Schedule_of_Values_-_MRF_Stormwater_Treatment_System.pdf
PDF 17 KB Posted
- Attached to
- MRF Stormwater Treatment System
- Solicitation number
- RFP No. PW-0175
- Issued by
- Santa Cruz County, San Francisco City, California
About this file
This document is a Schedule of Values for the MRF Stormwater Treatment System RFP No. PW-0175, associated with a California state and local contract opportunity. The project involves renting a stormwater treatment system for the Resource Recovery Facility's recycling yard and parking lot, designed to treat 400 gallons per minute through polymer injection, settling, and sand filtration to meet Industrial General Permit effluent limits. The rental period is specified for five months and includes comprehensive equipment mobilization, system setup, and demobilization.
The pricing structure is broken down into several key components: pre-construction expenses, system mobilization and demobilization, monthly equipment rental, and generator/fuel cell costs. The document provides a detailed breakdown of pricing for two (2) 20,000-gallon tanks, sand filter, various pumps, an industrial controller, and a polymer injection system. Additional provisions include options for extra equipment rental, such as additional tanks and on-call personnel, with a 10% contingency built into the total pricing structure. The pricing is set up on a 30-day billing cycle, allowing flexibility in equipment usage and potential contract adjustments.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MRF STORMWATER TREATMENT SYSTEM
RFP No. PW-0175
SCHEDULE OF VALUES
FOR PROPOSED CONTRACT TOTAL PRICE
PRE-CONSTRUCTION
1. Contract Expenses (i.e. bonds, insurance, etc.)
2. Project Planning and Coordination
Price as Lump Sum: $
SYSTEM MOBILIZATION
1. Transportation of equipment, including permits
2. Labor for installing turn-key treatment system
3. Initial 3 totes of polymer
4. Initial load of sand filter media
5. Initial startup and training
6. Mobilization of generator, fuel cell, and berm
7. Reach lift for system mobilization Included
Price as Lump Sum: $
SYSTEM DE MOBILIZATION
1. Labor to breakdown system
2. Transportation of all equipment off-site, including permits
3. Demobilization of generator, fuel cell, and berm
4. Tank cleaning excluded
5. Reach lift for system demobilization Included
Price as Lump Sum: $
GENERATOR AND FUEL CELL (30-day billing cycle)
1. Generator to power entire treatment system
2. 500-gallon fuel cell
3. Safeguard Berm
Price per Month: $
MONTHLY EQUIPMENT RENTAL (30-day billing cycle)
1. Two (2) 20,000 gallon tanks
2. One (1) Sand filter
3. One (1) filter pump
4. One (1) transfer pump
5. One (1) submersible intake pump
6. One (1) industrial controller
7. Polymer injection system
Price per Month: $
EXTRAS AND O&M AS NEEDED (DO NOT INCLUDE IN SUBTOTAL PRICE)
1. Additional 20,000 gallon tank (30-day billing cycle) $
2. Tank mobilization/demobilization $
3. Tank cleaning $
4. Replacement tote for polymer, include freight $
5. Hourly rate of on-call personnel $
SUBTOTAL $
10% CONTINGENCY $
GRAND TOTAL $