This document is a Scope of Work from the Illinois Department of Natural Resources (IDNR) for a project to replace the Auger Feed System at the Des Plaines Propagation Center. IDNR is seeking bids for parts and materials to replace eight feed lines, motors, feed cones, feed pans, and corresponding feed bins. The solicitation lists 31 specific line items that vendors must furnish and deliver by November 1, 2021. Bids may be submitted electronically or by email, and all questions must be submitted in writing no later than three business days before the bid due date.
The contract will be awarded to the lowest, responsible, and responsive bidder. Payment terms are subject to the State Prompt Payment Act, and any steel products used must be manufactured in the United States per the Steel Products Procurement Act. The contract has a one-year warranty on all work provided, and the bid prices must remain valid for 90 calendar days or an extended period agreed to in writing.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1Standard Terms and Conditions1~23.pdf | ||
| Standard CertificationsV.18.1~78.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ILLINOIS DEPARTMENT OF NATURAL RESOURCES
SCOPE OF WORK & PROJECT REQUIREMENTS
Date: July 23, 2021 File# 2-21-020
LOCATION: Des Plaines Propagation Center
PROJECT TITLE: Parts and materials to be used in the Auger Feed System
PROJECT NARRATIVE:
The Illinois Department of Natural Resources (IDNR) requires the replacement of eight feed lines originally installed in the 1950’s, in the Brooder House at Des Plaines Propagation Center located at 30550 S. Boathouse Road, Wilmington, IL 60481. IDNR is seeking a bid for parts and materials for the replacement of all eight auger lines, motors feed cones, feed pans, and corresponding feed bins.
SCOPE OF WORK:
Vendor shall furnish and deliver the following materials to the Des Plaines Propagation Center by November 1, 2021.
1) 8 – Hopper Assembly Feed Line 120 lb
2) 8 – Unloader Kit Single Poultry W/ Anchor Bearing
3) 180 – Tube Poultry Feed 1.75 4 On 10’
4) 200 – Hanger Feed Line (bottom strap)
5) 1760 – Auger Flexible 44mm feed line (feet)
6) 200 – Clamp 13/4” Feed Pipe
7) 8 – Control Pan End Line 110/240 Volts (CSA)
8) 8 – Drive Unit 1/3 HP 352 RPM 5/8” Shaft Poultry Feed Line
9) 8 – Light Kit EOL Control Pan
10) 704 – Feeder 14 Spoke Grill
11) 704 – Feeder Pan Extension Fin, 1 pc
12) 704 – Feeder Pan Drop Tube
13) 16 – Clamp and Insulator
14) 32 – Spring for Shocker Wire
15) 2 – Cable Galvanized 1 x 7 1/16” 1000’ Roll
16) 8 – Switch Assembly Hopper Level Control
17) 8 – Winch Ceiling based Electric with Control, rated for 5,000 lb
18) 280 – Adjuster Cord Universal 1/8” and 3/16” Yellow
19) 4 – Rod Suspension Rod 3/16” X 490’ Roll Cable
20) 8 – Strap Kit with Bolt for 5,000 lb Winch
21) 16 – Clevis Dead End 3/16” for Suspension Rod
22) 40 – Bolt Hex Cap 3/816 X 3” Zinc
23) 80 – Nut Hex Finish 3/816 Zinc
24) 40 – Washer Flat USS 3/8 X 1” Zinc
25) 40 – Washer Flat Fender 3/8 X 1-1/2” Stainless Steel
26) 40 – Bolt Lag Hex 3/8 X 3-1/2” Zinc
27) 300 – Screw Hook 5/16” x 3-1/2” Open End Zinc
28) 300 – Pulley 13/4” Split Fiberglass with Zinc Straps
29) 3 – Rope Diamond Braid No Fray, No Stretch Poly 3/16” X 1000’ Roll
30) 360 – Clamp Caple Galvanized 3/16”
31) 1 – Crank Drill Crank Ceiling Winch 5’
PROJECT SPECIFICATIONS & REQUIREMENTS:
1) Duration Quotes shall be good for ninety (90) calendar days after the submittal date, or for an extended period of time, if agreed to in writing by the Contractor and DNR.
2) Specified Materials Bids shall be based on providing all products/materials exactly as required by the project specifications. Contractor may select from the list of acceptable manufacturers, offer an “equal” product and provide proof of its capabilities to meet the project specifications or, for products specified only by reference or performance standards, select any product which meets or exceeds the specified standards, by any manufacturer, subject to the approval of DNR.
3) New Products Unless otherwise specifically provided in the contract documents, all materials, equipment and products incorporated in the work under the contract shall be new and of a suitable grade for the purpose intended.
4) Warranty The Contractor warrants that all work provided under the contract will be in conformance with the contract and free from defects in workmanship, materials, and equipment for a period of one year from the goods acceptance date. See Section B. Project Instructions and Notes, for any extended warranties that may apply.
| 5) | Steel Products |
| Any steel product(s) used or supplied in the performance of this contract shall be manufactured or produced in the United States, in accordance with the Steel Products Procurement Act, unless a waiver is granted by IDNR (30 ILCS 565/). |
6) Payment Payments, including late payment charges, will be paid in accord with the State Prompt Payment Act and rules when applicable, 30 ILCS 540/; 74 III. Adm. Code 900. This shall be the Contractor’s sole remedy for late payments by the State. Payment terms contained in Contractor’s invoice(s) shall have no force or effect.
| 7) | Contract Award |
| Contract award will be made to the lowest, responsible, responsive bidder. The Department of Natural Resources reserves the right to reject any or all bids. |
8) Term of Contract All equipment shall be delivered by November 1, 2021.
9) Bid Submittal Bids may be submitted electronically on BidBuy or by submitting the attached Bid Form to LeighAnn.Henline2@illinois.gov.
| 10) | Bid Submittal Date and Time |
| Refer to the BIDBUY solicitation for the bid date and time. |
11) Questions ALL QUESTIONS PERTAINING TO THE SCOPE OF WORK OR THE BIDBUY PROCEDURES, MUST BE DIRECTED TO LeighAnn.Henline2@illinois.gov. ALL QUESTIONS MUST BE SUBMITTED IN WRITING NO LATER THAN THREE (3) BUSINESS DAYS BEFORE THE BID DUE DATE.