Section_00100-003-_Technical_Specification_Revision.pdf

PDF 149 KB Posted

Attached to
Replacement Well No. 5 & Control Building
Solicitation number
2025-35
Issued by
Harris County, Corpus Christi City, Texas

About this file

This is a Technical Specification document for Construction Schedule requirements issued by a Texas municipality for the Replacement Well No. 5 & Control Building project, with an engineering estimated budget of $6,900,000.00. The specification establishes mandatory scheduling procedures for bidders and contractors, requiring submission of a Preliminary Construction Schedule as part of the initial bid proposal that demonstrates the bidder's ability to achieve Substantial Completion within the proposed calendar days. Following contract award, contractors must submit a Detailed Construction Schedule for City review and acceptance prior to commencing any construction activities. The detailed schedule must comprehensively identify all work activities, sequencing, durations, critical path activities, milestones, procurement lead times, and known constraints, with the number of calendar days proposed by the bidder establishing the Contract Time upon award.

The construction schedule must be submitted in Microsoft Project format or similar software, displaying activities, durations, start and finish dates, precedence relationships, and Gantt charts, with one PDF copy and one schedule file copy (.mpp) required. The specification mandates that schedules address major proposal items, long lead-time equipment or pre-fabricated items, engineering design and shop drawing requirements, critical path activities controlling Substantial Completion, initial acceptance inspection and punch list resolution, and final inspection and deliverable submittals. Any updates or revisions to the schedule must be submitted when rain days or time extensions are approved by the City, with such approvals requiring separate City authorization.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Specifications Construction Schedule

Section 00100-003 Page 1 Revised 9/9/2026

Section 00100-003

CONSTRUCTION SCHEDULE

1.0 GENERAL

1.1 This section covers preparation and submittal of Construction Schedule to ensure adequate planning and execution of construction activities within the Contract Time.

2.0 EXECUTION

2.1 Construction schedule must include all construction activities, activity durations, start and finish dates, precedence, critical path activities and major proposal items.

2.2 Construction Schedule must identify construction activities or tasks that include, but are not limited to, the following:

a) Major proposal items and related activities

b) Items requiring long lead-times to order/manufacture, or delivery, including equipment parts, motor/machinery or pre-fabricated items

c) Items requiring engineering design/calculations and shop drawings

d) Critical Path activities and activities that control achievement of Substantial

Completion

e) Substantial Completion Date based on the calendar days proposed in the Bid

f) Initial acceptance inspection and addressing punch list items

g) Final inspection and deliverable submittals

3.0 Submittals

3.1 Submit a Preliminary Construction Schedule with the Bid proposal

a) The Bidder shall submit a Preliminary Construction Schedule as part of the Bid

Proposal.

b) The Preliminary Construction Schedule shall identify the proposed sequence and anticipated duration of major work activities.

c) The schedule shall clearly demonstrate the Bidder’s ability to achieve Substantial

Completion within the number of Calendar Days stated in the Bid.

d) The number of Calendar Days proposed by the Bidder for achievement of

Substantial Completion shall, upon Contract Award, establish the Contract Time.

3.2 Submit a Detailed Construction Schedule Post-Award / Pre-Construction

a) After award of the Contract and prior to commencement of construction, the

Contractor shall submit a Detailed Construction Schedule for review and acceptance by the City.

b) The Detailed Construction Schedule shall expand upon the Preliminary

Construction Schedule and shall identify all work activities, sequencing, durations, Technical Specifications Construction Schedule

Section 00100-003 Page 2 Revised 9/9/2026 critical path activities, milestones, procurement lead times, and any known constraints.

c) The schedule shall demonstrate the Contractor’s plan to achieve Substantial

Completion within the established Contract Time and shall comply with all scheduling requirements specified in the Contract Documents.

d) The Contractor shall not commence construction activities until the Detailed

Construction Schedule has been submitted and accepted by the City.

3.3 Format – Microsoft Project or similar format showing Activities, duration, Start/Finish dates, precedence and Gantt Chart

3.4 Submit one (1) pdf copy of construction schedule and a copy of schedule file (.mpp), if using

MS Project.

3.5 Submit an updated/revised schedule when Rain Days or Time Extensions are approved by the

City. Rain days and time extensions must be approved separately by the City.

*END OF SECTION*