This document contains Special Provisions for a Sewer Lateral Replacement Project (SLRP) Invitation for Bid No. 26XXXX issued by the City of Palo Alto, California. The project involves replacing approximately 210 deteriorated public sewer laterals identified through review of maintenance records from the Sewer Overflows Alternative Program (SOAP). The work is structured as a three-year construction contract with approximately 70 laterals replaced annually. The primary objective is to improve the reliability of the City's wastewater collection system and reduce sanitary sewer overflows by replacing laterals with high-frequency maintenance records or documented structural integrity issues. Contractors must perform pre-construction and post-construction Closed-Circuit Television (CCTV) inspections with water introduction per Technical Specifications Section 2739, utilizing controlled flow rates of 15-30 gallons per minute for dry laterals and 10-20 gallons per minute for wet laterals. The preferred installation method is pipe bursting to minimize excavation; however, open-cut installation may be approved in specific circumstances such as when lateral alignment correction to perpendicular connection is feasible or when CCTV inspection identifies sags that cannot be corrected during pipe bursting. Construction hours are limited to 8:00 AM to 5:00 PM Monday through Friday, with additional restrictions for arterial streets, business districts, bicycle lanes, and areas within 1,500 linear feet of school grounds (9:00 AM to 4:00 PM). Winter holiday shutdowns are mandated for December 19, 2026 through January 3, 2027 and December 18, 2027 through January 2, 2028, during which all equipment and materials must be removed from job sites.

Contractors must submit all pre-construction submittals within 15 business days of Notice to Proceed issuance and shall provide at least 10 working days advance notification to Underground Service Alert (USA) prior to excavation work. A minimum of 5,000 linear feet of pipe bursting installation experience and 5,000 linear feet of open cut installation experience in the last three years is required, with relevant project references submitted on specified forms. The Contractor is responsible for obtaining parking permits for personnel vehicles and construction equipment, coordinating with the City Inspector for scheduling lateral installation inspections, and managing all traffic control plans for arterial streets and streets with bike lanes, which must be prepared by a Licensed Traffic Engineer or California Civil Engineer. The Contractor shall conduct in-person meetings with property owners at critical facilities such as hospitals, schools, and daycare centers no later than one day prior to construction start and maintain weekly notification logs. All equipment must be maintained in proper working condition with no City compensation for equipment downtime or repair time. Asbestos cement pipe (ACP) laterals shall not be pipe burst and must be handled and disposed of in accordance with all applicable federal, state, and local regulations. The City reserves the right to substitute sewer lateral replacement locations due to emergency repairs, unforeseen site conditions, or operational requirements, provided the total number of replacements does not exceed the original contract quantity, with no additional compensation for location changes unless separately approved in writing.

View the file

Other files

File Type Posted
Sewer_Lateral_Replacement_Project.pdf PDF
Payment_Bond.docx DOCX document
SLRP_-_Appendices.pdf PDF
Performance_Bond.docx DOCX document
SLRP_Index_&_Certification_Page.pdf PDF
utility-map-request-form.pdf PDF
Bid_Bond_Form.docx DOCX document
SLRP_-_Tech_Spec.pdf PDF
SLRP_Maps.pdf PDF
Construction_Contract,_General_Conditions,_and_Change_Orders.pdf PDF
SLRPBid_Table.xlsx XLSX spreadsheet
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEWER LATERAL REPLACEMENT PROJECT (SLRP)

SPECIAL PROVISIONS

IFB No. 26XXXX These Special Provisions supplement the General Conditions and shall govern in the event of inconsistency. Defined terms shall have the meanings assigned in the General Conditions unless modified by these Special Provisions.

SECTION 1 – WATER INTRODUCTION REQUIREMEMTS FOR CCTV INSPECTIONS

The City requires the Contractor to perform water introduction during both pre-construction and post-construction Closed-Circuit Television (CCTV) inspections to ensure optimal lateral inspection quality in identifying defects such as cracks, leaks, sags, and blockages. Water introduction shall be carried out in compliance with Section 2739 of the Technical Specifications, using controlled flow rates to minimize water consumption while maintaining standards. For dry laterals, a low flow rate of approximately 15 to 30 gallons per minute (gpm) shall be used, and for wet laterals, a reduced flow rate of approximately 10 to 20 gpm shall be used, or as approved by the City. The water introduction ensures the pre-construction CCTV inspections assess the condition of the existing sewer lateral and the post-construction CCTV inspections verify the integrity of the newly installed sewer laterals. To avoid blocking the CCTV camera view, water shall be introduced prior to the CCTV lateral inspection.

SECTION 2 – CCTV INSPECTION AND RECOMMENDATION OF LATERAL REPLACEMENT METHOD

In accordance with Section 2739 of the Technical Specifications, the Contractor shall perform pre-construction CCTV inspections of the sewer laterals. CCTV results shall be used to determine the appropriate sewer lateral installation method as described in Section 3. Pre-construction sewer main CCTV is required to locate the lateral tie-in location. The City does not require PACP defect report.

Based on the pre-construction CCTV findings, the Contractor shall recommend a replacement method for existing laterals. The Contractor’s installation recommendation shall be submitted to the City for review. The City will assess the recommendation based on technical feasibility, constructability, potential system impacts and compliance with the Technical Specifications and City of Palo Alto (CPA) Water Gas Wastewater (WGW) Utility Standards. No replacement method shall proceed without written approval from the City prior to construction.

Following lateral replacement, the Contractor shall perform post-construction CCTV inspection for the sewer laterals. The City shall evaluate the completed work through post-construction CCTV inspection. The City reserves the right to reject any work that does not meet project requirements, one (1) year from the date of completion, in accordance with IFB Part 5 General Conditions, subparagraph 12.2.1.

SECTION 3 – INSTALLATION METHOD

The City’s objective is for new sewer laterals to be installed utilizing a pipe bursting method of installation to minimize excavation. The Contractor shall not proceed with any alternative lateral installation methods without written approval from the City prior to construction and installation.

An open-cut method of installation may be accepted by the City in the following situations:

1. Per Section 2737 of the Technical Specifications, Section 1.04, the City’s objective is for new sewer laterals to be installed perpendicular to the existing sewer main whenever possible. Prior to commencing work, the Contractor shall pothole the existing sewer lateral to verify horizontal alignment and to determine whether correcting the alignment to a perpendicular connection is feasible, considering existing site constraints and obstructions. If lateral alignment correction is feasible, the new lateral shall be installed perpendicular to the existing sewer main by an open cut installation upon City’s approval of the new alignment and installation method. The existing lateral shall be abandoned, and payment shall be made in accordance with the applicable bid item unit price. If lateral alignment correction is not feasible, the new lateral shall be installed following the same alignment by utilizing pipe bursting method of installation.

2. Prior to commencing work, the Contractor shall perform pre-construction CCTV inspection of the existing sewer lateral in accordance with Section 2739 of the Technical Specifications. If the CCTV inspection determines that the existing lateral has sags that cannot be corrected during the pipe bursting installation of the new lateral, the new lateral shall be installed by an open cut installation upon City’s approval of the new alignment and installation method.

If the approved open cut installation method proves ineffective due to unforeseen subsurface conditions encountered during construction, the Contractor shall stop work, notify the City, and submit a revised installation proposal for approval prior to resuming work. Any costs, delays or rework resulting from failure to follow this process shall be the responsibility of the Contractor.

SECTION 4 – UNDERGROUND SERVICE ALERT (USA)

This provision modifies IFB Part 5 of the General Conditions, Section 3.28.1. Replace the five-day notification period with a minimum of ten (10) Working days advance notification to Underground Service Alert (USA) by calling 811 prior to any excavation work. The Contractor shall delineate the work areas with white paint and only the request utility markings at those locations where underground work will occur during the following month.

SECTION 5 – PROJECT HOURS OF WORK

The construction hours for this Project are 8:00 AM to 5:00 PM, Monday through Friday. No work shall be performed beyond the defined work hours, unless approved by the City. The Contractor must refer to the City’s Traffic Control Requirement.

Additional time restrictions may apply when work occurs within (1) downtown areas, business districts, arterial streets, (2) bicycle lanes, or (3) within 1,500 linear feet of school grounds or along designated school routes. Appendix M provides the list of lateral addresses including working time restriction categorization specified above.

Following table provides summary of working hours restrictions:

Addresses within
Allowed Working Hours (Monday through Friday)
Arterial/Major Streets; Downtown Area; Business District
9:00 AM to 4:00 PM
Bike Lanes
9:00 AM to 4:00 PM
1500 LF of a school
After 8:45 AM on school days

Appendix C provides more detailed description regarding the working hours restrictions when working in downtown areas, business districts, arterial streets, bike lanes, or near schools.

No work shall be permitted along school routes during the first week of school. If the work area is within City specified school routes during the first week of school, the Contractor must schedule their Work to avoid these routes. The anticipated start of school dates for the 2026-2027, 2027-2028, and 2028-2029 school years can be found in Appendix B.

SECTION 6 – NOTICE TO PROCEED AND SUBMITTALS

This provision modifies the contract as follows:

Replace first sentence in General Conditions Section 2.1.4, as follows, “Unless otherwise specified in the Contract Documents, including the Notice to Proceed, Contractor must submit all required pre-construction submittals to City for review and acceptance no later than fifteen days following the Execution Date set forth in the first paragraph of the Construction Contract.

Replace Section 800, Subsection 1.04.C with, “The Notice to Proceed (NTP) will be issued immediately after the Contract is fully executed with bonds and insurance. The pre-construction submittal process will begin after the NTP issuance, which will specify the project commencement date and pre-construction meeting date”.

Replace Section 800, Subsection 1.04.D with, “The Contractor must submit all pre-construction submittals, as specified in the Contract Documents or listed in the Construction Submittal List in IFB Appendices, for City’s approval within fifteen (15) business days from the Notice to Proceed issuance date.”

SECTION 7 – WINTER HOLIDAY SHUTDOWN

Construction activities shall not be performed during the City’s winter holiday shutdown for the following periods:

· December 19, 2026 – January 3, 2027

· December 18, 2027 – January 2, 2028 The winter holiday shutdown dates for the third year of the contract will be defined once the exact dates are available. During these shutdown periods, the City will require the Contractor to remove all construction equipment and materials from all job sites. The Contractor shall plan and account for the winter holiday shutdowns to avoid disputes regarding additional working days or compensation.

SECTION 8 – PARKING OF VEHICLES/PARKING PERMIT/STORING OF EQUIPMENT AND MATERIAL IN CITY ROW The Contractor is permitted to temporary store only the sewer lateral replacement and CCTV inspection equipment and materials within the City’s Right of Way (ROW) outside of working hours specified in Section 5 of Special Provisions document. Upon completion of the Work, all equipment and/or materials temporary stored within City’s ROW, will need to be removed. The storage of trench plates and backfill materials is allowed only for materials planned to be used for construction during the ongoing construction week.

The Contractor shall adhere to all of the City’s on-site storage policies. The City reserves the right to revoke the storage of vehicles and equipment within the City’s ROW in case of non-compliance with the City’s storage policies.

Portable restrooms must be on a trailer and moved to and from the active job site daily. If a portable restroom is left unhitched at the job site outside of permitted working hours, the Contractor must acquire an encroachment permit.

The Contractor is responsible for obtaining and paying (not compensated by the City) for all the other metered parking or permit-required parking spaces occupied by the Contractor’s personal vehicles, whether inside or outside the immediate construction zones. The City is not responsible for, nor will it compensate, any parking violations issued to Contractor personnel vehicles or construction equipment.

The following links provide additional information on business district locations, parking permit requirements, and instructions on how to obtain permits:

http://paloalto.parkingguide.com/ https://www.cityofpaloalto.org/Departments/Transportation/Parking/Parking-Programs https://www.cityofpaloalto.org/Departments/Transportation/Parking/Employees/Downtown-Employer-Employee-Parking https://www.cityofpaloalto.org/Departments/Transportation/Parking/Visitors/All-Day-Visitor-Parking-Permits https://www.cityofpaloalto.org/Departments/Transportation/Parking/Parking-Programs/Downtown-Color-Zone-Parking

SECTION 9 – TRAFFIC CONTROL

In addition to Technical Specifications Section 1500 , the Contractor shall submit site-specific traffic control plans for work on the following: arterial streets, and streets with bike lanes including the intersections affected by the work. The Contractor is responsible for construction site safety. Any changes from the approved traffic control plans shall be coordinated with and approved by the City.

The traffic control plans shall be prepared and stamped by either a Licensed Traffic Engineer or a Licensed California Civil Engineer as required by the City. Traffic control plans shall be developed in general conformance with the California Manual on Uniform Traffic Control Devices (CA MUTCD) and applicable City standards. The City’s Transportation Division shall review and approve the traffic control plan(s) prior to the Contractor commencing Work.

For work on streets that do not fall in the above categories, Contractor shall submit traffic control plans using the California Manual on Uniform Traffic Control Devices 2026, CA MUTCD.

An encroachment rider permit is needed for construction work that requires traffic control plan within the Caltrans’ ROW. The Contractor must apply for a separate encroachment permit which will be included in one or more bid items.

The Contractor will need to provide all required traffic control related equipment, including warning lights, arrow boards, traffic cones, and any other necessary traffic control equipment required to comply with the MUTCD and Section 1500 of the Technical Specifications.

Traffic shall be fully restored outside the permitted working hours.

SECTION 10 – PROGRESS PAYMENT AND BILLING

In addition to the payments and completion requirements in IFB Part 5 General Conditions Article 9, the Contractor shall also comply with all requirements stipulated in Technical Specifications Section 800 Additional Provisions for Utilities Contractors, Subsection 1.10.

SECTION 11 – INSPECTION AND COMPACTION TESTING

The City will assign a City inspector to provide part-time inspection. No dedicated full-time City inspector will be assigned exclusively to the project; therefore, the inspection scheduling has to be coordinated ahead of time. The City will assign a City Inspector to inspect the sewer laterals (prior and after the installation), to be present prior to backfilling and surface restoration, and to oversee compaction testing (which will be performed by the City).

The Contractor must notify the City of the installation schedule, which must also be included in the three-week look-ahead schedule and updated monthly construction schedules. During the weekly meeting, the Contractor must confirm the sewer lateral installation schedule so the City can ensure the City Inspector is on-site. The Contractor must also coordinate with the City to schedule the compaction testing during the City Inspector’s presence. Failure to confirm the schedule for the City inspector will make the Contractor responsible for any delays or additional costs incurred for the project.

SECTION 12 – RECESSED STEEL PLATES

Temporary recessed steel plates must be installed for the areas that are not restored on the streets open to vehicular, pedestrian and bicycle traffic. The plates must be flushed, with the surrounding asphalt surface to ensure safety; particularly on Class I and II Bicycle Lanes, Bicycle Boulevards, Arterial Roadways, or on the roads with a speed limit of 35 MPH or greater. The plates should be skid-resistant, have reflective coatings or tape for visibility, and be securely anchored to prevent movement, with temporary asphalt ramps for smooth transitions. Additional warning signage must be posted on Type II flashing barricades along these streets. This requirement does not apply to PCC-surfaced streets. Regular inspections, proper signage, and adherence to Technical Specifications and Public Works Standards (Drawing 405), are required to ensure safety and compliance throughout the Project.

SECTION 13 – RESTORATION

During the restoration phase, if the City is unable to perform restoration work, the Contractor shall be responsible for restoring all disturbed surface in kind following sewer lateral replacement, including but not limited to pavement, concrete, driveways, and decorative paths, in accordance with the Contract Documents.

Restoration involving specialty landscaping or hardscaping beyond standard restore-in-kind requirements shall be performed only with prior written authorization from the City and shall be compensated, if approved, under Bid Item 7 – Allowance for Landscaping/Hardscaping Restoration. Payment for such work shall be based on actual, reasonable costs incurred, subject to City review and approval, and shall not exceed the total allowance amount specified in the Bid Form for the entire project. No additional compensation beyond the established allowance will be provided.

SECTION 14– PUBLIC OUTREACH

The Contractor shall provide advance notification to affected property owners regarding sewer lateral replacement activities in accordance with Section 800, subparagraph 1.08.

Notifications shall be distributed to each affected customer as required by that section. In addition to the standard notification requirements, when sewer lateral replacement involves a critical facility such as a hospital, school, daycare center, church or similar facility, the Contractor shall conduct an in-person meeting with the property owner or facility representative no later than one day prior to the start of construction activities.

The Contractor shall maintain records of all notifications provided and shall submit a weekly notification log to the City. If sewer lateral replacement work does not commence within 15 calendar days of the original notification, the Contractor shall redistribute updated notifications to the affected property owners reflecting the revised construction schedule.

SECTION 15– EQUIPMENT

The Contractor is responsible for ensuring that all equipment used during construction activities is in proper working condition. In the event of equipment failure or breakdown during operations, the Contractor shall promptly repair or replace the malfunctioning equipment to minimize project delays. It is important to note that the City will not compensate the Contractor for any downtime or time spent repairing equipment resulting from such failures. The Contractor should have contingency plans in place to address equipment malfunctions promptly, ensuring that project timelines and quality standards are maintained without additional cost to the City.

SECTION 16– ACP PIPE AND HAZARDOUS MATERIAL DISPOSAL

The Contractor shall not pipe burst existing asbestos cement pipe (ACP) laterals. Any ACP encountered shall be handled, removed, transported and disposed of in strict accordance with all applicable federal state and local regulations. The Contractor is solely responsible for identifying ACP and for implementing all required safety practices, procedures and protective equipment necessary for its safe handling and disposal.

SECTION 17– FLEXIBILITY FOR SEWER LATERAL REPLACEMENT LOCATIONS

The overall project map provided in the Contract Documents shall serve as the basis for the bid. However, the actual list of sewer lateral replacement locations is subject to change.

If a listed sewer lateral becomes unavailable for installation due to emergency repairs, unforeseen site conditions, or other operational requirements, the City reserves the rights to substitute an alternate sewer lateral for installation. Any substituted sewer lateral shall be of comparable type, size, and function to the originally listed lateral. The City shall notify the Contractor of any such substitution in writing prior to the commencement of installation.

The City reserves the right to modify the list of sewer lateral replacement locations per each contract year based on urgency of need or operational priorities.

The Contractor shall remain flexible and responsive to changes to the list of sewer lateral replacement locations as directed by the City. Adjustment to the list of locations shall not be considered a change in project scope, provided that the total number of sewer laterals replaced does not exceed that quantity stated in the original Contract. No additional compensation shall be made for changes in sewer lateral locations unless otherwise approved in writing by the City.

SECTION 18– COORDINATION

The Contractor shall be responsible for all operations required to complete the Work, including, but not limited to, full coordination with the City, Palo Alto Unified School District, local schools, school principals, PTA Members, property occupants, and any other Contractors working in the area. When required, the Contractor shall attend coordination meetings with affected parties.

SECTION 19- SUPPLEMENTAL UNIT PRICING

“Unit prices” in Section 7.2.2.1 of the General Conditions are deemed to include any Supplemental Unit Pricing (SUP) submitted with the Contractor’s Bid as specified in the Bid Form. If during the course of the work, the City determines, at its sole discretion, that one or more of the specified SUP items is required for the Project, these SUPs shall be memorialized in a Field Order and/or Change Order. In that case, the Contractor will be bound by the SUP amount(s) submitted with its Bid, subject to adjustment pursuant to Section 7.2.9 of the General Conditions based on quantities completed. See Section 1025 of the Technical Specifications for each SUP item’s description and the basis for measurement and payment.

In addition, Section 9.1 of the General Conditions is modified to require that the pricing for any SUP item required by the Bid Form also be included in the Schedule of Values.

Nothing in the Contract Documents is intended to entitle the Contractor to the inclusion of any SUP item in the Contract Sum, except as authorized by the City pursuant to Article 7 of the General Conditions and this Special Provision.

SECTION 20 – CONTRACTOR’S EXPEREINCE

Contractor/Subcontractor shall provide relevant references of similar projects satisfactorily completed in the last three (3) years. Minimum experience of 5,000 LF of pipe bursting installation and minimum of 5,000 LF of open cut installation is required. Contractor/Subcontractor’s references shall be provided in Form 1 and Form 2 included in Appendix A.

Submitted Form 1 and Form 2 containing false or incomplete information may be grounds for disqualification of the Bidder and rejection of the submitted Bid.

SECTION 21 – SUBMITTALS

The list of construction submittals is provided in Attachemnt F. The submittal list is provided as guidance, and it is meant to inform potential Bidders about City’s typical submittal review. The submittal list is not an exhaustive list of applicable construction submittals. Please provide construction submittals confirming to the Contact Documents, City Standards, Rules and Regulations, Municipal Coder, and other applicable Local and Federal requirements.

END OF SECTION