This is a Schedule B Pricing document for Request for Proposal (RFP) No. 260000000649 issued by the State of Michigan for curb and gutter and M opening repairs on US-24 between Dixie Highway and another location in Oakland County. The scope of work includes removal and replacement of concrete curb and gutter, drainage structure repairs and cover replacements, material sampling and testing by an independent third party, aggregate base installation, erosion control measures, hand patching of hot mix asphalt, slope restoration, concrete pathway patching, and brick pathway restoration. The project also encompasses comprehensive traffic control devices including barricades, temporary signs, lighted arrow boards, portable changeable message signs (PCMS), and channelizing devices. Estimated quantities range from 28,500 linear feet of curb and gutter to 100 tons of aggregate base and 1,800 square yards of slope restoration work. Approximate repair locations are available for review via a Google Earth map provided in the RFP documentation.
Contractors must submit unit prices for each line item in the provided Excel spreadsheet format, with the option to also submit pricing in a non-modifiable format such as PDF. The price proposal must be comprehensive and include all direct and indirect costs such as one-time charges, setup fees, shipping, handling, and per-piece pricing. Contractors certify that prices are arrived at independently without consultation or agreement with other bidders. Quantities listed in the schedule are estimates only, and the State is not obliged to purchase in any specified amounts. All completed pricing schedules must be submitted as requested to avoid proposal disqualification.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1 - Questions & Answers.pdf | ||
| RFP 260000000649 Curb & Gutter Repair, Dixie Hwy.docx | DOCX document | |
| Attachment 1 - Prevailing Wage Information and Rates for Oakland County.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Contractor must enter company name here. |
| SCHEDULE B - PRICING |
| Request for Proposal (RFP) No.260000000649 |
Curb and Gutter, Detail M Opening Repair – US-24 BL/Dixie Hwy, Oakland County
1. The Contractor must provide a price proposal for the Contract Activities using the PRICE SCHEDULE table below. The price schedule must be submitted in this spreadsheet format (Excel or Sheets); however, you may also submit an additional pricing schedule in a non-modifiable format (e.g., PDF). Failure to complete the pricing schedule as requested may result in disqualification of your proposal.
2. Price proposals must include all costs, including but not limited to, any one-time or set-up charges, fees, and potential costs that Contractor may charge the State (e.g., shipping and handling, per piece pricing, and palletizing).
3. By submitting its proposal, the Contractor certifies that the prices were arrived at independently, and without consultation, communication, or agreement with any other Contractor.
| PRICE SCHEDULE |
| The approximate locations of the concrete curb and gutter and M opening repairs may be viewed in the Google Earth map at https://earth.google.com/earth/d/11zaFwQsUCNDtqusqKrGaHJHNrb1lga25?usp=sharing |
Quantities listed are estimates only; the State is not obliged to purchase in these or any other quantities.
Bidder must enter price quote in Unit Price column
| LINE # | ITEM DESCRIPTION | UNIT | QUANTITY | UNIT PRICE | TOTAL PRICE |
| 1 | Curb and Gutter, Removal | Ft | 28,500 | $0.00 | |
| 2 | Curb and Gutter, Concrete | Ft | 28,500 | $0.00 | |
| 3 | Dr Structure Repair | Ea | 30 | $0.00 | |
| 4 | Dr Structure Cover Replacement | Ea | 10 | $0.00 | |
| 5 | Material Sampling and Testing, Independent 3rd Party Contractor | LS | 1 | $0.00 | |
| 6 | Aggregate Base, 21AA | Tons | 100 | $0.00 | |
| 7 | Ero Con, Inlet Protection, Fabric Drop | Ea | 200 | $0.00 | |
| 8 | Hand Patching, HMA | Tons | 400 | $0.00 | |
| 9 | Slope Restoration | Syd | 1,800 | $0.00 | |
| 10 | Conc Pathway Patching | Syd | 600 | $0.00 | |
| 11 | Brickpath Restoration | Syd | 200 | $0.00 | |
| Total Curb & Gutter/M Openings Repair (Lines 1 through 11) | $0.00 | ||||
| 12 | Barricade, Type III, High Intensity, Double Sided, Lighted, Furn | Ea | 15 | $0.00 | |
| 13 | Barricade, Type III, High Intensity, Double Sided, Lighted, Oper | Ea | 15 | $0.00 | |
| 14 | Minor Traffic Devices | LS | 1 | $0.00 | |
| 15 | Sign, Type B, Temp. Prismatic, Furn | Sft | 1,100 | $0.00 | |
| 16 | Sign, Type B, Temp. Prismatic, Oper | Sft | 1,100 | $0.00 | |
| 17 | Lighted Arrow Board, Type C, Furn | Ea | 4 | $0.00 | |
| 18 | Lighted Arrow Board, Type C, Oper | Ea | 4 | $0.00 | |
| 19 | Sign Cover | Ea | 20 | $0.00 | |
| 20 | PCMS, NTCIP-Compliant, Furn | Ea | 2 | $0.00 | |
| 21 | PCMS, NTCIP-Compliant, Oper | Ea | 2 | $0.00 | |
| 22 | Channelizing Devices, 42 inch, Fluorescent, Furn | Ea | 600 | $0.00 | |
| 23 | Channelizing Devices, 42 inch, Fluorescent, Oper | Ea | 600 | $0.00 | |
| Total Traffic Control Devices (Lines12 though 23) | $0.00 | ||||
| GRAND TOTAL | $0.00 |