Section J Attachment 1 SOW Conference Room Repair.pdf

PDF 225 KB Posted

Attached to
Conference Room Repair
Solicitation number
12405B25Q0061
Issued by

About this file

This Statement of Work (SOW) outlines requirements for repairing the main conference room at the USDA Agricultural Research Service's Subtropical Horticulture Research Center in Miami, Florida. The scope includes installing 5/8" drywall with R13 batt insulation, sealing/priming/painting the room, installing cove base, 2'x2' suspended ceiling with AC vent, seven recessed lighting fixtures, commercial grade resilient flooring, and framing - all with materials and colors to be selected by Lab Personnel.

The contractor must complete the work within 30 days of notice to proceed, working Monday-Friday 7:00 AM to 4:30 PM. Key requirements include providing a Site Safety Specific Plan within 14 days of award, using bio-based materials where possible, maintaining daily reports, having a superintendent on-site during work, and providing their own restroom facilities. The facility will remain occupied during construction, requiring coordination with facility representatives to minimize disruption. The contractor must provide a 10-year guarantee on workmanship and materials. All contractors must be registered in SAM.gov prior to bidding and are encouraged to conduct a site visit before submitting proposals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture Agricultural Research Service

STATEMENT OF WORK

Repair Main Conference Room

Subtropical Horticulture Research Center 13601 Old Cutler Road

Building 89 Miami, Florida 33158

Statement of Work USDA, Agricultural Research Service

1. Scope of Work

The contractor shall provide all professional services necessary to repair the main conference room located at the USDA, ARS, Subtropical Horticulture Research Center, 13601 Old Cutler Road, Building 89, Miami, Florida 33158, and provide a detailed proposal with a cost breakdown for the project.

The contractor shall include all services and field labor, equipment, materials, testing and personal protective equipment necessary to perform the work. No Government equipment will be available for use by the contractor.

1.1. Base Bid

The contractor shall provide a detailed proposal and cost breakdown for the entire project as specified in this statement of work. All proposals shall be in unlocked MS Word format, and all cost proposals shall be detailed in unlocked MS Excel format with formulas working.

1.2. Site Visit

Contractors are encouraged to visit the site and be escorted by a government representative to confirm locations, dimensions, and conditions of the project before a bid is submitted. The site visit shall be for the purpose of observing first-hand any conditions relevant to the completion of this project. No consideration will be given to claims based on lack of knowledge of existing conditions, except where contract documents make definite provisions for adjustment in cost or extension due to existing conditions not readily foreseeable.

Contractor must be registered in System for Award Management, (SAM), prior to submitting a bid. Registration can be completed at www.sam.gov/portal/public/SAM

2. Project Summary

The project consists of the following elements:

1. Install 5/8” drywall with R13 batt insulation.

2. Seal/Prime/Paint conference room with a color selected by Lab Personnel.

3. Install cove base with a color selected by Lab Personnel.

4. Install 2’x2’ suspended ceiling of a pattern selected by Lab and AC vent.

http://www.sam.gov/portal/public/SAM

5. Install seven recessed lighting fixtures as selected by Lab Personnel.

6. Install commercial grade resilient flooring with a pattern selected by Lab.

7. Install Framing as selected by Lab Personnel.

8. Clean and dispose of debris.

The facility will be occupied during construction activities. All work shall be scheduled in advance and coordinated with the facility representative to minimize the disruption to daily operations and research programs.

3. Utilization of Bio-Based Products

The contractor shall utilize products and material made from bio- based materials as applicable, (e.g. bio-based greases; bio-based hydraulic fluids, bio-based absorbents), to the maximum extent possible without jeopardizing the intended end use of detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to the applicable Federal Specifications and Standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR). Products can be found at:

www.biopreferred.gov

4. Safety

The contractor will submit a Site Safety Specific Plan (SSSP)/Accident Prevention Plan in industry recognizable format to the Contracting Officer within 14 days of contract award. The Government shall review the SSSP prior to the start any construction activities.

Safety and health matters, as they relate to the work, are the exclusive responsibility of the contractor. The contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions that may be required by law or local authorities for the protection and security of the grounds, facilities, and personnel. Contractor shall coordinate with Lab Personnel and strictly always follow all Covid related precautions and procedures.

5. Contractor Requirements

The contractor shall provide a complete and functional installation, including all labor, supervision, tools, materials, equipment, apparatus, transportation, rigging http://www.biopreferred.gov/ and other equipment and services necessary to accomplish the work in accordance with the intent and meaning of this statement of work.

The project work shall be performed per the following guidelines:

1) Contractor will verify all dimensions and existing site conditions prior to beginning work.

2) The contractor shall always be responsible for protecting his work and ensuring the safety of his crew and ARS employees.

3) Contractor shall remove and dispose of all construction related materials from all work areas daily and remove these waste materials from the site on a weekly basis.

4) Contractor is required to manage the project and consult with the Government prior to beginning all work phases.

5) Contractor shall perform work in a manner that minimizes the impact to daily operations of the facility and its workers. The building will be occupied during construction work.

6) Contractor will provide daily reports of work performed to the AO and weekly status updates to the EPM.

7) Contractor must have a superintendent on the jobsite when crews are performing the installation work.

8) Contactor will provide their own restroom facility.

9) Contractor to include commissioning of the new HVAC system.

All work is to be performed according with building codes, ordinances and laws of the Authority having jurisdiction on the project. When the requirements of the building codes, ordinances, and laws conflict with any other part of the building codes, ordinances and laws, the most restrictive requirement shall prevail. The Contractor is responsible for obtaining all permits and construction approvals necessary to successfully complete the project.

6. Documentation Requirements

6.1. Material Submittals

The contractor shall submit for approval all documents/samples necessary to ensure requirements of project will be satisfied. Electronic submittals on all equipment and materials used on this project shall be submitted to the EPM, AO, and CO noted in this document. All applicable products will have the Miami Dade Notice of Acceptance highlighted or otherwise noted.

6.2. Pre-Construction Submittals

Prior to construction activities beginning the following submittals must be provided to the AO and EPM for approval.

1. Project Schedule (including daily work start/stop time)

2. Site Specific Safety Plan (SSSP) / Accident Prevention Plan

3. List of contract personnel of the general and subcontractors

7. General Requirements

7.1. Damage to Property:

The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired to pre-damaged condition to the satisfaction of the AO.

7.2. Inspection and Acceptance

A government representative shall inspect and approve the work performed on this project. The Contractor shall schedule inspection a minimum of 2 days in advance with the AO.

8. Period of Performance

The completion of this project shall not exceed 30 days from date of notice to proceed. A request for time extension must be submitted to the Contracting Specialist in writing. Each request must include specific and detailed reasons in support of the schedule alteration.

8.1. Work Hours:

Contractor work hours shall be Monday through Friday, 7:00 A.M. to 4:30 P.M.

except on Government holidays. Any changes to work schedule shall be submitted to Contacting Officer for written approval prior to schedule change.

9. Guaranty

The contractor shall provide and submit a single guarantee stating that all portions of the work are in accordance with Contract requirements. Guarantee all work against faulty and improper material and workmanship for a period not less than ten (10) years from date of final acceptance by the USDA, except where manufacturer guarantees or warranties are for longer terms. The contractor shall correct any deficiencies which occur during the guarantee period within 24 hours after notification.