Scope_of_Services_&_Project_Deliverables.docx
DOCX document 26 KB Posted
- Solicitation number
- 25-SQ-78KW
- Issued by
- Volusia County, Florida
About this file
The file is a Scope of Services document for the Volusia County Office of Recovery and Resiliency (ORR) and the City of New Smyrna Beach's Stormwater Master Plan (SMP) Phase II project. The project is a comprehensive stormwater management initiative involving developing a citywide stormwater model, conducting floodplain mapping, performing improvement alternative analysis, and related tasks. The scope of work includes seven primary tasks: project initiation, stormwater model development, level of service improvement alternatives analysis, floodplain mapping and FEMA permitting, public meetings, reporting, and project quality management. The consultant will be required to simulate various storm events, delineate hydrological units, develop model schematics, identify capital improvement projects, and prepare detailed reports and presentations.
The project is funded by a U.S. Department of Housing and Urban Development (HUD) Community Development Block Grant for Disaster Recovery (CDBG-DR), specifically aimed at recovering from damage caused by Hurricane Ian in September 2022. The project deliverables include five signed and sealed final reports, digital elevation models, comprehensive geodatabases, support data documentation, and multiple meeting attendances. The consultant will coordinate with the St. Johns River Water Management District, perform water quality benefit analyses, and develop GIS layouts for conceptual alternatives. The project emphasizes technical precision, requiring one-dimensional ICPR analyses, detailed model parameterization, and strict adherence to specific technical guidelines and standards set by various water management authorities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SMP Scope of Services – Phase II
Task 1 – Project Initiation
One (1) week of the kick-off meeting, the CONSULTANT shall prepare meeting minutes and distribute them to COUNTY staff for review and comment. A project estimate schedule shall be prepared and distributed at the kick-off meeting.
Task 2 – Stormwater Model Development
The required scope of services under this task, shall include but not be limited to:
Subtask 2.1 Stormwater Network Feature Database The CONSULTANT shall follow the Geographic Watershed Information System Database Design Document Version 2.1 (GWIS 2.1) published by the Southwest Florida Water Management District (SWFWMD) for with the Interconnected Channel and Pond Routing software called “StormWise” Version 4.08.03 or latest (formerly known as ICPR 4) by Streamline Technologies.
Subtask 2.2 Preliminary Model Schematic & Hyrdological Unit (Sub-basin) Delineation The CONSULTANT shall delineate the hydrological units (sub-basins) using GIS tools and available topographic information. The CONSULTANT shall develop the model schematic for the SMP using naming conventions approved by the COUNTY and CITY.
Subtask 2.3 Model Parameterization The CONSULTANT shall incorporate the parameterized model features into GWIS
2.1 identified below:
· CN Look-up table
· Selected design storm events
· Time of Concentration (Tc)
· Node Storage
· Initial water level conditions in the system to be modeled
· System outfall boundary conditions
· Channel representations
· Bridge representations
· Pipe representations
· Weir representations
· Drop structures
Subtask 2.4 Model Setup and Design Storm Simulations The CONSULTANT shall transfer model parameters from the GWIS 2.1 geodatabase into the StormWise model framework. The CONSULTANT shall review preliminary model results for a single design storm event for numeric stability (continuity error of less than 5 percent). The CONSULTANT shall simulate the Mean Annual, 5-year, 10-year, 25-year, 50-year, and 100-year storm events based on the Natural Resources Conservation Service (NRCS) Type II (Florida Modified) rainfall distribution of a 24-hour duration. In addition, the CONSULTANT shall simulate the 25-year storm based on SJRWMD 96-hour distribution and City of New Smyrna Beach 100-year 72-hour storm event to account for either closed basin / hydrological units that discharge to landlocked lakes and water bodies. The CONSULTANT shall confirm with the COUNTY and CITY, the rainfall volume associated with each design storm event in advance of the stormwater model simulations.
Note: The ICPR analyses for the Stormwater Master Plan Phase II shall be performed using the “one- dimensional” method. Such that Drainage Areas, Time of Concentration, and Curve Numbers must be determined by the engineer and shown in the ICPR pre and post condition models.
Task 3 – Level of Service (LOS) Improvement Alternatives Analysis
Subtask 3.1 Alternatives Analysis and Project Ranking The CONSULTANT shall identify feasible stormwater Capital Improvement Projects (CIP) to meet the COUNTY and CITY’s selected LOS for the structures within the model (within the SMP) that are predicted not to meet the assigned LOS. The CONSULTANT shall document each alternative with a description of the proposed project and each project’s advantages and disadvantages. The CONSULTANT shall rank all the alternatives using a ranking approach considering the following factors:
· Flood control benefit and Level-of-Service (LOS) improvements
· Permitting requirements
· Water quality and environmental benefits and compliance with NPDES and TMDL requirements
· Engineer’s opinion of probable design and engineering costs
· Engineer’s opinion of probable right-of-way / property acquisition cost (if applicable)
· Engineer’s opinion of probable construction cost
· Operation and Maintenance (O&M) needs long-term
· Public acceptance for alternative
For those alternatives that provide a water quality benefit, the CONSULTANT shall perform a desktop analysis using the BMP TRAINS tool to estimate the pollutant load reduction for total nitrogen (TN) and total phosphorous (TP). A minimum of three (3) alternatives that provide a water quality benefit shall be evaluated.
All proposed alternatives must be permitted without opposition from the St. John’s River Water Management District (SJRWMD). CONSULTANT must coordinate with SJRWMD staff on permitting requirements prior to finalizing the alternatives.
The CONSULTANT shall provide cost estimates at the present worth dollar value for each identified alternative. The cost estimates shall be based on the conceptual layout and shall be subject to change pending more detailed designs that are beyond the scope of this study. The stormwater improvement alternatives shall focus on identified flooding problem areas. The CONSULTANT also shall develop GIS layouts for each conceptual alternative.
Task 4 – Floodplain Mapping and FEMA Permitting
Subtask 4.1 – Floodplain Delineation The CONSULTANT shall delineate the floodplain based on available digital topographic information and modeled predicted peak stages for the 100-year storm event. Floodplain areas will be delineated based on the greater stage indicated from the 100-year, 24-hour stage event or higher storm intensity event if required by FEMA. The floodplain delineation digital shape features shall be included in the GWIS 2.1 database. The CONSULTANT also shall compare the preliminary floodplain with the effective FEMA flood hazard zone and document in the study. For those areas that do not have recent detailed one-foot contour information, the extent of the floodplain shall be approximated using FEMA 265 (Zone A Manual) guidelines.
Subtask 4.2 – FEMA Letter of Map Revision (LOMR) Package The CONSULTANT shall compile all the necessary documents and data necessary for submitting a Letter of Map Revision (LOMR) package to FEMA. This task shall focus on establishing base flood elevations for areas currently designated as Zone A and providing updated based flood elevation data for existing Zone AE areas where applicable. This task shall include the preparation and submittal to FEMA of the following:
· Complete application MT-2 forms
· LOMR submittal report that incorporates project documentation, model data, figures, exhibits prepared as part of the other aforementioned tasks in the proposal
· Annotated FIRM map for areas of requested map change
· Technical Support Data Notebook (TSDN) supporting documentation. The TSDN directory shall conform to current FEMA guidelines. The complete TSDN directory structure shall be developed, however, only those directories relevant to this study shall be populated.
· Internal Senior and Peer review QA/QC
· LOMR Package Production, Electronic Deliverables and Delivery
The CONSULTANT shall be responsible to address ALL FEMA requests for information (RAI) required to obtain FEMA’s approval of the LOMR.
Task 5 – Public Meetings
Subtask 5.1 – Meetings with County and/or City Commissioners The CONSULTANT shall attend two County or City Commission meetings that are coordinated by the COUNTY and/or CITY. The first meeting shall take place following the completion of the draft report. The second meeting shall provide a brief presentation of the study results with consideration of the comments received during the public meetings and from the County and/or City Commission on the draft report. The presentations shall be performed by the CONSULTANT and shall be prepared utilizing Microsoft Powerpoint and be limited to a maximum of 25 slides. The COUNTY and/or CITY shall schedule the presentation with the Commission.
Subtask 5.2 – Meeting with Citizen Groups The CONSULTANT shall attend and present at two (2) public meetings. The CONSULTANT shall prepare the necessary presentation materials for each meeting as well as respond to questions and solicit input regarding the proposed stormwater plans for the SMP. The COUNTY and/or CITY shall identify and secure the meeting venue.
Task 6 – Report
Subtask 6.1 – Stormwater Master Plan Final Flood Control Study Reports The CONSULTANT shall prepare the SMP Study Draft Reports for COUNTY and CITY review summarizing the data and results of Task 1 through Task 6 in digital (pdf) format. The CONSULTANT shall also provide, in digital format, the draft GWIS 2.1 geodatabase(s) of collected data used in the study and the StormWise (ICPR 4) stormwater model input. The CONSULTANT shall meet with the COUNTY and CITY to discuss the results of the reports and incorporate the COUNTY and CITY’s comments into the final reports. The CONSULTANT shall also provide meeting summary notes from both the County and/or City Commission and public meetings as an appendix to the draft and final reports. The CONSULTANT shall print and assemble the SMP report.
Control Study Final Reports into five hard copy with binders. The report shall include, but not be limited to, the following report section topics:
· Introduction
· Data Collection and Model Parameterization
· Model Development, Results, and LOS Evaluation Narrative
· Alternatives Analysis and Prioritization Narrative
· Summary and Conclusions Narrative Task 7 – Project Quality Management / Meetings Activities performed under this task consist of those general functions required to maintain the project schedule to ensure the quality of work included in this scope is consistent with COUNTY and/or CITY standards. Specific activities included are identified below:
Subtask 7.1 – Project Progress Meetings The CONSULTANT shall participate in three (3) project status review management meetings. These status meetings are intended for discussion regarding:
1) Results of data collection and survey needs
2) Results of stormwater model and LOS evaluation
3) Proposed alternatives, their advantages and disadvantages and their associated costs.
The CONSULTANT shall prepare meeting minutes following each progress meeting and provide them to the COUNTY and CITY within five (5) working days following the meeting.
The CONSULTANT shall coordinate and attend one (1) meeting with the SJRWMD to discuss the proposed alternatives.
Subtask 7.2 – Project Quality Management The CONSULTANT shall maintain an internal quality management system to review various milestone submittals.
Subtask 7.3 – Project Status Reports The CONSULTANT shall prepare and submit to the COUNTY a monthly written status report and invoice over the project’s duration. The CONSULTANT shall also provide bi-weekly e-mail updates.
Project Deliverables:
1) Five (5) signed and sealed (by a Professional Engineer registered in the State of Florida) of the SMP Study Final Report.
2) Digital Elevation Models (DEM) for the basin study where available.
3) GWIS 2.1 geodatabases containing:
· Hydrological units / sub-basins [ICPR_BASIN]
· Stormwater surface connectivity provided as the HydroNetwork [HYDREDGE and HYDROJUNCTION]
· Model Connectivity [ICPR_LINK and ICPR_NODE]
· Historical water levels [HISTORICAL_WATER_LEVELS]
· Land use map [GWID_LANDUSE]
· NRCS Soil Map [GWIS_SOIL]
· Curve Number Lookup Table [ICPR4_CURVE_NUMBER_ZONES]
· Delineated Floodplain [GWIS_FLOOD]
4) Support Data
· Documented flooding problems and complaints
· Topographic information (contours, break lines, spot grades, etc.)
· Basin boundary
· ERP’s incorporated into the basin model
· Data acquisition need locations
· Drainage System Classification for LOS analysis
· Model input / output files for the Mean Annual, 5-year,10-year, 25-year, 50-year, and 100-year, 24-hour events and the 25-year, 96-hour event (SJRWMD closed basin) and 100-year, 72-hour event (City of NSB LDR closed basin)
· Model input / output files for alternatives analysis
· Locations of final recommended alternatives
5) Meeting Attendance
· Kickoff meeting (one)
· Progress Meetings (three)
· SJRWMD Pre-Application meeting (one)
· County or City Commission Meetings (two)
· Public Meetings (two)