SCOPE_-_1807_N_W_St_-_OV_Jackson.docx

DOCX document 33 KB Posted

Attached to
NED Home Rehab - 1807 N W St
Solicitation number
NED-S-1807-092325
Issued by
Escambia County, Florida

About this file

This document is a Scope of Work for a housing repair project issued by the Escambia County Neighborhood Enterprise Division (NED) for a residential rehabilitation at 1807 N. W St. in Pensacola, Florida. The project involves comprehensive home repairs for homeowner Odie-Valencia Jackson, with a mandatory on-site walk-through scheduled for September 26, 2025, at 11 AM, and quotes due by October 1, 2025, at 1:00 PM. The project has a 60-day completion timeline with liquidated damages of $150 per day for delays. The scope primarily focuses on roofing repairs, including removing existing roof covering, replacing damaged decking, installing new architectural shingles, replacing vents and flashing, and trimming overhanging trees.

The project will be funded through the SHIP (State Housing Initiatives Partnership) Housing Repair Program, with no federal funding involved. Payment terms include a lump sum payment for bids under $15,000, with a phased payment schedule for larger projects involving an initial 40% draw after 50% work completion and subsequent draws based on project milestones. Contractors must meet specific requirements, including current W9, workers' compensation, liability insurance, and certifications. For projects valued at $25,000 or higher, a 100% Performance and Payment Bond is required. Bidders must submit quotes through the OpenGov portal, and the contract will be awarded to the lowest, most responsive, and most responsible quoter.

View the file

Other files

File Type Posted
NED_Home_Rehab_-_1807_N_W_St.pdf PDF
Bid_Scope_Materials_List.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ESCAMBIA COUNTY NEIGHBORHOOD ENTERPRISE DIVISION

SHIP Housing Repair – SCOPE OF WORK

OWNER:
Odie-Valencia Jackson
JOB NUMBER:
NED-S-1807-092225
ADDRESS:
1807 N. W St.
DATE PREPARED:
09-22-2025

Pensacola, 32505

WALK DATE:
09-26-2025 11:00 am
PHONE:
O-850.480.4440
QUOTES DUE:
10-01-2025 1:00 pm
QUOTE REVIEW:
10-02-2025 11:30 am

I/(we) certify that I/(we) have carefully examined the Housing Repair Specifications and Contractor Requirements related to the above referenced job, as furnished by Escambia County, and I/(we) have also examined the site on which the proposed work is to be performed. Based on these examinations, I propose to furnish all materials, tools, machinery and labor necessary to complete the work in a professional, workmanship manner and to complete the work at the prices listed.

TOTAL JOB COST

CONTRACTOR’S SIGNATURE

TITLE

QUOTE REVIEW:

FIRM

|_| ACCEPTED
|_| REJECTED

FIRM PHONE NUMBER

QUOTE REPRESENTATIVE

Escambia County Building Code

REQUIRED PERMITS AND INSPECTIONS:

By signing this document, you are certifying that your firm is not currently suspended, debarred, or in any way disqualified from participating in any state or federal funded housing rehabilitation programs.

All measurements are for reference only and should be confirmed by the bidder.

Mandatory ON-SITE walk-through: September 26, 2025, at 11AM

INSTRUCTIONS TO BIDDERS

Complete and submit the cover sheet and all numbered pages on this Scope of Work with a signature of the contractor, the total cost, and the completed itemized pricing table. Quote submissions will only be accepted online, via the OpenGov portal. Hand delivered email or fax submissions will NOT be accepted. All quotes must be received by the published “Quotes Due” deadline.

The quotes will be opened by a quote committee and awarded to the lowest, most responsive, and most responsible quoter. The opening of these quotes or the “Quote Review” will be held at 221 Palafox Place, Pensacola, FL 32502 on October 2, 2025, at 1130A. All interested members of the public are invited to attend. Should the total cost of this project exceed the funds available, then a removal of one or more of the pricing tables line items may be deleted in order to maintain the program’s budgetary restrictions.

CONTRACTOR’S RESPONSIBILITIES AND OBLIGATIONS

All repair work performed must be inspected, rough-ins and finals, and conform to state laws, and the Escambia County building codes and ordinances. The contractor is responsible for proper reattachment/hook-up of any/all of the following that apply, appliances, existing coaxial cable, telephone and interface, electric, water, and sewage. The contractor will only assist in moving the larger furniture and the contractor is not responsible for the removal of the homeowner’s trash, discarded belongings or furnishings. Labor, overhead, permits, insurance, and profit must be included into each itemized price and not listed as a separate itemized price or listed under “miscellaneous.” Non-compliance will result in rejection of bid. Review the “Bid Scope Materials List” for product lines and or their equivalents.

HOMEOWNER’S RESPONSIBILITIES AND OBLIGATIONS

The homeowner is responsible for maintaining existing utilities for the Contractor’s use during the rehabilitation period and for the removal of all belongings of furnishings from the designated work areas prior to the start date. The homeowner is also to be given options when selecting colors and styles of the products being replaced.

PAYMENT SCHEDULE

The payment will be lump sum payment at the project completion for bids and under $15,000. For bids over $15,000, the contractor will be eligible for a 40% draw once the NED confirms that 50% of the work has been completed as determined by line-item costs. Within 20 business days after the initial draw the contractor will be eligible for a substantial completion draw which is to be 150% less of any line-item costs that are not complete. The contractor will be eligible for final payment after the following conditions have been fulfilled:

*Completion of the Scope of Work

*Inspection/Sign-off by Building Inspections and/or Health Department
*Acceptance by the Homeowner (Homeowner’s Release & Warranty)
*Contractor’s Final Affidavit
*Warranty Paper provided to the Homeowner
*Premises free from all construction debris
*Submission of RRP Checklist Form
*Original Invoice from Contractor

*Surety’s Consent to Final Payment (if applicable)

COMPLETION DATE

There is a 60-day time limit on this rehabilitation project. For every day worked more than the contract period, liquidated damages of ONE HUNDRED and FIFTY DOLLAR ($150.00) per day will be assessed. During this timeline the homeowner is not to begin any new rehabilitation projects.

ESCAMBIA COUNTY NEIGHBORHOOD ENTERPRISE DIVISION

HOUSING REPAIR PROGRAMS

CONTRACTOR REQUIREMENTS

If your firm is awarded the bid for housing repair (SHIP or HUD programs), the following items must be current and on file to issue a Purchase Order.

*Current W9 and Sunbiz registration (less than one year old).
*County Vendor Information sheet (less than one year old).
*Worker’s Compensation as required by State Law OR exemption form.
*Commercial General Liability, Automobile Liability and Pollution Liability at

($1,000,000 coverage) listing Escambia County as a certificate holder and additional insured.

*Commercial General Liability, Automobile Liability and Pollution Liability certificates must state the following under additional Interest:

Escambia County C/O Neighborhood Enterprise Division 221 Palafox Place Suite 304 Pensacola, FL 32502-5844

All correspondence should be directed to the Neighborhood Enterprise Division, 221 Palafox Place, Suite 304, Pensacola, FL 32502 for review.

*For jobs valued at $25,000 or higher, a 100% Performance and Payment Bonds will be needed prior to the Notice to Proceed date. If the Bond is not filed within 10 days after the contract is signed, then a letter of insurability will be required. A Consent of Surety will be required before final payment. The contractor will be responsible for the recording of all bonds with Pam Childers, Clerk of The Circuit Court of Escambia County Florida.

Refer to BCC Office of Purchasing Risk Management Guidelines Procedure No: PP-180 (Performance and Payment Bonds) and PP-185 (Risk Management Guidelines) for further details. [http://www.myescambia.com/business/purchasing-policies-and-procedures]

Additionally, the Neighborhood Enterprise Division will maintain the following info in the contractor’s file:

*www.sam.gov Contractor may not be federally debarred and participate in this program

*State registered or State Certified Contractor License
*Escambia County Competency Board License
*Escambia County Business/Occupational License
*EPA RRP Renovator and Firm Certifications

Firms quoting Lead Based Paint Abatement jobs must also submit proof of Lead Abatement firm certification.

All information must be current at the time of the award. IF INFORMATION CANNOT BE PRODUCED IN A TIMELY MANNER, THE COUNTY RESERVES THE RIGHT TO AWARD THE BID TO THE NEXT MOST RESPONSIVE BIDDER.

SHIP Housing Repair Program Specifications PAGE 1

Odie-Valencia Jackson 1807 N. W St.

Pensacola, 32505 O-850.480.4440

SCOPE OF WORK

The rehabilitation of this owner-occupied, single-family, residence is to make the home safer, more energy efficient, and easier to access within the provisions of federal, state, and county laws and ordinances and the SHIP repair program. The rehabilitation of this home will include the following tasks as outlined below and the repaired areas are to match as close as possible to their existing surroundings. If additional tasks beyond those included in this scope are discovered, then additional funds may be allocated. Before any additional work is performed, written county approval will be needed. There is no federal funding for this project.

1.ROOFING:

Remove existing roof covering down to the decking and replace any deteriorated or damaged decking with like, kind, and quality of existing materials. Repair or replace any damaged roof framing to include rafter tails, rafters, and barge rafters. Refasten and certify decking attachment. Install a peel and stick underlayment water barrier. Replace the existing drip edge with a new metal drip edge. Install new slant-back vents, replace gas vent caps and all flashing as required. Replace all boots with new lead, EPDM or metal boots. Install 30-year architectural (CertainTeed Landmark or equivalent) roof shingle as per manufacturer’s specifications and/or a self-adhering modified bitumen roof system to any low sloped areas as per the Escambia County Building Code. Then install new shingle over the ridge vents. Budget 320 square feet for damaged decking replacement and install hurricane clips if they are missing. Trim any trees over hanging roof to clear roof by approximately 10’ and remove all debris from site. Repair or replace any damaged fascia and soffit with like material and match the finish as close as possible. Photographs are required for all stages of construction.

Roofing total $____________

Review the “Bid Scope Materials List” for product lines and or their equivalents.

File details come from the government source that posted it. Updated .