RFP - Scotia & Cliffton Park, NY - Signal & Surface - 20250115.pdf
PDF 819 KB Posted
- Attached to
- Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX
- Solicitation number
- 2117372
- Issued by
- Saratoga County, Schenectady County, Cheektowaga CDP, New York
About this file
This is a Request for Proposal (RFP) issued by Genesee & Wyoming Inc.'s Berkshire & Eastern Railroad (BERX) in conjunction with the New York State Department of Transportation (NYSDOT) for multiple warning device upgrades and surface replacements at six railroad crossings in Scotia and Clifton Park, NY. The project includes warning device upgrades and surface replacements at Vley Road, SR 147 (Sacandaga Road), and SR 911F (Freemans Bridge Road), as well as warning device installations and surface replacements at Air National Guard Road (CR 14), Ashdown Road, and Blue Barns Road (CR 110). Proposals are due by 3:00 PM EST on February 12, 2025. A non-mandatory pre-bid conference is scheduled for January 22, 2025 at 10:00 AM EST. Questions are due by January 29, 2025, and vendor selection is expected by February 26, 2025. The project must be completed by September 8, 2025.
The project will be awarded based on best value considering proposal price, understanding and ability to meet scope of work, quality assurance/reliability of service, and experience and technical support. The contractor must comply with New York State DOT requirements, Buy America provisions, and various federal regulations. Performance and payment bonds are not required, and prevailing wages do not apply. The contractor must maintain specific insurance coverage including $2 million per occurrence in commercial general liability and $6 million aggregate, $1 million in automobile liability, and railroad protective liability insurance. Minority, women, and disadvantaged business participation is encouraged but not required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Schedule - Scotia & Cliffton Park, NY - Signal & Surface.pdf | ||
| Exhibit 2 - Bid Form A & Scope of Work.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Engineering National Region Request for Proposal For
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and
Surface Replacements on the PAS_BERX:
Warning Device Upgrades and Surface Replacement at Vley Road
052571M – PIN# 1933.53 - MP 7.00; PAS-0000083; PSR-0000023
Warning Device Upgrades and Surface Replacement at SR 147 (Sacandaga Road)
052572U – PIN# 1933.52 - MP 7.57; PAS-0000085; PSR-0000025
Warning Device Upgrades at SR 911F (Freemans Bridge Road)
052569L – PIN 1933.54 - MP 5.59;
Warning Device Installation and Surface Replacement at Air National Guard Road (CR 14)
052567X – PIN# 1933.47 - MP 4.30; PAS-0000082; PSR-0000022
Warning Device Installation at Ashdown Road
052563V; PIN # 1933.45 - MP 0.79; PAS-000008; PSR-0000028
Warning Device Installation and Surface Replacement at Blue Barns Road (CR 110)
052564C; PIN # 1933.46 - MP 1.80; PAS-0000084; PSR-0000024
January 15, 2025
Genesee & Wyoming
13901 Sutton Park Drive South
Suite 270
Jacksonville, FL 32224
Genesee & Wyoming Engineering National Region – Section 100 Table of Contents
Page | 1
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
052571M, 052572U, 052569L, 052567X, 052563V, & 052564C
SECTION 00100
Table of Contents
Division 0 – Bidding Requirements
Section 00200 Invitation to Bid
Section 00300 Bid Form
Section 00400 Sample Agreement
Section 00500 Schedule 1 – Additional Project Specific Requirements (Public Funding)
Section 00600 Additional Contract Documents
Exhibits
Exhibit 1 G&W Standards & Specifications
Division 1 – General Requirements
Section 110 General
Section 120 Execution
Section 124 Controls of Materials
Section 128 Temporary Construction
Section 130 Delay of Trains
Section 140 Submittals
Section 150 Inspection
Section 160 Legal Relations and Responsibility
Section 170 Safety
Section 180 Protection of the Environment
Section 185 Protection of Property
Section 190 Measurement and Payment
Section 195 Closeout
Section 198 General Conditions Submittal List
Section 300 Payment GWRR
Section 400 Construction Schedule
Division 2 – Signal Specifications
GWI Signal Plans & Forms
GWI Signal Standards
GWI Signal Typicals
GWI Engineering Safety Rules
GWI Hazardous Materials Policy
GWI Highway-Rail Grade Crossing Warning System Specifications
GWI Roadway Worker Protection & Maintenance Machines Policy
GWI S&C Standards Reference Manual
GWI Signal Specifications
Sharefile Link to G&W Signal Standards
Genesee & Wyoming Engineering National Region – Section 100 Table of Contents
Page | 2
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
Exhibit 1a Additional Specifications
Exhibit 2 Bid Form A, Scope of Work
Exhibit 2a Signal Surveys & Plans
Exhibit 3 Track Charts, Timetables, & Project Location Map
Exhibit 4 Project Documents
Genesee & Wyoming Engineering National Region – Section 200 Invitation to Bid
Page | 3
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
SECTION 00200
INVITATION TO BID
1 INTENT
You are invited to submit a proposal for the Signal Crossing project for Berkshire & Eastern Railroad (BERX), in conjunction with the New York State Department of Transportation (NYSDOT). The Railroad is soliciting bids from qualified railroad signal contractors interested in the title project. Quantities stated represent our best estimate at this time and are subject to adjustment. All design, materials, hardware, incidentals, supervision, labor, and equipment will be supplied by the Contractor. The project launch and kick off are subject to state and corporate match funding availability. All contractors must have State and Local business licenses to operate in the State of New York. Schedule 1 outlines all the funding requirements applicable to this project. This RFP has been publicly advertised to meet all State funding requirements.
This invitation to bid is for the BERX Signal & Surface Improvements. This RFP will be conducted under a bid method and the Railroad will evaluate proposals and award the Project. The Railroad reserves the right to terminate planned Projects or add additional Projects as funding and priority allow.
Interested Bidders shall submit their proposal in accordance with this Invitation to Bid electronically via email to bbiesterveld@benesch.com and tsovann@benesch.com by 3:00 PM EST, February 12, 2025.
2 PROJECT DESCRIPTION
2.1 The proposed work shall consist of furnishing all design, labor, equipment, hardware, incidentals, and supervision to affect the railroads DOT Crossing Upgrade construction project in accordance with the Contract Documents.
2.2 Signal-related programs shall be done in accordance with the AREMA Manual for Railway
Engineering, G&W Standard Specifications, and the Project Specifications.
2.3 All work of signal repairs shall meet the Project Specifications.
3 CONTRACT DOCUMENTS AVAILABLE
3.1 All contract documents are available electronically via sharefile:
File Share - Login (benesch.com) User ID: NYProjects Password: Signal
4 SCOPE OF WORK
4.1 The Scope of Work document contains the summary scope of work for the project as detailed in the Contract Documents.
See Exhibit 2 – Bid Form A, Scope of Work
DOT Crossing Upgrade
Page | 4
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
The project consists of providing all labor, design, equipment, material, hardware, incidentals, and machinery for the following signal construction and rehabilitation:
The project shall consist of the following work:
Automatic Highway Grade Crossing Warning System:
• Vendor to provide design for project
• Grade crossing warning system installations project. Contractor to supply material on all. Contractor to provide supervision, labor, and equipment.
• Crossing Location: Vley Rd.: https://maps.app.goo.gl/tfpeXGWrpo6RgScj7
• Crossing Location: Sacandaga Rd.: https://maps.app.goo.gl/n7TPAYQZQj5Br3x99
• Crossing Location: Freemans Bridge Rd.:
https://maps.app.goo.gl/cu1bs9mDW8gzkxaM9
• Crossing Location: Air National Guard Road (CR-14):
https://maps.app.goo.gl/BTvYe7hiFTtHpstU6
• Crossing Location: Ashdown Rd.: https://maps.app.goo.gl/FjZYnA73Lx45nNeT7
• Crossing Location: Blue Barns Rd.:
https://maps.app.goo.gl/wbDYJwvBWQUFnV2M9
• 240V / 100 Amp Power Service
• DTMF Controller
• Include new head bonds and web bonds on any and all joints within the project limits
The Contractor shall be responsible for complete installation, final testing and placement of the automatic protection into operational service.
The Signal Vendor will be responsible to verify all existing conditions of Circuitry, OH & UG Utilities etc. PRIOR to construction. No change orders will be accepted due to utility location conflicts.
Vendor will coordinate flagging with Railroad or its designated representative. All necessary flagging services are provided by the Railroad. Train schedule and window of work may be coordinated with the Transportation department on a limited basis.
It is required, as per the Design Build Requirements (Sect 21), that the vendor awarded the work will be responsible for Maintenance of Traffic.
PLEASE NOTE: It is now a requirement that all new meter service poles will require a Back- Guy wire. Please plan to have this installed in an appropriate location to ensure no leaning of meter service pole occurs in future.
Upon completion all AIS documents plus designs must be provided within 20 days. (Design Build Requirements, item 8).
The installation of this project must conform to the current FRA requirements regarding the necessary Retro-Reflective striping to be installed as per MUTCD CHAPTER 8B. SIGNS AND
MARKINGS.
The installation of this project must conform to the current FRA requirements regarding the current FRA Final Rule 49 CFR Part 234, RIN 2130-AC12 related to Emergency Notification Signs (ENS). The current Railroad Specification for this sign and mounting requirements are attached in the Standard Reference Drawings ES1024.0-1 & ES1024.0-2 for reference to this requirement.
If this project requires the installation of Insulated Joints and\or Thermite Welding as part of the Crossing Warning System Installation, it is the Signal Vendor’s responsibility to install these joints as part of the project scope. All cost related to the installation of these joints will
Page | 5
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
be the responsibility of the Signal Vendor and must be included in your Bid Quote.
The following standard reference drawings have been attached for your reference and use pertaining to this project. It will be the Design/Build Vendors Responsibility to comply with these standards:
ES1024.0-1
ES1024.0-2
The Contractor shall obtain and pay for all licenses and/or permits that may be necessary. They shall arrange for all local inspections that may be necessary and pay all fees in connection with such inspections.
Contractor shall perform every practical test to ensure that the system is functioning properly and that faulty components are replaced before attempting to place the system in service. If having been placed in service an early failure takes place, he shall maintain adequate inventory to ensure prompt correction.
Any requirements by the agency to provide a PE stamp/certification are the responsibility of the awarded contractor.
4.2 The quantities and units given are selected to convey the overall magnitude of the major tasks of the project but the individual line items shall be paid on a lump sum basis
(signal projects).
4.3 The quantities shown are estimated quantities only intended to provide a basis for progress billings.
4.4 The Contractor may submit bids for any line item for which they can provide a quality service at a competitive rate.
4.5 Daily working hours will be provided at maximum time possible consistent with required train operations and hours of service requirements, with a target of 8 hours occupancy per work day. However 8 hours per day is not guaranteed and may not be continuous hours.
Awarded contractor(s) to provide construction schedule at least 30 days in advance.
4.6 Prevailing wages are not a requirement for the programs included in this Request for Proposal.
4.7 Performance and payment bonds are not a requirement for the programs included in this
Request for Proposal.
4.8 Vendor will coordinate flagging with Railroad or its designated representative. All necessary flagging services are provided by the Railroad. Train schedule and window of work may be coordinated with the Transportation department on a limited basis.
4.9 A minimum of 21 day notice is required in writing to the Railroad and Benesch prior to the start of construction.
4.10 It is the goal of the Railroad to work efficiently and productively until the project is complete.
All signal-related work must be completed by September 8, 2025; see Contract Section 3.1.
4.11 Upon removal, existing crossing material listed in scope above must be kept in working order and provided back to G&W. The Contractor will be solely responsible for the disposal of all unused or removed equipment, waste, debris, and applicable material, including but not limited to Ties, Track, OTM, Ballast, Sub-Ballast, material spoils, Warning Devices and Equipment, foundations, etc. All unused or removed equipment and material shall be properly disposed of in a suitable and authorized disposal facility. All material to de disposed of that is considered to be hazardous materials per Federal, State, or Local laws, must be disposed of in a suitable facility with the manifest documentation completed within 45 days of the
Page | 6
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
installation, and records furnished to G&W contacts as stipulated in §3.3 of General Specifications 180 – Protection of the Environment. Any failure on the part of the Contractor to complete and submit this information will result in a penalty of $1000 per day, until the disposal and all records are accurately completed in full. The Contractor will additionally be responsible for any penalties, fines, or legal action taken against Contractor or Railroad for improper records assessed by any Federal, State, Local, Public, or Private entity as a result of the disposal of all unused or removed equipment and material.
4.12 Vendors are required to submit pictures of completed crossing work no more than 5 days after construction completion. At minimum, clear images of all four quadrants of subject crossing must be shown.
5 PRE-BID CONFERENCE
5.1 There will be a non-mandatory pre-bid conference meeting at 10:00 AM EST, Wednesday, January 22, 2025 Via tele-conference 1-872-242-8836; Meeting ID: 122 378 65#
5.2 The conference call will continue as necessary to address Bidder questions.
5.3 Not used.
5.4 The pre-bid conference is intended to provide Bidder with an open forum in which to discuss the project and further his understanding of the Work. The pre-bid conference is not intended to supplement or replace the information contained in the Contract
5.5 Railroad shall publish the minutes of the pre-bid conference call.
5.6 Any discussion items the Railroad deems to be an alteration of the Contract Documents shall be issued as an addendum to the Contract Documents.
5.7 All questions concerning the work or technical aspects of this bid shall be addressed via email to Benesch bbiesterveld@benesch.com and tsovann@benesch.com no later than 12:00 PM
EST January 29, 2025. Questions will be answered in the form of an addendum distributed to all bidders. Oral explanations or interpretations given before the award of the contract will not be binding. Any questions received past the deadline will not be considered.
6 SITE ACCESS
6.1 Railroad’s operating right-of-way is off limits to all unescorted personnel.
6.2 Prior to entering the site for any purposes, the Bidder must arrange access through the
Railroad.
6.3 Such access shall be granted at the convenience of the Railroad and shall be arranged so as to afford equal opportunity for all bidders.
6.4 All personnel entering Railroad property shall comply with Railroad’s safety requirements as shown in the General Conditions.
7 PROPOSAL
7.1 Bidders are instructed to submit proposals for the Work on the attached Proposal Form.
7.2 Daily and hourly labor and equipment pricing is intended to provide a basis for issuing expedient change orders for time and material work and calculating standby time.
7.3 Project schedule information is intended to gage the responsiveness of Contractor and set milestones for the Work.
7.4 Project management team experience information is intended to gage the ability of the project management to execute the Work.
Page | 7
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
7.5 Alternative proposals for the Work may be considered by Railroad provided that the alternative clearly states the benefit of the alternative to the Railroad.
8 BIDDER’S REPORTING/DISCLOSURE AGREEMENT
8.1 Funding for this project may be utilizing federal, state or railroad funding, and is subject to the reporting and operational requirements of the funding agency. Each bidding contractor, including all prime and subcontractors are subject to audit by federal, state, or other funding agency. By submitting a bid for this project, you accept all responsibility to comply with the terms of reporting and audit requirements of the funding agency. Any failure to comply with the reporting and audit requirements may result in cancellation, termination, or suspension of the bidder contract(s) and/or payment(s).
9 DUE DILIGENCE
9.1 Prior to submitting his Bid, Bidder shall carefully examine the Contract Documents to determine the nature of the Work and shall report to Railroad any discrepancies found.
9.2 Bidder shall prepare his Bid considering the conditions reasonably anticipated during the Work such as expected weather, railroad traffic delays and site conditions discernible from the Contract Documents and site visits.
9.3 No payment increase consideration will be given to the Bidder for conditions which are determinable by examining the Contract Documents. Bidders are responsible for consulting the reference standards.
9.4 Records of subsurface investigation made by Railroad may be viewed by bidder upon request. Access to these records is for the convenience of bidder. Railroad is not responsible for the sufficiency of the records.
9.5 Any questions relative to the Contract Documents must be settled by the Bidder before submitting his bid. Request for interpretation shall be made in writing to Railroad who shall issue such interpretations he deems necessary in the form of addenda to the to the Invitation to Bid.
9.6 By preparing his bid and executing the Contract, Contractor represents that he has familiarized himself with the local conditions under which the Work is to be performed, and correlated his observations with the requirements of the Contract Documents.
10 WITHDRAWAL AND MODIFICATION OF BIDS
10.1 Bids may be withdrawn or modified upon written or facsimile request received from Bidder prior to the time set for opening.
11 AWARD
11.1 Railroad may waive any formalities, technicalities, or irregularities contained in any or all of the proposals. Railroad may further reject any part of any bid which in the opinion of Railroad will be insufficient to deliver the Work.
11.2 Railroad may accept any bid it deems to be in the best interest of Railroad and shall award the entire scope of Work to Bidder of Railroad’s choice.
11.3 The project will be awarded at GWRR's sole discretion to the contractor whose proposal offers the best value based on the following (but not limited to) criteria that will determine the total cost of the purchase service:
• Proposal Price
• Understanding and Ability to meet Scope of Work
Page | 8
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
• Quality Assurance/Reliability of Service
• Experience and Technical Support
12 EXECUTION OF CONTRACT
12.1 The successful Bidder shall execute the Contract within ten (10) calendar days after the date of the Notice of Award. Railroad will consider the Contract fully executed when the required Contract and Certificates of Insurance are executed and submitted to the Railroad.
12.2 If the successful Bidder fails to execute said documents within ten (10) days of the Notice of Award, the Railroad may, at its sole discretion, determine that the Bidder has abandoned the Contract. At that time the bid shall be declared null and void and the Railroad may award the contract to another Bidder.
12.3 Contractor must be willing to sign and abide by attached Construction Agreement, Contractor Code of Ethics, Safety Rules.
13 SCHEDULE OF EVENTS
Activity Date Comment
Advertise Date Wednesday, January 15, 2025
Pre-bid Conference Wednesday, January 22, 2025 1000 EST
Bidder Questions Due Wednesday, January 29, 2025 1200 EST
Proposal Due Wednesday, February 12, 2025 1500 EST
Selection/Award Wednesday, February 26, 2025
(Design) NTP Wednesday, March 12, 2025 On or before
Design Plans Due Friday, April 11, 2025 30 days after assigned
Final Acceptance Monday, September 8, 2025 Contingent on DOT schedule
AIS Plans Due Sunday, September 28, 2025 Within 20 Days of Installation
Final Billings & Documentation Thursday, October 23, 2025 Within 45 Days of Installation
YOUR PROPOSAL IS DUE NO LATER THAN 3:00 PM EST February 12, 2025. Any bids received after the deadline will not be considered. Please submit your bid written proposal based on the attached General Specifications and using Bid Forms in Section 00300 to the following:
Via email: tsovann@benesch.com and bbiesterveld@benesch.com
Sincerely, Benjamin P. Biesterveld
Ben Biesterveld Project Manager – Rail Division Alfred Benesch & Co.
(920) 841-0249
Genesee & Wyoming Engineering National Region – Section 300 Bid Form
Page | 9
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
Section 00300
Bid Form
TO: Ms. Kristine Storm DATE:
VP Purchasing Genesee and Wyoming, Inc.
Email: Kristine.Storm@GWRR.com
1. PROPOSAL. The undersigned, as Bidder, declares that he has carefully examined the nature of the proposed Work and the proposed Contract Documents and has read any and all addenda issued prior to this date. Bidder proposes and agrees, should this Proposal be accepted, to furnish all necessary supervision, labor, construction equipment, material, tools, supplies, transportation and other means of construction and to do all Work as shown, detailed and specified in the Contract Documents at the times and locations determined by Railroad and that he will abide by all provisions of the Contract Documents and that, in accordance with the lump sum price established below, contractor will bill Railroad for all work performed for and accepted by Railroad.
2. TERM OF AGREEMENT. In submitting this Proposal, the undersigned agrees that the unit prices proposed herein shall remain in effect for a period of sixty days and thereafter for the duration of the contract.
3. ACCEPTANCE OF PROPOSAL. The undersigned has checked all of the figures contained in this Proposal and understands that Railroad will not be responsible for any errors or omissions on the part of the undersigned in preparing this Proposal.
In submitting this Proposal, it is understood that the right is reserved by Railroad to waive any formalities, technicalities, or irregularities in, or reject any or all Proposals, or to accept any Proposal, should it be deemed in Railroad's best interest. A Proposal may be considered irregular and may be rejected if it fails to include the fully executed Proposal Documents or if Bidder fails to furnish required data. It is agreed that this Proposal may not be withdrawn for a period of sixty (60) days after the opening thereof.
4. AFFIRMATION OF NON-COLLUSION. The undersigned affirms that in making such Proposal, neither he nor any company that he may represent, nor anyone on behalf of him or his company, directly or indirectly, has entered into any combination, collusion, undertaking or agreement with any other Bidder or Bidders to maintain the prices of said Work, or any compact to prevent any other Bidder or Bidders from bidding on said Contract or Work and further affirms that such Proposal is made without regard or reference to any other Bidder or Proposal and without any agreement or understanding or combination, either directly or indirectly, with any other person or persons with reference to such bidding in any way or manner whatsoever.
5. CONTRACT EXECUTION. The undersigned, when notified of the acceptance of this Proposal, does hereby agree to enter into a Contract and return such signed (executed) Contract to Railroad along with the required Certificates of Insurance within ten (10) calendar days after the date of Notice of Award and Acceptance.
Page | 10
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
6. ADDENDA ACKNOWLEDGMENT. The undersigned acknowledges receipt of the following:
Addendum Number Date Addendum Number Date
7. COMPLIANCE WITH LAWS AND REGULATIONS. It is agreed that the undersigned has complied or will comply with all requirements of local, State and Federal Laws and Regulations, and that no legal requirement has been or will be violated in making or accepting this Proposal, in awarding the Contract and/or in the production of the work.
8. SUBCONTRACTOR LIST. The following is a list of all subcontractors to be employed during the performance of the contract. The undersigned agrees that any changes to this list must have the express written consent of Railroad, such consent not to be unreasonably withheld.
Name Address Function
9. UNIT PRICES. All work performed by Bidder as Contractor shall be progress billed to Railroad in accordance with the unit prices given in the supplied bid form and only up to the bid amount.
Contractor agrees to complete entire scope of work for the amount of $ which is the same as the Bid Form A.
10. ALTERNATIVE PROPOSAL. Attached to this Proposal are ________ sheets detailing Bidder(s) proposed alternative to the scope of work detailed above.
11. LABOR AND EQUIPMENT RATES. Attached to this Proposal are ________ sheets detailing the equipment consist and the fully loaded hourly and daily labor and equipment rental equipment rates in effect for this proposal. It is understood that these rates will be used to calculate any time and material work authorized by Railroad as well as to calculate any Standby time granted by the Railroad.
12. TIME OF COMPLETION. All work performed by Bidder as Contractor shall be completed no later than September 8, 2025. Attached to this proposal are _______________ sheets detailing the critical path for completing the project within this time. It is understood that changes to this critical path are subject to Railroad(s) approval.
Page | 11
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
13. KEY PROJECT STAFF. Attached to this Proposal are resumes detailing the experience of Bidders proposed key project management staff. It is understood that changes to the proposed project management staff are subject to Railroad(s) approval.
14. SIGNIFICANT RAILROAD PROJECTS. Attached to this Proposal are at least 3 detailed project descriptions of projects in which similar track-related projects were performed. Provide the following information: Railroad Name, Railroad Contact, Detailed Project Description, Bidder’s Scope of Work on the Project and Bidders Project Management.
15. SCHEDULE. The undersigned bidder agrees to complete the project in accordance with the following schedule:
Activity Date Comment
Advertise Date Wednesday, January 15, 2025
Pre-bid Conference Wednesday, January 22, 2025 1000 EST
Bidder Questions Due Wednesday, January 29, 2025 1200 EST
Proposal Due Wednesday, February 12, 2025 1500 EST
Selection/Award Wednesday, February 26, 2025
(Design) NTP Wednesday, March 12, 2025 On or before
Design Plans Due Friday, April 11, 2025 30 days after assigned
Final Acceptance Monday, September 8, 2025 Contingent on DOT schedule
AIS Plans Due Sunday, September 28, 2025 Within 20 Days of Installation
Final Billings & Documentation Thursday, October 23, 2025 Within 45 Days of Installation
Page | 12
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
Bid Form A’s
Schedule of Unit Prices
BERX Signals
Bid Form A
File Share - Login (benesch.com)
Access the Bid Form at the link Above, download the worksheet, input prices, “Save As” an Excel file, and return with bid package.
Worksheet will automatically calculate totals.
These categories should be stated on your cover letter and be all inclusive in the total cost quoted. Cost for Freight, Shipping, Tax, or any other ancillary cost must be all included in your quoted price. A complete Bill of Material list must also be included with your bid quote to accompany the cover letter. This information will be considered confidential for Genesee & Wyoming Inc. use for bid evaluation and vendor selection. Genesee & Wyoming Inc. will not provide bid information to other vendors. Please provide the Quotes at your earliest convenience.
NAME OF BIDDER (COMPANY NAME):
PRINTED NAME OF AUTHORIZED PERSON:
SIGNATURE OF AUTHORIZED PERSON:
TITLE: BUSINESS ADDRESS:
DATE:
Genesee & Wyoming Engineering National Region – Section 400 Sample Agreement Page | 13
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
Section 00400
GENERAL DESIGN AND BUILD AGREEMENT
(GRANT PROJECT)
TABLE OF CONTENTS
1. PROJECT DEFINED
2. EQUIPMENT/RAILROAD OPERATIONS
3. PERIOD OF PERFORMANCE AND UNIT PRICES
4. TERMINATION
5. PERFORMANCE AND PAYMENT BOND
6. CONTRACTUAL STATUS/RELATIONSHIP OF PARTIES
7. CHANGES: MODIFICATIONS
8. CLAIMS
9. TRANSPORTATION
10. COMPLIANCE WITH LAWS/PERMITS
11. TRANSFERS/ASSIGNS
12. INSPECTION
13. WARRANTY
14. INSURANCE
15. INDEMNITY
16. REMOVAL OF RUBBISH
17. WAIVER
18. APPLICABLE LAW
19. SEVERABILITY
20. NON-EXCLUSIVITY
21. HEADINGS
22. SURVIVAL
23. ENTIRE AGREEMENT
24. UNDERSTANDING OF REQUIREMENTS
25. THIRD-PARTY BENEFICIARIES
SCHEDULE 1 - ADDITIONAL PROJECT SPECIFIC REQUIREMENTS (PUBLIC FUNDING)
APPENDIX A - PERIOD OF PERFORMANCE, SCOPE OF WORK, AND SPECIFICATIONS
APPENDIX B - UNIT PRICING
APPENDIX C - CONTRACTOR RIGHT OF ENTRY AGREEMENT, INCLUDES EXHIBIT A
ATTACHMENT 1 - GWI CODE OF ETHICS AND CONDUCT
ATTACHMENT 2 - ROADWAY WORKER PROTECTION TRAINING POLICY
ATTACHMENT 3 - 49 CFR PART 219 - FRA DRUG AND ALCOHOL REGULATION
& CFR PART 243 – TRAINING, QUALIFICATIONS, AND OVERSIGHT
ATTACHMENT 4 - CONTRACTOR SAFETY RULES
Page | 14
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
GENERAL DESIGN AND BUILD AGREEMENT
This General Design and Build Agreement ("Agreement") dated as of DATE, is by and between Berkshire
& Eastern Railroad (BERX), a division of the Pittsburg & Shawmut Railroad, having its principal offices at 200 Meridian Centre Boulevard, Suite 300, Rochester, NY 14618 ("Railroad") and CONTRACTOR, having its principal offices at ADDRESS ("Contractor").
In consideration of the mutual covenants and agreements set forth herein, the parties hereto agree as follows:
1. PROJECT DEFINED
1.01 Contractor will perform work more particularly described in Appendix A attached hereto and made a part hereof ("Project"), it being understood that the Project is fully described and set forth in the plans and specifications prepared for this Agreement. Should any work or material not directly or indirectly denoted in the plans and specifications be necessary for the proper carrying out of the obvious intentions thereof, Contractor shall furnish any such material and do any such work as fully as if it were particularly delineated or described in the plans and specifications. The plans and specifications shall control all discrepancies between plans and specifications and the Agreement.
1.02 Nothing in this Contract shall be viewed or interpreted as requiring Railroad to purchase services of the type contemplated herein or otherwise exclusively from Contractor or as requiring Contractor to provide services of the type contemplated herein or otherwise exclusively to Railroad. Both Railroad and Contractor are free to purchase and provide such services to other parties. Contractor understands that Railroad does not guarantee the volume of Services that Railroad may purchase from Contractor.
1.03 Contractor shall perform work related to the Project in a professional manner, in accordance with American Railway Engineering and Maintenance-of-Way Association (AREMA) Standards and to the sole satisfaction and acceptance of Railroad and Railroad Standard Construction Specifications in Appendix A.
1.04 All work shall be performed in a safe and professional manner and in accordance with material safety data sheets (MSDS) and all Federal, state and local laws and regulations, including those established by administrative agencies, so as not to create a safety hazard to Railroad, Contractor, their agents, employees or subcontractors, or to property, or to third parties and their property or interfere with the normal use and operation of Railroad property and business.
1.05 Whenever the term "Engineer" is used in this Agreement it means the Chief
Engineer of the Railroad or his designee.
2. EQUIPMENT/RAILROAD OPERATIONS
2.01 Contractor at its sole cost and expense shall furnish all materials, labor, tools, equipment and machinery necessary and appropriate to complete the Project in a substantial and workmanlike manner to the sole satisfaction and acceptance of the Railroad.
2.02 The Contractor shall provide all equipment necessary to perform the work properly and complete the Project by the required completion date. Equipment shall be in good operating condition and shall conform to the applicable standards prescribed by the Association of American Railroads and the Federal Railroad Administration ("FRA") for such type of equipment (if any). Contractor must comply with all rules and regulations as set forth by the FRA including the sections concerning Roadway Maintenance Machines. Contractor at its sole cost and expense shall be responsible for the maintenance and repair of any and all equipment used by Contractor during the Project.
2.03 Contractor shall furnish, bear and pay, and shall save Railroad free of, any and all labor and expense of, and incident to, compliance with the aforementioned rules, regulations and requirements.
Page | 15
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
2.04 Whenever the work included in this Project is by the side of or contiguous to railroad tracks used and operated by Railroad, Contractor shall use the utmost vigilance in every stage of the execution of the work related to the Project in order to protect effectively against all accidents and/or damages on said railroad by reason of the Project. Contractor shall at all times during the progress of the Project so manage and execute the same in a manner that minimizes the impact on and possible interference with the operation, management and/or maintenance of said railroad or with the business or traffic of the same.
2.05 The Project shall be managed so as not to interfere with the progress of any contiguous work. The Contractor is responsible for scheduling the activities of its forces, its subcontractors and vendors as well as other contractors that may be working on or near Railroad’s property or in Railroad’s facilities. The Engineer may direct changes in the management of the Project to ensure compliance with this Section 2.
2.06 CONTRACTOR SHALL FAMILIARIZE ITSELF WITH APPLICABLE
RAILROAD SAFETY RULES (SEE ATTACHMENT 4) (THE “SAFETY RULES”), WHICH ARE
BY REFERENCE MADE A PART OF THIS AGREEMENT. CONTRACTOR SHALL COMPLY
WITH THE SAFETY RULES, TOGETHER WITH ALL ORDINANCES OF ANY FEDERAL,
STATE OR LOCAL GOVERNMENTAL AUTHORITY AND SHALL REQUIRE ITS
EMPLOYEES AND SUBCONTRACTORS TO COMPLY THEREWITH, AND SHALL
RELEASE, PROTECT, DEFEND, INDEMNIFY AND SAVE AND HOLD HARMLESS THE
RAILROAD, ITS PARENT, AFFILIATES AND SUBSIDIARIES, AND THE RESPECTIVE
SHAREHOLDERS, DIRECTORS, OFFICERS AND EMPLOYEES OF EACH (HEREINAFTER,
COLLECTIVELY THE “RAILROAD INDEMNITEES”) FROM AND AGAINST ANY AND ALL
LOSS, DAMAGE, COST AND EXPENSE AND ALL CLAIMS, ACTIONS AND DEMANDS
ARISING OUT OF VIOLATION OF ANY OF SAID SAFETY RULES AND REQUIREMENTS.
2.07 Prior to entry onto Railroad’s property to commence the Project, the parties shall enter into a Contractor Right of Entry Agreement, a form of which is attached hereto as Appendix C and made a part hereof. Railroad shall furnish flagging service which, in its sole judgment, it deems necessary to protect people and property on the rails while work on the Project proceeds. Contractor shall proceed with extreme caution while working on or near Railroad’s property or Railroad’s facilities and Contractor's employees shall comply with the directions of Railroad personnel while on or near Railroad’s property or in Railroad’s facilities. The foregoing is not intended and shall not be deemed to limit or modify Contractor's status as an independent contractor.
2.08 Whenever the progress of the work related to the Project in any manner affects the use or operation of lines of Railroad or other entities affiliated with Railroad, Contractor shall, at its own cost and expense, comply with all the conditions that may be imposed by Railroad.
3. PERIOD OF PERFORMANCE AND UNIT PRICES
3.01 Work related to the Project shall be commenced on the first date specified on Appendix A and shall be completed to Railroad's specification on or before the second date specified on Appendix A ("Completion Date") or such later date as Railroad may have authorized in writing pursuant to the terms herein. The parties hereto agree that time is of the essence. Contractor shall submit to Railroad a detailed schedule for performance of the Project in a form acceptable to Railroad, which schedule shall comply with all scheduling requirements of this Agreement. Railroad, at its sole discretion, may direct Contractor to make modifications and revisions in said schedules to ensure compliance with this Agreement and non-interference with other work. The contractor agrees to commence the work under this Agreement upon the date of “notice to proceed” by the VP Engineer or Railroad designee. Contractor is required to submit a work schedule that must be approved by the VP Engineer or Railroad designee prior to work start-
up. Contractor shall have project completed no later than September 8, 2025. Should the contractor fail to meet this time requirement, the contractor shall pay to Railroad a breach of contract penalty of One Thousand ($1,000) dollars per day (seven days per week) and the Contractor shall reimburse Railroad all costs incurred as a result of that delay. These costs may include, but are not limited to: wages and expenses
Page | 16
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
for Railroad inspectors, delays in train operations, interest and penalties to Railroad vendors and other contractors, administrative and legal costs.
3.02 In the event Railroad deems the Contractor is not proceeding according to the agreed to Project schedule or upon becoming aware of the occurrence of any breach of contract or any event that, with notice or lapse of time or both, would constitute a breach of contract (“Breach of Contract”), Railroad may order that the Project be prosecuted in such order, at such points and with such force as shall be adequate to insure its completion by the Completion Date. If required, Contractor, at its own expense, shall work nights, weekends and/or holidays to ensure that the Project is completed on time and no extra compensation shall be demanded by Contractor for such work.
3.03 If at any time Contractor shall refuse or neglect to execute the Project with a force sufficient, in the opinion of the Engineer, to insure its completion within the time specified in the Agreement, or to furnish sufficient materials as needed for that purpose, a Breach of Contract shall exist and Railroad may direct the employment of such additional laborers and foremen, and the purchase of sufficient materials, as it may deem necessary to perform the Project, regardless of the cost of such wages and such prices, and Contractor shall pay all persons so employed for their services and for materials furnished. Any such amount which shall be paid by Railroad may be claimed by Railroad required by this Agreement, without prejudice, however, to any remedy which Railroad may have or may be entitled to have against Contractor for Breach of Contract. The foregoing is not intended and shall not be deemed to limit or modify Contractor's status as an independent contractor.
3.04 Contractor agrees to perform the work as indicated in this Agreement for the unit prices specified in Appendix B attached hereto.
4. TERMINATION
4.01 This Agreement may be terminated by either CONTRACTOR or the Railroad with ten (10) days’ written notice of termination in the event of either CONTRACTOR’s or the RAILROAD’s bankruptcy, insolvency or assignment of this Agreement for the benefit of creditors or with thirty (30) days’ written notice in the event of RAILROAD or CONTRACTOR’s default of the terms of this Agreement or at any time and for any reason by the RAILROAD with a sixty (60) days’ written notice. Projects in process will be completed to the satisfaction of the RAILROAD before final payment and provisions of Sections 11 survive termination.
4.02 In the event that the CONTRACTOR insurance contained in Section 14 hereof lapses or is cancelled, Railroad may terminate this Agreement effective the next business day upon notice to the CONTRACTOR.
4.03 Unless otherwise directed by Railroad, upon receipt of any notice of termination from Railroad, Contractor shall stop the terminated work, direct its subcontractors to stop the terminated work, cancel all existing orders for supplies relating to the terminated work, and otherwise take reasonable actions necessary to mitigate costs.
4.04 Within thirty (30) days after termination, Contractor may submit to Railroad its actual costs incurred to the effective date of termination. IN NO EVENT SHALL RAILROAD
INDEMNITEES BE LIABLE TO CONTRACTOR FOR ANY COSTS THAT EXCEED THE
UNPAID BALANCE OF THE AGREEMENT, OR FOR CONSEQUENTIAL, SPECIAL,
INCIDENTAL, PUNITIVE OR INDIRECT DAMAGES, INCLUDING LOST OR
ANTICIPATORY PROFITS OR UNABSORBED OVERHEAD, EVEN IF RAILROAD HAS BEEN
ADVISED OF THE POSSIBILITY OF SUCH DAMAGES.
4.05 Neither termination nor revocation of this Agreement shall affect any claims and liabilities which have arisen or accrued hereunder, and which, at the time of termination or revocation, have not been satisfied; neither party, however, waiving any third party defenses or actions.
5. PERFORMANCE AND PAYMENT BOND
Page | 17
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
5.01 Performance and payment bonds are not required for this Project.
6. CONTRACTUAL STATUS/RELATIONSHIP OF PARTIES
6.01 In performing services under this Agreement, Contractor shall operate as and have the status of an independent contractor. Contractor shall employ, pay from its own funds, and discharge all persons engaged in the performance of the Project and such persons shall be under Contractor's supervision, direction and control. Contractor shall be subject to the general oversight and guidance of the Engineer or whomever he may appoint in order to ensure safety and compliance with this Agreement. Under no circumstances shall this Agreement be interpreted as creating an employer/employee relationship between Contractor and Railroad. Contractor shall not be treated as an employee of Railroad for tax or any other purposes and Contractor shall be responsible for the payment of its own estimated and self-employment tax, if any, for Federal Income Tax purposes. Contractor shall also be responsible for all tax withholdings of its employees.
6.02 CONTRACTOR HEREBY ACCEPTS FULL AND EXCLUSIVE
LIABILITY FOR THE PAYMENT OF ANY AND ALL CONTRIBUTIONS OR TAXES FOR
UNEMPLOYMENT INSURANCE, MEDICAL AND OLD AGE RETIREMENT BENEFITS,
PENSIONS OR ANNUITIES NOW OR HEREINAFTER IMPOSED UNDER ANY STATE OR
FEDERAL LAWS WHICH ARE MEASURED BY THE WAGES, SALARIES OR OTHER
REMUNERATION PAID TO PERSONS EMPLOYED BY IT ON THE PROJECT.
CONTRACTOR SHALL ALSO INDEMNIFY AND SAVE HARMLESS RAILROAD
INDEMNITEES FROM ANY SUCH CONTRIBUTIONS OR TAXES OR LIABILITY THEREFOR
AND FURTHER SHALL OBEY ALL LAWFUL RULES AND REGULATIONS AND MEET ALL
LAWFUL REQUIREMENTS WHICH NOW OR HEREAFTER MAY BE ISSUED OR
PROMULGATED UNDER SAID RESPECTIVE LAWS BY DULY AUTHORIZED LOCAL,
STATE OR FEDERAL OFFICIALS.
6.03 Contractor shall at all times be represented on the Project by a competent superintendent who shall be satisfactory to the Engineer.
6.04 Contractor shall assign personnel with demonstrated competence and experience in the type of work specified in this Agreement. The credentials of such personnel shall be submitted to railroad for review should Railroad so request. The foregoing is not intended, and shall not be deemed, to limit or modify Contractor's status as an independent contractor, as provided herein.
6.05 This Agreement is placed subject to all the provisions of the Clayton Anti-Trust Act, and if Railroad is advised by its counsel that this Agreement violates or is contrary to the provisions of Section 10 of said Act of Congress, then Railroad shall inform Contractor and thereupon this Agreement shall be terminated.
7. CHANGES: MODIFICATIONS
7.01 All modifications of this Agreement must be approved by authorized representatives of Railroad's Engineer and shall be by written agreement of the parties signed by their duly authorized representatives.
8. CLAIMS
8.01 If at any time during the period of performance of this Agreement, Contractor shall deem itself to have become entitled to make any claim or demand against Railroad other than, or additional to, the compensation expressly stipulated in this Agreement, Contractor shall give notice in writing to Railroad, specifying such claim or demand, the ground thereof, and the amount thereof.
9. TRANSPORTATION
9.01 Contractor shall provide, pay for, and be liable for all transportation for men, equipment, tools and materials.
Page | 18
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
10. COMPLIANCE WITH LAWS/PERMITS
10.01 Whenever doing any work embraced within the Project it may be necessary to occupy temporarily, use or obstruct any street, highway, or public place or to do anything whatever in connection with public property, or whenever it shall be necessary in order to comply with building laws or orders of courts or governmental agencies, Contractor shall, at its own cost and expense, procure all necessary approvals, licenses and permits therefore, and in performing the Project Contractor shall comply with all applicable Federal, state and local laws, regulations, ordinances, and agency or court orders, including, without limitation, laws and regulations: (i) pertaining to building and construction; and (ii) pertaining to environmental protection, air and water pollution, and disposal of debris and refuge; and (iii) prohibiting discrimination on grounds of race, color, national origin or sex. Contractor shall pay for all charges of any kind related to the performance of the Project.
10.02 CONTRACTOR SHALL BE RESPONSIBLE FOR AND SHALL
PROTECT, INDEMNIFY, DEFEND AND HOLD THE RAILROAD INDEMNITEES HARMLESS
FROM ANY AND ALL COSTS AND EXPENSES, INCLUDING, WITHOUT LIMITATION,
JUDGMENTS, FINES, PENALTIES, COSTS AND LOSS OF EVERY KIND WHATSOEVER,
WHICH MAY ARISE OR RESULT FROM, OR BY REASON OF THE VIOLATION OF ANY
APPLICABLE CITY, BOROUGH, VILLAGE OR OTHER LOCAL GOVERNMENTAL
ORDINANCE, OR OF A LAW OF ANY STATE, OR THE DISTRICT OF COLUMBIA, OR OF
THE UNITED STATES, OR OF ANY ORDER OF ANY AGENCY OR COURT, DURING
CONTRACTOR'S PERFORMANCE HEREUNDER.
10.03 Contractor warrants that its performance of this Agreement, as of the date of its execution, is not prohibited by or in violation of any law.
11. TRANSFERS/ASSIGNS
11.01 This Agreement shall inure to the benefit of and be binding upon the successors and assigns of the parties hereto; provided, however, that Contractor shall not sell, subcontract, assign, delegate or otherwise transfer this Agreement or any of its rights or obligations hereunder without the prior written consent of Railroad.
11.02 No approved assignment, letting, transfer or subcontract, whether for labor or material or both, shall under any circumstances relieve Contractor of its obligations or liabilities under this Agreement or have any bearing on the granting or refusing of any extension of the Completion Date, should the subcontractor fail to perform the work undertaken by it. Contractor shall give personal attention and superintendence to the Project.
12. INSPECTION
12.01 All materials of every description used under this Agreement and all workmanship pursuant hereto shall be of the grade specified, and where quality is not specified shall be of the best for the purpose that can be obtained. Material and work shall at all times be open to the inspection, acceptance, or rejection by the Engineer and of such person or persons as they may designate to represent them, as hereinbefore provided. No omission or failure on the part of the Engineer to disapprove or reject any work of the Project at the time of a monthly or other estimate, or during the inspection of the Project shall be construed to be an acceptance of any defective work or part of the Project. Contractor shall be required to correct any imperfect work whenever discovered. If any work be condemned by the Engineer as defective or improperly done, such defective or improper work shall be taken down and rebuilt, or the defects otherwise remedied by Contractor, at its sole expense, as the Engineer in charge of the Project may direct;
and in default thereof the same may be done by Railroad at Contractor's expense. The provisions of this section shall apply to work done by subcontractors as well as to work done by direct employees of Contractor.
13. WARRANTY
13.01 Contractor warrants that the Project shall be performed in a safe and effective
Page | 19
Scotia & Cliffton Park, NY - Multiple Warning Device Upgrades and Surface Replacements on the PAS_BERX:
manner and shall be free from latent and patent defects in quality and workmanship and shall be in full conformity with the plans and specifications set forth in Appendix A. Contractor also warrants that the Project as complete shall be fit for Railroad's purpose as indicted herein and in documents attached hereto or made a part hereof by reference or if otherwise known to Contractor.
13.02 Contractor, without cost to Railroad, shall remedy any defects that are due to workmanship or to Contractor's failure to fulfill any of its obligations under this Agreement which appears within a period of one (1) year from the date when the Project is fully accepted and certified complete. This obligation is without prejudice to any other rights or remedies afforded by law to Railroad in the event of Breach of Contract by Contractor.
13.03 CONTRACTOR SHALL BE RESPONSIBLE FOR AND SHALL
PROTECT, INDEMNIFY, DEFEND AND HOLD THE RAILROAD INDEMNITEES, THEIR
CUSTOMERS, AND ANY THIRD PARTY HARMLESS FROM INJURY, DEATH, LOSS,
DAMAGE OR EXPENSE WHATSOEVER, AS SET FORTH IN SECTION 15 HEREOF,
HOWSOEVER ARISING, WHICH MAY BE SUFFERED AS A RESULT OF OR IN
CONNECTION WITH A BREACH OF ANY OF THE FOREGOING WARRANTIES, OR AS A
RESULT OF ANY ACCIDENTS OR…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .