SECTION 01 14 00 Work Restrictions.pdf

PDF 34 KB Posted

Attached to
PKA Restriping 500 Ramp Federal contract opportunity
Solicitation number
FA442725R0003
Issued by
Department of the Air Force Air Mobility Command

About this file

This document is a section from a Statement of Work (SOW) for a federal contract opportunity. It outlines the work restrictions and access requirements for a construction project at Travis Air Force Base.

The key details include: Contractor personnel must obtain permission to interrupt any activity roads, railroads, or utility services at least 15 calendar days in advance. Contractors are restricted to the work site, must comply with Travis AFB regulations, and obtain security clearance. Regular working hours are from 7:30 AM to 4:30 PM Monday through Friday. Work outside of regular hours requires prior approval from the Contracting Officer. Utility cutovers and interruptions must be scheduled after normal working hours or on weekends/holidays. The related federal contract opportunity is for PKA Restriping on the 500 Ramp at Travis AFB, solicitation number FA442725R0003. An organized site visit is scheduled for December 4, 2024 and questions are due by December 11, 2024.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 14 00, Page 1

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 SPECIAL SCHEDULING REQUIREMENTS

a. Permission to interrupt any Activity roads, railroads, and/or utility service shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Project become familiar with and obey Project regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials shall be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

1.2.1.1 Employee List

The Contractor shall provide to the Contracting officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract. The Contractor shall adhere to the requirements of the Air Force Background Checks requirements in obtaining access to Travis Air Force Base for the life of the contract. A copy of these requirements will be provided at the preconstruction conference.

1.2.2 Travis Air Force Base

Ensure that Contractor personnel employed on the Project become familiar with and obey Travis Air Force Base regulations. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification. Comply with the following conditions:

a. Restrict employees/representatives to the work site and control travel directly to and from the work site.

b. Restore all traffic/parking/security signs and markings, including space numbers, designations, and lines, to their original form if such signs/markings are defaced or deleted during construction/repair.

c. Be responsible for control and security of Contractor-owned equipment and materials at the work site. Report immediately

SECTION 01 14 00, Page 2 missing/lost/stolen property to the Travis Air Force Base Police Department as each case occurs.

d. Seventy-two hours prior to making any penetrations (such as tunneling under, cutting through a fence or building) in a restricted area, contact the Travis Air Force Base Security Office to make arrangements for a security guard or other measures required to meet all security requirements. Cost of security guard will be charged to the Contractor.

e. Seventy-two hours prior to performing any work on the airfield, contact the Travis Air Force Base Airfield Management Operations Desk at 707-424-2836 for prior approval and publishing of the Notice-to-Airman (NOTAM) prior to any work commencing.

1.2.3 Working Hours

Regular working hours shall consist of an 8-1/2 hour period, established by the Contractor Officer, between 7:30 a.m. and 4:30 p.m., Monday through Friday, excluding Government holidays.

1.2.4 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.2.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours."

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --