This is a Standard Form 30 (SF-30) Amendment of Solicitation/Modification of Contract for a Defense Logistics Agency Energy (DLA Energy) intoplane solicitation. Amendment 0001 for solicitation SPE60725R0202 introduces a new M3.02 clause allowing offerors to submit alternative escalators or revise prices. Submissions are due June 17, 2025, at 9:00 AM Eastern Time at Fort Belvoir, Virginia.
The amendment provides detailed evaluation guidelines for offers using alternative escalators. Offerors proposing alternative escalators must submit base reference pricing, reference dates, and 12-month historical price data. For evaluation purposes, the government will calculate a standardized comparison by establishing each offeror's price margin and then comparing 12-month average prices from the most recent complete period prior to the reference date (e.g., August 2023-July 2024 for an August 1, 2024 reference date). Offerors must sign and return the amendment but are not required to resubmit offers if no changes are made.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO.
See Block 14
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE SPE607 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE FACILITY CODE
SPE60725R0202
X
2025 MAR 31
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of OffersX is extended, is not extended.
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
12. ACCOUNTING AND APPROPRIATION DATA (If required)
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc. ) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).X
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
E. IMPORTANT: Contractor is not, X is required to sign this document and return copies to issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A NAME AND TITLE OF SIGNER (Type or print)
NSN 7540-01-152-8070
Previous edition unusable
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
16B. UNITED STATES OF AMERICA15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
(a) By completing Items 8 and 15, and returning
DLA ENERGY
INTOPLANE
8725 JOHN J. KINGMAN ROAD
FORT BELVOIR VA 22060
15C. DATE SIGNED 16C. DATE SIGNED
D. OTHER (Specify type of modification and authority)
3. EFFECTIVE DATE
See Attached Continuation Sheet(s).
(X)
CHECK ONE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
13. THIS APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CONTINUATION SHEET REFERENCE NO. OF DOCUMENT BEING CONTINUED: PAGE 2 OF 2 PAGES
SPE60725R0202 - 0001
Amendment 0001 for SPE607-25-R-0202 is being ISSUED to include M3.02 clause. Offerors may submit alternate escalators or otherwise revise prices with submissions due June 17, 2025 @ 9:00 AM Ft. Belvoir, Virginia time. An offeror proposing to use an alternative escalator must provide the base reference price, base reference date, and price data for the full 12-month period preceding the base reference date. Offerors must sign and return this amendment, but are not required to resubmit offers if there are no changes.
M3.02 EVALUATION OF OFFERS WHERE Alternate ESCALATORS ARE USED (DLA ENERGY March 2021)
(a) FOR EVALUATION PURPOSES ONLY, when any offeror proposes alternate escalators as a basis for economic price adjustment for any line item, an evaluation factor will be applied to the Final Proposal Revision (FPR) prices for all offers on such line items. The evaluation factor will ensure that all offerors are evaluated on an equal basis by determining the offerors’ average prices for the full 12-month period preceding the base reference date.
(b) The offeror's margin (plus or minus) will be established as the difference between the FPR price and the base reference price for the posting or publication being used for each offer. The base reference price is the price in effect on the base reference date in the posting or publication being used for the offer. The margin will then be added to the 12-month average of the posting or publication used for that offer to determine the offeror’s evaluated price. The 12-month average will be calculated over the most recent complete 12-month period prior to the established reference date (i.e., (i.e., if reference date is August 1, 2024, then the 12-month period would be August 2023-July 2024).