Schedule - Scotia & Cliffton Park, NY - Signal & Surface.pdf
PDF 48 KB Posted
- Attached to
- Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX
- Solicitation number
- 2117372
- Issued by
- Saratoga County, Schenectady County, Cheektowaga CDP, New York
About this file
This schedule outlines timelines for multiple warning device upgrades and surface replacements project in Scotia & Cliffton Park, NY along the PAS_BERX rail line. The project encompasses six locations: Vley Road, SR 147 (Sacandaga Road), SR 911F (Freemans Bridge Road), Air National Guard Road, Ashdown Road, and Blue Barns Road. Key dates include: advertising on January 15, 2025, a pre-bid conference on January 22, 2025 at 1000 EST, bidder questions due January 29, 2025 at 1200 EST, proposals due February 12, 2025 at 1500 EST, and selection/award on February 26, 2025. The project timeline extends through October 23, 2025, with design plans due April 11, 2025, final acceptance by September 8, 2025, AIS plans due September 28, 2025, and final billings and documentation due October 23, 2025.
The schedule indicates a structured progression of activities spanning 281 days total from advertisement to final documentation. Each location is assigned specific PIN numbers and PAS/PSR reference numbers for tracking purposes. The design phase begins with NTP on March 12, 2025, allowing 30 days for design plan completion, followed by a DOT-contingent final acceptance period and subsequent documentation requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit 2 - Bid Form A & Scope of Work.xlsx | XLSX spreadsheet | |
| RFP - Scotia & Cliffton Park, NY - Signal & Surface - 20250115.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity Date Comment Duration from previous activity Running Duration
Advertise Date Wednesday, January 15, 2025 0 0
Pre-bid Conference Wednesday, January 22, 2025 1000 EST 7 7
Bidder Questions Due Wednesday, January 29, 2025 1200 EST 7 14
Proposal Due Wednesday, February 12, 2025 1500 EST 14 28
Selection/Award Wednesday, February 26, 2025 14 42
(Design) NTP Wednesday, March 12, 2025 On or before 14 56
Design Plans Due Friday, April 11, 2025 30 days after assigned 30 86
Final Acceptance Monday, September 8, 2025 Contingent on DOT schedule 150 236
AIS Plans Due Sunday, September 28, 2025 Within 20 Days of Installation 20 256
Final Billings & Documentation Thursday, October 23, 2025 Within 45 Days of Installation 25 281
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
Warning Device Upgrades and Surface Replacement at Vley Road – 052571M – PIN# 1933.53 - MP 7.00; PAS-0000083; PSR-0000023
Warning Device Upgrades and Surface Replacement at SR 147 (Sacandaga Road) - 052572U – PIN# 1933.52 - MP 7.57; PAS-0000085; PSR-0000025
Warning Device Upgrades at SR 911F (Freemans Bridge Road) - 052569L – PIN 1933.54 - MP 5.59;
Warning Device Installation and Surface Replacement at Air National Guard Road (CR 14) - 052567X – PIN# 1933.47 - MP 4.30; PAS-0000082; PSR-0000022
Warning Device Installation at Ashdown Road, MP 0.79 - 052563V; PIN # 1933.45; PAS-000008; PSR-0000028
Warning Device Installation and Surface Replacement at Blue Barns Road (CR 110), MP 1.80 - 052564; PIN # 1933.46; PAS-0000084; PSR-0000024
File details come from the government source that posted it. Updated .