Scope of Work__191N6526Q0100_SITC of addressable fire alarm system.pdf

PDF 129 KB Posted

Attached to
Supply, Installation, Testing and Commissioning of addressable fire detection/alarm system
Solicitation number
191N6526Q0100
Issued by

About this file

This is a Statement of Work (SOW) for the one-to-one replacement of an addressable fire detection and alarm system at an office building within the U.S. Embassy compound in New Delhi, India.

The project involves replacing an obsolete System III fire detection system in a three-story building with basement with new addressable detection devices, while reusing existing wiring infrastructure. The scope includes installation of smoke detectors, heat detectors, manual call stations, horn/strobe notification devices, and two fire alarm control panels (FACP)—one main panel at the ground floor guard booth and one slave/repeater panel in the basement FAC office. The contractor must provide all labor, materials, tools, and equipment, including GI electrical conduits where required, and comply with NFPA 72, National Electric Code, and National Fire Alarm Code standards. The system must incorporate analog-addressable, network-capable control panels with optical fiber networking, programmable smoke detectors using multi-criteria algorithms, addressable manual fire alarm boxes, UL 1971-compliant synchronized visible notification appliances, and sealed valve-regulated lead acid batteries sized at 120 percent of calculated capacity to support 24-hour quiescent load plus five-minute alarm operation. The work is divided into four phases: design and shop drawings submission, detector replacement with minimal building coverage gaps, panel migration with continued fire detection coverage throughout, and final testing and commissioning. The contractor must submit a Bill of Quantities, cut sheets, timeline, safety and quality control plan, and provide cost per running meter for wiring as a separate line item. Work is restricted to U.S. Embassy business hours (08:30-17:00, Monday-Friday) with 48-hour advance notice required for staff access and material deliveries. The estimated project duration is three weeks from Notice to Proceed, with final acceptance inspection and two-week submittal of commissioning reports and as-built drawings required upon completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work for Installation of one-to-one replacement of Fire

Detection System, Office Building, US Embassy, New Delhi.

SYNOPSIS

The Embassy of the United States of America is in need of replacement of existing obsolete addressable fire detection/alarm system in one of the office buildings at

Enclave Compound of American Embassy in Chanakya Puri by a qualified company specializing in that work.

The office building is a three-story building with one basement and two floors.

Currently a system III is feeding the signals to a NOTIFIER repeater which further conveys the signals to Master Panel at a remote location.

The scope of the project is a one-for-one replacement of devices (detectors, pull stations, annunciators, etc.) using the existing infrastructure (i.e. conductors, etc.)

along with a complete replacement of the main panel with existing addressable repeater panel.

GENERAL REQUIREMENTS

The contractor is expected to go through the Scope of work and come prepared with questions for USG (United States Government) rep.

The contractor will be responsible for technically qualified labor, specialized materials and associated tools and equipment required to carry out all works, unless stated otherwise in other section(s) of this SOW.

The contractor prepares and submit quotes formulated from this scope of work and a walkthrough of the site to see the existing condition.

The contractor is to provide a work schedule as part of the project submittal requirement after contract award. Schedule is to conform to the contract required duration.

The contractor is to submit as part of the submittals a safety and quality control plan for the project for review and approval.

Contractor quotes shall accompany cut sheets for the detectors, pull stations, strobes etc. for evaluation purposes. Contractor quote shall also mention that the proposed materials is latest and available upon requirement (do not have a long lead items).

Contractor shall provide cost of the wiring per running meter as a sperate line item to be considered in case there is a requirement for additional wiring or replacement of existing.

All material and work statements need to be approved by Subject Matter Experts back in US.

The contractor must abide by all necessary safety requirements (EM181-1-1) and standards during the construction. Specific safety requirements for this work would be proper PPE and working at heights over 1.5m per work requirement.

Nonconformance to proper safety requirements may lead to project suspension and possibly cancellation. The U.S Government is not liable for injuries or provision of required safety equipment.

The contractor shall provide 48 hours in advance a request for access of staff, providing full names, type of vehicles with plate numbers intended to access the compounds and any material delivery intended to be brought into the compound.

Work hours for this project will be typical U.S. Embassy business hours of 08.30 hours to 17.00 hours, Monday to Friday. No work will happen on Saturday, Sunday or mission holidays. Different or additional workdays or hours as may be needed must be pre-approved by the COR and a minimum of 48hrs in advance must be requested from the contractor.

All installations shall be in accordance with the NFPA 72, National Electric Code and National Fire Alarm Code requirements

The contractor is responsible for removal and disposal offsite (at an approved disposal site) of all debris arising from the construction.

BIDS SUBMISSION REQUIREMENTS:

1. BOQ for the entire project.

2. Cut sheets of the items / materials / Equipment’s proposed for this project.

3. Tentative Timeline for the project.

PROJECT REQUIREMENTS:

Contractor shall prepare shop drawings showing location of all the detectors on all the floors along with location of the master panel and slave / secondary panel.

Proposed shop drawings shall also show any new requirement for wiring and new circuits from each floor to the master and slave panel. Product information for the devises and panels shall be submitted for approval along with shop drawings.

Location of master panel is fixed at the ground floor and slave panel in the FAC office in basement.

No work shall start without any approved shop drawings/product submittals and work schedule.

Contractors will be shared with drawings as available with USG.

Actual measurements and verification of conformance of the design is the responsibility of the contractor.

Contractor shall prepare a tentative BOQ based on their design proposal and submit along with their quote for understanding of the evaluator about the design concept and devises used.

Currently Elevator Recall Interlocking is part of the existing fire detections system.

Any change in the system due to any replacement or repair and impacting functionality shall bring the system back to the existing working group. To ensure these items shall be tested towards end of the project while carrying out final testing and commissioning of the system. Contractors will be liable to check the condition of the wiring and to ensure that condition of the wiring is good for another 10-15 years.

SCOPE OF WORK

The contractor shall provide all supervision, labor, tools/equipment, and material to safely install a fire detection/alarm system. At a minimum, the following work must be done:

Where required, Contractor is to provide and install GI electrical conduits to link conduit boxes to be used for smoke detectors, horn/strobe and manual call station devices. All conduits are to be run to the proposed location for the fire alarm control panel located at the ground floor.

Where required, support for the conduits can be done with properly sized GI saddle

/ clips or any other means deemed feasible and approved by the Contracting

Officer Representative (COR) for the contract. Any coring and drillings through walls and floor slabs shall strictly be coordinated with the COR to minimize any impacts to the building’s structural integrity.

Project will be divided in to following phases:

Phase I

1. Vendor shall prepare shop drawings based on existing installations.

2. Submission of the cut sheets for all the items proposed for replacement.

These will be required along with the bid for approval.

3. Vendor shall disconnect the existing repeater panel installed next to the existing system III panel. Minimum troubles shall report to the master panel installed in a remote location.

Phase II

1. Contractor shall replace all detectors – one to one – within few days on both the floors and also connect the wires to the new repeater panel directly.

2. Contractor shall put two team on job to work in non restricted area and in restricted area under cleared American Escort and devised procured by Embassy.

3. The building at any given point of time shall not be without fire detection system coverage.

Phase III

1. Repeater panel is already installed and shall be used to connect the wires from OLD panel to the new panel.

2. Contractors to ensure that there will be minimum time window for this replacement. The building cannot be left uncovered from fire threat. At any given point of time the building should have detection system active. The contractor must ensure that any new equipment’s installed shall either integrated with the existing system or new system is active parallelly to cover the risk of fire.

Phase IV

1. Testing, Commissioning and final approval from COR.

WIRING

A. Low Voltage System Wiring per relevant codes:

1. Wire shall be data grade low capacitance sized for initiating device circuits, with signaling line circuits, no less than 1 mm and not larger than 1.5 mm as required by manufacturer.

2. Minimum size for notification appliance circuits is 2.5 mm (14 AWG), maximum 4 mm (12 AWG).

3. Provide surge suppression for all circuits, connected prior to any system devices within the structure.

4. Conductors and cables for initiating device circuits, signaling line circuits, and notification appliance circuits that are not run underground shall be approved/listed for such use and shall be listed for environmental conditions in which they are installed.

Contractor shall provide two fire alarm control panels (FACP) (one as master panel in the guard booth and repeater panel in FAC office in basement) thus

a. MAIN FIRE ALARM CONTROL PANEL

A. The main fire alarm systems controls shall:

1. Be an analog-addressable and network capable.

2. Be capable of optical fiber network communications.

3. Be provided with a minimum 80-character screen or LCD.

4. Not incorporate integral radio transmitters.

5. Incorporate programmable function means, such as a momentary key operated switch or keypad.

6. Have capability to be placed in maintenance bypass mode temporarily so that

NAC

circuits are not energized upon input of specific device address or zone.

Maintenance bypass shall require a key or password to be activated and shall restore to normal mode automatically after 4 hours if not returned to normal mode manually. Upon de-activation of notification appliances, any existing alarm shall be transferred to a visual indicator on main FACU and FAAP. Any subsequent alarms from other zones shall cause the alarm notification appliances to re-activate.

7. Be capable of supporting a system printer. Contractor to provide printer for proposed system.

8. Receive and indicate common trouble and supervisory (if applicable) from remote power supplies (NAC extenders), slave control units, and any other interconnected control units, including suppression system controls.

9. Include USB port(s) for system upload / download.

10. Main FACP to be situated at ground floor next to the guard post.

System power supplies:

1. Primary power supply:

a. Obtain primary power for FACP from a dedicated emergency power circuit and terminated in accordance with relevant codes.

b. Supply shall be accessible only to authorized personnel. Identify supply as

“FIRE ALARM CIRCUIT” using label or phenolic plate; either shall be red.

c. Provide transient surge protection at the power input to each cabinet.

2. Secondary power supply:

a. Provide sealed valve regulated lead acid (VRLA) batteries as secondary power supply.

b. Secondary power supply shall supply energy to system with sufficient capacity of 24 hours under maximum quiescent load and at end of that period shall be capable of operating all alarm notification appliances used for evacuation for five minutes.

Size batteries at 120 percent of calculated size to compensate for alarm reserve and aging.

d. Provide automatic battery-charging circuitry for each standby battery bank in system.

All system battery charge rates and terminal voltages shall be read using fire alarm control panel LCD display in service mode, indicating directly in volts and amperes

All battery boxes shall be produced by the same manufacturer as the FACP and shall be

Any new item to be introduced in the system must be L/CE listed. SENSITIVE

BUT UNCLASSIFIED

System Programming Software: Provide latest software revision. Programming shall be Microsoft Windows based. Use of Virtual PC add-ons is not permitted.

Configure system with most current version or revision. Proprietary software shall be licensed to the U.S. Consulate, Kolkata for life of system at no additional charge

(no annual fee from manufacturer). Site-Specific Software (database): Provide two copies of the configuration (site-specific software, using nonvolatile memory) for

U.S Embassy use upon system acceptance. One copy shall be left inside the control unit, and the second copy shall be provided to COR at time of Commissioning.

Remote FACP Panel shall be compatible with main system controls and shall be produced by same manufacturer as Main FACP system.

The Remote FACP system controls and Main FACP system controls shall be networked using optical fiber cable run in minimum of 25mm schedule 40 GI.

Interiorly, the cables shall be run in the same GI conduits surface to the walls and fastened as necessary to relevant building members and terminated in the panels using necessary termination conduit accessories.

SYSTEM DEVICES

A. Initiating Devices.

1. Signal Transmission: By copper wire or fiber optic only. Aluminum conductors are not permitted.

2. Smoke Detectors: Addressable multi-criteria smoke detectors that can be programmed to use a combination of smoke, heat, and time for specific applications.

3. Heat Detectors: Shall be selected to operate at a temperature no less than 11 deg

C (20 deg F) above the maximum expected ambient temperature.

4. Bases, Smoke and Heat Detectors: Shall be programmable only using switches on the base or detector. Separate handheld or stationary programming units shall not be used.

5. Manual fire alarm boxes: Shall be of the addressable type and shall conform to accessibility requirements of the Architectural Barriers Act (ABA) and shall be red in color. Break glass type manual fire alarm boxes shall not be permitted.

B. Notification Devices:

1. Visible Notification Appliances: UL 1971 compliant and synchronized as required by NFPA 72. Visible notification appliances shall be multi-candela, red in color, and SENSITIVE BUT UNCLASSIFIED labeled “FIRE” with white letters

2. Audible Notification Appliances: Electronic horns, sounder-bases or speakers complying with UL 464.

Audible notification appliances shall be silence able using “Alarm Silence” function. Visible notification appliances shall remain activated after audible silence until control panel reset.

Contractor shall perform system’s testing and commissioning in accordance with the systems manufacturer’s provisions as stated in the systems operations and maintenance manuals. Such tests shall be coordinated with and witnessed by the contracts COR. The commissioning reports shall be submitted in both hard and soft copies as part of the project close out submissions.

Contractor is to provide an as built drawing for the installed system and submit two hard copies and a soft copy in a CD format. Soft copy of the drawing shall be saved in both CAD and PDF formats.

FINAL ACCEPTANCE

When requested by the contractor, a preliminary acceptance inspection shall be scheduled. The contractor shall make good all defects, deficiencies and omissions noted down during

SENSITIVE BUT UNCLASSIFIED

preliminary acceptance inspection and shall inform in advance the USG representative of the need for conducting a final inspection.

After a final acceptance inspection is completed by the contractor and the USG and all previous deficiencies are found to be addressed, final acceptance shall be communicated in writing through the Contracting Officer Representative (COR) to the contractor.

Contractor shall submit all testing and commissioning reports and as built drawings in the required formats to the COR within two weeks of project close out completion.

Estimated duration of performance of all works is 3 weeks from date of Notice to proceed.

------- END OF STATEMENT OF WORK -------