE. Use three (3)- point measurements for measuring resistance to ground of ground rods. Maintain earth ground resistance at 25 Ohms or less.

Remove existing Hub Cabinet and Foundation:

· Remove the existing controller cabinet where shown on the drawings, or as directed by the Engineering.

· Coordinate plan for removal with the Traffic Engineer at least 10 days in advance of proposed work.

· Deliver the existing termination cabinet to the City of Pittsburgh's Traffic Unit, or as directed by the Engineer.

· Remove existing hardware as indicated.

· Remove the existing foundation in its entirety.

· Securely cover the excavation after completion and remain covered when no work is in progress. Keep the excavation reasonably dry and free of mud until placement of the concrete.

· Cut down the existing foundation to a depth of 12” below grade. This includes the removal of the rebar cage, grounding rod, and anchor bolts.

· Neatly cut the sides of the excavation.

· Excessive damage to the existing pavement caused by the Contractor, as determined by the Engineer, is corrected at the Contractor’s expense.

MEASUREMENT AND PAYMENT – Each

ITEM 9000-0002 – ALL MOUNT FIBER OPTIC TERMINATION ENCLOSURE

DESCRIPTION

This work consists of furnishing and installing of a wall mounted enclosure and the subsequent splicing of fiber optic cables by breaking out the required buffer tube(s) from the backbone cable and fusion splicing the appropriate fiber(s) from the fiber optic backbone or drop fiber cable at the locations indicated.

MATERIAL

Provide Wall Mounted Fiber Optic Termination Enclosure that meets the following:

· Handles up to six cables in a butt configuration.

· Prevents the intrusion of water without the use of encapsulates.

· Capable of accommodating splice organizer trays that accept fusion splices.

· Provisions for storing fiber splices in an orderly manner, mountings for splice organizer assemblies, and space for un-spliced fiber. Utilize re-enterable splice organizers.

· UL rated splice case.

· Provide enclosure that does not require specialized tools, equipment or additional parts for re-entry and subsequent reassembly.

· Accommodate fiber bend radius of the proposed cables.

· 2-96 count single mode fibers and 2-12 count single mode fibers as indicated in the contract drawings. Enclosure must be large enough to handle splicing of 2-12 count multimode fibers as indicated in the contract drawings.

· Removable side panels for easy access during installation and maintenance

· Wall-mountable

· Top and bottom entry for cables

· Strain relief brackets for fiber protection and alignment

· Availability for slack spool installation

Provide all mounting equipment to ensure a fully functional system. Mounting equipment shall be in accordance with field conditions and per manufacturers recommended guidelines.

CONSTRUCTION

Locate intended mounting position shown in the contract drawings. Coordinate with the City Traffic Engineer for access to the room in the City County Basement. Attach the enclosure to the wall according to manufacturer’s guidelines. Perform fusion splice for the mainline splices. 45-days prior to start of the fiber optic cabling installation, submit the proposed locations of the mainline splice points for review by the Department.

Provide cable entrances and slack loop storage per the manufacturer’s product guidelines. Splice and terminate fibers as shown in the contract drawings.

Perform all splicing in accordance with NECA/FOA 301 Standard, latest edition. or appropriate manufacturer instructions. Ensure all splices are performed inside the enclosure.

Terminate the cable as directed by City of Pittsburgh utilizing break out kits and LC connectors to match the modern connector style. Mid span access shall not disturb or compromise any fibers not being spliced in the main fiber run. Use duct caps to protect the ends of all single-mode fibers. Use a minimum bend radius of 20 times the diameter of the conduit per Section 954.3(c) and install with a pulling force not to exceed 300 pounds. Leave additional slack at cabinet to allow for proper cable termination.

After the fiber optics is installed, test the cable for continuity and attenuation as a minimum. Verification of all testing shall be provided to City of Pittsburgh’s Engineer prior to the acceptance of the fiber optics installation. Testing costs are incidental to this item.

MEASUREMENT AND PAYMENT – Each

ITEM 9000-0003 – 412 BOULEVARD OF THE ALLIES BUILDING 4TH FLOOR CLOSET IT RACK

This work is providing an IT rack inside the 412 Boulevard of the Allies Building 4th floor closet.

MATERIAL

Provide an IT rack that meets or exceeds the following specifications:

· Maximum 7 feet tall

· Standard EIA, 19-inch rack

· Minimum 20-inch depth

· Allows for easy positioning of equipment or shelves with marked and numbered rack-mount spaces

· Includes pre-punched holes to allow for the addition of vertical wire managers on each side

· Able to be secured to the ground to prevent unwanted movement

· Able to withstand a maximum load of 1500lbs of equipment

Provide vertical wire managers on both sides of the IT rack that meet or exceed the following specifications:

· Maximum 7 feet tall

· Minimum 6-inch width

· Minimum 20-inch depth

Contractor shall field measure existing conditions before ordering equipment.

CONSTRUCTION

Install proposed IT rack inside 412 Boulevard of the Allies Building 4th floor closet so that the proposed IT rack is equidistant from the northern and southern walls. Install vertical wire mangers on both sides of the proposed IT rack. Ensure that the proposed IT rack and the vertical wire managers are adequately spaced from the existing rack located in the 412 Boulevard of the Allies Building 4th floor closet. Install the proposed IT rack and vertical wire managers on the western side of the existing rack, so that there remains enough room for entry to the room. Ensure that the proposed IT rack and vertical wire managers are not installed in the opening pathway of any doors that open into the room and that all doors are able to open fully. Secure proposed IT rack to the floor per manufacturer’s recommendations.

ITEM 9000-0008 – 12-PORT SINGLEMODE FIBER OPTIC TERMINATION PANEL

ITEM 9000-0009 – 12-PORT MULTIMODE FIBER OPTIC TERMINATION PANEL

ITEM 9000-1207 – 96-PORT SINGLEMODE FIBER OPTIC TERMINATION PANEL

DESCRIPTION

This work is furnishing, installing, terminating, mounting, and testing fiber optic cables, fiber optic cable termination panels, fiber optic lateral/drop cables and fiber optic backbone cables from outside plant fiber optic cable to factory manufactured connectors in a cabinet that provides front access to terminated fibers.

MATERIAL

Provide fiber optic termination panel (FTP) that meets or exceeds the following specifications:

· Number of terminations as indicated

· Uses LC connectors

· Access: Front and rear, fold-down or swing out

· Cabinet Painted Metal Construction

Provide panel with space and a mechanism for storing fiber splices and slack for both used and unused fibers within the panel.

Provide FTP’s as rack-mountable to EIA 19-inch equipment racks.

Provide fiber pigtails (single mode or multi-mode respectively) that meet the optical characteristics of the drop cable used, including mode diameter.

CONSTRUCTION

Install panels so connectors are accessible to a technician standing in front of the cabinet with the front door open. Install panels to accommodate fiber optic patch cables between any two connectors without reaching the patch cables’ minimum bending radius.

On the panel optically connect each connector to a fiber in the 12-strand fiber drop cable; connection to not cause in excess of 0.3 dB optical signal loss when tested at 1310nm.

Terminate with connectors all fibers entering the cabinet on the rear of the connector panel. Provide and install jumpers of sufficient length to connect the front side of the connector panel to the fiber equipment contained within the cabinet as specified herein.

Make Terminations by pre-terminated cable assemblies or by fusion splicing pre-terminated fiber pigtails (single mode or multi-mode respectively) to the fiber backbone cable or drop cable as described herein and as indicated. Mechanical, chemical, or epoxy type connectors and splices are unacceptable.

Refer to Fiber Optic Cable specification for testing requirements.

Unity price includes installation of all connectors, fiber optic terminations and jumper cables necessary to make the final connections from the fiber entering the cabinet to the fiber equipment located at each location.

ITEM 9000-0012 – Fiber Optic Testing

This work is the testing of the integrity of the fiber optic cable using an Optical Time-Domain Reflectometer (OTDR).

MATERIAL – None

CONSTRUCTION

Do not exceed 0.75 db insertion loss per mated connector pair. Where the installed Fiber Optic connector assembly to terminate onto a connector at a Fiber Optic device and the said mating device connector is not separable from the device, then the insertion loss of the single installed Fiber Optic connector assembly will be less than 0.35dB.

Perform optical power tests before and after splice for attenuation on the spliced Fiber Optic line longer than 1,000 feet. Do not exceed 0.3dB insertion loss for each splice. Document results and submit to the Representative.

Perform optical power tests end to end for each new fiber installed under this project. Do not exceed maximum attenuation of 0.5 dB/km @ 1310nm and 0.4 dB/km @ 1550nm.

Test each fiber optic strand using a certified fiber optic testing technician utilizing standard OTDR instruments.

Provide a fiber optic trace graphic showing attenuation over distance along with pairs of connections, splices, and faults.

Replace fiber optic cable run if OTDR testing reveals unsatisfactory dB loss, per requirements listed herein.

MEASUREMENT AND PAYMENT – Lump Sum

This item includes only the testing and documentation of the installed Fiber Optic Communications System as identified in the approved plans.

All materials - fiber optic cables, connectors, network switches, patch panels, surge protection, inner ducts, conduit, etc. are provided and paid for under separate items.

ITEM 9000-0114 – 96 STRAND FIBER OPTIC CABLE SPLICE ENCLOSURE

This work is the furnishing and installing of fiber optic splice enclosures and the subsequent splicing of fiber optic cables by breaking out the required buffer tube(s) from the backbone cable and fusion splicing the appropriate fiber(s) from the fiber optic backbone or drop fiber cable at the locations indicated.

MATERIAL

Design splice enclosures for use under the most severe conditions such as moisture, vibration, and impact as demonstrated by manufacturer’s specifications and minimum specifications listed below:

PHYSICAL REQUIREMENTS

Provide splice enclosure that meets the following:

· Handles up to twelve (12) cables in a butt configuration.

· Prevents the intrusion of water without the use of encapsulates.

· Capable of accommodating splice organizer trays that accept fusion splices.

· Provisions for storing fiber splices in an orderly manner, mountings for splice organizer assemblies, and space for un-spliced fiber. Utilize re-enterable splice organizers.

· UL rated splice case.

· Provide enclosure that does not require specialized tools, equipment, or additional parts for re-entry and subsequent reassembly.

· Provisions for controlling the fiber bend radius to a minimum of twenty times the Outer Diameter of the cable or 38mm, whichever is larger.

Provide proof and type of factory tests for approval by the engineer.

CONSTRUCTION

Install the splice enclosure according to the Manufacturer’s recommended guidelines. Perform fusion splice for the mainline splices. Forty-five (45) days prior to the start of the fiber optic cabling installation, submit the proposed locations of the mainline splice points for review by the Department.

Perform splicing as per Manufacturer instructions for the supplied splice enclosure units.

Perform drop cable splicing for each device location at locations shown on the plans.

Perform all splicing in accordance with NECA/FOA 301 Standard, latest edition, or appropriate manufacturer instructions. Contain all drop cable splices within fiber splice enclosures. Refer to Fiber Optic Cable specification for testing requirements.

Affix the splice enclosure to the side of the manhole using the cable support brackets. Properly dress and affix all cables to rails or racks within the manhole. No cables or enclosures are permitted to lie on the floor.