Scope_and_Diagrams.docx
DOCX document 151 KB Posted
- Solicitation number
- 26-056UM-IFB
- Issued by
- Hillsborough County, Florida
About this file
This Scope of Work document pertains to the City of Plant City, Florida's municipal communication tower generator replacement project funded through FEMA. The project requires a qualified contractor to furnish and install a complete standby power system, including a 14 kW EPA-certified diesel generator rated at 1.0 power factor and 60 Hz for single-phase 120/240V operation. The generator must be factory-assembled, weatherproof, and sound-attenuated for outdoor installation, accompanied by a subbase fuel tank sized for minimum 48-hour runtime. Additional deliverables include an Automatic Transfer Switch sized for the generator and tower electrical load, all conduit, conductors, grounding, and terminations between the generator, ATS, and existing main distribution panel, a reinforced concrete generator pad constructed per structural specifications, factory-authorized startup services, and onsite load bank testing to verify generator capacity and performance. The contractor must minimize downtime during the transition from the existing to the new generator, with any required downtime not to exceed 12 hours, and must restore all disturbed surfaces and leave the site in clean condition upon completion.
The contractor shall provide all manufacturer-required accessories including battery, battery charger, block heater, vibration isolators, and control panel, along with a sound-attenuated enclosure meeting applicable noise-reduction requirements. All work must comply with NEC Article 250 for equipment grounding and bonding. The contractor shall submit complete test results and commissioning documentation and provide a minimum one-year manufacturer's warranty along with all Operations and Maintenance manuals, wiring diagrams, startup reports, and warranty documentation. This critical project maintains uninterrupted backup power to essential utility infrastructure, including the Water Reclamation Facility, Water Treatment Plant South, and all lift stations throughout the City, ensuring continuous operation during power outages and emergency events.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work The Contractor shall furnish all labor, materials, equipment, tools, transportation, and services necessary to provide and install a complete standby power system for the communication tower, including a standalone diesel generator, automatic transfer switch (ATS), generator pad, testing, and all associated electrical work. Work shall include, but not be limited to, the following:
· Furnish and install one (1) EPA‑certified diesel standby generator, rated 14 kW, 1.0 PF, 60 Hz, single‑phase, 120/240V.
· Generator shall be a factory‑assembled, weather‑proof, sound‑attenuated unit suitable for outdoor installation.
· Provide sub‑base fuel tank sized for a minimum of 48 hours of runtime at the specified load.
· Provide all manufacturer‑required accessories including battery, battery charger, block heater, vibration isolators, and control panel.
· Provide sound‑attenuated enclosure meeting applicable noise‑reduction requirements.
· Furnish and install an Automatic Transfer Switch sized for the generator and tower electrical load.
· ATS shall be provided by the generator manufacturer.
· Provide and install all conduit, conductors, grounding, and terminations between the generator, ATS, and the existing main distribution panel.
· Provide all equipment grounding and bonding in accordance with NEC Article 250.
· Construct a reinforced concrete generator pad in accordance with project structural details.
· Coordinate pad dimensions, anchor locations, and conduit stub‑ups with the generator manufacturer’s requirements.
· Provide factory‑authorized startup of the generator and ATS.
· Perform on‑site load bank testing to demonstrate generator capacity and performance.
· Submit complete test results and commissioning documentation.
· Provide a minimum one‑year manufacturer’s warranty.
· Provide all O&M manuals, wiring diagrams, startup reports, and warranty documentation.
· Contractor shall restore all disturbed surfaces and leave the site in clean condition upon completion.
· The Contractor shall minimize downtime during the transition from the existing generator to the new generator to ensure back up power for the communication tower systems is maintained, with any downtime kept to a minimum, not more than 12 hours.
image1.png image2.png image3.png