SCOPE_-_SHIP_-_7870_Herrington_Dr_-_Hutchins_C.docx

DOCX document 33 KB Posted

Attached to
NED Home Rehab - 7870 Herrington Dr
Solicitation number
NED-S-7870-040726
Issued by
Escambia County, Florida

About this file

This is a Scope of Work document issued by the Escambia County Neighborhood Enterprise Division for residential rehabilitation services under the State Housing Initiatives Partnership (SHIP) program at 7870 Herrington Drive in Pensacola, Florida. The project encompasses three primary work categories: mandatory roofing work including removal and replacement of roof covering, repair of approximately 320 square feet of damaged decking and framing, installation of new underlayment, drip edge, vents, flashing, 30-year architectural shingles or modified bitumen roof system for low-sloped areas, hurricane clips, tree trimming, fascia and soffit repair, and gutter replacement; mandatory electrical work including rewiring to comply with the National Electrical Code, hardwired smoke detectors with battery backup, LED bathroom lighting fixtures, and drywall repair; and optional plumbing work involving removal and replacement of tub/shower units with walk-in shower installation, grab bars, new faucets, and piping replacement. A mandatory on-site walk-through is scheduled for April 14, 2026, at 11:00 AM. Quote submissions are due April 22, 2026, at 1:00 PM through the OpenGov portal, with quote review and contractor selection occurring April 23, 2026, at 1:00 PM. The project completion deadline is 60 days from the Notice to Proceed.

Bidders must submit itemized pricing for all work with labor, overhead, permits, insurance, and profit included in line-item pricing rather than as separate charges. For projects under $15,000, payment will be a lump sum upon project completion. For projects exceeding $15,000, contractors receive a 40 percent draw upon confirmation of 50 percent work completion, a substantial completion draw thereafter, and final payment upon project completion, building inspection sign-off, homeowner acceptance, and submission of required documentation. Liquidated damages of $150 per day apply for work extending beyond the 60-day contract period. Eligible bidders must be licensed, insured, and in good standing with Escambia County, with current W-9 forms, Sunbiz registration, state or state-certified contractor licenses, Escambia County Competency Board licenses, worker's compensation insurance or exemption, Commercial General Liability insurance with $1,000,000 coverage naming Escambia County as certificate holder and additional insured, EPA RRP certifications, and proof of non-debarment status via sam.gov. Projects valued at $25,000 or higher require 100 percent Performance and Payment Bonds. There is no federal funding for this project; funding sources are not specified in the scope document.

View the file

Other files

File Type Posted
NED_Home_Rehab_-_7870_Herrington_Dr.pdf PDF
SCOPE_-_SHIP_-_7870_Herrington_Dr_-_Hutchins_C.docx DOCX document
Bid_Scope_Materials_List.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ESCAMBIA COUNTY NEIGHBORHOOD ENTERPRISE DIVISION

SHIP Housing Repair – SCOPE OF WORK

OWNER:
Cheneka Hutchins
JOB NUMBER:
NED-S-7870-040726
ADDRESS:
7870 Herrington Drive
DATE PREPARED:
04-07-2026

Pensacola, FL 32534

WALK DATE:
04-14-2026 11:00 am
PHONE:
504.638.1183
QUOTES DUE:
04-22-2026 1:00 pm
QUOTE REVIEW:
04-23-2026 1:00 pm

I/(we) certify that I/(we) have carefully examined the Housing Repair Specifications and Contractor Requirements related to the above referenced job, as furnished by Escambia County, and I/(we) have also examined the site on which the proposed work is to be performed. Based on these examinations, We propose to furnish all materials, tools, machinery and labor necessary to complete the work in a professional, workmanship manner and to complete the work at the prices listed.

TOTAL JOB COST

CONTRACTOR’S SIGNATURE

TITLE

QUOTE REVIEW:

FIRM

|_| ACCEPTED
|_| REJECTED

FIRM PHONE NUMBER

QUOTE REPRESENTATIVE

Escambia County Building Code

REQUIRED PERMITS AND INSPECTIONS:

By signing this document, you are certifying that your firm is not currently suspended, debarred, or in any way disqualified from participating in any county, state, or federal funded housing rehabilitation programs.

All measurements are for reference only and should be confirmed by the bidder.

Mandatory ON-SITE walk-through: April 14, 2026, at 11AM

INSTRUCTIONS TO BIDDERS

The bidder must complete, sign, and upload the cover sheet and all numbered pages on the Scope of Work. The bidder must also complete the itemized pricing table and include a total cost. Failure to do any of these requirements will result in the bid being rejected. Hand delivered, emailed or faxed submissions will NOT be accepted. Submissions are only accepted online, via the OpenGov portal. All quotes must be received by the published “Quotes Due” deadline.

The quotes will be opened on the “Quotes Due” and awarded to the lowest and most responsible bidder. The opening of these quotes or the “Quote Review” will be held at 221 Palafox Place, Pensacola, FL 32502 on April 23, 2026. Should the total cost of this project exceed the funds available, then a removal of one or more of the optional pricing tables line items may be removed to maintain the program’s budgetary restrictions.

CONTRACTOR’S RESPONSIBILITIES AND OBLIGATIONS

All repair work performed must be inspected and conform to state laws, and the Escambia County building codes and ordinances. The contractor is responsible for proper reattachment or hook-up of any of the following that apply; appliances, existing coaxial cable, telephone and interface, electric, water, and sewage. The contractor will only assist in moving the larger furniture and the contractor is not responsible for the removal of the homeowner’s trash, discarded belongings or furnishings. Labor, overhead, permits, insurance, and profit must be included into each itemized line-item price and not listed as a separate itemized price or listed under “miscellaneous.” Non-compliance will result in rejection of bid. Review the “Bid Scope Materials List” for product lines and or their equivalents.

HOMEOWNER’S RESPONSIBILITIES AND OBLIGATIONS

The homeowner is responsible for maintaining existing utilities for the contractor use during the rehabilitation period and for the removal of all belongings and furnishings from the designated work areas prior to the start date. The homeowner is also to be given options when selecting colors and styles of the products being replaced.

PAYMENT SCHEDULE

The payment will be lump sum payment at the project completion for bids and under $15,000. For bids over $15,000, the contractor will be eligible for a 40% draw once the NED confirms that 50% of the work has been completed as determined by line-item costs. Within 20 business days after the initial draw the contractor will be eligible for a substantial completion draw which is to be 150% less of any line-item costs that are not complete. The contractor will be eligible for final payment after the following conditions have been fulfilled:

*Completion of the Scope of Work

*Inspection/Sign-off by Building Inspections and/or Health Department
*Acceptance by the Homeowner (Homeowner’s Release & Warranty)
*Contractor’s Final Affidavit
*Warranty Paper provided to the Homeowner
*Premises free from all construction debris
*Submission of RRP Checklist Form
*Original Invoice from Contractor

*Surety’s Consent to Final Payment (if applicable)

COMPLETION DATE

There is a 60-day time limit on this rehabilitation project. For every day worked more than the contract period, liquidated damages of ONE HUNDRED and FIFTY DOLLAR ($150.00) per day will be assessed. During this timeline the homeowner is not to begin any new rehabilitation projects.

ESCAMBIA COUNTY NEIGHBORHOOD ENTERPRISE DIVISION

HOUSING REPAIR PROGRAMS

CONTRACTOR REQUIREMENTS

If your firm is awarded the bid for housing repair (SHIP or HUD programs), the following items must be current and on file to issue a Purchase Order.

*Current W9 and Sunbiz registration (less than one year old).
*County Vendor Information sheet (less than one year old).
*Worker’s Compensation as required by State Law OR exemption form.
*Commercial General Liability, Automobile Liability and Pollution Liability at

($1,000,000 coverage) and listing Escambia County as a certificate holder and a additional insured.

*Commercial General Liability, Automobile Liability and Pollution Liability certificates must state the following under Additional Interest:

Escambia County C/O Neighborhood Enterprise Division 221 Palafox Place Suite 304 Pensacola, FL 32502-5844

All correspondence should be directed to the Neighborhood Enterprise Division, 221 Palafox Place, Suite 304, Pensacola, FL 32502 for review.

*For jobs valued at $25,000 or higher, a 100% Performance and Payment Bonds will be needed prior to the Notice to Proceed date. If the Bond is not filed within 10 days after the contract is signed, then a letter of insurability will be required. A Consent of Surety will be required before final payment. The contractor will be responsible for the recording of all bonds with Pam Childers, Clerk of The Circuit Court of Escambia County Florida.

Refer to BCC Office of Purchasing Risk Management Guidelines Procedure No: PP-180 (Performance and Payment Bonds) and PP-185 (Risk Management Guidelines) for further details. [http://www.myescambia.com/business/purchasing-policies-and-procedures]

Additionally, the Neighborhood Enterprise Division will maintain the following info in the contractor’s file:

*www.sam.gov Contractor may not be federally debarred and participate in this program

*State registered or State Certified Contractor License
*Escambia County Competency Board License
*Escambia County Business/Occupational License
*EPA RRP Renovator and Firm Certifications

Firms quoting Lead Based Paint Abatement jobs must also submit proof of Lead Abatement firm certification.

All information must be current at the time of the award. IF INFORMATION CANNOT BE PRODUCED IN A TIMELY MANNER, THE COUNTY RESERVES THE RIGHT TO AWARD THE BID TO THE NEXT MOST RESPONSIVE BIDDER.

SHIP Housing Repair Program Specifications PAGE 1

Cheneka Hutchins

7870 Herrington Drive

Pensacola, FL 32534

504.638.1183

SCOPE OF WORK

The rehabilitation of this owner-occupied, single-family, residence is to make the home safer, more energy efficient, and easier to access within the provisions of federal, state, and county laws and ordinances and the SHIP repair program. The rehabilitation of this home will include the following tasks as outlined below and the repaired areas are to match as close as possible to their existing surroundings. If additional tasks beyond those included in this scope are discovered, then additional funds may be allocated. Before any additional work is performed, written county approval will be needed. There is no federal funding for this project.

1.ROOFING:

Remove existing roof covering down to the decking and replace any deteriorated or damaged decking with like, kind, and quality of existing materials. Repair or replace any damaged roof framing to include rafter tails, rafters, and barge rafters. Refasten and certify decking attachment. Install a peel and stick underlayment water barrier. Replace the existing drip edge with a new metal drip edge. Install new slant-back vents, replace gas vent caps and all flashing as required. Replace all boots with new lead, EPDM, and or metal boots. Install 30-year architectural (CertainTeed Landmark or equivalent) roof shingle as per manufacturer’s specifications and/or a self-adhering modified bitumen roof system to any low sloped areas as per the Escambia County Building Code. Then install new shingle over the ridge vents. Then install new shingle over the ridge vents. Budget 320 square feet for damaged decking replacement. If they are missing or outdated install hurricane clips on every rafter or truss, with a minimum of 6 pictures illustrating said strapping. Trim any trees over hanging roof to clear roof by approximately 10’ and remove all debris from site. Repair or replace any damaged fascia and soffit with like material and match the finish as close as possible. Replace the existing gutters with new 6” seamless gutters only where gutters are currently installed. This is to include 4” downspouts, splash blocks, and diverters as needed. Photographs are required for all stages of construction.

Roofing total $____________

2.ELECTRICAL:

Re-wire as needed or required to conform to the national electrical code as per the Escambia County Building Code. All smoke detectors should be hardwired with battery back-up. Replace the bathroom fixture, shall be LED or have led light bulbs installed. Repair drywall damage from rewiring and paint to match as close as possible.

Electrical total $_______________

SHIP Housing Repair Program Specifications PAGE 2

Cheneka Hutchins

7870 Herrington Drive

Pensacola, FL 32534

504.638.1183

OPTIONAL:

3.PLUMBING:

Remove the existing tub/shower and shower walls from the bathroom. Replace it with a paneled walk-in shower unit with reinforced grab bars. Repair surrounding areas and replace the tub/shower faucet with a new tub/shower set. Install new vanity sink faucets with pop up drains. Replace any old piping and fittings with new, install new braided supply lines and ¼ turn brass valves. All work is to be completed as per the Escambia County Building Code.

Plumbing total $_____________

Review the “Bid Scope Materials List” for product lines and or their equivalents.

File details come from the government source that posted it. Updated .