This document is a calculation template for Service Disabled Veteran Owned Small Business (SDVOSB) contractors to demonstrate compliance with self-performance requirements for solicitation 36C24924R0083. The template requires offerors under NAICS code 236220 (General Construction) to show that at least 15% of personnel costs will be performed by the SDVOSB prime or verified SDVOSB subcontractors, while specialty trade contractors under NAICS codes 237 and 238 must demonstrate 25% self-performance.
The form provides a detailed breakdown structure where contractors must itemize personnel and material/equipment costs by specification division, followed by profit, home office overhead, and bond costs. It includes a specific calculation method to determine the self-performance percentage by taking the total personnel costs of SDVOSB contractors divided by total personnel costs multiplied by 100. Personnel costs are defined to include laborers, mechanics, tradesmen, and office personnel directly charged to the project such as project managers, superintendents, administrative staff, and estimators.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK (36C24924R0083)
Offerors for General Construction (NAICS code 236220) must provide at least 15 percent (25% for specialty trade NAICS codes with 237 and 238 prefix) of the cost of the contract performance incurred for personnel must be performed by the Service Disabled Veteran Owned Small Business (SDVOSB) awardee or those of a verified SDVOSB subcontractor. Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service disabled veteran-owned small business concerns. Below is a suggested format.
Specification Division SDVOB Vendor (Y or N) Personnel Cost Material/Equipment Costs
Division 01 $ $
Division 02 $ $ Division 03 $ $ (Add additional lines as necessary for each Division applicable to this project)
Sub Total (Personnel Costs, Material/Equipment Costs)
Profit $ Home Office Overhead $ Bond $ Grand Total $
Calculation of self-performed personnel costs:
1. Total personnel costs * both prime and all subcontractors: $
2. Subtract all subcontractor personnel costs* that are not SDVOSB companies that will perform work on this contract: $
3. Remainder is ‘Total amount of work to be self-performed under the Contract’: $
4. Self-performed work = Line 3/Line 1 x 100 = %
*personnel costs include labors, mechanics, other tradesmen, and office personnel directly charged to the project (includes project manager, job superintendent, administrative, estimators, etc.)