This document is an aerial site map with project scope annotations for a road construction initiative. The project encompasses a road section measuring 710 linear feet with a total area of 36,470 square feet. The scope is divided into two distinct work areas with different specifications. The primary work area, highlighted in green on the eastern portion of the site, represents the proposed full-depth reconstruction zone requiring subgrade testing. The secondary work area, indicated in red in the central portion of the site, is designated for mill and overlay operations and does not require subgrade testing. A second phase of work is explicitly identified on the map as not included in this current project scope.

The annotations clearly delineate the testing requirements and construction methodology for contractor reference, with the full-depth area requiring geotechnical subgrade evaluation while the mill and overlay section involves surface treatment only.

View the file

Other files

File Type Posted
Draft Statement of Work.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

this area is the proposed full depth area and need sub grade testing

Road Length -

710 LF

Area- 36,470 SF this area is mill and overlay- no need for sub grade testing

Second Phase - Not part of this project