Section 40 (Project Manual) Scope of Work.pdf
PDF 289 KB Posted
- Attached to
- WYS Airport Access Road Reconstruction
- Solicitation number
- MDT-316397-MS
- Issued by
- Gallatin County, Montana
About this file
This is a Scope of Work document from the Montana Department of Transportation (MDT) for the West Yellowstone Airport Access Road Reconstruction Project (contract number MDT-316397-MS). The project encompasses comprehensive road reconstruction work at Yellowstone Airport in West Yellowstone, Montana, with deliverables including mobilization, traffic control, erosion control, pavement removal, asphalt milling, shoulder grading, aggregate base course installation, asphalt surface application, pavement markings, speed limit sign installation, and seeding/hydromulching. Schedule I includes removal of 44 square yards of concrete pavement and 7,352 square yards of asphalt, 5,479 linear feet of shoulder grading, installation of 1,400 tons of asphalt surface course, and erosion control measures across 2 acres, while Schedule II involves smaller quantities including 6 square yards of concrete removal, 1,908 square yards of asphalt removal, and 357 tons of asphalt surface course. Bids opened on March 11, 2026, with responses due by April 1, 2026 at 3:00 PM MDT.
The contractor must furnish all labor, materials, equipment, tools, transportation, and supplies required for project completion. Contractors must be registered with the Montana Department of Labor and Industry and comply with state prevailing wage rate requirements for highway construction as of July 1, 2025. Any bid totaling $150,000 or greater requires bid security equal to 10% of the total bid amount, with failure to submit this security resulting in automatic disqualification. Contractors must submit payment terms of Net 30 as part of their bid response. The contract document establishes that the Owner reserves the right to make alterations in quantities and work as necessary, with changes representing a significant change in character of work requiring supplemental agreements if they constitute increases or decreases in total contract cost exceeding 25% or changes in total cost of major contract items exceeding 25%. The Contractor is responsible for maintaining traffic safety, providing for free and unobstructed movement of aircraft in airport operations areas, and maintaining any existing roads open during construction, leaving the site in neat and presentable condition upon completion. Inquiries regarding the solicitation should be directed to Michele Smith at mismith@mt.gov or (406) 444-6033.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Yellowstone Airport Terminal Access Maps.pdf | ||
| 1376474-event.pdf | ||
| PREVAILING WAGE RATES_HWYCONSTRUCTION_1JUL2025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 10 Definition of Terms Page 1 of 4
AC 150/5370 -10H – Dec 2018 N:\0726\045 - Airport Access Rd Reconstruction\04 Design\Specifications\02 - FAA General and Technical Provisions\Part 1 - General Contract Provisions\01 Section 40 Scope of Work.docx
Section 40 Scope of Work
40-01 Intent of contract. The intent of the contract is to provide for construction and completion, in every detail, of the work described. It is further intended that the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies required to complete the work in accordance with the plans, specifications, and terms of the contract.
40-02 Alteration of work and quantities. The Owner reserves the right to make such changes in quantities and work as may be necessary or desirable to complete, in a satisfactory manner, the original intended work. Unless otherwise specified in the Contract, the Owner’s Engineer or RPR shall be and is hereby authorized to make, in writing, such in-scope alterations in the work and variation of quantities as may be necessary to complete the work, provided such action does not represent a significant change in the character of the work.
For purpose of this section, a significant change in character of work means: any change that is outside the current contract scope of work; any change (increase or decrease) in the total contract cost by more than 25%; or any change in the total cost of a major contract item by more than 25%.
Work alterations and quantity variances that do not meet the definition of significant change in character of work shall not invalidate the contract nor release the surety. Contractor agrees to accept payment for such work alterations and quantity variances in accordance with Section 90, paragraph 90-03, Compensation for Altered Quantities.
Should the value of altered work or quantity variance meet the criteria for significant change in character of work, such altered work and quantity variance shall be covered by a supplemental agreement. Supplemental agreements shall also require consent of the Contractor’s surety and separate performance and payment bonds. If the Owner and the Contractor are unable to agree on a unit adjustment for any contract item that requires a supplemental agreement, the Owner reserves the right to terminate the contract with respect to the item and make other arrangements for its completion.
40-03 Omitted items. The Owner, the Owner’s Engineer or the RPR may provide written notice to the Contractor to omit from the work any contract item that does not meet the definition of major contract item. Major contract items may be omitted by a supplemental agreement. Such omission of contract items shall not invalidate any other contract provision or requirement.
Should a contract item be omitted or otherwise ordered to be non-performed, the Contractor shall be paid for all work performed toward completion of such item prior to the date of the order to omit such item. Payment for work performed shall be in accordance with Section 90, paragraph 90-04, Payment for Omitted Items.
40-04 Extra work. Should acceptable completion of the contract require the Contractor to perform an item of work not provided for in the awarded contract as previously modified by change order or supplemental agreement, Owner may issue a Change Order to cover the necessary extra work. Change orders for extra work shall contain agreed unit prices for performing the change order work in accordance with the requirements specified in the order, Section 10 Definition of Terms Page 2 of 4
N:\0726\045 - Airport Access Rd Reconstruction\04 Design\Specifications\02 - FAA General and Technical Provisions\Part 1 - General Contract Provisions\01 Section 40 Scope of Work.docx and shall contain any adjustment to the contract time that, in the RPR’s opinion, is necessary for completion of the extra work.
When determined by the RPR to be in the Owner’s best interest, the RPR may order the Contractor to proceed with extra work as provided in Section 90, paragraph 90-05, Payment for Extra Work. Extra work that is necessary for acceptable completion of the project, but is not within the general scope of the work covered by the original contract shall be covered by a supplemental agreement as defined in Section 10, paragraph 10-59, Supplemental Agreement.
If extra work is essential to maintaining the project critical path, RPR may order the Contractor to commence the extra work under a Time and Material contract method. Once sufficient detail is available to establish the level of effort necessary for the extra work, the Owner shall initiate a change order or supplemental agreement to cover the extra work.
Any claim for payment of extra work that is not covered by written agreement (change order or supplemental agreement) shall be rejected by the Owner.
40-05 Maintenance of traffic. It is the explicit intention of the contract that the safety of aircraft, as well as the Contractor’s equipment and personnel, is the most important consideration. The Contractor shall maintain traffic in the manner detailed in the Construction Safety and Phasing Plan (CSPP).
a. It is understood and agreed that the Contractor shall provide for the free and unobstructed movement of aircraft in the air operations areas (AOAs) of the airport with respect to their own operations and the operations of all subcontractors as specified in Section 80, paragraph 80-04, Limitation of Operations. It is further understood and agreed that the Contractor shall provide for the uninterrupted operation of visual and electronic signals (including power supplies thereto) used in the guidance of aircraft while operating to, from, and upon the airport as specified in Section 70, paragraph 70-15, Contractor’s Responsibility for Utility Service and Facilities of Others.
b. With respect to their own operations and the operations of all subcontractors, the Contractor shall provide marking, lighting, and other acceptable means of identifying personnel, equipment, vehicles, storage areas, and any work area or condition that may be hazardous to the operation of aircraft, fire-rescue equipment, or maintenance vehicles at the airport in accordance with the construction safety and phasing plan (CSPP) and the safety plan compliance document (SPCD).
c. When the contract requires the maintenance of an existing road, street, or highway during the Contractor’s performance of work that is otherwise provided for in the contract, plans, and specifications, the Contractor shall keep the road, street, or highway open to all traffic and shall provide maintenance as may be required to accommodate traffic. The Contractor, at their expense, shall be responsible for the repair to equal or better than preconstruction conditions of any damage caused by the Contractor’s equipment and personnel. The Contractor shall furnish, erect, and maintain barricades, warning signs, flag person, and other traffic control devices in reasonable conformity with the Manual on Uniform Traffic Control Devices (MUTCD) (http://mutcd.fhwa.dot.gov/), unless otherwise specified. The Contractor shall also construct and maintain in a safe condition any temporary connections necessary for ingress to and egress from abutting property or intersecting roads, streets or highways.
40-06 Removal of existing structures. All existing structures encountered within the established lines, grades, or grading sections shall be removed by the Contractor, unless such existing structures are otherwise specified to be relocated, adjusted up or down, salvaged, abandoned in place, reused in the work or to remain in place. The cost of removing such
Section 10 Definition of Terms Page 3 of 4
N:\0726\045 - Airport Access Rd Reconstruction\04 Design\Specifications\02 - FAA General and Technical Provisions\Part 1 - General Contract Provisions\01 Section 40 Scope of Work.docx existing structures shall not be measured or paid for directly, but shall be included in the various contract items.
Should the Contractor encounter an existing structure (above or below ground) in the work for which the disposition is not indicated on the plans, the Resident Project Representative (RPR) shall be notified prior to disturbing such structure. The disposition of existing structures so encountered shall be immediately determined by the RPR in accordance with the provisions of the contract.
Except as provided in Section 40, paragraph 40-07, Rights in and Use of Materials Found in the Work, it is intended that all existing materials or structures that may be encountered (within the lines, grades, or grading sections established for completion of the work) shall be used in the work as otherwise provided for in the contract and shall remain the property of the Owner when so used in the work.
40-07 Rights in and use of materials found in the work. Should the Contractor encounter any material such as (but not restricted to) sand, stone, gravel, slag, or concrete slabs within the established lines, grades, or grading sections, the use of which is intended by the terms of the contract to be embankment, the Contractor may at their own option either:
a. Use such material in another contract item, providing such use is approved by the RPR and is in conformance with the contract specifications applicable to such use; or,
b. Remove such material from the site, upon written approval of the RPR; or
c. Use such material for the Contractor’s own temporary construction on site; or,
d. Use such material as intended by the terms of the contract.
Should the Contractor wish to exercise option a., b., or c., the Contractor shall request the RPR’s approval in advance of such use.
Should the RPR approve the Contractor’s request to exercise option a., b., or c., the Contractor shall be paid for the excavation or removal of such material at the applicable contract price. The Contractor shall replace, at their expense, such removed or excavated material with an agreed equal volume of material that is acceptable for use in constructing embankment, backfills, or otherwise to the extent that such replacement material is needed to complete the contract work.
The Contractor shall not be charged for use of such material used in the work or removed from the site.
Should the RPR approve the Contractor’s exercise of option a., the Contractor shall be paid, at the applicable contract price, for furnishing and installing such material in accordance with requirements of the contract item in which the material is used.
It is understood and agreed that the Contractor shall make no claim for delays by reason of their own exercise of option a., b., or c.
The Contractor shall not excavate, remove, or otherwise disturb any material, structure, or part of a structure which is located outside the lines, grades, or grading sections established for the work, except where such excavation or removal is provided for in the contract, plans, or specifications.
40-08 Final cleanup. Upon completion of the work and before acceptance and final payment will be made, the Contractor shall remove from the site all machinery, equipment, surplus and discarded materials, rubbish, temporary structures, and stumps or portions of trees. The Contractor shall cut all brush and woods within the limits indicated and shall leave the site in a
Section 10 Definition of Terms Page 4 of 4
N:\0726\045 - Airport Access Rd Reconstruction\04 Design\Specifications\02 - FAA General and Technical Provisions\Part 1 - General Contract Provisions\01 Section 40 Scope of Work.docx neat and presentable condition. Material cleared from the site and deposited on adjacent property will not be considered as having been disposed of satisfactorily, unless the Contractor has obtained the written permission of the property Owner.
END OF SECTION 40