SD_FLAP CR23A(1)_FinalHydraulicsMemo.pdf
PDF 27 MB Posted
- Attached to
- SD FLAP CS23A(1) - DELTA-01 ACCESS ROAD Federal contract opportunity
- Solicitation number
- 6982AF23B000020
About this file
This solicitation is for a road improvement project in Jackson County, South Dakota. The project scope involves paving 0.51 miles of County Road CS-23A to a width of 24 feet including two 11-foot travel lanes and one-foot shoulders. Additional work includes installing MUTCD signage and striping, constructing embankments to address erosion areas, replacing three culverts with larger sizes to improve drainage, and decreasing future maintenance needs. The estimated price range for the work is between $700,000 to $2 million. The project aims to improve public access to the Delta 01 Launch Control Facility. The soliciting agency is the Federal Highway Administration within the Department of Transportation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Opening Summary SD FLAP CS23A(1) DELTA 01 ACCESS ROAD.pdf | ||
| Interested Bidders List 6982AF23B000020.pdf | ||
| 6982AF23B000020 AMD A001 SF30.pdf | ||
| QUESTIONS AND ANSWERS SD FLAP CS23A(1) Delta 01 Access Road_05 25 2023.pdf | ||
| QUESTIONS AND ANSWERS SD FLAP CS23A(1) Delta 01 Access Road 05 23 2023.pdf | ||
| SD FLAP CS23A(1) Final Pavments Report.pdf | ||
| SD FLAP CS23A(1) AD Plans.pdf | ||
| IFB 6982AF23B000020 SD FLAP CS23A(1) DELTA 01 ACCESS ROAD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CFLHD | SD FLAP CS23(1)
Final Hydraulics Recommendations Memo hdrinc.com 1670 BroadwaySuite 3400Denver, CO 80202-4824
(303) 764-1520
Memo Date: Thursday, February 02, 2023
Project: SD FLAP CS23A(1) Delta-01 Access Road
To: Aaron Estep, CFLHD; Nate Mascarenas, CFLHD
From: Amy Finseth, HDR
Subject: Final Hydraulics Recommendations Memo
Introduction Jackson County Road CS-23(A) provides the sole access to the Delta-1 Launch Control Facility, which is a part of the Minuteman Missile National Historic Site. The existing gravel roadway is deteriorated with washboards and potholes and cannot support continued or increased vehicular traffic by heavy recreational vehicles, campers, tour buses, and local heavy agricultural equipment.
The proposed project includes clearing and grubbing, rehabilitation, widening, and asphalt paving of the existing aggregate section of approximately 0.5 miles of Jackson County CS-
23(A). The project limits are from the existing asphalt limits, approximately 900 feet north of the westbound (WB) Interstate 90 (I-90) ramp intersections, to the intersection just north of the
Delta-01 visitor parking access. The proposed roadway will be 24-foot width with 11-foot lanes and 1-foot shoulders. MUTCD signing and striping will be installed, and drainage and erosion control improvements will be needed at select culverts to maintain the integrity of the proposed roadway and provide for positive flow.
The scope of the drainage for this Project includes analysis of existing culverts and roadside ditches and recommendations for culvert replacement, ditch sections for capacity and temporary or permanent channel lining. Best management practices (BMPs) will be recommended in the memo for sediment and erosion control. The scope of work does not include developing erosion control plans. The Stormwater Pollution Prevention Plans (SWPPP) and Notice of Intent (NOI) will be completed by the contractor.
The Project is located just north of I-90 between Wall and Kadoka at the interchange of I-90 and
CS23(A). The location maps were obtained from the SDDOT Geographic Information Systems
(GIS) maps for state highway data.
CFLHD | SD FLAP CS23(1) Delta01 Final Hydraulics Recommendations
Figure 1 Location Maps
Criteria A drainage design criteria memo was developed for the project and provided to CFL prior to the
30% submittal. Hydrologic and hydraulic components of the project include developing hydrology, culvert, and ditch analysis. Erosion and sediment control measures will also be recommended.
The drainage criteria developed for this Project is based on the U.S. Department of
Transportation Federal Highway Administration (FHWA) Project Development and Design
Manual (PDDM) and local criteria from South Dakota Department of Transportation (SDDOT)
Drainage Manual (DM). Jackson County does not have design criteria. Therefore, SDDOT was referenced for local criteria.
The roadway classification is designated as low-standard road based on 48 ADT (<1500) and non-critical road designation.
Table 1 summarizes drainage design criteria for the drainage components included in the
Project.
Table 1 H&H Criteria
Design Feature PDDM Criteria
Peak Flow Methods Rational Method – up to 200 acres
Rural Regression Equations for areas > 200 acres Culverts
Capacity Design and Stability
Design: 25-yr (cross culverts)
10-yr (parallel culverts)
Check: 100-yr
Headwater Elevation
HW/D
New culverts: less than the bottom of the roadway aggregate base layer
Existing: less than the shoulder hinge point
Headwater depth to culvert diameter ratio, HW/D: 48” or smaller 1.5
WSEL limited by unacceptable hazards to human life or property
Minimum Size Cross-road culvert : 24” or equivalent
Parallel culvert : 18" or equivalent
Pipe Material
Minimum pipe classification
RCP: Class II, Metal 0.064"
50-year service life
Minimum and
Maximum Outlet Velocity
Minimum : 3 fps
Maximum : as determined by HEC22; matching existing channel velocities.
Outlet Protection
* Vo>6 fps consider erosion protection
Vo > 10 fps, consider gabion protection
Vo > 15 fps, consider energy dissipation
Roadside Ditches
Capacity Design 10-yr storm event
New: WSEL less than bottom of roadway aggregate base layer
Existing: WSEL less than shoulder hinge point
Stability Design
Permanent Lining: 10-year flood
Temporary lining: 2-year flood
Determined by permissible shear stress
*Slope Minimum: 0.5%
Slopes at absolute minimum of 0.2% should use a paved section
*Side Slopes 4:1 inslope – 3:1 maximum backslope
*Depth 3.5 ft below elevation of the subgrade shoulder
*SDDOT Typical Channel Lining
(Listed in order of preference)
HEC-15
*Temporary: crimped straw (mulch), erosion control blanket, wood fiber mulch, bonded fiber matrix
*Permanent: vegetation (retardance Class B – see Figure 9.4-A of SDDOT
DM (Chapter 9, page 9-17)
*Indicates local preference/criteria in addition to the PDDM.
The criteria memo developed for the Project is included in Appendix A.
Hydrology Hydrology was developed for local basins, up to 200 acres, using the rational method. Basins exceeding 200 acres used rural regression equations from USGS and included in the DM, Chapter 7 Hydrology. South Dakota (SD) has seven hydrologic subregions. The project is located in sub-region C. The regression equations for sub-region C were developed for basins between 0.06 and 904 square miles (38-578,560 acres). The 25-year regression equation standard error of estimate is 50%.
The DM provides intensity duration curves for each region of the state. The project falls between
Rapid City, Pierre and Winner. The National Oceanic and Atmospheric Administration (NOAA)
Precipitation Frequency Data Server was used to compare the data found for the site with the three locations and was within the range of the three regions. NOAA Atlas 14 point precipitation depths for the project are listed in Table 1 for the frequencies developed for the hydrologic and hydraulic analysis.
Table 2 NOAA Atlas 14, Point Precipitation Frequency Estimates, Rainfall Depth
Duration (minutes)
2-Year (inches)
10-Year (inches)
25-Year (inches)
100-Year (inches)
5 0.34 0.55 0.69 0.91
10 0.50 0.80 1.00 1.33
15 0.61 0.98 1.22 1.62
30 0.82 1.32 1.66 2.19
60 1.00 1.68 2.13 2.86
Soil information was determined using the Natural Resources Conservation Service (NRCS)
Web Soil Survey for Jackson County Area, South Dakota, Northern Part. Information was collected on 5/26/22. The hydrologic soil for the surrounding area is all C and D soils. The larger components include Arvada loam, Nunn loam, Pierre clay and smaller percentages of other loams, complex or clays. The full soil report is included in Appendix B
The DM, Figure 7.9-C includes the rural regression equations for each region. Subregion C equations for the frequencies used on the project are listed in Table 3.
Table 3 USGS Rural Regression Equations for South Dakota, Subregion C
Recurrence Interval (years)
Equation
2 Q = 25 CA 0.569
10 Q = 125 CA 0.579
25 Q = 207 CA 0.573
100 Q = 379 CA 0.566
Runoff drains from southeast to northwest across the site. But also drains from west to east across the site crossing CR23(A) multiple times. Additional contours were needed to determine offsite contributing areas. Data was acquired from Geo Spatial Data Gateway, 10-meter digital elevation model (DEM), to produce two-foot contours to delineate basins initially using ArcMap.
Basin boundary shape files that were then brought into ORD to check with project survey and to delineate smaller basins along the roadway. An overall basin map developed in ArcMap shows the larger offsite basins and local basins along the roadway alignment are shown on the following three maps developed using ORD. Basin Maps are included in Appendix B. Areas on the south and north limits of the project drain along the west side of CR23(A), drain across
CR23(A) through culverts and then merge with the main basin (Basin 1) draining to the low point which then drains across the project from east to west near station 112. Basins are primarily large undeveloped offsite basins with landcover consistent of meadow grass with shallow to steeper drainages. Smaller basins drain along CR23(A) contributing to roadside diches and driveway culverts. The roadside ditches also wind from draining at the toe of slope then away from CR23(A). Table 4 provides a list of each basin contributing to the Site. Basin 1 exceeds
200 acres therefore flows were developed using the rural regression equation for subregions C.
All other basins followed rational method to determine peak flows. Basins were evaluated during the 95% design and some refinements were made. Results are shown in the table below. Full calculations are included in Appendix B.
Table 4 Hydrologic Calculations
Basin ID Area
(acres) C10
Q10
(cfs) C25
Q25
(cfs) C100
Q100
(cfs) 1 744 N/A 136 N/A 226 N/A 413
2 0.66 1.32 1.32 0.44 2.1 0.52 3.4
3 11.70 7.88 8.01 0.31 14.1 0.42 22.2
Sub3 1.70 0.24 1.58 0.34 2.8 0.49 5.3
4 5.00 0.32 4.73 0.47 7.5 0.41 8.7
5 1.40 0.35 1.38 0.45 2.2 0.44 2.8
6 0.18 0.43 0.43 0.47 0.5 0.55 1.1
7 0.35 0.37 0.83 0.47 1.3 0.54 2.0
8 0.31 0.37 0.70 0.47 1.1 0.60 1.9
Basin ID Area
(acres) C10
Q10
(cfs) C25
Q25
(cfs) C100
Q100
(cfs) 9 9.50 0.21 5.97 0.31 11.06 0.49 23.15
0.23 0.14
0.22 0.52 0.72 0.57 1.42
11 0.46 0.36 1.03 0.46 1.64 0.60 2.82
12 0.11 0.21 0.15 0.31 0.27 0.55 0.64
Additional information is included in Appendix B including basin maps, rational calculations, regression calculations, soil data and rainfall data.
Floodplain Impacts
The project is not located in an area of Federal Emergency Management Agency (FEMA) mapping therefore, there are no floodplains identified within the project.
Hydraulics
Existing Conditions
There are three locations where existing culverts cross CR23(A). There is one culvert near station 104+75, three at the low point near station 113+27 and one more located near station
119+12. There are three driveway culverts and one additional location at a field access where a
6-inch PVC has been installed. There are a combination of V and trapezoidal roadway ditches that run along the project. Ditches along the west side of CR23(A) drain along the road to the low point where it joins a main drainageway that flows to the west. Ditches along the east drain along and then away from the road into the main drainage that crosses at the low point of
CR23(A). West and east ditches drain from the south to the low point as well as from the north end of the Project to the low point. On the east two of the parallel culverts, 125 & 127, were recently constructed with the new parking lot. The third culvert, 101, drains under a field access near the beginning of the project on the east. The 6-inch PVC is located on the west near station 110+45. The low point is located near station 113+27. At this location there are three existing culverts.
Photos from the site visit show some of the existing culverts have crushed ends. All cross culverts are corrugated metal pipes (CMP) with projecting ends. All culverts are shallow with minimal cover. Appendix A includes photos of the existing conditions.
Table 5 summarizes the existing culverts and the hydraulic results. The scoping visit noted that roadway overtopping does occur. HW/D should be 1.5 or less and headwater elevation (HWEl) should be below the shoulder hinge point. Cross culverts should convey the 25-year peak flow.
Roadside ditch culverts will convey the 10-year peak flow. Culverts were analyzed using FHWA
HY8 software. Existing condition results are included in Appendix C. Driveway or cross culverts list the appropriate design storm based on criteria and the other column is blank.
Table 5 Existing Culverts
Culvert
ID
Approximate Roadway Station
Diameter (inches)
Material Q10
(cfs) Q25
(cfs)
Edge of Gravel
Elevation (feet)
Headwater Elevation
(feet)
HW/D
Outlet Velocity
(fps)
101 101+50R 18 RCP 1.3 - 2549.42 2547.42 0.4 3.2
105 104+75 24 CMP - 22.3 2548.08 2548.05 1.3 6.6
110 110+45L 6 PVC 1.4 - 2546.04 2546.03 2.4 4.1
112+45 112+76 113+27
CMP
CMP
CMP
- 226 2543.28 2543.38 2.7 7.6
119 119+12 12 CMP - 11.1 2550.59 2550.08 0.4 0.8
125 125+00R 18 RCP 1.2 - 2566.38 2564.82 0.3 7.5
127 127+00R 18 RCP 0.15 - 2575.73 2573.52 0.1 2.0
Roadside ditches are trapezoidal and follow the profile of the road to low points and ultimately drain to the west. Some locations have sedimentation and there is an area of a significant scour hole on the east side just off the edge of pavement near roadway station 103+50 Rt. A photo is included in the site visit photos in Appendix A.
Proposed Design
Culverts were analyzed for proposed conditions and compliance with new culvert design standards. The three cross culvert locations do not meet current criteria and will be replaced at the same location with a new configuration that complies with current standards. Due to site conditions, limited vertical profile and right of way (ROW) constraints variances to criteria are still required. In addition, multiple barrels will be required to meet HWEl and HW/D design standards and provide the minimum cover requirements. For new culverts the PDDM requires the HWEl shall be below the bottom of the aggregate base layer, HW/D of 1.5 or less and a minimum diameter of 24-inches. FHWA concrete pipe culvert installation standard detail 602-7 specifies a minimum cover of 12-inches and is defined from top of pipe to the subgrade for flexible pavements. The pavement section is 8-inches roadbed reconditioning, 7-inches of roadway aggregate and 4.5-inches of asphalt concrete pavement.
Culvert profiles have been lowered as much as possible to minimize ROW impacts. To fit a 24-inch minimum diameter pipe significant ditch grading would be required or vertical adjustment of the roadway profile. Vertical adjustment of that degree did not align with the scope, budget or
ROW for the project. Culverts were optimized as much a possible with the given constraints to meet criteria.
Table 6 lists the hydraulic analysis of the proposed cross culverts. The following variances are needed for proposed conditions. Proposed culverts 105 and 119 are 18-inch equivalent to meet cover requirements and minimize grading. This is less than the minimum diameter and will require a variance. Culvert 113+27 does exceed HW/D criteria but does meet the headwater elevation criteria. The road profile was adjusted but does not allow for a larger diameter culvert at this location. This is at the low point of the road. A variance for HW/D would be required for this culvert.
The DM recommends outlet velocity over 6 fps should consider outlet protection. All cross culverts will add flared end sections (FES) or headwalls (HW) and FHWA standard riprap aprons.
The parallel culverts that were recently installed, meet design criteria and will remain.
Table 6 Proposed Culvert Replacements
Culvert
ID
Roadway Station
Diameter (inches)
Material Q25
(cfs)
Bottom of Aggregate base layer Elevation
(feet)
Headwater Elevation
(feet)
HW/D
Outlet Velocity
(fps)
105 104+77 3- 23x14
(18 equiv)
HERCP 20.8 2547.4 2547.6 1.2 6.3
112+42 112+74 113+27
2-36 2-36
RCP
RCP
RCP
2544.9 2544.6 2544.4
2543.8 1.3 1.4 1.8
8.3 8.9 8.7
119 119+12 2 – 23x14 (18 equiv)
HERCP 11.5 2549.9 2550.7 1.0 7.1
Roadside ditches will be narrowed due to the roadway widening. Ditches at minimum should be reconditioned to ensure positive drainage and revegetated with adequate lining to prevent erosion. Roadside ditch capacity and permanent lining was evaluated for the 10-year peak flows using FHWA Hydraulic Toolbox. Ditches meeting design standards and do not require additional lining. Ditches were found to be stable with vegetation.
Tall grass is found in the existing ditches, 0.03 was used for manning’s n for capacity calculations. Sides slopes varied but were typically 4:1 or 3:1. Trapezoidal bottom width varies to a minimum of approximately three feet.
The following table lists the ditch sections that were evaluated along the project.
Ditch Section
Q10
(cfs)
Depth of Flow (feet)
Lining
Allow Shear Stress (lb/ft2)
Max Shear Stress (lb/ft2)
100-105 Lt 1.4 0.2 Vegetation 4.6 0.1
107-105 Lt 4.7 0.3 Vegetation 1.9 0.3
107-110 Lt 16.9 1.3 Vegetation 1.4 0.8
117-113 Rt 0.4 0.1 Vegetation 6.9 0.06
125-122 Rt 1.6 0.2 Vegetation 1.5 0.5
127-125 Rt 1.1 0.3 Vegetation 1.1 1.1
128-127 Rt 0.2 0.2 Vegetation 3.5 0.2
125-119 Lt 6.3 0.7 Vegetation 1.1 1.1
Channel stability was evaluated with hydraulic toolbox based on soil type, surface cover, longitudinal slope and 10-year flows. The project consists of loams and clays. The plasticity index was determined from NRCS Web Soil Survey to be 24 for Nunn-Beckton loams, 2 to 6 percent slopes. Based on the site parameters ditches were found to be stable and no additional lining is required. Vegetation will be re-established after construction. Interim conditions should include native seeding, soil retention blanket and fiber rolls for ditch check dams to protect from erosion during revegetation. Calculations are included in Appendix C.
Stormwater Control Measures
The limits of disturbance for the project are approximately 3.1 acres. The project’s construction stormwater discharges must include a general stormwater construction permit number
SDR100000 effective on April 1, 2018 from South Dakota Department of Agriculture and Natural
Resources (DANR) in conformance with the National Pollutant Discharge Elimination System
(NPDES). The contractor will be responsible for acquiring the permit.
No permanent water quality is required since the Project is located outside of either a Phase I or
II Municipal Separate Storm Sewer System (MS4) permit area. Phase I MS4s are entities with populations over 100,000. Phase II MS4s are areas of at least 50,000 or designated by the
Secretary as needing coverage.
Wetland impacts were not anticipated at project scoping. However, it was determined there are wetlands at the culvert outlets. Disturbance of wetlands does not require mitigation.
FHWA standard erosion and sediment control measures will be used. Velocity was evaluated at each culvert outlet and standard riprap aprons are included. Areas that are disturbed during construction will be re-established. Fiber rolls will be used as perimeter control, culvert inlet and outlet protection and in ditches.
Summary
The proposed drainage improvements for the project include culvert replacement and ditch reconditioning to meet CFLHD and local SDDOT criteria. Roadway widening and installation of larger diameter culverts were designed not to impact right-of-way (ROW). Two variances are required to accommodate the limitations of the site without adding work and cost to the project.
The minimum pipe diameter at culverts 105 and 119 and HW/D criteria for culvert 112 at station
113+27.
hdrinc.com 1670 Broadway Suite 3400 Denver, CO 80202-4824
References
• Design of Roadside Channels with Flexible Linings, Federal Highway Administration
(FLH), Hydraulic Engineering Circular (HEC) No. 15, Third Edition. September 2005.
• Detail Drawings: FP-14, Central Federal Lands Highway Division (CFLHD).
• Drainage Manual, South Dakota Department of Transportation (SDDOT). May 2022.
• GIS Web Map Gallery, State Highway Data, SDDOT. June 1, 2022.
• Highway Hydrology, Federal Highway Administration, Hydraulic Design Series No. 2
(HDS2), FHWA-NHI-02-001. 2002.
• NOAA Atlas 14 Point Precipitation Frequency Estimates, NOAA. May 24, 2022.
• Project Development and Design Manual (PDDM), Federal Lands Highway (FLH).
December 2012.
• Road Design Manual, South Dakota Department of Transportation (SDDOT). May 2022.
• Standard Drawings, Federal Lands Highway (FLH).
• Stormwater Permit for Construction Activities, South Dakota Department of Agriculture &
Natural Resources. April 1, 2018. Stormwater Construction (sd.gov)
• Web Soil Survey Hydrologic Soil Group – Jackson County Area, South Dakota, Northern
Part, NRCS. May 26, 2022.
Appendix A
Criteria Memo
Site Photos
CFLHD | SD FLAP CS23A(1)
Drainage Design Criteria Memo
Date: Monday, June 13, 2022
Project: SD FLAP CS23A(1) Delta-01 Access Road
To: Aaron Estep, CFLHD
From: Amy Finseth, HDR
Subject: Drainage Design Criteria Memo
Project Description Jackson County Road CS-23A provides the sole access to the Delta-1 Launch Control Facility, which is a part of the Minuteman Missile National Historic Site. The existing gravel roadway is deteriorated with washboards and potholes and cannot support or sustain continued or increased vehicular traffic by heavy recreational vehicles, campers, tour buses, and local heavy agricultural equipment.
The proposed project includes clearing and grubbing, rehabilitation, widening, and asphalt paving of the existing aggregate section of approximately 0.5 miles of Jackson County CS-23A.
The project limits are from the existing asphalt limits, approximately 900 feet north of the WB I-
90 ramp intersections, to the intersection just north of the Delta 1 visitor parking access. The proposed roadway will be 24-foot width with 11-foot lanes with 1-foot shoulders. MUTCD signing and striping will be installed, and drainage and erosion control improvements will be needed at select culverts to maintain the integrity of the proposed roadway and provide for positive flow.
This memo outlines the criteria for hydrologic and hydraulic (H&H) design based on the U.S.
Department of Transportation Federal Highway Administration (FHWA) Project Development and Design Manual (PDDM) and local criteria from South Dakota Department of Transportation
(SDDOT) Drainage Manual (DM). Jackson County does not have design criteria. Therefore, SDDOT was referenced for local criteria.
The scope of H&H includes preliminary analysis of existing conditions. Calculate peak discharges based on appropriate methods and evaluate six existing culverts. Evaluate proposed conditions and recommend rehabilitation, replacements and extensions as appropriate. Design proposed structures to meet the outlined criteria. Analyze roadside ditches for capacity and temporary /permanent linings.
The roadway classification is designated as low-standard road based on 48 ADT (<1500) and non-critical road designation.
Design Criteria Drainage design will include developing hydrology, culvert and roadside ditch analysis. Erosion and sediment control measures will also be recommended. The Stormwater Management Plan
(SWMP) will be developed by the contractor.
Drainage Criteria is outlined in Table 3 following the PDDM and DM for applicable design components of the project based on low-standard road. Tables 1 & 2 provide hydrologic information for the region to develop peak flow.
Hydrology Hydrology will be developed for local basins, up to 200 acres, using the rational method. Basins exceeding 200 acres will use rural regression equations from USGS and included in the DM, Chapter 7 Hydrology. South Dakota (SD) has seven hydrologic subregions. The project is located in sub-region C. The regression equations for sub-region C were developed for basins between 0.06 and 904 square miles (38-578,560 acres). Basins that fall within 38 and 200 acres will be evaluate by both methods. The 25-year regression equation standard error of estimate is
50%. Values will be provided in the drainage memo.
The DM provides intensity duration curves for each region of the state. The project falls between
Rapid City, Pierre and Winner. The National Oceanic and Atmospheric Administration (NOAA)
Precipitation Frequency Data Server was used to compare the data found for the site with the three locations and was within the range of the three regions. NOAA Atlas 14 point precipitation depths for the project are listed in Table 1 for the frequencies developed for the hydrologic and hydraulic analysis.
Table 1 NOAA Atlas 14, Point Precipitation Frequency Estimates, Rainfall Depth
Duration (minutes)
2-Year (inches)
10-Year (inches)
25-Year (inches)
100-Year (inches)
5 0.34 0.55 0.69 0.91
10 0.50 0.80 1.00 1.33
15 0.61 0.98 1.22 1.62
30 0.82 1.32 1.66 2.19
60 1.00 1.68 2.13 2.86
The DM, Figure 7.9-C includes the rural regression equations for each region. Subregion C equations for the frequencies used on the project are listed in Table 2.
Table 2 USGS Rural regression Equations for South Dakota, Subregion C
Recurrence Interval (years)
Equation
2 Q = 25 CA 0.569
10 Q = 125 CA 0.579
25 Q = 207 CA 0.573
100 Q = 379 CA 0.566
The project is in Jackson County between Wall and Kadoka just north of I-90 at CS-23A interchange. The project is not located in an area of Federal Emergency Management Agency
(FEMA) mapping therefore, there are no floodplains identified within the project.
Hydraulics Hydraulic criteria is summarized below for the specific design elements included in the scope of the project. The table was developed primarily based on the PDDM but compared with local criteria. Where specific local preferences or criteria was found in the DM that has been listed and is indicated by an asterisk in the table.
Table 3 H&H Criteria Summary
Design Feature PDDM Criteria
Peak Flow Methods Rational Method – up to 200 acres
Rural Regression Equations for areas > 200 acres Culverts
Capacity Design and Stability
Design: 25-yr (cross culverts)
10-yr (parallel culverts)
Check: 100-yr
Headwater
New culverts: less than the bottom of the roadway aggregate base layer
Existing: less than the shoulder hinge point
HW/D: 48” or smaller 1.5
WSEL limited by unacceptable hazards to human life or property
Minimum Size Cross-road culvert : 24” or equivalent
Parallel culvert : 18" or equivalent
Pipe Material
Minimum pipe classification
RCP: Class II, Metal 0.064"
50-year service life
Minimum and
Maximum Outlet Velocity
Minimum : 3 fps
Maximum : as determined by HEC22; matching existing channel velocities.
Outlet Protection
* Vo>6 fps consider erosion protection
Vo > 10 fps, consider gabion protection
Vo > 15 fps, consider energy dissipation
Roadside Ditches
Capacity Design
10-yr storm event
New: WSEL less than bottom of roadway aggregate base layer
Existing: WSEL less than shoulder hinge point
Stability Design
Permanent Lining: 10-year flood
Temporary lining: 2-year flood
Determined by permissible shear stress
*Slope Minimum: 0.5%
Slopes at absolute minimum of 0.2% should use a paved section
*Side Slopes 4:1 inslope – 3:1 maximum backslope
See Figure 1 for typical county road ditch section
*Depth 3.5 ft below elevation of the subgrade shoulder
*SDDOT Typical Channel Lining
(Listed in order of preference)
HEC-15
*Temporary: crimped straw (mulch), erosion control blanket, wood fiber mulch, bonded fiber matrix
*Permanent: vegetation (retardance Class B – see Figure 9.4-A of SDDOT
DM (Chapter 9, page 9-17)
*Indicates local preference/criteria in addition to the PDDM.
SDDOT Road Design Manal Chapter 7, Figure 7-3 provides typical ditch sections. Figure 1 is the typical county road ditch section included in that figure. Along the site there are both V and trapezoidal ditch sections. The project will attempt to maintain the existing ditch geometry or aim to attain a similar section shown in Figure 1 where feasible. But due to widening and right-of-way the section with a 10-foot bottom will not fit within the project limits and a V ditch will be proposed as the typical dich section.
Figure 1 Typical Ditch Section (SDDOT)
The following software or references will be used for the culvert and ditch hydraulics. FHWA software will be used for hydraulic analysis. Hydraulic Toolbox will be used to determine ditch capacity and temporary or permanent lining. HY8 will be used to determine culvert capacity.
Erosion Control Erosion and sediment control will use standard best management practices (BMPs) used by
FHWA. Anticipated BMPs include culvert inlet and outlet protection, check dams, fiber roll and rolled erosion control product.
References
• Drainage Manual, South Dakota Department of Transportation (SDDOT). May 2022.
• Highway Hydrology, Federal Highway Administration, Hydraulic Design Series No. 2
(HDS2), FHWA-NHI-02-001. 2002.
• NOAA Atlas 14 Point Precipitation Frequency Estimates, NOAA. May 24, 2022.
• Project Development and Design Manual (PDDM), Federal Lands Highway (FLH).
December 2012.
• Road Design Manual, South Dakota Department of Transportation (SDDOT). May 2022.
• Techniques for Estimating Peak-Flow Magnitude and Frequency Relations for South
Dakota Streams, Water-Resources Investigations Report 98-4055, U.S. Department of the Interior U.S. Geological Survey. 1998.
1670 Broadway, Suite 3400, Denver, CO 80202-4824 hdrinc.com
APPENDIX A – SITE PHOTOS
1670 Broadway, Suite 3400, Denver, CO 80202-4824 hdrinc.com
Appendix B
Hydrology
Hydrologic Soil Group—Jackson County Area, South Dakota, Northern Part (Delta1)
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
5/26/2022
260800 261400 262000 262600 263200 263800
260200 260800 261400 262000 262600 263200 263800
43° 54' 18'' N
1°
9'
'' W 43° 54' 18'' N
1°
6'
0'
' W
43° 50' 57'' N
1°
9'
'' W
43° 50' 57'' N
1°
6'
0'
' W
N
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 14N WGS84 0 500 1000 2000 3000
Feet 0 250 500 1000 1500
Meters Map Scale: 1:17,300 if printed on B portrait (11" x 17") sheet.
AFINSETH
Rectangle
AFINSETH
Callout Project Location
MAP LEGEND MAP INFORMATION
Area of Interest (AOI) Area of Interest (AOI)
Soils Soil Rating Polygons
A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Lines A
A/D
B
B/D
C
C/D
D
Not rated or not available
Soil Rating Points A
A/D
B
B/D
C
C/D
D
Not rated or not available
Water Features Streams and Canals
Transportation Rails
Interstate Highways
US Routes
Major Roads
Local Roads
Background Aerial Photography
The soil surveys that comprise your AOI were mapped at 1:24,000.
Please rely on the bar scale on each map sheet for map measurements.
Source of Map: Natural Resources Conservation Service Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as of the version date(s) listed below.
Soil Survey Area: Jackson County Area, South Dakota, Northern Part Survey Area Data: Version 11, Sep 14, 2021
Soil map units are labeled (as space allows) for map scales 1:50,000 or larger.
Date(s) aerial images were photographed: Mar 29, 2021—Sep 22, 2021
The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident.
Hydrologic Soil Group—Jackson County Area, South Dakota, Northern Part (Delta1)
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
5/26/2022
Hydrologic Soil Group
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
Ar Arvada loam D 248.0 11.9%
As Arvada-Slickspots complex
D 24.6 1.2%
BcB Beckton loam, 2 to 6 percent slopes
C 48.1 2.3%
CbB Cactusflat-Weta complex, 1 to 6 percent slopes
C 143.3 6.9%
HsC Hisle-Slickspots complex, 0 to 9 percent slopes
D 13.8 0.7%
Ko Kolls clay D 53.5 2.6%
KyC Kyle clay, 6 to 9 percent slopes
D 13.6 0.7%
LcD Larvie-Conata clays, 6 to 15 percent slopes
D 11.0 0.5%
MoB Metre-Larvie clays, 2 to 6 percent slopes
D 0.8 0.0%
NuA Nunn loam, 0 to 3 percent slopes
C 78.7 3.8%
NuB Nunn loam, 3 to 6 percent slopes
C 566.5 27.3%
NuC Nunn loam, 6 to 9 percent slopes
C 255.9 12.3%
NwB Nunn-Beckton loams, 2 to 6 percent slopes
C 245.6 11.8%
PcB Pierre clay, 3 to 6 percent slopes
D 28.1 1.4%
PeC Pierre clay, 6 to 9 percent slopes
D 249.5 12.0%
PhB Pierre-Hisle complex, 1 to 6 percent slopes
D 43.2 2.1%
PsD Pierre-Samsil clays, 6 to 15 percent slopes
D 18.9 0.9%
W Water 10.5 0.5%
WeA Weta silt loam, 0 to 3 percent slopes
C 23.0 1.1%
Totals for Area of Interest 2,076.7 100.0%
Hydrologic Soil Group—Jackson County Area, South Dakota, Northern Part Delta1
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
/01121345627892:;4<=>2?92:>@6A;B2C2
D;E53A;B2B5=>F2G5H;I592J;<3K2L5I;3592MJ1N2
D53A3<H>F28OP?QCRS92D;BTA3<H>F2U7V7PWRWXS2
Y4>Z53A;BF2CR8?P782[3NN
����̀�a� b0c/d2beYfcbcd1dc0/2geYhMY/fi2YJdcj1dYJ
���k���� �������l� �����&������_������̂����������&��� �m�� �����n� &�o ���&�p����&� ����������&�q�p����a��##� ��r����� st
��s������&�u�����
��$��l�&� �v���$" ������&�v�����$+$�� bg235w<45@ bLJUw56>H2x;AB32x@>EAxA353A;B2[@>y<>BEz2>63A=53>62{A3K2WV|2E;B[AH>BE>2AB3>@Z5462}AB2ABEK>6~7
L<@53A;B 1Z>@5T>2@>E<@@>BE>2AB3>@Z542}z>5@6~
7 C R 7V CR RV 7VV CVV RVV 7VVV
RU=AB VPCQC
VPOOW
VP8RC
VPR8W
VPX?X
VPQW8
VPWVX
7PVC
7P7?
7POV
7VU=AB VPOWW
VP8WQ
VPXXC
VP?VO
7PVV
7P7X
7POO
7PRV
7PQO
7PW7
7RU=AB VP8?X
VPXVX
VP?V?
VPW?V
7PCC
7P8C
7PXC
7P?O
CP77
CPOO
OVU=AB VPXRO
VP?7X
7PVW
7POC
7PXX
7PWC
CP7W
CP8?
CP?X
OP7Q
XVU=AB VPQ?8
7PVV
7POQ
7PX?
CP7O
CP8W
CP?X
OPCR
OPQQ
8P7?
CUK@ VPW7R
7P7W
7PXR
CPV8
CPX7
OPVX
OPRO
8PV7
8PX?
RPCV
OUK@ VPW?R
7PCW
7P?V
CPCR
CP?W
OP8V
OPWO
8P8W
RPCR
RP?R
XUK@ 7P7X
7PRV
CPV?
CPRQ
OPC?
OP?8
8P8O
RPVO
RP?X
XPR7
7CUK@ 7P8R
7PQQ
CPOC
CP?V
OP8W
8PV8
8PXC
RPCC
XPVX
XPQ7
C8UK@ 7PQW
CPV?
CPRW
OPVR
OPQC
8PCQ
8P?X
RP8W
XPOX
QPVQ
CUH5z CPV8
CPOW
CPWQ
OP8Q
8P7W
8PQQ
RPOQ
RPWW
XP?R
QPRC
OUH5z CPCC
CPRQ
OP7?
OPQV
8P8R
RPVR
RPX?
XPOO
QPCC
QPWC
8UH5z CPOQ
CPQO
OPOX
OPWV
8PXQ
RPOV
RPWR
XPXO
QPRQ
?PO7
QUH5z CPQX
OP7Q
OP?Q
8P8Q
RPO8
XPV8
XPQX
QPR7
?PRR
WPOQ
7VUH5z OP77
OPRQ
8PO8
RPVV
RPW8
XPQV
QP8?
?PCW
WP87
7VPO
CVUH5z 8P77
8PXW
RPXR
XP8X
QPXV
?PRV
WP8C
7VP8
77PX
7CPX
OVUH5z 8PWQ
RPXR
XPQ?
QPQC
WPVC
7VPV
77PV
7CP7
7OP8
78PR
8RUH5z XPVQ
XPWC
?PC?
WP8V
7VPW
7CPV
7OP7
78PC
7RPX
7XPQ
XVUH5z QPVO
?PVO
WPX7
7VPW
7CPR
7OP?
78PW
7XP7
7QPR
7?PR
�����������������%���������������l&��� ��l��������# s�%l� �l�������#�����-������#����������� ��& �o���� �l�l�&����������
��&��!�&&�l��" �l������� �l����������� �]���%������������ l������� ����������p����"������� �l�l&��%���%�%�� ����������������������%���������%���l����"��
����st r��p����o�� bg2T@5xKAE54
/��0����1��
2345676389:3;5
<=3;;65>3;86?8993:@
/01234560734831109:
/01234560734;0<
/01234560734031907
A;9
BCC@;
DC;9
BCC@;
DC;9
/��0����1��
2������ �%�����#�3�%%� 4������&�5�����������
4������&�6����� 4������&�6��� �3���� �)���7����6����8�"�!���
9��������'��8��3 9��������:���� "���
A>@B
Description
Hydrologic soil groups are based on estimates of runoff potential. Soils are assigned to one of four groups according to the rate of water infiltration when the soils are not protected by vegetation, are thoroughly wet, and receive precipitation from long-duration storms.
The soils in the United States are assigned to four groups (A, B, C, and D) and three dual classes (A/D, B/D, and C/D). The groups are defined as follows:
Group A. Soils having a high infiltration rate (low runoff potential) when thoroughly wet. These consist mainly of deep, well drained to excessively drained sands or gravelly sands. These soils have a high rate of water transmission.
Group B. Soils having a moderate infiltration rate when thoroughly wet. These consist chiefly of moderately deep or deep, moderately well drained or well drained soils that have moderately fine texture to moderately coarse texture.
These soils have a moderate rate of water transmission.
Group C. Soils having a slow infiltration rate when thoroughly wet. These consist chiefly of soils having a layer that impedes the downward movement of water or soils of moderately fine texture or fine texture. These soils have a slow rate of water transmission.
Group D. Soils having a very slow infiltration rate (high runoff potential) when thoroughly wet. These consist chiefly of clays that have a high shrink-swell potential, soils that have a high water table, soils that have a claypan or clay layer at or near the surface, and soils that are shallow over nearly impervious material. These soils have a very slow rate of water transmission.
If a soil is assigned to a dual hydrologic group (A/D, B/D, or C/D), the first letter is for drained areas and the second is for undrained areas. Only the soils that in their natural condition are in group D are assigned to dual classes.
Rating Options
Aggregation Method: Dominant Condition
Component Percent Cutoff: None Specified
Tie-break Rule: Higher
Hydrologic Soil Group—Jackson County Area, South Dakota, Northern Part Delta1
Natural Resources Conservation Service
Web Soil Survey National Cooperative Soil Survey
/01121345627892:;4<=>2?92:>@6A;B2C2
D;E53A;B2B5=>F2G5H;I592J;<3K2L5I;3592MJ1N2
D53A3<H>F28OP?QCRS92D;BTA3<H>F2U7V7PWRWXS2
Y4>Z53A;BF2CR8?P782[3NN
����̀�a� b0c/d2beYfcbcd1dc0/2geYhMY/fi2YJdcj1dYJ
���k���� �������l� �����&������_������̂����������&��� �m�� �����n� &�o ���&�p����&� ����������&�q�p����a��##� ��r����� st
��s������&�u�����
��$��l�&� �v���$" ������&�v�����$+$�� bg235w<45@ bLJUw56>H2x;AB32x@>EAxA353A;B2[@>y<>BEz2>63A=53>62{A3K2WV|2E;B[AH>BE>2AB3>@Z5462}AB2ABEK>6~K;<@�7
L<@53A;B 1Z>@5T>2@>E<@@>BE>2AB3>@Z542}z>5@6�
7 C R 7V CR RV 7VV CVV RVV 7VVV
RU=AB OPCX
8PVQ
RP8C
XPRW
?PCO
WPRO
7VPW
7CPO
78PC
7RPX
7VU=AB CPOW
CPW?
OPWQ
8P?C
XPVC
XPW?
QPWX
?PW?
7VP8
77P8
7RU=AB 7PW8
CP8C
OPCO
OPWC
8PWV
RPX?
XP8Q
QPOV
?P8O
WPO7
OVU=AB 7PO7
7PXO
CP7?
CPXR
OPO7
OP?8
8POW
8PWX
RPQO
XPOO
XVU=AB VPQ?8
7PVV
7POQ
7PX?
CP7O
CP8W
CP?X
OPCR
OPQQ
8P7?
CUK@ VP8R?
VPRW8
VP?C8
7PVC
7POV
7PRO
7PQX
CPV7
CPO8
CPXV
OUK@ VPOC?
VP8CW
VPXV7
VPQ8W
VPWX7
7P7O
7PO7
7P8W
7PQR
7PWR
XUK@ VP7WO
VPCRV
VPO8Q
VP8OV
VPR8?
VPX8C
VPQOW
VP?87
VPWQW
7PVW
7CUK@ VP7CV
VP78Q
VP7WO
VPCOC
VPC?W
VPOOR
VPO?O
VP8OO
VPRVO
VPRRQ
C8UK@ VPVQR
VPV?Q
VP7V?
VP7CQ
VP7RR
VP7Q?
VPCVO
VPCCW
VPCXR
VPCW8
CUH5z VPV8O
VPVRV
VPVXC
VPVQC
VPV?Q
VPVWW
VP77C
VP7CR
VP78O
VP7RQ
OUH5z VPVO7
VPVOX
VPV88
VPVR7
VPVXC
VPVQV
VPVQW
VPV??
VP7VV
VP77V
8UH5z VPVCR
VPVC?
VPVOR
VPV87
VPV8W
VPVRR
VPVXC
VPVXW
VPVQW
VPV?Q
QUH5z VPV7X
VPV7W
VPVCO
VPVCQ
VPVOC
VPVOX
VPV8V
VPV8R
VPVR7
VPVRX
7VUH5z VPV7O
VPV7R
VPV7?
VPVC7
VPVCR
VPVC?
VPVO7
VPVOR
VPVOW
VPV8O
CVUH5z VPVVW
VPV7V
VPV7C
VPV7O
VPV7X
VPV7?
VPVCV
VPVCC
VPVC8
VPVCX
OVUH5z VPVVQ
VPVV?
VPVVW
VPV77
VPV7O
VPV78
VPV7R
VPV7Q
VPV7W
VPVCV
8RUH5z VPVVX
VPVVX
VPVV?
VPVVW
VPV7V
VPV77
VPV7C
VPV7O
VPV78
VPV7R
XVUH5z VPVVR
VPVVX
VPVVQ
VPVV?
VPVVW
VPV7V
VPV7V
VPV77
VPV7C
VPV7O
�����������������%���������������l&��� ��l��������# s�%l� �l�������#�����-������#����������� ��& �o���� �l�l�&����������
��&��!�&&�l��" �l������� �l����������� �]���%������������ �l������� ����p����"������� �l�l&��%���%�%�� ����������������������%���������%���l����"��
����st r��p����o�� bg2T@5xKAE54
/��0����1��
2345676389:3;5
<=3;;65>3;86?8993:@
/01234560734831109:
/01234560734;0<
/01234560734031907
A;9
BCC@;
DC;9
BCC@;
DC;9
/��0����1��
2������ �%�����#�3�%%� 4������&�5�����������
4������&�6����� 4������&�6��� �3���� �)���7����6����8�"�!���
9��������'��8��3 9��������:���� "���
A>@B
")23A
§̈¦I-90
25922600
2594 2588
26062580
2572 2
25702
4 2562
6 2524
2522 2522
2568 2572
Source: Esri, Maxar, Earthstar Geographics, and the GIS User Community
PATH: \\DEN-GISSRV1\GISDATA\DATA\SOUTH DAKOTA\JACKSONCOUNTY\SD FLAP TO15 DELTA\SD-FLAPDELTA.MXD - USER: AFINSETH - DATE: 10/2/2022
CFLHD SD FLAP TO15 DELTA01
OVERALL BASIN MAP
0 340 680 1,020 1,360 Feet
I
Basin ID
Area (acres)
Basin Label
11.7
5.0
1.4
9.5
LEGEND
ID
Area (acres)
Basin Label
Basin Boundary
Flow Arrows
Contour Note:
This map covers major offsite basins. Minor basins are shown on Basin Maps 1-3.
Begin Project
End Project
N00°44'50"E
.0
P O
B
N
0.7 ac
B2
101+18
Begin Project
CL CS-23AI-90
1.7 ac subB3
Legend
Basin Boundary
Existing Contours
Direction of Flow
Design Point
(square miles)
Area (acres) or
Basin ID
DP1
DP2
744 ac
B1
11.7 ac
B3 xx AC
B1
:2
P
M c to b e r
D e lt a D r a in a g e B a s in
M a p s
D r a in a g e M e m o S h e e ts
S h e e t] c p w w o r k in g \c e n tr a l0
\d
\B a s in
S
D F
L A
P C
S A
.d g n
DRAINAGE BASIN MAPS
DELTA-01 ACCESS ROAD
STATE PROJECT
NUMBER
SHEET
SD
SD FLAP CS23A(1)
DELTA-01 ACCESS ROAD
.1
P I
N
CL CS-23A
1.4 ac
B5
Culverts Sta 104+77
Culverts Sta 112+42
Culverts Sta 112+74
Culverts Sta 113+27
0.3 ac
B8
0.4 ac
B70.2 ac
B6
Legend
Basin Boundary
Existing Contours
Direction of Flow
Design Point
(square miles)
Area (acres) or
Basin ID
DP1
DP1
DP8DP3
DP7
DP5
744 ac
B1
11.7 ac
B3 xx AC
B1
5.0 ac
B4
:5
S e p te m b e r
D e lt a D r a in a g e B a s in
M a p s
D r a in a g e M e m o S h e e ts
S h e p w w o r k in g \c e n tr a l0
\d
\B a s in
S
D F
L A
P C
S A
.d g n
DRAINAGE BASIN MAPS
DELTA-01 ACCESS ROAD
STATE PROJECT
NUMBER
SHEET
SD
J B
N
0.5 ac
B11
0.1 ac
B12
CL CS-23A
End Project 127+45
Culverts Sta 119+12
Legend
Basin Boundary
Existing Contours
Direction of Flow
Design Point
(square miles)
Area (acres) or
Basin ID
DP1
DP9
DP10
DP11
DP12
0.2 ac
B10
744 ac
B1
9.5 ac
B9 xx AC
B1
:2 c to b e r
D e lt a D r a in a g e B a s in
M a p s
D r a in a g e M e m o S h e e ts
S h e p w w o r k in g \c e n tr a l0
\d
\B a s in
S
D F
L A
P C
S A
.d g n
DRAINAGE BASIN MAPS
DELTA-01 ACCESS ROAD
STATE PROJECT
NUMBER
SHEET
SD
Rational Method
Runoff Coefficients Project: SD FLAP 23A(1) Delta01 Computed: CB Date: 9/20/2022
Existing Hydrology Checked: AF Date: 9/22/2022
Sub-Basin Data
Basin ID Description
Total Area
(ac)
2 D/W Culvert STA 101+45R 0.66 0.24 0.29 0.34 0.44 0.52 C 22.7% 0.15 0.51
3 Cross Culvert STA 104+77 11.70 0.90 0.19 0.24 0.34 0.41 C 1.2% 0.14 11.56 sub3 Roadside Ditch STA 100-105L 1.70 0.25 0.19 0.24 0.34 0.49 C 17.1% 0.29 1.41
Roadside Ditch STA 107-105L/
Cross Culvert STA 104+77 5.00 3.04 0.32 0.37 0.47 0.41 C 1.6% 0.08 4.92
Roadside Ditch STA 107-110L/
6" PVC at field access 1.40 0.57 0.30 0.35 0.45 0.44 C 7.1% 0.10 1.30
6 Roadside Ditch STA 110-112R 0.18 0.27 0.32 0.37 0.47 0.55 C 27.8% 0.05 0.13
7 Roadside Ditch STA 117-113R 0.35 0.49 0.32 0.37 0.47 0.54 C 25.7% 0.09 0.26
8 Roadside Ditch STA 117-113L 0.31 0.54 0.32 0.37 0.47 0.60 C 35.5% 0.11 0.20
Roadside Ditch STA 128-119L/
Cross Culvert STA 119+12 9.50 0.16 0.16 0.21 0.31 0.49 C 15.6% 1.48 8.02
10 Roadside ditch 125-123R 0.23 0.14 0.37 0.14 0.52 0.57 C 30.4% 0.07 0.16
11 swale 127-125R to d/w culvert STA 125R 0.46 1.35 0.31 0.36 0.46 0.60 C 37.0% 0.17 0.29
Roadside ditch STA 128-127R/
Parking Lot d/w culvert 127R 0.11 0.01 0.16 0.21 0.31 0.55 C 27.3% 0.03 0.08
Type of Drainage Area
Streets:
Pavement
Meadows
Composite
C100
*C values determined from DM, Chapter 7 Hydrology, Table 7.13-A Runoff Coefficients for the Rational Equation
Composite
C25
Composite
C2
Composite
C5 Hydrologic Soils Group
Percent
Impervious
Area
Impervious (ac)
Area Pervious
(ac)
0.7-0.95
0.10-0.40
Composite
C10
Runoff Coefficient
SDDOT 7.13-A
Runoff Coefficients for the Rational Equation
Standard Form SF-1 . Time of Concentration
Project: SD FLAP 23A(1) Delta01 Computed: CB Date: 9/20/2022
Checked: AF Date: 9/22/2022
SUB-BASIN DATA INITIAL/OVERLAND FLOW TRAVEL TIME
(ti) (tt)
*see Tabl 3-3
Basin ID Description
Intercept
Coefficient (k)
2 D/W Culvert STA 101+45R 0.29 23 0.66 35 2558 2556 0.057 3 341 2556 2547 0.026 0.3 1.7 3.34 7 6.8
3 Cross Culvert STA 104+77 0.19 1 11.70 39 2562 2561 0.026 5 1456 2561 2546 0.010 0.3 1.1 22.83 28 28.0 sub3 Roadside Ditch STA 100-105L 0.19 17 1.70 61 2563 2562 0.016 9 828 2562 2546 0.019 0.4 1.9 7.37 16 16.2
Roadside Ditch STA 107-105L/
Cross Culvert STA 104+77 0.32 2 5.00 100 2556 2554 0.020 12 1084 2554 2546 0.007 0.3 0.9 20.08 32 32.2
Roadside Ditch STA 107-110L/
6" PVC at field access 0.30 7 1.40 100 2551 2550.5 0.005 21 488 2551 2545 0.011 0.3 1.1 7.32 28 28.5
6 Roadside Ditch STA 110-112R 0.32 28 0.18 18 2547 2546 0.056 2 220 2546 2540 0.027 0.3 1.7 2.12 4 5.0
7 Roadside Ditch STA 117-113R 0.32 26 0.35 19 2553.5 2553 0.026 3 319 2553 2540 0.041 0.3 2.1 2.51 5 5.4
8 Roadside Ditch STA 117-113L 0.32 35 0.31 18 2553.5 2553 0.028 3 382 2553 2541 0.031 0.3 1.8 3.63 6 6.3
Roadside Ditch STA 128-119L/
Cross Culvert STA 119+12 0.16 16 9.50 100 2582 2580 0.020 12 1246 2580 2549 0.025 0.3 1.6 13.30 25 25.5
10 Roadside ditch 125-123R 0.37 30 0.23 27 2565 2563 0.074 3 266 2563 2553 0.038 0.3 1.9 2.31 5 5.0
11 swale 127-125R to d/w culvert STA 125R 0.31 37 0.46 30 2576 2575.5 0.017 5 186 2576 2564 0.062 0.3 2.5 1.26 6 6.2
Roadside ditch STA 128-127R/
Parking Lot d/w culvert 127R 0.16 27 0.11 19 2575 2574.5 0.026 3 105 2575 2574 0.005 0.3 0.7 2.56 5 5.4
Notes: HEC-22 Table 3-3. Intercept Coefficients for Velocity vs Slope English Unit Conversion
1. Overland Flow, T = 0.42 / P2^0.5 (nL/√s)^0.8 (HEC2 (Section 2.5 / SDDOT, Equation 7.8) Land Cover/Flow Regime k
2. Travel Time, Tt = L/60V (SDDOT, Equation 7.8) Forest with heavy ground litter; hay meadow (overland flow) 0.076 0.11324
3. Velocity, V = 33kS^0.5 (SDDOT, Equation 7.8) Trash fallow or minimum tillage cultivation; contour or strip cropped; woodland (overland flow) 0.152 0.22648
4. Shallow Concentrated Flow Velocity, Vt = HEC22, Eqaution 3-4 V=KukSp^0.5 Short grass pasture (overland flow) 0.213 0.31737
5. k HEC22 Table 3-3 Cultivated straight row (overland flow) 0.274 0.40826
6. Minimum Tc = 10 minutes Nearly bare and untilled (overland flow); alluvial fans in western mountain regions 0.305 0.45445
Grassed waterway (shallow concentrated flow) 0.457 0.68093
Unpaved (shallow concentrated flow) 0.491 0.73159
Paved area (shallow concentrated flow); small upland gullies 0.619 0.92231
C5
Length
(ft)
Elevation
Start
Elevation
End
Slope
(ft/ft)
Percent
Impervious
FINAL Tc
(min)
Total
Area
(ac) ti
(min)
Length
(ft)
Elevation
Start
Elevation
End
So
(ft/ft) Velocity
Travel
Time Tt
(min) tc = ti + tt
(min)
Rational Analysis
Standard Form SF-2 . Storm Drainage System Design (Rational Method Procedure) Corridor / Design Package: SD FLAP 23A(1) Delta01 Computed: CB Date: 9/20/2022
Checked: AF Date: 9/22/2022
Design Storm: 10-yr
B A
S
IN
I D
A R
E A
A
C
R U
N O
F F
C O
E F
F t c
(M
IN
C .A
(A C
I
IN
H R
Q
(C
S
S U
M
C *A
(A C
I
(I N
H
R
Q
(C F
S
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
D/W Culvert STA 101+45R 2 2 0.66 0.34 6.79 0.22 5.96 1.32 roadside ditch to existing d/w culvert
Cross Culvert STA 104+77 3 3 11.70 0.24 28.01 2.84 2.82 8.01 ofsite to roadside ditch to Culvert Sta 104+77
Roadside Ditch STA 100-105L 3 sub3 1.70 0.24 16.23 0.41 3.82 1.58 sub area ditch flows
Roadside Ditch STA 107-105L/
Cross Culvert STA 104+77 3 4 5.00 0.37 32.23 1.83 2.58 4.73 32.23 5.09 2.58 13.13 offsite to roadside ditch to Culvert Sta 104+77
Roadside Ditch STA 107-110L/
6" PVC at field access 5 5 1.40 0.35 28.47 0.50 2.78 1.38 offsite from west to roadside ditch to existing d/w pvc
Roadside Ditch STA 110-112R 6 6 0.18 0.37 5.00 0.07 6.59 0.43 roadside ditch drains into B1
Roadside Ditch STA 117-113R 7 7 0.35 0.37 5.40 0.13 6.45 0.83 roadside ditch drains into B1
Roadside Ditch STA 117-113L 8 8 0.31 0.37 6.33 0.11 6.12 0.70 roadside ditch drains offsite to west
Roadside Ditch STA 128-119L/
Cross Culvert STA 119+12 9 9 9.50 0.21 25.45 1.97 3.03 5.97 offsite to roadside ditch to Culvert 119+12 to B1
Roadside ditch 125-123R 10 10 0.23 0.14 5.00 0.03 6.59 0.22 6.25 0.22 6.15 1.37 roadside ditch drains into B1 swale 127-125R to d/w culvert STA 125R 11 11 0.46 0.36 6.25 0.17 6.15 1.03 6.25 0.19 6.15 1.17 existing d/w culvert to B10
Roadside ditch STA 128-127R/
Parking Lot d/w culvert 127R 12 12 0.11 0.21 5.45 0.02 6.43 0.15 existing d/w culvert to B11
(1) Basin Description linked to C-Value Sheet (7) =Column 4 x Column 5
(2) Basin Design Point (8) Intensity from Noah 14 Atlas
(3) Enter the Basin Name from C Value Sheet (9) =Column 7 x Column 8
(4) Basin Area linked to C-Value Sheet (10) =Column 6 + Column 21
(5) Composite C linked to C-Value Sheet (11) Add the Basin Areas (7) to get the combined basin AC
(6) Time of Concentration linked to C-Value Sheet (12) =28.5*P/(10+Column 10)^0.786
(13) Sum of Qs
REMARKSLOCATION
D E
S
IG
N P
O
IN
T DIRECT RUNOFF TOTAL RUNOFF
Rational Analysis
Corridor / Design Package: SD FLAP 23A(1) Delta01 Computed: CB Date: 9/20/2022
Checked: AF Date: 9/22/2022
Design Storm: 25-yr
A R
E A
D
S
IG
(n a m e
A R
E A
A
C
R U
N O
F F
C O
E F
C .A
(A C
I
IN
H
S
S U
M
C *A
(A C
I
(I N
H
R
Q
(C F
S
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
D/W Culvert STA 101+45R 2 2 0.66 0.44 6.8 0.29 7.44 2.14 roadside ditch to existing d/w culvert
Cross Culvert STA 104+77 3 3 11.70 0.34 28.0 4.01 3.52 14.12 ofsite to roadside ditch to Culvert Sta
104+77
Roadside Ditch STA 100-105L 3 sub3 1.70 0.34 16.2 0.58 4.77 2.78 sub area ditch flows
Roadside Ditch STA 107-105L/
Cross Culvert STA 104+77 3 4 5.00 0.47 32.2 2.33 3.22 7.51 32.23 6.93 3.22 22.31 offsite to roadside ditch to Culvert Sta
104+77
Roadside Ditch STA 107-110L/
6" PVC at field access 5 5 1.40 0.45 28.5 0.64 3.47 2.21 offsite from west to roadside ditch to existing d/w pvc
Roadside Ditch STA 110-112R 6 6 0.18 0.47 5.0 0.08 6.02 0.51 roadside ditch drains into B1
Roadside Ditch STA 117-113R 7 7 0.35 0.47 5.4 0.16 8.05 1.32 roadside ditch drains into B1
Roadside Ditch STA 117-113L 8 8 0.31 0.47 6.3 0.14 7.64 1.11 roadside ditch drains offsite to west
Roadside Ditch STA 128-119L/
Cross Culvert STA 119+12 9 9 9.50 0.31 25.5 2.92 3.79 11.06 offsite to roadside ditch to Culvert 119+12 to B1
Roadside ditch 125-123R 10 10 0.23 0.52 5.0 0.12 6.02 0.72 6.25 0.37 7.68 2.82 roadside ditch drains into B1 swale 127-125R to d/w culvert STA 125R 11 11 0.46 0.46 6.2 0.21 7.68 1.64 6.25 0.25 7.68 1.90 existing d/w culvert to B10
Roadside ditch STA 128-127R/
Parking Lot d/w culvert 127R 12 12 0.11 0.31 5.4 0.03 8.03 0.27 existing d/w culvert to B11
(1) Basin Description linked to C-Value Sheet (7) =Column 4 x Column 5
(2) Basin Design Point (8) Intensity from Noah 14 Atlas
(3) Enter the Basin Name from C Value Sheet (9) =Column 7 x Column 8
(4) Basin Area linked to C-Value Sheet (10) =Column 6 + Column 21
(5) Composite C linked to C-Value Sheet (11) Add the Basin Areas (7) to get the combined basin AC
(6) Time of Concentration linked to C-Value Sheet (12) =28.5*P/(10+Column 10)^0.786
(13) Sum of Qs
REMARKSLOCATION
D E
S
IG
N P
O
IN
Corridor / Design Package: SD FLAP 23A(1) Delta01 Computed: CB Date: 9/20/2022
Checked: AF Date: 9/22/2022
Design Storm: 100-yr
A R
A
D
S
IG
(n a m e
A R
E A
A
C
R U
N O
F F
C O
E F
C .A
(A C
I
IN
H
S
S U
M
C *A
(A C
I
(I N
H
R
Q
(C F
S
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
D/W Culvert STA 101+45R 2 2 0.66 0.52 6.79 0.35 9.8 3.41 roadside ditch to existing d/w culvert
Cross Culvert STA 104+77 3 3 11.70 0.41 28.01 4.76 4.7 22.21 ofsite to roadside ditch to Culvert Sta 104+77
Roadside Ditch STA 100-105L 3 sub3 1.70 0.49 16.23 0.84 6.3 5.29 sub area ditch flows
Roadside Ditch STA 107-105L/
Cross Culvert STA 104+77 3 4 5.00 0.41 32.23 2.04 4.3 8.74 32.23 7.64 4.3 32.69 offsite to roadside ditch to Culvert Sta 104+77
Roadside Ditch STA 107-110L/
6" PVC at field access 5 5 1.40 0.44 28.47 0.62 4.6 2.83 offsite from west to roadside ditch to existing d/w pvc
Roadside Ditch STA 110-112R 6 6 0.18 0.55 5.00 0.10 10.9 1.08 roadside ditch drains into B1
Roadside Ditch STA 117-113R 7 7 0.35 0.54 5.40 0.19 10.7 2.02 roadside ditch drains into B1
Roadside Ditch STA 117-113L 8 8 0.31 0.60 6.33 0.18 10.1 1.87 roadside ditch drains offsite to west
Roadside Ditch STA 128-119L/
Cross Culvert STA 119+12 9 9 9.50 0.49 25.45 4.61 5.0 23.15 offsite to roadside ditch to Culvert 119+12 to B1
Roadside ditch 125-123R 10 10 0.23 0.57 5.00 0.13 10.9 1.42 6.25…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .